Preface: The Fieldwork Was Commenced On 22 January 2008 Completed On 29 January 2008
Preface: The Fieldwork Was Commenced On 22 January 2008 Completed On 29 January 2008
The investigation work for this project was started on the instruction of M/S
B.B.R (INDIA) PVT LTD. The fieldwork was commenced on 22th January 2008
The report has been prepared after careful study of all data collected
during fieldwork and laboratory testing and it deals with geotechnical properties
of the sub-soil. Section-I of this report covers the fieldwork & engineering
laboratory test results and borelog data sheets. Section -III deals location plan
SHEET NO.
SECTION - I
1.0 INTRODUCTION 02
2.0 LOCATION 03
3.0 EXPLORATION PROGRAMME & TECHNIQUES 03
4.0 FIELD WORK 04
5.0 LABORATORY TESTS 05 – 06
6.0 SUMMARY OF TEST RESULTS 07
7.0 ENGINEERING CLASSIFICATION, INTERPRETATION AND 08 – 10
GENERALISED BORELOG
8.0 GROUND WATER TABLE 11
9.0 EVALUATION & CONCLUSION 11 - 18
SECTION - II
LABORATORY TEST RESULT 19 – 20
BORELOGS 21 – 23
SECTION - III
e - log p CURVES 28 – 30
MOHR - DIAGRAM 38 - 39
ANNEXTURE 40
1.0 INTRODUCTION:
The fieldwork has been carried out by M/S SPACESCAPES, 51 L&T ROAD
HOWRAH -711103 and the soil samples are tested for identification and
geotechnical parameters by M/S ROOTS (STRUCTURAL & GEOTECHNICAL
CONSULTANT) 816, GRND & 2ND FLOOR DEODAR PLACE,
GARIA KOLKATA –700084.
.
Engineering evaluation of the suitability of different types of foundation and
estimation of bearing capacity is done after compilation and interpretation of all
field and laboratory test results including other relevant information’s. This report
deals with the findings from the above.
2.0 LOCATION :
The aim and objective of the present study is to bring out the stratigraphy,
strength and settlement characteristics of different strata subsequent to which
suitability of different types of foundation could be established. This objective is
accomplished by borehole studies including field & laboratory tests followed by
the necessary interpretation and analysis.
The soil exploration programme is drawn to find out the general stratification and
soil parameters which when put to analysis would provide the best possible
knowledge of foundation behaviour at this site. The programme included:
A brief description of method of boring, field tests, collection of samples etc. and
type of equipments used are given below.
BORING
Boring through the soil is carried out by using 200mm dia auger to advance the
boreholes up to about 5.0M followed by wash boring technique up to the
termination depth. Casings are used up to 5.0M below the G.L. to provide
stability of side of the boreholes. Bentonite solution of adequate density is used
for overall stabilization of the boreholes.
BULK DENSITY
It is the ratio of the weight [moist] and volume of the sample.
CONSOLIDATION TEST
The quantities of the different items of fieldwork done are summarized below:
Standard Penetration Tests : 48
Undisturbed Samples : 06
The samples are initially identified by manual identification test [IS 1498-1970].
Table – 1, & 2 show the laboratory test results. The variations of N-values with
depth are shown in Figs –2. The e V s log p curves grain-size distribution curves
& Mohr –Diagram are shown in Figs- 6 to 17.
7.0 ENGINEERING CLASSIFICATION, INTERPRETATION & GENERALISED
BORELOG :
Barring minor variations, all the boreholes showed identical sub-soil stratification
up to the depth explored.
The deposits at this site may broadly be classified as per following:
Description : Grey/bluish grey sandy silt/silty fine sand with trace clay.
Relative Density : Medium dense
Classification : SM
Thickness : 1.0M
N-value [field] : Range : 11 – 25
Av. : 15
N- VALUE CORRECTION
Effective overburden pressure at the center of layer 6.5 t/m2 {assuming water
table at GL}
Nfield [av.] = 15
Correction factor, CN = 1.0
Corrected N = 15
N- VALUE CORRECTION
The foundation system should satisfy the following two criteria beside others
which may be dependent to a particular site condition.
[a] The net foundation load intensity on the soil should not exceed the
permissible bearing capacity of soil in shear.
[b] Settlement under the load should not exceed the specified values in
IS 1904-1983.
SHALLOW FOUNDATION
Sc = 1.3
Sq = 1.2
S = 0.8
ic = iq = i =1.0 for no inclination of footing
For < 100, dq = d = 1
dc = 1 + (0.2)(D/B)tan[ 450 + Φ/2]
The depth correction factors are to be applied only when backfilling is done with
proper compaction.
For = 00,
Nc = 5.14
Nq = 1.0
N = 0.0
The expression for net bearing capacity reduces to
Qult]net = CNcScdc = [1.3 x 2.9 x 5.14 x 1.16] = 22.5 t/m2
Net permissible bearing capacity in shear for a factor of safety value of 2.5,
qnet) safe = 9.0 t/m2
The bearing capacity of all other sizes of footings including strip footings [L/B>2]
are estimated in the similar manner. With these values of bearing capacities,
settlements are computed for different size of footings with different L/B ratio.
Settlement computation for strip footings is done considering L/B=10 and
therefore the predicted settlements are likely to be conservative for L/B ratio
slightly greater than 2.
COMPUTATION OF SETTLEMENT
Computation of immediate settlement may be done using the following formula
(Janbu) :
Total settlement, ρT = ρi + ρc
a] IMMEDIATE SETTLEMENT
St B qn µ1 µ0 ES ρi
I 2500 9.00 0.60 0.77 1450 7.17
II & III 8850 0.72 0.30 0.76 3075 0.47
b] CONSOLIDATION SETTLEMENT
The estimated bearing capacities and anticipated settlements for all other size of
footings are summarized in Table – A
- 6.0 - 48
1.5
9.0 6.0 43 51
2.0
9.0 - 56 -
2.5
9.0 - 65 -
3.0
Notes : Depth correction factor & geological correction factors have been
applied on consolidation settlement.
: Approximately 10% of total settlement would occur immediately on
imposition of load.
: L/B > 2 indicates strip footing. Computation is done for L/B - 10
PILE FOUNDATION
The vertical load carrying capacity of bored cast-in-situ concrete piles can be
estimated by using the “Static Formula”as per IS code
Qu = a.C.As + k.pd.tand.As + Ab.pd.Nq
Where,
Qu = ultimate load
a = adhesion factor depending on the consistency of cohesive soil
C = undrained cohesion
As = p.d.l
d = dia. of pile
l = length of pile shaft for estimation of skin friction
k = earth pressure coefficient depending on relative density of sandy soil
pd = effective overburden pressure at the concerned depth
d = = angle of internal friction of soil
Ab = p/4.d2
Nq = bearing capacity factor depending on the -value of the sandy deposit
The vertical load carrying capacities of bored cast-in-situ concrete piles are
estimated by using the “Static Formula” and are presented in the following table.
Cut off level = 2.0M below the e.g.l
Founding level = 20M below the e.g.l [the piles shall be resting in the St-III of
dense to very dense sand layer]
Shaft length = 18.0M
Frictional resistance
St – I
Frictional resistance = a.C.As
= [0.7 x 2.9 x 5.5] pd MT
= 35d MT
St – II & III
Founding level = 20M
Embedded length = 12.5M
Frictional resistance = k.pd.tand.As
= [1.5 x 11.8 x tan280 x 12.5] pd MT
= 370d MT
[ k = 1.5 for medium dense sand &
pd [at the centre of the concerned depth] = 11.8 t/m 2 ]
[d = = 370 but restricted to 280 to take into any effect of disturbance due to
installation of piles]
Tip resistance
End bearing resistance = Ab.pd.Nq
pd at the pile tip [restricted to the value corresponding to 15 times pile dia.]
= 12.3 t/m2
For = 280, Nq = 17
End bearing resistance = [p/4.d2 x 12.3 x 17] MT
= 164d2 MT
[Unit base resistance = 12.3 x 17 = 209.1 t/m 2 < 10.7 MN/m2]
Ultimate load bearing capacity of a single pile = [405d + 164d 2] MT
Dia.of pile C.O.L[M] Shaft length[M] Allowable load*[MT]
[mm]
400 2.0 18.0 62
450 2.0 18.0 71
500 2.0 18.0 80
ALOK KR GUHA
ME [CIVIL],MIE,MIGS
[CONSULTING GEOTECHNICAL
ENGINEER]