0% found this document useful (0 votes)
99 views

Test Estimation Techniques

Estimation is predicting the effort required to complete a task using incomplete or uncertain data. There are several techniques for estimating software testing efforts, including Delphi technique, work breakdown structure, three point estimation, and functional point method. These techniques involve breaking down work into components, gathering expert opinions through surveys, and using statistical data to calculate optimistic, most likely, and pessimistic estimates. Accurate estimation allows testing activities to be planned and budgets set appropriately.

Uploaded by

ankush
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views

Test Estimation Techniques

Estimation is predicting the effort required to complete a task using incomplete or uncertain data. There are several techniques for estimating software testing efforts, including Delphi technique, work breakdown structure, three point estimation, and functional point method. These techniques involve breaking down work into components, gathering expert opinions through surveys, and using statistical data to calculate optimistic, most likely, and pessimistic estimates. Accurate estimation allows testing activities to be planned and budgets set appropriately.

Uploaded by

ankush
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

What is Estimation?

“Estimation is the process of finding an estimate, or approximation, which is a value that is


usable for some purpose even if input data may be incomplete, uncertain, or unstable.”

The Estimate is prediction or a rough idea to determine how much effort would take to complete
a defined task. Here the effort could be time or cost. An estimate is a forecast or prediction and
approximate of what it would Cost. A rough idea how long a task would take to complete. An
estimate is especially an approximate computation of the probable cost of a piece of work.

The calculation of test estimation techniques is based on:

 Past Data/Past experience


 Available documents/Knowledge
 Assumptions
 Calculated risks

Before starting one common question arises in the testers mind is that “Why do we
estimate?” The answer to this question is pretty simple, it is to avoid the exceeding timescales
and overshooting budgets for testing activities we estimate the task.

Few points need to be considered before estimating testing activities:

 Check if all requirements are finalize or not.


 If it not then how frequently they are going to be changed.
 All responsibilities and dependencies are clear.
 Check if required infrastructure is ready for testing or not.
 Check if before estimating task is all assumptions and risks are documented.

Software Estimation Techniques


There are different Software Testing Estimation Techniques which can be used for estimating a
task.

1) Delphi Technique
2) Work Breakdown Structure (WBS)
3) Three Point Estimation
4) Functional Point Method

1) Delphi Technique:

Delphi technique – This is one of the widely used software testing estimation technique.

Delphi Method is based on surveys and basically collects the information from participants who
are experts. In this estimation technique each task is assigned to each team member & over
multiple rounds surveys are conduct unless & until a final estimation of task is not finalized. In
each round the thought about task are gathered & feedback is provided. By using this method,
you can get quantitative and qualitative results.

In overall techniques this technique gives good confidence in the estimation. This technique can
be used with the combination of the other techniques.

2) Work Breakdown Structure (WBS):

A big project is made manageable by first breaking it down into individual components in a
hierarchical structure, known as the Work breakdown structure, or the WBS.

The WBS helps to project manager and the team to create the task scheduling, detailed cost
estimation of the project. By using the WBS motions, the project manager and team will have a
pretty good idea whether or not they’ve captured all the necessary tasks, based on the project
requirements, which are going to need to happen to get the job done.

In this technique the complex project is divided into smaller pieces. The modules are divided into
smaller sub-modules. Each sub-module is further divided into functionality. And each of the
functionality can be divided into sub-functionalities. After breakdown the work all functionality
should review to check whether each & every functionality is covered in the WBS.

Using this you can easily figure out what all task needs to completed & they are breakdown into
details task so estimation to details task would be more easily than estimating overall Complex
project at one shot.

Work Breakdown Structure has four key benefits:

 Work Breakdown Structure forces the team to create detailed steps:


In The WBS all steps required to build or deliver the service are divided into detailed task
by Project manager, Team and customer. It helps to raise the critical issues early on,
narrow down the scope of the project and create a dialogue which will help make clear
bring out assumptions, ambiguities, narrow the scope of the project, and raise critical
issues early on.
 Work Breakdown Structure help to improve the schedule and budget.
WBS enables you to make an effective schedule and good budget plans. As all tasks are
already available so it helps in generating a meaningful schedule and makes scheming a
reliable budget easier.
 Work Breakdown Structure creates accountability
The level of details task breakdown helps to assign particular module task to individual,
which makes easier to hold person accountable to complete the task. Also the detailed
task in WBS, people cannot allow hiding under the “cover of broadness.”
 Work Breakdown Structure creation breeds commitment
The process of developing and completing a WBS breed excitement and commitment.
Although the project manager will often develop the high-level WBS, he will seek the
participation of his core team to flesh out the extreme detail of the WBS. This
participation will spark involvement in the project.
3) Three Point Estimation:

Three point estimation is the estimation method is based on statistical data. It is very much
similar to WBS technique, tasks are broken down into subtasks & three types of estimation are
done on this sub pieces.

Optimistic Estimate (Best case scenario in which nothing goes wrong and all conditions are
optimal.) = A

Most Likely Estimate (most likely duration and there may be some problem but most of the
things will go right.) = M

Pessimistic Estimate (worst case scenario which everything goes wrong.) = B

Formula to find Value for Estimate (E) = A + (4*M) + B / 6

Standard Deviation (SD) = = (B – A)/6

Now a days, planning poker and Delphi estimates are most popular testing test estimation
techniques.

4) Functional Point Method:

Functional Point is measured from a functional, or user, point of view.

It is independent of computer language, capability, technology or development methodology of


the team. It is based on available documents like SRS, Design etc.

In this FP technique we have to give weightage to each functional point. Prior to start actual
estimating tasks functional points are divided into three groups like Complex, Medium & Simple.
Based on similar projects & Organization standards we have to define estimate per function
points.

Total Effort Estimate = Total Function Points * Estimate defined per Functional Point

Let’s take a simple example to get clearer:

Weightage Function Points Total

Complex
5 5 25

Medium
3 20 60
Simple
1 35 35

Function Total Points 120

Estimate defined per point 4.15

Total Estimated Effort (Person Hours): 498

Advantages of the Functional Point Method:

 In pre-project stage the estimates can be prepared.


 Based on requirement specification documents the method’s reliability is relatively high.

Disadvantages of Software Estimation Techniques:

 Due to hidden factors can be over or under estimated


 Not really accurate
 It is based on thinking
 Involved Risk
 May give false result
 Bare to losing
 Sometimes cannot trust in estimate

Software Estimation Techniques Conclusion:

There may be different other methods also which can be effectively used for the
project test estimation techniques, in this article we have seen most popular Software
Estimation Techniques used in project estimation. There can’t be a sole hard and fast rule for
estimating the testing effort for a project. It is recommended to add on to the possible
knowledge base of test estimation methods and estimation templates constantly revised based
upon new findings.

You might also like