06 Introduction To IS1893
06 Introduction To IS1893
INTRODUCTION
Roof slabs constructed either by RC or RCC needs insulation for thermal comfort and
waterproofing treatment to prevent leakage of water. Both these requirements are effectively
full fill by brick bat coba treatment, the details of which are being below:-
All existing treatment, coatings on roof slab top is to be removed and surface cleaned by
hard wire brush and washed with water. The surface should be free from any oil, grease, dust
etc. Remedial measured by provided to all structural cracks. Expansions joints should be
treated as per standard practice.
All non-structural cracks more than 0.5 mm wide and construction joints if any,
should be cut in “V” shape, cleaned with wire brush and washed, the cracks are then filled by
polymer modified cement or mortar using acrylic polymer, with addition cement slurry mix is
spread upon cleaned SSD roof surface. Over this 15 mm thick cement, sand mortar, 1:4
admixed, with water proofer is laid.
BRICKBATLAYING
On the above green mortar, a layer of brick bats, soaked over night in water, is laid,
having an average thickness of about 110 mm, about 70 mm near rain water pipe and
150 mm at ridge.
The gaps between the brick bats are generally kept between 15 and 20 mm.
These gaps are filled with cement sand mortar, 1:4, admixed with waterproofer. In hot
and dry weather, the surface should be covered with wet gunny bags immediately
after finishing. Curing should start next day and continued for 7 days.
FINISHING-LAYER
The top surface is then finished smooth with 20 mm thick cement sand mortar, 1:4,
admixed with a water proofer. All liquid admixtures should be mixed with the mixing
water. The surface when green is marked with 300 mm false squares. Curing is to be
done by ponding.
Page 1