0% found this document useful (0 votes)
71 views1 page

Doc2 PDF

This document provides a progress report for various work items on a construction project. It shows the quantity and units of measurement for each work item, the progress made today, the cumulative progress to date, the remaining quantity left to complete, and the percentage completed for excavation, improved subgrade, subbase course, base course, and asphaltic concrete (ATB) course work items. Excavation is 70% complete according to the report.

Uploaded by

mosammat suma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views1 page

Doc2 PDF

This document provides a progress report for various work items on a construction project. It shows the quantity and units of measurement for each work item, the progress made today, the cumulative progress to date, the remaining quantity left to complete, and the percentage completed for excavation, improved subgrade, subbase course, base course, and asphaltic concrete (ATB) course work items. Excavation is 70% complete according to the report.

Uploaded by

mosammat suma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Quantity Today's Progress Cumulative Remaining Completed

Work Item
m3 m3 Progress m3 Quantity m3 %
Excavation 396 20 277 119 70%
Improved Subgrade 7,438.00 0 0 7,438 0%
Subbase Course 2,603.30 0 0 2,603 0%
Base Course 2,231.40 0 0 2,231 0%
ATB Course 1,115.70 0 0 1,116 0%