Work Item
m3 m3 Progress m3 Quantity m3 %
Excavation 396 20 277 119 70%
Improved Subgrade 7,438.00 0 0 7,438 0%
Subbase Course 2,603.30 0 0 2,603 0%
Base Course 2,231.40 0 0 2,231 0%
ATB Course 1,115.70 0 0 1,116 0%