Implementation of Expansion Loops
Implementation of Expansion Loops
net/publication/283579086
CITATIONS READS
0 2,886
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
AN ADAPTIVE NEURO-FUZZY APPROACH FOR MODELING THE EFFECTS OF WATER-IN-DIESEL EMULSION ON DIESEL SPRAYS View project
All content following this page was uploaded by Bekir Kagan Yavuz on 09 November 2015.
INFORMATIVE
Contents
2
INFORMATIVE
October 2015
INTRODUCTION TO INFORMATIVE
This document provides the rationale for certain requirements and recommendations for
expansion loops commonly used in Oil & Gas Industry.
The information in this document is maintained by the relevant subject matter experts,
industrial standards, norms, procedures and documents for the following purposes:
Documentation of the reason and background for certain requirements, particularly
where those requirements have raised questions for expansion loops;
Inclusion of calculation charts and nomogram, if applicable, to explain the
methodology of calculation and design related.
This information can be used as guidance when considering new projects or deviation
requests for expansion loops.
1
INFORMATIVE
October 2015
1. INTRODUCTION
1.1. SCOPE
This document specifies requirements and gives recommendations for expansion loops in
piping systems built in accordance with ASME B31.3. It applies to piping for all types of
process fluids and all utility fluids.
Expansion loops are mechanical barriers/arrangements to absorb over stress due to thermal
expansion increasing the flexibility of the pipelines without decreasing their mechanical
strength.
This document is prepared to improve the safety of construction in the site and so process.
This document covers the piping systems in which the connection parts of elbows, fittings,
and pipe ends are all welded.
This document contains the requirements of the regular expansion loops and three
dimensional expansion loops.
1.2. DEFINITIONS
Term Definition
CAD Computer Aided Drafting
DN Diameter Nominal. The DN prefix indicates the nominal diameter of a piping
system component in millimetres.
EJMA Standards of the Expansion Joint Manufacturers Association
Fluid Gas, vapour, liquid or combinations thereof
Site The area where welding joint of the spool parts are conducted
GTAW Gas Tungsten Arc Welding
Long-Run Piping Piping with length more than one pipe support span.
MESC Materials and Equipment Standards and Code. The MESC codes are
contained in the Catalogue Management Tool (CMT) system.
NPS Nominal Pipe Size
PEFS Process Engineering Flow Scheme
PFD Process Flow Diagram
2
INFORMATIVE
October 2015
Term Definition
PFS Process Flow Scheme
PipeStress The engineer(s) approved by the Principal to undertake pipe stress analysis
Engineer for a project. The engineer is responsible for obtaining data from disciplines
as appropriate, creation, maintenance and issue of the pertinent pipe stress
analysis documentation detailed within this standard, analysis and approval
of all stress critical lines and the timely dissemination of pipe
support/restraint information.
Pipeline A pipeline is a system of pipes and other components used for the
transportation of fluids between (but not within) plants. A pipeline typically
extends from pig trap to pig trap (including the pig traps). If no pig trap is
fitted, the pipeline extends to the first isolation valve within the plant
boundaries.
Piping Piping is an assembly of straight and bent pipes, fittings, flanges, gaskets,
valves and other components (e.g., expansion joints, swivel joints, strainers,
devices for mixing, separating, distributing, metering and flow control). It
also includes pipe supporting elements and insulation.
NOTE: Piping does not include supporting structures (such as frames of buildings,
stanchions or foundations) or equipment (e.g., heat exchangers, vessels, columns,
pumps) or instrument impulse pipes. Instrument specifications apply downstream
the last joint of the last process to instrument valve or valve assembly, defined for
the instrument connection in the mechanical piping class. This can include the
5 mm restriction nipple where applicable.
Piping Class Piping Class is an assembly of piping components, suitable for a defined
service and design limits, in a piping system.
Spec Break The physical location as a single point dividing one piping class from
another.
Site The area where welding joint of the spool parts are conducted
Shop The area where the spool parts are manufactured
3
INFORMATIVE
October 2015
Figure 2.1: An expansion loop over the supports Figure 2.2: A typical expansion joint
The expansion loops can be symmetrical (Figure 2.3) or asymmetrical (Figure 2.4) in terms
of their position in between the anchors or fix supports. The abbreviations in the figures are
available on the page 7. The symmetrical loops are more effective since they damp the
stress equally from both sides [Ref: 2]. However, the asymmetrical ones are also used
commonly in the field depending on the spacing conditions of pipe ways or to utilize existing
loop spacing.
Figure 2.3: Asymmetrical expansion loop Figure 2.4: Symmetrical expansion loop
The points below should be considered during the engineering phase of the loops:
1. The layout of the main line
2. Process conditions
3. Standards & Procedures
4. Stress level on the fittings
5. Process safety rules
6. Cost-wise approach
4
INFORMATIVE
October 2015
3.1. MATERIALS
This document does only cover the materials of carbon steel pipes and fitting elements. The
material types different than carbon steel should be consulted to subject matter experts
complying with the related industrial norms and standards.
The material specifications of pipes, elbows and all fitting elements to be used in expansion
loops should be align with the specification details of main line.
The expansion joints are only recommended to be used if there is not enough space
available in the site for expansion loops.
3.2. CONSIDERATIONS
The loops on the line affects all the other lines in the pipe way, therefore the sizes of the
arms of the loops should be calculated sensitively using the methods mentioned below or
similar methodologies.
In the pipe rack, there are generally several lines standing side by side and the arms of the
loops travel along these parallel lines (Figure 3.1). The course of the arms existing in the site
may cause to abandon the implementation of optimum length/width, L/W ratio (Equation
3.2), for the new loops. In such cases, the total length of the loops mounted in the site, L L,
should be longer than the calculated total length.
Guide Support, G1
In the design phase of pipelines, the line which exposed to the maximum thermal expansion
due to process conditions is located in the most outer position in the rack. In the same way,
the lines exposed to the lower thermal expansions can be positioned in the inner positions.
3D loops (Figure 3.2), are commonly preferred because they prevent the possible conflicts to
the other lines and do not disturb the basic design of the route of the new line. In these kind
of loops, the height of the rising arm, H, are commonly accepted as 1m [Ref: 02].
5
INFORMATIVE
October 2015
The rising arms in the 3D loops are very functional reducing the overall stress level in the
elbows as well as simplifying the loop’s design. On the other hand, they do not contribute to
the flexibility of the main line since they do not change the position of centre of gravity with
respect to the base line of Mitchell shown below (Figure 3.3).
Center
The guide supports mounted on the both sides of the loop, G 1 and G2 in Figure 4.4, have the
critical role for the functionality of the loop. The elbows can slip through the axis of the main
line instead of slipping laterally thanks to the guide supports.
Deflection without
Expansion Loop
Deflection with
Expansion Loop
Hot Fluid
Insulation
Spacing
6
INFORMATIVE
October 2015
The total length of the expansion loop consists of, 1 width (W), 2 lengths (L) and 2 heights
(H) if available (Figure 3.2). The equation of total length of the loop, LL, in terms of arm
geometry is shown below:
LL = W + 2L (Equation 3.1)
The optimum L/W ratio is specified generally in the literature as below [Ref: 4 and 5]:
L = 2W (Equation 3.2)
In order to calculate the minimum required loop length, L L, there are three common methods
given below:
Calculating with Kellogg’s Chart
Calculating with Nomogram
Calculating with one-step formula
The arm size values of a new horizontal loop should be directly used in the field to
implement. However the 3D loops can be selected for implementation if there is not
available space for those calculated arm lengths.
The inputs required for the calculation are listed below in US units:
Total length of the loop, LL, ft
Width of the loop W, ft
Length of the loop L, ft
The distance between two fix supports, LF, ft
The distance between two guide supports, LG, ft
Elasticity of Modulus, E, psi (ASME B31.3 Table C-6)
Outer diameter of the pipe, D, in
Thermal expansion, Δ, in
Thermal expansion coefficient, α, in/100ft (ASME B31.3 Table C-1)
Maximum temperature difference, ΔT, °F
Maximum allowable material stress, S, psi (ASME B31.3 Table A-1)
In downstream businesses, due to the construction of the pipe racks, the distance between
guide supports can be assumed as 20ft (6mt) in general where the support elements are
mounted on the main support columns of the pipe rack.
The maximum temperature to be used in thermal expansion calculation is also the max
design temperature of the pipe. For the minimum temperature, the minimum ambient
temperature recorded value can be used.
I.e. The lowest recorded temperature for Adana in Turkey was −6.4 °C (20.5 °F) [Ref: 6].
7
INFORMATIVE
October 2015
The K1 and K2 values to be used in the chart are the inverse ratios of the distance between
guide supports to the loop width and the loop length respectively:
𝑊 = 𝐾1 . 𝐿𝐺 (Equation 3.6)
𝐿 = 𝐾2 . 𝐿𝐺 (Equation 3.7)
The designer of the loop should select one of the K 1 or K2 values with respect to the physical
conditions in the site. The chosen value and the value to be read in the y- axis of the chart
are used to determine the loop width, W, and the loop length, L, values.
8
INFORMATIVE
October 2015
The nomogram is used with the equation of 3.3 to find the details of the loop such as width
and length:
LL
W
LL
LL
LL = 2L+W
9
INFORMATIVE
October 2015
3.𝐸.𝐷.∆
𝐿𝐿 = √ (Equation 3.8)
144.𝑆 𝐴
Using LL and the equation of 3.3, the details of the loop width and loop length can be found.
4. CONCLUSION
The expansion loops have crucial role to absorb the thermal stress and to sustain the layout
of the pipe lines for years. The design phase for the expansion loops should be sensitively
taken into account before the construction phase. All the three methods mentioned above
are recommended to apply before the design of the expansion loops for comparison and
affirmation purposes [7].
After the calculation phase of design, the stress levels of the high risk part of the loop should
be checked. Caesar II v5.20 can be used to analyse stress levels especially on elbow parts
to check whether there is an over-stress condition or not. If there is an over-stress available,
the loop can be redesigned as a 3D loop model with rising arms or an additional horizontal
loop can be considered providing in between same fix supports.
5. REFERENCES
[1] Website: http://www.usbellows.com/expansion-joint-catalog/torsiona.htm
[2] ASME B31.3, 2002: “ASME Code For Pressure Piping”
[3] Kellogg, M.W., 1956: “Expansion Loops and Expansion Joints”, Chapter 5
[4] Thermacor, 2002: “Expansion Calculations and Loop Sizing”, TDCD 16.103
[5] Sardar, M., 2008: “Design of Steam Piping including Stress Analysis”, Mechanical
Engineering Department, PI of Engineering & Applied Sciences
[6] Website: http://www.meteor.gov.tr/veridegerlendirme/il-ve-ilceler-istatistik.aspx?m=ADANA
[7] Hayden, L.E.,“Grooved and Pressfit Piping Systems”, Chapter A9
10