0% found this document useful (0 votes)
109 views1 page

Boundry Wall Detail Boq

This document provides a bill of quantities for constructing a boundary wall for Mr. Pintu Agrawal. It includes 7 items with descriptions and measurements for excavation, PCC, concrete, murrum filling, reinforcement bars, brickwork, and plastering. The total cost of the project is Rs. 563404.9 or Rs. 1408.5 per running foot.

Uploaded by

Akash Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
109 views1 page

Boundry Wall Detail Boq

This document provides a bill of quantities for constructing a boundary wall for Mr. Pintu Agrawal. It includes 7 items with descriptions and measurements for excavation, PCC, concrete, murrum filling, reinforcement bars, brickwork, and plastering. The total cost of the project is Rs. 563404.9 or Rs. 1408.5 per running foot.

Uploaded by

Akash Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BOUNDARY WALL For Mr.

PINTU AGRAWAL
S.no. Description No L B H/D Quantity Unit Rate Amount
1 excavation for columns
15 1.68 1.83 1.52 70.14
11 1.68 1.83 1.52 51.43
121.57 CUM 210 25530.2
2 PCC
1:3:6 (1 cement : 3 coarse sand :
6 graded stone agg. 20 mm nominal size)
for columns 15 1.68 1.83 0.1 4.60
11 1.68 1.83 0.1 3.37
7.98 cum 2700 21532.9
3 M-20 Grade
Footing 15 1.38 1.53 0.23 7.26
11 1.38 1.53 0.23 5.33
Columns upto natural ground level
C1 15 0.53 0.53 0.9 3.79
11 0.40 0.53 0.9 2.10
Ground beam GB1 1 119.512 0.2 0.4 9.56
Coping 1 119.512 0.2 0.1 2.39
Columns 15 0.53 0.53 2.1 8.85
11 0.4 0.53 2.1 4.90
30.43 cum 3500 106516.6

4 MurrumFilling with proper compaction & Consolidation 95.12 cum 250 23778.8

5 FE-500D
thermo mechanically treated bars 2965.15 kg 48.00 142327.2
6 brick work with Well Burnt Clay 200 mm Bricks
cement mortar 1:6 ( 1 cement : 6
coarse sand )
(SOR item no-7.5.4/40)
above plinth and upto 5 floor level
1 115.012 0.2 2.1 48.31 CUM 3150 152161.1
7 Providing and making 15 mm thick
cement plaster on the rough side of
single or half brick wall of mix 1:5
(1 cement : 5 fine sand)
Full Column Moulding 18 600 10800.0
Half Column Moulding 15 400 6000.0
wall 2 115.012 2.4 552.06
top 1 115.012 0.2 23.00
575.06 SQM 130 74757.9

TOTAL Rs 563404.9
per rft 1408.5

Y:\RAJENDRA JAIN\Pintu agrawal\SUTARIA SIR\R23 BOUNDRY WALL 8.5.2019\boundry wall detail boq1