Subcontracting With GST
Subcontracting With GST
With Challan
Define Shipping Data for Plants: Assign Sales Organization, Distribution Challan and
Division should be maintained for Supplying Plant from which the components are to be
delivered. Table view – V_001W_IV, T. Code – SM30 Or SPRP -> SAP Ref. IMG -> Materials
Managment -> Purchasing -> Purchase Order -> Set up Stock Transport Order -> Define
Shipping Data for Plants
New Billing Type define – ZSN SC Challan (No Taxes), ZSP – SC Invoice (with Taxes)
Use the existing SD Pricing Procedure or define a new Pricing Procedure for
Subcontracting process
Set up “Delivery to Billing Type” Copy Control. Copied with Billing Type “FX” and Sales
Order “OR
Material Master - Material Master should be available in system for both Finished and
Raw Materials (T. Code – MM01). Components must have stock in the system. Extend the Sales
View for the Raw Materials or Components
Customer - Create Customer (T. Code – XD01) with necessary details as per
Subcontractor Vendor
Vendor - Maintain Subcontractor Vendor (T. Code – XK01) and assign Customer in the
Vendor Master data.
Sales Condition Record - Maintain Sales Condition Record for Material Pricing (T. Code
– VK11)
If we are using T. Code – ME2O for issuing components to vendor, then system will
create Outbound Delivery. And then Go To Change Delivery (T. Code – VL02N) to do PGI, which
will generate Goods Issue document using Movement Type – 541.
Post Goods Receipt - When Vendor sends the materials, we post the Goods Receipt in
the system using T. Code – MIGO with reference to Subcontracting PO having Movement Type
101 for final or end products and Mov. Type 543 for Components. Consumption of Components
material from the Vendor Stock and Stock update for the Final Products.
Invoice Receipt - Post Invoice Receipt for Subcontracting Vendor for the service
charges paid to the Subcontractor through T. Code – MIRO with reference to Subcontracting PO