Assignments 1 and 2 Engineering Project Management
Assignments 1 and 2 Engineering Project Management
Special Instructions
1. Answer all questions, and ensure that your answers have the coverage, and are in the format,
requested.
3. Your answers should be properly referenced and reflect that you have undertaken research
outside the study material. You are to use the Harvard AGPS referencing system, information
which is available from the USQ Library webpage:
http://www.usq.edu.au/library/referencing/harvard-agps-referencing-guide
5. You will require an abstract and table of contents for your answer to Part B.
6. You should include a word count for each of Part A and Part B of Question 1. Word counts
exclude the List of References.
7. It is expected that your written answers will be produced using electronic word processing.
The ‘.pdf’ format is preferred for written answers.
10. Please note that if plagiarism or cheating is detected in this assignment it will result in no
marks for the assignment. Students should ensure they clearly understand the meaning of
plagiarism and cheating. In particular, students should understand that while they may
collaborate with other students on the conceptual ideas in their assignments, the final written
report submitted by each student must be unique, and must not contain the written material of
(a) any other student in the course, or (b) by any other person without due acknowledgement.
Assignments are expected to be submitted to plagiarism detection software at the time of
submission.
11. Applications for extensions of assignment submission must be made in writing to the Course
Examiner together with accompanying documentation as specified in the Assessment of
Compassionate and Compelling Circumstances Procedure. The application and all supporting
documentation must be submitted electronically.
An Assignment submitted after the deadline without an approved extension of time will be
penalised. The penalty for late submission without a pre-approved extension will be specified
in the assignment instructions. At the very least, the penalty for late submission is a reduction
by 5% of the maximum Mark applicable for the Assignment, for each University Business
Day or part Business Day that the Assignment is late. An Assignment submitted more than ten
University Business Days after the deadline will have a Mark of zero recorded for that
Assignment.
Course Examiners may refuse to accept Assignments for Assessment purposes after Marked
Assignments and/or feedback have been released. If Compassionate and Compelling
Circumstances appear to exist, Course Examiners must consider these before refusing to
accept an Assignment.
See: http://policy.usq.edu.au/documents/14749PL#4.2_Assignments
You are managing a project that is scheduled to take 12 months to complete and has a budgeted actual
cost (BAC) of $1,000,000.
Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the (6 marks)
text to the calculation of the Estimate at Completion (EAC) of the project.
You are managing a second project that has the same time and cost specifications as those in Question
1 (a), but which is 40% complete at the Status Date, when Actual Costs are $350,000.
Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the (6 marks)
text to the calculation of the Estimate at Completion (EAC) of the project.
Comment on each of these projects from the point of project performance, paying particular attention
to the following:
Briefly discuss two (2) advantages and two (2) disadvantages of Earned Value Project Management.
Marking:
Background
You have recently been appointed as a project manager in a large engineering organisation. Some
examples of such an organisation include, but are not limited to:
Consultant
Government organisation
Construction company
Installation company
Asset management provider
Maintenance services provider
Other.
The organisation may be operating in one or more engineering disciplines, such as civil, mechanical,
electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.
Your organisation has asked you to review the management of a medium sized project (up to $5
million in value), which is to be completed within two (2) years of its commencement. The project has
at least 20 main activities.
The project commenced eight (8) months ago. The first six (6) weeks were spent developing the
project charter and preparing the original project management plan. Project execution (carrying out the
work) commenced immediately the project management plan was completed and approved.
There will be a one (1) month project closing period at the end of the project. During this time,
equipment will be tested and commissioned (if relevant to your project), and the project will be
finalised.
The existing business case and project charter are not detailed. Similarly, the project management
plan, including a basic Gantt chart and high level budget is not well detailed or described.
1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from
poor understanding of lead times for delivery of particular project components. There are no
other significant factors that should impact on project delivery.
2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of
critical activities. They do not have clear scheduled completion dates.
3. There have been delays in procuring some critical project resources. There may be alternative
suppliers.
4. While there were a number of specialised personnel for particular aspects of the project
available at the start of the project, they were not booked ahead of when they were required.
Most of these resources are now booked for several months ahead. Few alternatives are
available.
5. As a result of the influence of a number of stakeholders, there has been significant scope
creep, which with the current rate of progress will delay delivery by one (1) month. This scope
creep also threatens to impact on the project’s business case.
6. Some components of the project have not been delivered or built to the required quality
specification. Consequently, there have been delays while defects have been rectified.
You have been charged with delivering a revised project management plan to deliver the project on
time; and with providing a report to the Project Sponsor explaining the actions you have taken.
Your Task
Nominate an organisation of your choice, and the engineering discipline or disciplines in which it
is operating.
Nominate a suitable project (for example, road development, subdivisional development, power
station, mobile phone network, mining, provision of industrial equipment, installation,
maintenance, surveying) to use as an example.
2. Prepare a revised project charter, including an updated business plan. (30 marks)
3. Prepare an updated project management plan for completing the project within its original
timeline.
(130 marks)
Notes:
The project charter should include a revised business case for the project and link the
project with your organisation’s strategic plan. On the basis of this business case, the
project sponsor will make a decision about the future of the project.
You may assume that the project sponsor has allowed the project timeline to be increased
by one (1) month to allow for the scope creep already approved. However, further scope
creep is not permitted.
The project scope management plan should include a section on controlling scope creep
The project time management plan should include a Gantt chart showing the major project
activities.
The project cost management plan should include all costs reasonably expected to be
incurred in delivering the project. These costs may include estimates for ensuring
completion of the project.
4. Prepare a plan for executing, monitoring and controlling the project (10 marks).
5. Prepare a plan for any testing and commissioning, and for closing the project
(10 marks)
succinctly outlines the steps you have taken to deliver the project within its original timeframe
(as extended by permitted scope creep of one (1) month)
explains why they have been taken
demonstrates how they will enable the project to be completed within its original timeframe
discusses the additional costs that will be incurred to achieve this target
(50 marks)
ASSIGNMENT 1
QUESTION 1
PART A:
GIVEN DATA:
TO FIND:
Also,
SOLUTION:
a. I order to find Earned Value, we use the formula EV = % of completed work × BAC
Therefore, EV = $ 250,000
1|Page
Also finding the Estimate at Completion (EAC) of the project using the following formulae:
2|Page
Since the CPI value is less than 1, the project is over budgeted. So the To-Complete Performance
Index(TCPI) is given as;
Therefore, TCPI = 1
3|Page
PART B:
GIVEN DATA:
TO FIND:
SOLUTION:
a. I order to find Earned Value, we use the formula EV = % of completed work × BAC
Therefore, EV = $ 400,000
4|Page
Also finding the Estimate at Completion (EAC) of the project using the following formulae:
5|Page
Since the CPI value is greater than 1, the project is under budgeted. So the To-Complete
Performance Index(TCPI) is given as;
PART C:
Cost Variance: Cost Variance is the difference between Earned Value and Actual Cost. In
the first project, cost variance is a negative value which indicates that this is an over budget
project. While in the second project, the value is positive indicating that the project is under
budget.
Schedule Variance: Schedule Variance is the difference between Earned Value and
Planned Value. In the first project, schedule variance is a negative value. Thus we can
conclude that the project is behind schedule. But the value is positive for the second project
which makes it obvious that the project is ahead of the schedule.
Cost Performance Index: Cost Performance Index is the ratio between Earned Value and
Actual Cost. When we look at the first project, cost performance index is less than 1, which
indicates that the project funds are not efficiently utilized. But the cost performance index
for the second project is greater than 1, which means that the project funds are used
efficiently.
Schedule Performance Index: Schedule Performance Index is the ratio between Earned
Value and Planned Value. Schedule performance index for the first project is less than 1,
which means that the project is not progressing as the rate originally planned. But the
schedule performance index for the second project is greater than 1 indicating that the work
is progressing better than the rate originally planned.
Estimated Actual Cost: Estimated Actual Cost is the total expected budget of the project.
First project is an over budget project when compared with the second project which is an
under budget project.
6|Page
The first project is an over budgeted and beyond schedule project and thus the overall
performance is low. The measures that could be taken to complete the project successfully is
to utilize the budget efficiently and work harder and faster to bring the project near schedule
and budget.
On the other hand, the second project shows an overall good performance and I suppose the
only thing required now required is to continue the work without delay to successfully
complete the project.
PART D:
Two advantages of Earned Value Project Management Plan are:
Earned Value Project Management Plan makes sure that all the project parameters are
on track. It tracks the project in terms of work, time and cost.
Earned Value Project Management makes it easy to recover from any delay’s occurred
due to unexpected events.
Earned Value Project Management Plan does not give importance to maintaining
project quality. While taking care of project progress, the quality is often neglected.
But quality is among the key objectives of any project. Thus, maintaining both these
aspects in an equilibrium are often a good challenge.
Huge preparation about the project has to be done to understand each and every aspects
of the project clearly. This process of implementing the Earned Value Project
Management Plan can often be too time consuming.
7|Page
ABSTARCT
For many years, the state of Kerala in southern India has lagged behind the rest of the nation in the
area of urban public transportation. The ever growing traffic on the roads of Kerala has forced the
Government to employ Logitech Metro Rail Corporation Limited(LMRC), which has a reputation
of being the pioneer organization contributing efficiently to urbanization in India.
In a state like Kerala, where the majority of people rely on public transport, the necessity of an
efficient urban transportation was an issue that needed immediate attention. Addressing to the
issue, the Government of Kerala brought forward LMRC, a highly reliable, economic and
convenient metro rail project that could be the perfect solution to the current inefficient public
transportation system.
With the project, LMRC and the Government of Kerala aims at eradicating the transportation
related issues faced by the common people and provide a permanent solution to it. Implementation
of the metro rail network over a stretch of 26.5 km, starting from Petta to Aluva, which is among
the most crowded areas of Kerala will help ease the uncontrollable traffic levels and issues
associated with it.
LMRC is a Government funded project with an estimated budget of $5 million and is to be
completed within a time frame of two (2) years. A highly skilled team of experts, headed by the
project manager will be responsible for the completion of the project.
8|Page
TABLE OF CONTENTS
7. References…………………………………………………………………………24
9|Page
QUESTION 2(a)
Over the last few years, the state of Kerala has undergone rapid development in terms of
industrialization, which has resulted in a rapid population growth. The estimated cost of
completion of the project is $5 million in value and the Government of Kerala has categorized it
as a medium sized project. The metro rail project is to be completed within two (2) years of its
commencement. The rail network is to be constructed over a 26.5 km stretch from Petta to Aluva.
LMRC surveyed the area and has divided the entire project into three (3) major phases, with at
least 20 main activities.
Since the metro rail project involves surveying, construction, industrial equipment’s and
mechanical works, the project can be categorized under Civil & Mechanical disciplines.
10 | P a g e
11 | P a g e
12 | P a g e
Wages $ 800,000
TOTAL $ 5,000,000
LMRC is a Kerala Government funded metro rail project, which aims at solving the current
transportation related issues faced by the common people and contribute positively towards
community welfare. After a proper survey, the experts of LMRC has identified the areas that need
immediate attention. The proposed project covers the most congested areas, a stretch of 26.5 km
starting from Petta to Aluva. Implementation of the rail network will help reduce the traffic volume
by almost 75 %.
The entire project is divided into three (3) major phases, which is again sub-divided into almost
20 major activities. The initial part of the project would be the legal acquisition of land from
concerned authorities. Then the traffic has to be re-directed and road widening along with rail track
construction has to be done. An expertise team of engineers from Civil & Mechanical department
will be allocated and they as a team would be responsible for the construction of tracks and the
machinery/equipment’s needed. Once the tracks are fully constructed, a sample test run will be
13 | P a g e
initiated and the results would be evaluated. Necessary changes if required will also be done to
ensure reliability.
Stakeholders’ have a great impact on the entire project right from the initial phase to its completion.
In this metro rail project also, the stakeholders will be completely involved throughout the project.
The stakeholders’ for this project are identified as Internal Stakeholders’ and External
Stakeholders’.
Internal Stakeholders’ are:
The Government of Kerala.
Kerala State Road Transport Department.
Project Manager.
Quality Inspector.
Technical Manager.
And, External Stakeholders’ are:
Suppliers.
Workers.
Common people.
The needs of stakeholders include successful completion of the project within the estimated time
frame and budget, project sustainability, uninterrupted supply of raw materials, financial support
for the project, quality of end product etc.
14 | P a g e
METRO RAIL
CONSTRUCTION
15 | P a g e
Similarly, Tools and Techniques include project plan methodology, further planning and
facilitation methods. Outputs include updated project management plan and results. The project
team headed by the project manager (me) will be following these techniques to conclude the
project within the allocated time frame and budget.
Project Time Management technique is allocated by LMRC to have proper planning and execution
of the project and try best to complete the project successfully within the expected time period of
16 | P a g e
two (2) years. Proper understanding and scheduling of project activities are done. The activities
and time allocation for each activity is shown below in the form of a Gantt chart:
LMRC adopts Project Cost Management to ensure that the organization will be able to complete
the metro rail project successfully within the expected budget frame of $ 5 million. LMRC is a
Government funded project. So preparing a proper budget plan is utmost important and is a primary
requirement of the project objective. The expert project management team of LMRC have prepared
an estimate of budget distribution, which is as follows:
17 | P a g e
Wages $ 800,000
TOTAL $ 5,000,000
Project Quality Management is adopted by LMRC to ensure the scope and sustainability of the
project. Project quality is among the primary stakeholder requirements. An on-field Quality
Inspector will be allocated to ensure proper maintenance of quality. Quality of raw material,
equipment’s and the skill of workers contribute to high quality of the overall project. Quality check
is initiated at various stages of the project to ensure proper functioning. If an error is detected,
rectification process is initiated immediately to prevent loss of time and budget. Satisfying the
needs of the stakeholders is the key objective of the project.
18 | P a g e
Project Human Resource Management deals with the management of humans involved in the
project. Forming a group of skilled and understanding people is a key factor which fruitfully
contributes to the successful completion of the project as per the set objective. Proper manager is
the key person responsible for maintaining and supporting proper human resource.
People involved in the project may vary to each other in terms of culture, background and ethnicity.
So apart from project manager, a human resource manager who specializes in managing human
assets is involved in the project progression phase to deal with the issues if any detected. Workers
being the major human resource needs intense attention. Proper planning and executing of
workers’ wages, providing a good working environment and understanding them are important.
LMRC has a strong team of workers’ and maintaining these human assets are efficiently executed
by LMRC.
Procurement is the process of obtaining goods and services from suppliers outside of the
organization. Proper managing of these supplies are very important. Since the entire project has to
be completed within the budget frame of $ 5 million, selection of procurements should be effective
in quality & quantity. Raw materials for the metro coach production is supplied by a Chinese
Company. Only after proper negotiations, LMRC decided to invest on procurements.
19 | P a g e
Project Requirement: Once a properly planned lay-out is drafted, the next phase is
estimating the raw materials required, machinery & equipment’s and the diversity of work-
force needed for the successful completion of the project. The requirements of the
stakeholders are identified.
Detail Design: Preliminary design lay-outs for the track and coaches are made. Project
prototypes are also created to get a better understanding of the entire project.
Construction: Construction of the rail tracks, road widening and construction of coaches
are to be initiated.
Testing & Result: Once the construction is done, a test run over the new track is initiated
to gather data’s. Any needed rectification is done and the final results are drawn. The
project is then closed.
LMRC is a Government funded metro rail project. So the main activity resources are provided
largely by the Government. Few procurements are also undertaken. The duration for completing
the project successfully is two (2) years. But the project sponsors have allowed the project timeline
to be increased by one (1) month to allow for the scope creep already approved.
3.7 Project Schedule, Cost and Budget:
The LMRC undertaken project is a two (2) year project, which began on 24th September 2014
and is expected to complete by the end of October 2016. The total estimated budget of the
project is $5 million and is funded by the Government.
20 | P a g e
Wages $ 800,000
TOTAL $ 5,000,000
Shown above is an estimate of cost & budget. Once the estimation is done. Then the team has to
work on controlling each stages or activities of the project within the estimated budget frame.
Acquisition of land legally requires the highest expenditure, followed by raw material, machinery
and equipment’s. Cost management is among the hardest challenge faced by LMRC, so a proper
planning and execution of the technique is highly essential.
LMRC with the metro rail project aims at providing an urban mode of transportation to the
common people of Kerala. So utmost care has been taken to execute the project with perfection
and great satisfaction. Before the start of the project, a team of well experienced and skilled
21 | P a g e
engineers, contractors, quality inspectors and workers were formed. After the initial planning
phase, the execution of the project was undertaken. Procurement of raw materials, availability of
local raw materials, machinery & equipment’s, requirement of skilled labor forces and allocating
duties to engineers are the key plans in executing. During the construction phase, proper
monitoring of work, maintenance of machinery & equipment’s is undergone. Any issues detected
are prioritized and an appropriate solution is immediately drafted. The controlling phase involves
activities such as testing, identifying defects and importantly not slowing down the pace of the
project. The allocated time is two (2 years) and a budget frame of $ 5 million, LMRC will take
necessary controlling steps to try its best to finish the project successfully within the time-frame
and budget limit.
5. Plan for any Testing and Commissioning, and for Closing the Project:
Once the construction is completed, a test run is conducted on the new track to study and
understand the project performance and quality. The project manager will review the final output
and further documentations will be initiated. The quality inspector will study the test results and
rectify any detect if identified. Once the entire processor is completed from testing to documenting,
the project will be closed.
22 | P a g e
QUESTION 2(b)
This report is drafted to outline the steps undertaken to successfully complete the project within
the time frame. The main reason to come up with a revised project management plan is to avoid
the scope creep and complete the in expected time. An additional time of one (1) month is being
allocated by the sponsors though. Planning, Executing, Monitoring & Controlling and Testing &
Result are the steps taken by LMRC to deliver the project in the expected time frame.
The project lagged a proper plan initially. But while drafting the revised management structure, a
team of skilled engineers along with the project manager came up with a proper plan which could
be implemented. After drafting the plan, the execution of the outlined plan had to be done. The
construction work included properly planned activities and the work force used were also skilled
and trained. Having a detailed plan structure allowed the LMRC team to execute the project with
standard and eliminating time loss. Monitoring & Controlling also played a key role to the success
of the project. A team of quality inspectors were recruited, who could keep monitoring each phase
of the project during its execution phase and completed phase. Adopting this technique of
involving special on-field quality inspectors proved to be highly profitable as the errors were
immediately identified and rectified, which helped in maintaining the pace of the project without
hindering the expected quality. Then a proper testing of each phase of the project was initiated and
the respective results were tabulated and studied. A test run on the newly constructed track is
initiated and is reviewed to understand the efficiency and for the detection of any flaws. Once all
the tests on track is completed. A detailed project report is documented and is submitted to the
Government of reviewing. An additional cost of $200,000 will be incurred to successfully
implement the revised project management plan. Recruitment of skilled labors and procurement
of rail coach materials from China will be included in this additional cost. Thus by adopting a
revised project management plan helped LMRC to complete the project successfully within the
time frame.
23 | P a g e
REFERNCES
2016, B. (2005) Metros - mass transit systems - Bombardier transportation. Available at:
http:<//www.bombardier.com/en/transportation/products-services/rail-vehicles/metros.html>.
(Accessed: 26 April 2016).
2016, S. (2016) World’s largest railway companies as of april 6, 2015, based on market value (in
billion U.S. Dollars). Available at: http:<//www.statista.com/statistics/260683/the-largest-energy-
railway-companies-worldwide-based-on-market-value/>. (Accessed: 28 April 2016).
Watch, P. (2016) Project monitoring and control phase in planning management. Available at:
http:<//www.projectmanagementwatch.co.uk/project-monitoring-and-control-phase-in-planning-
management> (Accessed: 28 April 2016).
nc, B.H. (2008) Definition of the closing process group in project management. Available at:
http:<//www.brighthubpm.com/project-planning/1676-what-is-involved-in-the-project-closing-
stage/#imgn_1>. (Accessed: 29 April 2016).
Sparrow, P. and penna, 4 (2012) Earned value management: Advantages and disadvantages.
Available at: http:<//www.ianswer4u.com/2011/12/earned-value-management-advantages-
and.html>. (Accessed: 21 April 2016).
24 | P a g e
Special Instructions
1. Answer all questions, and ensure that your answers have the coverage, and are in the format,
requested.
3. Your answers should be properly referenced and reflect that you have undertaken research
outside the study material. You are to use the Harvard AGPS referencing system, information
which is available from the USQ Library webpage:
http://www.usq.edu.au/library/referencing/harvard-agps-referencing-guide
4. You will require a table of contents for your answers to Question 1(a), and Question 2.
5. You will require an abstract and table of contents for your answer to Question 1(b).
6. You should include a word count for all questions. Word counts exclude the List of
References.
7. It is expected that your written answers will be produced using electronic word processing.
The ‘.pdf’ format is preferred for written answers.
10. Please note that if plagiarism or cheating is detected in this assignment it will result in no
marks for the assignment. Students should ensure they clearly understand the meaning of
plagiarism and cheating. In particular, students should understand that while they may
collaborate with other students on the conceptual ideas in their assignments, the final written
report submitted by each student must be unique, and must not contain the written material of
(a) any other student in the course, or (b) by any other person without due acknowledgement.
Assignments are expected to be submitted to plagiarism detection software at the time of
submission.
For further information refer to the University’s Academic Integrity Policy 13752PL
11. Applications for extensions of assignment submission must be made in writing to the Course
Examiner together with accompanying documentation as specified in the Assessment of
Compassionate and Compelling Circumstances Procedure. The application and all supporting
documentation must be submitted electronically.
An Assignment submitted after the deadline without an approved extension of time will be
penalised. The penalty for late submission without a pre-approved extension will be specified
in the assignment instructions. The penalty for late submission is a reduction by 5% of the
maximum Mark applicable for the Assignment, for each University Business Day or part
Business Day that the Assignment is late. An Assignment submitted more than ten University
Business Days after the deadline will have a Mark of zero recorded for that Assignment.
Course Examiners may refuse to accept Assignments for Assessment purposes after Marked
Assignments and/or feedback have been released. If Compassionate and Compelling
Circumstances appear to exist, Course Examiners must consider these before refusing to
accept an Assignment.
See: http://policy.usq.edu.au/documents/14749PL#4.2_Assignments
The projects for which the organisation provides its services encompass all disciplines of engineering,
plus related disciplines like construction.
Your main responsibility is the management of a program of approximately six (6) engineering
projects in your organisation.
You have just taken over this particular program, and are keen to make an impression.
Three (3) of the six (6) projects in this program are progressing well towards a satisfactory result. The
remaining three (3) projects, Project A, Project B and Project C require attention.
The information given below about each project is fairly basic. You are expected to develop additional
details about each project as part of your answer, and for each project nominate an example project
(for example, an infrastructure development project for Project A, development of a new
manufacturing system for Project C) for which to develop your answers. Further information with
respect to these matters is in sub-questions 1 and 2 of Question 1(a).
Project A
Project A is a planning, design and implementation infrastructure development project (about $15
million in value and expected to take about three years from the start of planning to completion),
which is well advanced in its planning component. While the project is progressing well in terms of
time, cost and quality, there are a number of sustainability and stakeholder management issues with it.
This project is being undertaken in an environmentally sensitive area in which live a number of
property owners who are quite concerned with the impact of the project on their environment. In
particular, they are concerned that a thorough environmental risk assessment has not been undertaken
with respect to the long-term impact on the sensitive bushland area in which they live. They are also
concerned that completion of the project, through providing the basis for significant property
development and destruction of bushland, will forever change the social fabric of their region. They
have formed a Landholders’ Action Committee that is determined to prevent the project from
succeeding. The delays caused by the concerns of the property owners have the potential to threaten
the completion of this project satisfactorily.
There is an alternative, less controversial route for the infrastructure being developed. This route is
acceptable to the Landholders’ Action Committee. It will, however, cost an addition $1.5 million to
use this route, which will result in a six month delay to delivery of the project.
Project B
Some of the specialised components used for this project are only obtainable from overseas suppliers,
and are difficult to transport over the rough terrain near the project site. There has been a delay on
ordering these components. The transportation of these components, which has to be booked several
months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the
requisite set of skills to install them.
There are also a number of other risks associated with this project, including a quite basic business
case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks
and the potential for significant penalties to be levied if it is not completed in time for the local
Member of Parliament to officially open it.
Project C
Project C is a small (about $2 million in value) but complex project that has as its purpose the
development of a new computer based management system, and is highly complex in nature. In
particular, it has a number of small interrelated sub-systems that are mutually dependent, and does not
have a well-defined direction. It is currently about 40 per cent complete.
This project is being developed by staff of your organisation, with the assistance of specialist
contractors as required. Differences between the development staff and organisational management
about the direction that the project should take threaten, however, to impact on its successful delivery.
Similarly, requests by organisational management for scope change are numerous, and change control
procedures are poor. To date, the project manager has successfully managed to manage requests. This
may not always be the case.
If the new system achieves its desired goals, the organisation would be expected to achieve
considerable productivity improvements. However, it is threatened by non-completion unless all
parties involved successfully resolve their differences about the direction of the project.
There has been a recent change in the composition of the Board of Directors of the organisation. The
new Board has decided that the organisation should develop a more focused strategic direction, and in
particular wishes to focus on projects with strong business cases, well defined project charters and
very clear objectives that must be agreed to by key stakeholders. All projects must be very closely
aligned to the particular engineering disciplines represented in the organisation. There is a strong focus
on minimising risks to the organisation and on good communication between all parties in all projects.
In addition, there is a strong focus on project completion.
The new Board is committed to completion of existing projects, and will provide the necessary
resources to compete these projects, even at a potential loss, in order to maintain and build its client
base. It is, however, not keen to undertake further internally focused projects like system development.
The Board does, however, want to be prudent in the way that it manages its projects, and to build a
platform for a successful future.
The Board therefore urgently requires that you review these projects and present a report on what steps
you will take to ensure that all three projects that require attention will be completed on time and to
the required quality. Losses are to be minimised. Internal projects are to be carefully scrutinised to see
whether they could be outsourced if that is a better option.
You will accordingly need to undertake a review of all three (3) projects to ascertain whether they fit
the organisation’s new strategic direction and what action should be taken given the potential risks
associated with them.
Your Task
1. Nominate three (3) example projects for discussion. (30 marks – 10 marks per project)
Nominate an organisation of your choice, and the engineering discipline or disciplines in which it
is operating.
Nominate three (3) suitable projects (for example, road development, subdivisional development,
power station, mobile phone network, mining, provision of industrial equipment, installation,
maintenance, surveying, research and development) to use as examples for your discussion.
These projects should be consistent with your nomination of the type of engineering disciplines in
which your organisation operates.
2. Define key characteristics of each project nominated. (75 marks – 25 marks per project)
For example:
3. Review each of the projects nominated in the background with respect to their alignment
with corporate direction and the principles of good project and program management.
Areas to consider in this review include, but are not limited to:
Potential risks in delivering the project and subsequent to delivery of the project
Sustainability of the project and its outcomes
Other matters considered important to the achievement of these objectives
This plan should take into account each of the issues described above, and summarise the
following points:
Summarises your analysis of each of the three (3) projects you have been asked to assess.
(30 marks – 10 marks per project)
Describes your proposed solution for each project, including the feasibility of implementing it.
(30 marks – 10 marks per project)
Discusses, from an overall program management perspective, how the projects within your
program can be better assessed, prior to acceptance by the organisation, for feasibility and
alignment with the Board’s strategic direction for your organisation.
(30 marks)
What in your opinion are the three (3) main issues that project managers are likely to face in
the next 50 years?
Why are they likely to be the main issues that project managers are likely to face?
How would you expect the practice of project management to change over the years to meet
these issues?
What is your overall assessment of how projects might be managed in the future?
Marking
Identification of issues, discussion, analysis (120 marks)
Identification and explanation of each issue (10 marks per issue) (30 marks)
Discussion of why each issue is important (10 marks per issue) (30 marks)
Analysis of how the practice of project management will change to meet them
(10 marks per issue) (30 marks)
Overall assessment how projects will be managed in the future (30 marks)
ENG 8208 _
ADVANCED
ENGINEERING
PROJECT
MANAGEMENT
ASSIGNMENT - 2
TABLE OF CONTENTS
1. Nomination of Projects………………………………………. 2
6. Question 2…………………………………………………….. 25
7. References…………………………………………………….. 29
1|Page
1. NOMINATION OF PROJECTS
For many years, the state of Kerala in southern India has lagged behind the rest of the nation in the
area of urban public transportation. The ever increasing traffic on the roads has forced the
economic and convenient metro rail project that could be the perfect solution to the current
LMRC, which has a reputation of being the pioneer organization contributing efficiently to
urbanization in India, has currently undertaken 6 projects. Of these 6 projects, three (3) projects
are progressing well towards successful completion. The Metro Rail Project is one among the three
(3) which is progressing well along with two (2) other major projects in neighboring states. But
the remaining three (3) subsidiary metro rail projects face few issues. The following are the three
(3) projects:
1. Road Development: Developing a proper road network over a 26.5 km stretch, from Petta to
Aluva, where the metro rail project was previously implemented, is a new project undertaken
by LMRC. The existing road network was completely damaged during the metro rail
development in those areas to regulate traffic congestion and easy accessibility to metro
stations. This is a AUD 13.5 million project which is currently experiencing disagreement from
the property owners who are quite concerned with the impact of the project on their
2|Page
environment, particularly the long-term impact on the sensitive bushland area in which they
live. The project is categorized under civil and mechanical disciplines of engineering.
2. Manufacturing Metro Rail Coaches: The manufacturing of metro rail coaches is another project
undertaken by LMRC. But the project is not performing well from the start. The Earned Value
analysis shows that the project is not achieving its planned cost or progress targets. The quality
requirements are also not properly met. The coach construction facility is located in a remote
engineering. LMRC has collaborated with a renowned Japanese Company to seek assistance
with delivery of few specialized components required for the construction of coaches, but the
transportation of these components over the rough terrain near the project site had to be booked
3. Metro Rail Track Security System: Developing a new computer-based track security system is
a highly complex project. This project is being developed by the technical staff of LMRC, with
that are mutually dependent and does not have a well-defined direction. The new Board of
Directors of the organization aims at developing a more focused strategic direction with a well-
defined project charter and very clear objectives. A strong focus on maximizing good
communication between all parties involved in the project is also given. This project is a small
budget project and deals mainly with software & IT discipline of engineering.
3|Page
In a state like Kerala, where the majority of people rely on public transport, there is utmost
metro rail project previously undertaken by LMRC was successful, but the on-going three (3)
subsidiary projects are facing issues. All the issues needed to be fixed and a revised approach
1. ROAD DEVELOPMENT: The metro rail project is implemented over a stretch of 26.5 km
starting from Petta to Aluva. These are among the most crowed areas of Kochi with huge
number of residents’ and businesses. As the metro rail track construction ended, the
condition of the existing road network deteriorated to an unusable state. Thus the Kerala
government decided to involve LMRC in yet another project; road development alongside
the metro rail track. This would regulate the currently troubling traffic congestion
especially during peak hours of the day and also facilitate easy access of people to metro
stations. Regulating the traffic congestion of these areas is among the key organizational
strategy. The estimated cost of road development project is AUD 13.5 million and is
expected to complete within a period of three (3) years. The acquisition of land and raw
materials, machinery & equipment’s are among the costliest part of the project. The major
Internal Stakeholders’:
a. The Government of Kerala.
b. Kerala State Road Transport Department.
c. Project Manager.
d. Quality Inspector.
e. Technical Manager.
4|Page
External Stakeholders’:
a. Suppliers.
b. Workers.
c. Common people.
The project is performing well in terms of cost, time and the quality, but a number of
stakeholder management issues and environmental issues persists. But the heart of the city
is covered by a bushland and continuing further construction of road would have long-term
impact on the sustainability of the bushland. So the residents around those areas are
concerned about the continuation of project. An alternative route has been suggested by
the Landlords’ Action Committee and is under consideration. It will, however, add an
additional cost of AUD 1.5 million to the project’s total budget and an extra six months on
project timeline.
yet another project undertaken by LMRC and the project fits with the current organizational
constructed in a remote area, which would be away from the hustles of the city. The total
budget of the project is estimated to be AUD 5 million and is expected to complete within
a time frame of 18 months. Without proper surveying of the area, the LMRC identified a
remote area on the outskirts of city for the purpose of constructing a facility that can aid
the manufacturing of metro coaches. The site was considered highly suitable for the
purpose as it is almost abandoned, but no emphasis on the accessibility to the area was
considered. The manufacturing of metro coaches has not yet started because some of the
specialized components needed for the manufacturing of coaches has to be obtained from
5|Page
Japan, but is hindered due to the delay on ordering these components and the difficulty
faced to transport the needed components over the rough terrain near the current location.
Upon conducting Earned Value analysis, it is found that the project though 30 percent
complete is not achieving its planned cost or progress targets. The main stakeholders’
Lack of proper planning and improper communication with the foreign supplier are the
other factors that accounts to the overall failure of the project. There are also other risks
associated with the project such as rudimentary project charter, poor definition of expected
ensure safety and proper functioning of metro rail is a small project that completely fit with
LMRC’s current organizational strategic direction. The estimated cost of the project is
AUD 2 million with a time frame of 12 months to complete. LMRC has planned to install
a new computer-based security management system. This new system has a number of
small interrelated sub-systems that are mutually dependent, which makes the project highly
complex in nature.
Considering the complexity of the project, assistance from specialist contractors are
management about few changes made in the project direction, however, it is to impact
positively to the project. The organizational management requests for scope change are
The major stakeholders’ involved in this project are LMRC, government of Kerala,
additional contractors, organizational management team, workers etc. This project does not
6|Page
have a particular long or short term impact on the environment as such. To date, the project
manager has been able to manage the terms and conditions put forward by the
organizational management team. There has been a change recently on the composition of
the Board of Directors. The new Board has decided to be more focused on the strategic
direction, particularly to develop a proper project charter, strong business cases and very
Project A:
PROJECT CHARTER
Project Description/Plan:
The new road will be constructed alongside the metro rail track over a stretch of 26.5 kms.
LMRC aims to complete the project in an estimated budget of AUD 13.5 million.
7|Page
External Stakeholders’:
a. Suppliers.
b. Workers Union.
c. Common people/Property owners.
Percentage Completed 57 %
8|Page
PROJECT TIMELINE
Business Case:
This is a government funded project that aims to improve the transportation system for the common
people of Kochi. Logitech Metro Rail Corporation(LMRC) is a pioneer organization that has
contributed positively to India’s growth by successfully completing numerous projects across India
and overseas. LMRC’s management team has already succeeded in completing the Metro Rail
Project for Kerala and now has started Road Development as a subsidiary project. The primary
objective of the project is to regulate the traffic congestion and to facilitate the easy access of
people to metro stations. The project began successfully on 18th March 2016. The estimated budget
of the project is AUD 13.5 million and the duration of the project is estimated to be three (3) years.
The project has successfully completed 57 % of its work within the expected budget and time
frame. Already AUD 8.2 million has been invested towards the project. Land acquisition and cost
of raw materials, machinery & equipment’s are the category that needed the investment. Though
the project is progressing well in terms of cost, time and quality, there are a number of
9|Page
sustainability of sustainability and stakeholder management issues that needs attention. At the
heart of the city where the next phase of the road development has to be done, lies an
environmentally sensitive area in which live a number of property owners who are quite concerned
about the negative impact that the project could have on the environment. They are in particular
concerned that a thorough environmental risk assessment has not been undertaken with respect to
the long-term impact that this project could have on the sensitive bushland area. To prevent the
project from succeeding, the property owners’ have formed a Landholders’ Action Committee,
which would determine the future of the project. A less controversial alternative route, which is
acceptable by the Landholders’ Action Committee as well is being developed. The alternative
route, however, cost an additional AUD 1.5 million and an extension of six months to the estimated
project time line. But the extra amount does not concern LMRC by anyways. The financial
supporter of the entire project is Government of Kerala and the government officials has confirmed
their support to continue the project. The officials have estimated that the revenue that could be
generated in a span of 2 years after the successful completion of road development would be much
more than the total amount spent on it. So economically the project is highly feasible.
Internal Stakeholders’:
3. Project Manager.
4. Quality Inspector.
5. Technical Manager.
10 | P a g e
External Stakeholders’:
1. Suppliers / Contractors.
2. Workers Union.
The Government of Kerala is the key shareholder of the project. The government is determined in
providing an urban means of transportation and reducing the traffic congestion of the city. Being
the key stakeholder, the government is responsible for clearing all the legal issues related with
acquisition of land, property owners concerns and so on. The entire project is financially supported
by the Kerala government. Kerala State Road Transport Department is responsible for redirecting
the current traffic to other alternative routes during the resurfacing and repairing phase. Project
Manager is the one who plans the entire project and is in constant contact with the other
stakeholders’, especially the government, contractors and workers. The quality manager ensures
that the project quality is maintained at every phase; from starting to successful completion and
the technical manager is responsible for maintaining the technical aspects of the project.
Contractors, workers and the common people are external stakeholders’, yet play a key role in the
success of the project. The contactors are responsible for supplying with raw materials and
equipment’s. The workers for a big project of this kind has to be skilled and are recruited by the
worker’s union of Kerala. The common people, though are not directly contribute much to the
11 | P a g e
Project B:
PROJECT CHARTER
Project Description/Plan:
12 | P a g e
Percentage Completed 30 %
PROJECT TIMELINE
Business Case:
Manufacturing of metro coaches is another project undertaken by LMRC. This project has an
estimated budget of AUD 5 million and is expected to complete within a time frame of 18 months.
13 | P a g e
The project is 30 percent complete, but currently is delayed due to few issues. Before the actual
manufacturing of coaches, a development facility in a remote area, on the outskirts of the city was
constructed. This was categorized as the initial phase of this project. An evaluation of project progress
was done after the initial stage. It was identified upon conducting Earned Value analysis that the
project was not achieving its planned cost or progress targets, and also has not achieved quality
requirements.
Another concern is about the delay in ordering of few components used in manufacturing coaches
from overseas supplier and the difficulty in transporting these components over the rough terrain near
the project site. The transportation of these vital components from Japan had to be booked much
earlier, but was not taken care of. Other issues are rudimentary project charter, poor definition of
2. Project Manager.
3. Quality Inspector.
4. Overseas Suppliers.
5. Contractors.
6. Workers Union.
The government of Kerala financially supports the entire project. The Kerala government is the
legal authority and acts as the main decision-making body. The project manager plans and executes
the entire project. Project manager will always be in touch with the government through e-mails
14 | P a g e
or direct calls. It is the project manager’s duty to properly plan the project and try best to complete
the project successfully within the estimated time and cost. The quality inspectors are responsible
for monitoring and constantly tracking the progress of each phase of the project. Any progress or
issues related to the project is reported to the project manager by the quality inspectors. In this
project, few specialized parts related to the coach manufacturing had to be obtained from a
Japanese company. They act as an overseas contractor/supplier. Apart from this, local contractors
will also be involved in the project. The labors are provided by the worker’s union of Kerala.
Project C:
PROJECT CHARTER
Project Description/Plan:
The system is highly complex in nature as it has a number of mutually dependent interrelated sub-
systems.
15 | P a g e
of Directors of LMRC.
charter.
b. Additional contractors.
Percentage Completed 40 %
PROJECT TIMELINE
16 | P a g e
Business Case:
Development of a track security system is a small budget project undertaken by LMRC. Developing
a new computer based security system is highly complex in nature as it has a number of small
interrelated subsystems that are mutually dependent. The project is estimated to cost AUD 2 million
upon completion and has to be delivered in a year’s time. The project completed 40 percent with few
negligible issues. There has been a recent change in the composition of the Board of Directors of the
organization. The new board decided to develop a more focused strategic direction with strong
business case, well defined project charters and clear objectives. The project is economically feasible.
a. Government of Kerala.
b. Additional contractors.
17 | P a g e
The government of Kerala financially supports the entire project. The Kerala government is
the legal authority and acts as the main decision-making body. Additional contractors are
involved in this project keeping in mind its complex nature. Organizational management is a
special body of computer engineers, analysists and system developers and so on. They are
solely responsible for the development of the new computer based security system. Additional
All the three projects have issues that needs rectification so as to complete the project
successfully within the estimated time and budget. Shown below are the issues with each
Project A:
Issues:
Solutions:
A proper planning about the area of construction had to be done during the planning phase.
18 | P a g e
A general meeting should be organized and all the stakeholders’ must be made introduced
to each other to prevent future conflicts. Project manager should be able to manage the
An alternative route that could minimize the impact on the sensitive bushland could be
Proper negotiations with the property owners about the new strategic plans of the
organization could solve the disagreement issues and take the project to a success.
These are the few issues that the road development project is currently facing. Apart from these,
there is absolutely nothing wrong in the project. It is progressing well in terms of time, cost and
quality. However, the new plans have to executed properly and special care should be taken to
maintain the expenses. Upon following the revised plan, the project would definitely complete
successfully. So, there is absolutely nothing wrong in undertaking any future projects by LMRC.
Project B:
Issues:
Earned Value analysis shows that the project is not achieving its planned cost or progress
targets.
Difficulty in transporting these components over the rough terrain near the project site.
Lack of tradespeople with the requisite set of skills to install the components.
The project has a very basic business case, rudimentary project charter and poor definition of
19 | P a g e
Risk of significant penalties to be levied if the project is not completed within the estimated
time.
Solutions:
Lack of proper communication between the stakeholders, project engineers and workers is the
main reason for not achieving the projects planned cost or progress targets.
The lack of coordination between the project manager and the overseas supplier has caused a
delay in ordering of few vital components needed for the project. Delay in booking will affect
the project negatively, but still can be brought back to the track with proper planning.
Skilled labor force must be utilized in installing the components. Help from overseas
A well explained business case, project charter and a well-defined definition of expected
If the issues are correctly addressed with good results, then the project could be a success and
LMRC should be doing similar projects in the future without repeating the same mistakes again.
Project C:
Issues:
The system has a number of interrelated sub-systems that are mutually dependent.
20 | P a g e
Solutions:
A well-defined direction should be set and understood before beginning of the project.
The new board of should review the project and understand the previously committed mistakes.
A good communication should be established between all parties involved in the project.
If the new Board of Directors are successful in proper reviewing of the project and decide quickly
the best way to react to cut down the loss and finish the project within the estimated time, then
there is nothing wrong for the organization to take up similar projects in future.
QUESTION 1 (b)
LMRC has always been delivering successful projects. But now the organization has decided to
move in a radical new direction considering the type of projects undertaken currently. Most of the
projects undertaken are big budget and would definitely create huge revenue for the company. As
the head of the new strategic development conducted by the organization, I have been responsible
for 6 new projects. Three (3) projects out of six (6) are smoothly heading towards successful
completion. But the other three (3) are being delayed or interrupted due to few issues. These issues
The following are the issues that are being detected after analysis of each project:
21 | P a g e
Road development is a subsidiary project to the previously completed Metro Rail Project in the
city of Kochi, Kerala. The project had a proper plan before starting and is almost half way through.
The project began on 18th March 2016 and is expected to complete successfully within 3 years of
time period. The early analysis shows that the project was progressing well in terms of cost, time
and quality. But during the second phase of the project, a number of sustainability and stakeholder
management issues arose. The property owners who lived in the area, had concerns about the
proper completion of environmental risk assessment. The heart of the city is covered by a bushland
and continuing further construction of road would have a long-term impact on the sustainability of
the bushland. So the residents around those areas are concerned about the continuation of project.
An alternative route has been suggested by the Landlords’ Action Committee and is under
consideration. It will, however, add an additional cost of AUD 1.5 million to the project’s total
The initial phase of this project is to develop a coach manufacturing facility in a remote area
outside the hustles of the city. The entire project is estimated to cost AUD 5 million and has to be
completed within the time frame of 18 months. The project began on 28th January 2016. Upon 30
percent completion, an Earned Value analysis was conducted. The analysis shows that the project
is not achieving its planned cost or progress targets. Also the major delay in starting the
manufacturing phase is due to the unavailability of some specialized components that would be
necessary in the manufacturing process of the coaches. These components have to be obtained
from an overseas supplier. The delay in ordering the components and the difficulty of transporting
it through the rough terrane near the manufacturing facility have had a cumulative damage to the
22 | P a g e
overall progress of the project. Also the lack of having tradespeople with the requisite set of skills
to install them has just increased the concerns. The project also has other risks such as, basic
business case, rudimentary project charter and poor definition of expected outcomes.
Metro rail track security system is a small budget project undertaken by LMRC. The entire project
has an estimated budget of AUD 2 million. The target is to develop a new computer based security
management system. But the computer based security management system has a number of small
interrelated sub-systems that are mutually dependent, thus making the entire project highly
complex. There are few differences between the development staff and organizational
management about the direction of the project. however, those concerns could have a positive
impact on the overall success of the project. The organizational management has requested for
scope change and the project manager, till date was successful in managing the requests. There
has been a recent change in the composition of the Board of Directors of the organization. The
new board decided to develop a more focused strategic direction with strong business case, well
Though these projects have few issues, my proposed solutions are highly feasible and could
The current environmental sustainability issue and the associated objection on continuation of the
project by the property owners can be sorted out by conducting a proper environmental risk
assessment. If the risk assessment shows long-term impact on the environment, then the
organization can opt for the additional route that is being suggested and agreed upon by the
23 | P a g e
property owners and the Landholders’ Action Committee. The additional cost could easily be
incurred within months after successful completion of the project. The solution is among the most
This project has not met planned cost or progress targets. Even the quality standards are not up to
the mark. All these issues arise due to lack of proper planning and involving stakeholders’, project
manager, quality inspectors, contractors etc during each phase of the project. Thus involvement of
project stakeholders’, project manager and quality inspectors is highly important. Feedbacks about
each stages of the project should be analyzed and errors must be detected. The delay in ordering
should not have happened. Now recruitment of skilled labors must be done quickly to facilitate the
manufacturing process without any further delay. The delivery of components should be made
quicker by requesting the overseas supplier. High-standard business case and a well-defined
project charter must be drafted in order to avoid confusions or delays. If the solutions are taken
into consideration, then the project can be highly feasible with a little effort from the entire team.
The complex nature of this project due to the presence of a number of interrelated sub-systems that
are mutually dependent, makes it a highly difficult project to execute. The initial step to be taken
is to involve a special team of computer software expertise to develop the new intended computer
based security management system. With the recent change in the composition of Board of
Directors of the organization, it has become much easier to approach the entire project in a different
and better way. My suggestion is to conduct a detailed review of the work done so far by the newly
formed body, identify the errors and come up with perfect solutions. A high necessity of
24 | P a g e
establishing good communication between all parties of the project is needed. The new body
should provide necessary resources to complete this project even at a potential loss, which at this
From an overall program management perspective, all the three projects can be successfully
completed if a proper plan is drawn. A well-defined business case and project charter must be
present. Establishment of proper communication among all the stakeholders of the project must be
ensured. Proper monitoring of each project to understand the status should be frequently done.
QUESTION 2
Advancement in Technology:
Each new day passes by witnessing the advent of new technologies. Project management now is
based on human resources and individual skills. However recent technological advancements in
the information technology field has paved way for the introduction of project management
software’s. This software’s are precise in decision making and calculations. With the help of these
software’s Project managers will be able to improve the quality and standards of the projects they
work on. In time, different projects undertaken by the project managers becomes complex. At
present Project Management includes very little use of software’s. Project managers across the
world still use traditional project management methods and consider these software’s as being an
aid rather than being the driving force behind the actual project management. Complex nature of
25 | P a g e
future projects will definitely make the project managers to rely on software driven project
management.
Professional development of Project Managers will be focused mainly on reality based learning
and on-job training programs. Project Managers will be trained in such a way that they will be able
to perform and apply what they learned to their current projects. In other word’s the Project
Managers will be trained according to the project which Is presently in hand unlike the current
way of teaching them general concepts. Universities that currently offer Project Management
courses will have to alter their way of teaching so as to concentrate more on making the course
Projects in earlier days was comprised only of a single discipline of engineering. Be it civil
mechanical, chemical, electrical, the engineers didn’t have the need to collaborate much. However,
in the future, a college degree and specialization in a particular engineering discipline might not
be enough to successfully complete a project. The complexity of the modern projects will demand
Advancement in Technology:
In order to cope up with the advance in technology, universities that offer project management
courses should mandatorily include a program in project management software’s. As a result, all
students will be able to have a basic knowledge on project management software’s. Software’s are
26 | P a g e
usually made on an evolutionary basis. They get updated every now and then according to
advancement in science and technology. Evolution in software’s either make them easier to use or
more complex in nature. This can affect the ability of an average project manager. So as to get rid
of the problem every project management team should be employed with a software specialist.
This not only increases the efficiency of the team, it also improves the quality and overall outlook
of the project.
Project management teams play a critical role in driving operation efficiencies. MNC’s will then
be in hunt for a project manager who has various other skills such as negotiation, communication,
critical thinking, change management and imperative decision making and leadership skills.
Universities that offer project management courses should not only teach course material but also
teach values that are essential for a project manager to develop interpersonal and intrapersonal
skills. A pattern on what goes on around the world should be noted and the upcoming project
managers should be given training in developing trends rather than still focusing on basic project
management concepts. Introducing a more pragmatic and prudent approach which will help in
With progress in science and technology at its peak and never ending, it would be difficult for a
particular individual with a certain specialization to understand and comprehend all aspects of a
project. Institutes that trains project managers should take up this as a serious issue and start
environment is affected by various factors like social, economic and technological aspects.
27 | P a g e
Therefore, a change in any of these factors can be highly influential to the organizational
environment. As mentioned earlier, Project Management in the future will be more daunting due
to the rapid technological advancements and therefore project managers are to be trained in such
a way that they can be able overcome the complexity that they are faced with in the projects that
A project manager needs both structural elements and change management elements in order to
succeed with the project and realize the benefits of the project. Generally, the project managers
aim is to guarantee the deliverables and keep focus on the product. What is as of now seen and
supported is for the project manager to concentrate on quality to a higher degree and to choose the
project management team likewise. Thus, significance should be given to “why the project has
been initiated” rather than “what the project is to deliver”. In order to progress responsibly, project
managers should just try to survive now and thrive later, they have to consider demographics,
Project management educators should move beyond the conventional ways of educating the
upcoming project managers by taking up a broader learner based practical approach. A central IT
support system with unquestionable knowledge base should be adopted to improve efficiency of
project management teams in top organizations. Even greater emphasis will be given to human
resource development. Project managers will undergo progressive strategic planning sessions in
order to promote efficient strategic alignment. With the help of education, improvements in the
field of science and technology we can predict the changing nature of project management teams.
Team leaders in the future will be able to understand the dynamics of the people in the team and
at all levels including the cognitive structures that create and influence decision making. Also
28 | P a g e
globalization will play a major part in the progress of the project management fraternity. As the
size and complexity of a project increase companies and people from different companies will
work together even when placed miles apart. Even though this might pose a unique challenge in
the form of eliminating an age old concept of “hands on management” which is still considered
With the ever changing face of technology and continuous increase in demands for better and safe
lifestyle, the area of project management will continue to play a significant role in the changing
REFERENCES
http://www.mpug.com/articles/10-trends-ruling-project-management-that-will-
affect-your-future/
http://implementconsultinggroup.com/inspiration/articles/project-manager-of-the-
future/
http://www.pmi.org/learning/future-of-project-management/future-leaders-will-
need-to-change-the-way-they-manage-their-teams.aspx
Watch, P. (2016) Project monitoring and control phase in planning management. Available
at: http:<//www.projectmanagementwatch.co.uk/project-monitoring-and-control-phase-
29 | P a g e