Open navigation menu
Close suggestions
Search
Search
en
Change Language
Upload
Sign in
Sign in
Download free for days
0 ratings
0% found this document useful (0 votes)
127 views
NEC Core Clause
NEC Core Clause
Uploaded by
Jhonny Wanky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download now
Download
Save NEC Core Clause For Later
Download
Save
Save NEC Core Clause For Later
0%
0% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
0 ratings
0% found this document useful (0 votes)
127 views
NEC Core Clause
NEC Core Clause
Uploaded by
Jhonny Wanky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download now
Download
Save NEC Core Clause For Later
Carousel Previous
Carousel Next
Save
Save NEC Core Clause For Later
0%
0% found this document useful, undefined
0%
, undefined
Embed
Share
Print
Report
Download now
Download
You are on page 1
/ 24
Search
Fullscreen
- a® TCC 3 Engineering and Construction Contract CORE CLAUSES od General Actions 10 8 40.4 The Empioyer, the Contractor, the Project Manager and the Supervisor shall, act as stated ‘in this contract and in a spirit of mutual trust and co-operation. Identified and defined 11 terms 14.1 In these conditions of contract, terms identified in the Contract Data are in italics and defined terms have capital initials. 11.2 (1) The Accepted Programme Is the programme identified In the Contract Data or is the latest programme accepted by the Project Manager. The latest programme accepted by the Project Manager supersedes previous Accepted Programmes. (2) Completion is when the Contractor has * done all the work which the Works Information states he is to do by the Completion Date and * corrected notified Defects which would have prevented the Employer from using the works and Others from doing their work. If the work which the Contractor Is to do by the Completion Date Is not stated in the Works Information, Completion is when the Contractor has done all the work necessary for the Employer to use the works and for Others to do their | work. 8 (3) The Completion Date is the completion date unless later changed in accordance with this contract. (4) The Contract Date is the date when this contract came into existence. (5) A Defect is + part of the works which is not in accordance with the Works Information | 2 or 8 + a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor's design which the Project. \_ Manager has accepted. (6) The Defects Cortificate is either a list of Defects that the Supervisor has notified before the defects date which the Contractor has not corrected or, if there are no such Defects, a statement that there are none. (7) Equipment is items provided by the Contractor and used by him to Provide the Works and which the Works Information does not require him to include in the works. (8) The Fee is the sum of the amounts calculated by applying the subcon- tracted fee percentage to the Defined Cost of subcontracted work and the direct fee percentage to the Defined Cost of other work. www.neccontract.com © copyright nec 2005 3=" N1EC 3 engineering and Construction Contract main option clauses secondary option clauses cost ‘components contract data Interpretation and the law 12 424 42.2 12.3 12.4 (9) A Key Date is the date by which work is to meet the Condition stated. The Key Date is the key date stated in the Contract Data and the Condition is the condition stated in the Contract Data unless later changed in accordance with this contract, (10) Others are people or organisations who are not the Employer, the Project Manager, the Supervisor, the Adjudicator, the Contractor or any employee, Subcontractor or supplier of the Contractor. (44) The Parties are the Employer and the Contractor. (12) Plant and Materials are items intended to be included in the works, (13) To Provide the Works means to do the work necessary to complete the works in accordance with this contract and all incidental work, services and actions which this contract requires. (14) The Risk Register is a register of the risks which are listed in the Contract Data and the risks which the Project Manager ot the Contractor has notified as an early warning matter. It includes a description of the risk and a description of the actions which are to be taken to avold or reduce the risk. (15) The Site is the area within the boundaries of the site and the volumes above and below it which are affected by work included in this contract. (16) Site Information is information which * describes the Site and its surroundings and * is in the documents which the Contract Data states it is in. (47) A Subcontractor is a person or organisation who has a contract with the Contractor to * construct or install part of the works, * provide a service necessary to Provide the Works or * Supply Plant and Materials which the person or organisation has wholly or partly designed specifically for the works. {18) The Working Areas are those parts of the working areas which ere ‘* necessary for Providing the Works and * used only for work in this contract unless later changed in accordance with this contract, (1.9) Works information is information which either * specifies and describes the works or + states any constraints on how the Contractor Provides the Works and is either ‘* in the documents which the Contract Data states itis * in an instruction given in accordance with this contract. In this contract, except where the context shows otherwise, words in the Singular also mean in the plural and the other way round and words in the masculine also mean in the feminine and neuter. This contract is governed by the faw of the contract. No change to this contract, unless provided for by the conditions of contract, has effect unless it has been agreed, confirmed in writing and signed by the Parties. This contract is the entire agreement between the Parties. 4 © copyright nec 2008 ‘www.neccontract.comcore Clauses “” NEC 3 ‘Communications The Project Manager and the Supervisor Adding to the Working ‘Areas, Early warning www.neecontract.com 43 13.4. 13.2 133 13.4 13.5 13.6 13.7 13.8 14 14.4 14.2 14.3 14.4 45 45.1 16 16.1. Each instruction, certificate, submission, proposal, record, acceptance, notification, reply and other communication which this contract requires Is ‘communicated in a form which can be read, copied and recorded. Writing is in the language of this contract. ‘A. communication has effect when itis received at the last address notified by the recipient for receiving communications or, if none is notified, at the address of the recipient stated in the Contract Date, If this contract requires the Project Manager, the Supervisor or the Contractor to reply to @ communication, unless otherwise stated in this contract, he replies within the period for reply. The Project Manager replies to a communication submitted or resubmitted to him by the Contractor for acceptance. If his reply is not acceptance, the Project Manager states his reasons and the Contractor resubmits the commu- nication within the period for reply taking account of these reasons. A reason for withholding acceptance is that more information is needed in order to assess the Contractor's submission fully. ‘The Project Manager may extend the period for reply to a communication if the Project Manager and the Contractor agree to the extension before the reply Is due. The Project Manager notifies the Contractor of the extension which has been agreed. The Project Manager issues his certificates to the Employer and the Contrac- tor. The Supervisor issues his certificates to the Project Manager and the Contractor. ‘A notification which this contract requires is communicated separately from ‘other communications. ‘The Project Manager may withhold acceptance of a submission by the Contractor. Withholding acceptance for a reason stated in this contract is not a compensation event. The Project Menager's or the Supervisor's acceptance of a communication from the Contractor or of his work does not change the Contractor's responsi- bility to Provide the Works or his liability for his design. The Project Manager and the Supervisor, after notifying the Contractor, may delegate any of their actions and may cancel any delegation. A reference to an action of the Project Manager or the Supervisor In this contract includes an action by his delegate. The Project Manager may give an instruction to the Contractor which changes the Works Information or @ Key Date. ‘The Employer may replace the Project Manager or the Supervisor after he has Notified the Contractor of the name of the replacement. ‘The Contractor may submit a proposal for adding an area to the Working Areas to the Project Manager for acceptance. A reason for not accepting is that the proposed area is either not necessary for Providing the Works or used for work not in this contract. ‘The Contractor and the Project Manager give an early warning by notifying the other as soon as either becomes aware of any matter which could increase the total of the Prices, delay Completion, delay meeting a Key Date or impair the performance of the works in use. ‘© copyrightnec 20055 core cee main ‘option clauses. ‘secondary option clauses ‘cost ymponents iz ‘contract data
You might also like
NEC4 Compensation Event Template
PDF
100% (1)
NEC4 Compensation Event Template
8 pages
Article No. 1 To Go Retrospective, or To Go Prospective by Chris Larkin
PDF
No ratings yet
Article No. 1 To Go Retrospective, or To Go Prospective by Chris Larkin
3 pages
Module 2
PDF
No ratings yet
Module 2
120 pages
Contract Negotiation Data
PDF
No ratings yet
Contract Negotiation Data
1 page
Appendix I Contractor ' S Overhead Costs
PDF
No ratings yet
Appendix I Contractor ' S Overhead Costs
5 pages
Contract Management
PDF
No ratings yet
Contract Management
2 pages
Why You Need Mep Coordinat
PDF
No ratings yet
Why You Need Mep Coordinat
7 pages
Hudson 1
PDF
No ratings yet
Hudson 1
9 pages
Valuation Method
PDF
No ratings yet
Valuation Method
3 pages
Calculation of HOOH 1
PDF
No ratings yet
Calculation of HOOH 1
2 pages
Network Diagrams
PDF
50% (2)
Network Diagrams
8 pages
1 - Mr. Toby Randle - FIDIC Red and Pink Books Development
PDF
No ratings yet
1 - Mr. Toby Randle - FIDIC Red and Pink Books Development
15 pages
SCL D176 Bailey Jan15
PDF
No ratings yet
SCL D176 Bailey Jan15
28 pages
Claims On Construction Projects - Quantification and Prevention - Notes
PDF
No ratings yet
Claims On Construction Projects - Quantification and Prevention - Notes
2 pages
FIDIC Seminar Brochure
PDF
No ratings yet
FIDIC Seminar Brochure
4 pages
هيئة البيئة ابوظبي
PDF
No ratings yet
هيئة البيئة ابوظبي
41 pages
CDR.05 Appraisal of Contractual Claims: Dr. Gianluca Di Castri
PDF
No ratings yet
CDR.05 Appraisal of Contractual Claims: Dr. Gianluca Di Castri
9 pages
NEC3 ECC Contract
PDF
No ratings yet
NEC3 ECC Contract
83 pages
Waste-Management EDITED
PDF
No ratings yet
Waste-Management EDITED
20 pages
Standard Forms of Contract
PDF
No ratings yet
Standard Forms of Contract
3 pages
NEC Contract Option E
PDF
No ratings yet
NEC Contract Option E
7 pages
Solid Waste Management 2011
PDF
100% (1)
Solid Waste Management 2011
10 pages
Attachment 2.1 - EOT Final Submission Report Prepared by SCM Consultancy (002)
PDF
No ratings yet
Attachment 2.1 - EOT Final Submission Report Prepared by SCM Consultancy (002)
46 pages
Eot Claim
PDF
No ratings yet
Eot Claim
5 pages
Environmental Impact Assessment EIA of N
PDF
No ratings yet
Environmental Impact Assessment EIA of N
136 pages
Mosey, David. PPC 2000 - The First Standard Form of Contract For Project Partnering
PDF
No ratings yet
Mosey, David. PPC 2000 - The First Standard Form of Contract For Project Partnering
18 pages
Unit-6 Environmental Services
PDF
No ratings yet
Unit-6 Environmental Services
31 pages
Only The Content of The FIDIC Subcontract 2009
PDF
No ratings yet
Only The Content of The FIDIC Subcontract 2009
8 pages
Company Name Div: Elec/Mech/Civil/ Interior: Internal Approval For Material Submittal
PDF
No ratings yet
Company Name Div: Elec/Mech/Civil/ Interior: Internal Approval For Material Submittal
6 pages
Structure of A Construction Claim
PDF
No ratings yet
Structure of A Construction Claim
3 pages
Dispute in Construction - Contr
PDF
No ratings yet
Dispute in Construction - Contr
8 pages
Construction Law From Beginner To Practitioner Second Edition Jim Mason instant download
PDF
No ratings yet
Construction Law From Beginner To Practitioner Second Edition Jim Mason instant download
89 pages
Eichleay Formula Calculations
PDF
No ratings yet
Eichleay Formula Calculations
3 pages
JBCC C and Cguide 2014 03 Complete 2
PDF
No ratings yet
JBCC C and Cguide 2014 03 Complete 2
74 pages
Employer's Requirements
PDF
No ratings yet
Employer's Requirements
2 pages
Employer: Contract No. NE/2017/07 Cross Bay Link, Tseung Kwan O - Articles of Agreement Main Bridge and Associated Works
PDF
No ratings yet
Employer: Contract No. NE/2017/07 Cross Bay Link, Tseung Kwan O - Articles of Agreement Main Bridge and Associated Works
20 pages
A Guide To Claims
PDF
100% (1)
A Guide To Claims
13 pages
Orange Book 2nd Edition 2011 Addendum
PDF
No ratings yet
Orange Book 2nd Edition 2011 Addendum
4 pages
Mw21 - 9c Respond To The Contractors Proposal For A Possible Variation
PDF
No ratings yet
Mw21 - 9c Respond To The Contractors Proposal For A Possible Variation
3 pages
Chapter4 Project Time Management
PDF
No ratings yet
Chapter4 Project Time Management
28 pages
JBCC NS Subcontract 2013 Edition
PDF
No ratings yet
JBCC NS Subcontract 2013 Edition
32 pages
Nec4 Termination Notice Example
PDF
No ratings yet
Nec4 Termination Notice Example
2 pages
NEC 3 - Pricing Template PT2024 - 01
PDF
No ratings yet
NEC 3 - Pricing Template PT2024 - 01
43 pages
Section V - Contract Adminstration Procedures Major Buildings
PDF
No ratings yet
Section V - Contract Adminstration Procedures Major Buildings
13 pages
Mistake Contract Law
PDF
No ratings yet
Mistake Contract Law
25 pages
Slide Management Contracting
PDF
No ratings yet
Slide Management Contracting
3 pages
Module 3 & 4
PDF
No ratings yet
Module 3 & 4
88 pages
Nec3-Ecc Template (Revnov2015) (3) Design and Construct Weather Protection Structure
PDF
No ratings yet
Nec3-Ecc Template (Revnov2015) (3) Design and Construct Weather Protection Structure
45 pages
7 Corbett UK - Clause-7 - Details
PDF
No ratings yet
7 Corbett UK - Clause-7 - Details
4 pages
Assignment-EMCM (Contract Management) Q2
PDF
No ratings yet
Assignment-EMCM (Contract Management) Q2
36 pages
Progress Claims
PDF
No ratings yet
Progress Claims
43 pages
NEC4 ECC Contractor Submission Workflow
PDF
No ratings yet
NEC4 ECC Contractor Submission Workflow
9 pages
Construction Contract Template 1
PDF
No ratings yet
Construction Contract Template 1
8 pages
Evs PPT Eia 91-100
PDF
No ratings yet
Evs PPT Eia 91-100
30 pages
Project Scheduling
PDF
No ratings yet
Project Scheduling
61 pages
International Construction Contract Law - 2014 - Klee - Appendix B Sample Letters
PDF
No ratings yet
International Construction Contract Law - 2014 - Klee - Appendix B Sample Letters
19 pages
NEC 3 Clauses
PDF
No ratings yet
NEC 3 Clauses
53 pages
NEC 3 Engineering and Construction Contract - Grupo 1
PDF
No ratings yet
NEC 3 Engineering and Construction Contract - Grupo 1
3 pages
Full Set - CV04 - Nec3
PDF
No ratings yet
Full Set - CV04 - Nec3
258 pages
Section - 30001
PDF
No ratings yet
Section - 30001
25 pages
Rise and Fall Method To Reduce A Leveling Field Book Page: Name BS IS FS Rise Fall Corr Fin. Height 5
PDF
No ratings yet
Rise and Fall Method To Reduce A Leveling Field Book Page: Name BS IS FS Rise Fall Corr Fin. Height 5
1 page
Strain in Balanced Condition.
PDF
No ratings yet
Strain in Balanced Condition.
6 pages
History of Road Development
PDF
100% (1)
History of Road Development
4 pages
Danny Tirta Winata 1306437025 Sabrina Nurul Hidayah 1306437145
PDF
No ratings yet
Danny Tirta Winata 1306437025 Sabrina Nurul Hidayah 1306437145
4 pages
Problem Formulation
PDF
No ratings yet
Problem Formulation
6 pages
Shallow Foundation
PDF
100% (1)
Shallow Foundation
36 pages
Eco Waste Management
PDF
No ratings yet
Eco Waste Management
9 pages
Data Calculation H-05
PDF
No ratings yet
Data Calculation H-05
14 pages
Properti Material Modul C 1-5
PDF
No ratings yet
Properti Material Modul C 1-5
10 pages
Laporan Mekanika Fluida H-02
PDF
No ratings yet
Laporan Mekanika Fluida H-02
19 pages
Civil Engineering Building Construction Materials Paper Masonry
PDF
No ratings yet
Civil Engineering Building Construction Materials Paper Masonry
8 pages
Aria Aradhea Academic Writing
PDF
No ratings yet
Aria Aradhea Academic Writing
2 pages