1. The document provides cost analyses and unit prices for installing different types of roofing materials, including bitumen roof tiles and ridge capping. 2. Unit prices are provided for labor costs by role, materials costs per unit, total costs, overhead/profit percentages, and final unit prices for various roofing installation jobs. 3. Specifications are given for the pitch/slope of the roof and dimensions of the materials for each type of installation analyzed.

Uploaded by

Supardi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
610 views

Ahs 2019

1. The document provides cost analyses and unit prices for installing different types of roofing materials, including bitumen roof tiles and ridge capping. 2. Unit prices are provided for labor costs by role, materials costs per unit, total costs, overhead/profit percentages, and final unit prices for various roofing installation jobs. 3. Specifications are given for the pitch/slope of the roof and dimensions of the materials for each type of installation analyzed.

Uploaded by

Supardi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Analisa Harga Satuan

2 o o
1m Pasang Atap Bitumen Bergelombang Monolayer 3 mm ( kemiringan atap Minimum 10 - 15 )
Uk. 200 x 95 x 0.30 cm, Jarak Rangka Gording atau Reng max. 45 cm
HARGA JUMLAH
No. URAIAN PEKERJAAN SATUAN SATUAN KOEFISIEN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 95,000.00 0.140 13,300.00
2 Tukang kayu OH 110,000.00 0.070 7,700.00
3 Kepala Tukang OH 135,000.00 0.007 945.00
4 Mandor OH 165,000.00 0.007 1,155.00
Jumlah 23,100.00
B BAHAN
1 Atap Bitumen Bergelombang Monolayer 3 mm Lbr 155,000.00 0.748 115,862.50
2 Paku atau Sekrup bh 1,100.00 9.150 10,065.36

Jumlah 125,927.86
C Jumlah A + B 149,027.86
D Overhead & Profit 15% 22,354.18
E Harga Satuan Pekerjaan ( C+D) 171,382.04

2 o
1m Pasang Genteng Bitumen Bergelombang Monolayer 3 mm ( kemiringan atap > 15 )
Uk. 106 x 40 x 0.30 cm, Jarak Rangka Gording atau Reng max. 32 cm
HARGA JUMLAH
No. URAIAN PEKERJAAN SATUAN SATUAN KOEFISIEN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 95,000.00 0.200 19,000.00
2 Tukang kayu OH 110,000.00 0.100 11,000.00
3 Kepala Tukang OH 135,000.00 0.010 1,350.00
4 Mandor OH 165,000.00 0.010 1,650.00
Jumlah 33,000.00
B BAHAN
1 Genteng Bitumen Bergelombang Monolayer 3 mm Lbr 48,800.00 3.724 181,716.56
2 Paku atau Sekrup bh 1,100.00 16.150 17,765.00

Jumlah 199,481.56
C Jumlah A + B 232,481.56
D Overhead & Profit 15% 34,872.23
E Harga Satuan Pekerjaan ( C+D) 267,353.79
00/00/2018 • Confidential •1
Analisa Harga Satuan
2 o
1m Pasang Genteng Bitumen Bergelombang Memanjang Monolayer 3 mm ( kemiringan atap > 10 )
Uk. 195 x 96 x 0.30 cm, Jarak Rangka max. 46 cm
HARGA JUMLAH
No. URAIAN PEKERJAAN SATUAN SATUAN KOEFISIEN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 95,000.00 0.140 13,300.00
2 Tukang kayu OH 110,000.00 0.070 7,700.00
3 Kepala Tukang OH 135,000.00 0.007 945.00
4 Mandor OH 165,000.00 0.007 1,155.00
Jumlah 23,100.00
B BAHAN
1 Genteng Bitumen Bergelombang Monolayer 3 mm Lbr 145,000.00 0.723 104,885.75
2 Paku atau Sekrup bh 1,100.00 11.765 12,941.18

Jumlah 117,826.93
C Jumlah A + B 140,926.93
D Overhead & Profit 15% 21,139.04
E Harga Satuan Pekerjaan ( C+D) 162,065.97

Pemasangan 1 m panjang nok bitumen Monolayer


HARGA JUMLAH
No. URAIAN PEKERJAAN SATUAN SATUAN KOEFISIEN HARGA
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 95,000.00 0.084 7,980.00
2 Tukang kayu OH 110,000.00 0.125 13,750.00
3 Kepala Tukang OH 135,000.00 0.013 1,755.00
4 Mandor OH 165,000.00 0.004 660.00
Jumlah 24,145.00
B BAHAN
1 Nok / Ridge Onduline Lbr 82,000.00 1.438 117,875.00
2 Sekrup / Paku bh 1,100.00 10.000 11,000.00
Jumlah 128,875.00
C Jumlah A + B 153,020.00
D Overhead & Profit 15% 22,953.00
E Harga Satuan Pekerjaan ( C+D) 175,973.00