Traction Transformer 3011
Traction Transformer 3011
0002/TRANSF-02
SPECIFICATION NO.
DMES-T/0002/DMRC-E-PS-TRANSF-02
SPECIFICATIONS FOR
TRACTION TRANSFORMER
Issued on:
Date Stage
17th May 2017 Draft-1.
31st august 2017 Draft-2.
20th sept 2017 Draft-3.
30th Oct 2017 Draft-4.
Page 1 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Stage Date
Draft -1. 17-May-17
Draft -2 31-Aug-17
Draft -3 20-Sep-17
Draft -4 30-Oct-17
Page 2 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 3 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
TRACTION TRANSFORMER
SCOPE
These specifications are applicable to Traction Transformer of 2-phase 220 kV / 132 kV / 110 kV /
66 kV (for line 2A) primary voltage and 1-phase, 27.5KV secondary voltage. Traction Transformer
shall be designed for outdoor installation and for operation at frequencies of 50 Hz.
The Traction Transformer shall be complete with all Parts, Fittings, and oil for the first filling, and
accessories necessary for its efficient operation, including mounting frame work of steel. All such
Parts, Fittings and Accessories shall be deemed to be within the scope of this Specification, whether
specifically mentioned or not. The Traction Transformer shall be of proven design.
1. Governing Specifications
The Traction Transformers shall comply with the standards of the International Electro
Technical Commission (IEC60076) or equivalent Indian standards
1.1 Standards
The Traction Transformer shall satisfy the requirements given below and shall also comply
with standards in force when they are manufactured, particularly which are in the following
table. (unless otherwise stipulated in the specifications, the latest version of the following
standards shall be applicable): -
S. No. Specification No. Title of Specification
1. IEC:60076-1,2,3,4,5 &7 Power Transformer
2. IEC : 60214 Tap changer for power transformer
3 IEC 60296 Insulating oil for Transformer
IS 12463:1988 along with
Insulating oil for Transformer (revise for Ester
3A additional requirements of
Oil)
RDSO
3B IEC 61099 Synthetic Ester Oil (SEO) for power transformers
3C IS16081 Synthetic Ester Oil (SEO) for power transformers
4 IS335 Insulating oil for Transformer
5 IEC 60028 Conductor for Insulated cable
6 IEC 60137 Insulating Bushing for rated Voltage above 1KV
7 IEC 617-2 Earthing terminal
Page 4 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
1.2 Abbreviations
TT- Traction Transformer
IEC- International Electro-technical Commission
IS- Indian Standard
OLTC- On Load Tab Changer
ONAN- Oil Natural Air Natural
ONAF- Oil Natural Air Force
NIFPS –Nitrogen Injection Fire Protection System
2. Technical Requirement
2.1 Characteristics:-
The Traction Transformers at TSS shall meet the following characteristics:
- 2-phase Primary winding of 220kV/132kV/110kV/66kV (for line 2A)
- 1-phase secondary winding 0f 27.5KV
- Entirely submerged in mineral oil tank
- Outdoor type, suitable for tropical conditions, satisfying the climatic conditions of
Mumbai.
- On load tap changer on primary windings
- Possibility of various overload conditions
- Separated oil conservator with aircell.
- Cooling by natural oil circulation and banks of radiators mounted on the tank
- Both transformers shall be identical
- Transformer noise level should not exceed 75dB measured at a distance of 1.5 m
- The Vector group shall be I. i.
- Should have symphonic filter.
- The two transformers at any Traction Substation are not meant to work in parallel
Page 5 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 6 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
vessel. The voltage ratio shall be checked according to the guaranteed figures and the
tolerances stipulated in the standards.
Page 8 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 9 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
In case the transformer losses during tests are found greater than the values guaranteed in
the offer, a consolidated penalty shall be paid by the contractor, according to the following
formula (for the tolerance permissible according to IEC standard):
2.11 Windings
The winding conductors shall be made of best quality high conductivity electrolytic copper,
in compliance with the standard (IEC 60028) requirements.
Both windings, primary and secondary, shall be designed to withstand over-voltages and
over-currents in case of direct short-circuit across the medium voltage terminals with the
primary winding line for three seconds.
Construction shall take into account electrodynamics and thermal constraints specific to
railway traction duty.
The adjustments windings shall be designed specifically to withstand direct short-circuit of
all part of the adjustment turns that may occur at the contact plates of the on-load tap
changer. The windings, connections and terminal links shall be properly brazed so as to
withstand the shocks and vibrations that may occur during transport or short-circuit.
Tests on samples shall be carried out and results submitted for approval before starting
assembly of the transformer windings. Current density for each winding shall be not more
than 2.5 A/mm². The insulation material used for the transformer windings and connections
shall be at least of class A.
shall be realized in conformity with the IEC 60137 standard. Special care shall be taken
against transmission of vibrations by employing a damping system and suitable fittings.
The design shall take into account the ease of overhaul. It should be possible to withdraw
and to remove the transformer at ease. Interchangeability between transformers shall be
achieved through the use of identical elements.
The link between secondary terminals of the transformer and the 25 kV switchgear shall be
made by cables connected directly at the outside of the secondary bushing. Bushings shall
be realized in conformity with the IEC 60137 standard.
NOTE: -Employer may go for primary and secondary connections through Dry plug
type termination on the transformer as applicable. The vendor may quote the price
separately in the addition/deletion items given in the BOQ for the change in the
transformer tank design suitable for this type arrangement and cost of dry plug type
termination inplace of porcelain bushing.
Page 11 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 12 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
- alarm in case of minor fault such as local overheating of windings or core (small gas
discharge),
- tripping-out in case of major fault (violent gas discharge) and excessive oil leakage.
Both transformer and load-tap changer oil circuits shall be equipped with "buchholz"
protection.They shall be connected to the oil pipe between the tank and the expansion
vessel, without any flat part and any less than 50mm bend.
It shall be free for access and maintenance; a by-pass system shall be provided to enable oil
flow without interrupting operation during maintenance checks.In order to ease gases
chemical analysis, the gas-sampling device shall be accessible during transformer operation,
at man’s working level.
Thermostat
The thermostat itself shall be installed in the monitoring box, while the indicator on it facade
and the thermal probe shall be installed into the tank with appropriate pocket.
Earth fault
The insulated tank shall only be connected to the earth through a resin cast core/ring type
current transformer as per GTP, which shall be linked to the control system via monitoring
cabinet terminal block.
Page 13 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Material Steel
3 mm for front cover & base frame
Minimum thickness of Steel sheets 2 mm for rear door
1.6 mm for roof plate, bottom plate & side covers
Powder Coating :
Exterior RAL 7032, Texture finish
Interior RAL 7032, Texture finish
Base frame Black
Thickness Min. 80 microns of Power coating
The Contractor shall submit to the Employer, the complete details of the Control &
Monitoring Cabinets, including details of the structure, process of finish and painting,
wiring, terminal blocks, cubicle illumination heating etc, for Employer’s approval.
The details adopted for Control and Relay panels, Bay Control and Protection units,
Transformer and On-load tap changer cubicles and all other Control and Monitoring
Cabinets, located inside the RSS Control Room shall be identical to project an aesthetically
good appearance
All the external surface of the transformer shall be given first coat of Epoxy zinc rich
(having minimum 83% metallic zinc) primer (Min.50 microns thickness), first intermediate
coat of epoxy zinc phosphate paint (Min.60 microns thickness), intermediate coat of Epoxy
high build MIO (Min.80 microns thickness), and final coat of glossy Aliphatic Acrylic
polyurethane (Min.50 microns thickness). The total dry film thickness (DFT) of the paints
shall be minimum 240 microns and should withstand 120°C. The shade of paint shall be
gray shade 631 as per IS: 5.
All steel surfaces which are in contact with insulating oil shall be painted with heat resistant
oil- insoluble insulating varnish.
After baring, all metal surfaces shall receive anti-corrosion process:
- natural stainless for Bolts & screws
- hot dip galvanization for radiators
- rust-proofing and anti-corrosion paint for tank, oil expansion vessel and other metal
surfaces.
The transformer and its accessories shall be completely painted in plant. The necessary
touch-ups shall be executed on-site after erection.This protection shall be fully guaranteed
for five years starting from provisional taking over. Should any noticeable deterioration by
rust or corrosion appear before this time elapses, the contractor shall be responsible for
repainting at his own expense and for renewing his guarantee for the work performed.
The painting and preserving of panels for transformer protection should be similar match
with that of other control and relay panels provided in the control room.
Page 15 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
SCOPE
Notwithstanding the technical specifications and requirements mentioned herewith any
modification can be incorporated for correct operation of nitrogen injection fire protection
system without extra cost. The full details of the same are required to be submitted to
DMRC for approval.
OPERATIONAL CONTROLS
The system shall be provided with automatic control for fire prevention and fire extinction.
Besides automatic control remote electrical push button control on control box and local
manual control in the fire extinguishing cubicle shall be provided. Spare interlocks are to be
provided for ensuring that it should not be possible to close HV or LV circuit breakers to
energize the transformer after the activation of the fire prevention and, fire extinction
Page 16 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
system.
For Prevention:
- Differential relay,
- Buchholz relay paralleled with pressure relief valve
For Extinction:
- Fire detector.
- Buchholz relay paralleled with pressure relief valve
SYSTEM EQUIPMENTS
A. Fire Extinguishing Cubicles (FEC), placed on plinth at about minimum 5 meter away
from the transformer shall consist of:
1 Nitrogen Gas cylinder with regulator and failing pressure electrical contact
manometer.
2 Oil drain pipe with mechanical quick drain valve.
3 Electro mechanical control equipments for oil drain and pre determined regulated
nitrogen release.
4 Pressure monitoring switch for backup protection for nitrogen release.
5 Limit switches for monitoring of the system.
6 Flanges on top panel for connecting oil drain and nitrogen injection pipes for
transformer.
7 Panel lighting
8 Oil drain pipe extension of suitable sizes for connecting pipes to oil pit.
B. Control box with activating, monitoring devices and line faults indicators. (To be placed
in control room). It should have audio visual alarm indication and push button switches.
C. Pre-stressed non return valve (PNRV) to be fitted in the conservator pipe line, between
conservator and buccholz relay operating mechanically on transformer oil flow rate with
electrical signals for monitoring.
D. Fire detectors to be fixed on transformer tank up cover and On Load tap Changer for
sensing fire.
E. Signal box to be fixed on transformer side wall for terminating cable connections from
fire detectors and PNRV
F. All other consumables necessary for complete system.
Page 17 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
TECHNICAL DETAILS
Fire extinction period
On commencement of Nitrogen injection : Maximum 30 seconds
On system activation up-to post cooling : Maximum 3 minutes
Fire detectors heat sensing temperature : 141 degcelcius
Heat sensing areas : 800 mm radius
Pre-stressed non-return valve setting for operation : Minimum 60 ltr per minute
Power Source :
Control Box :110 V DC
Fire fighting cubicles for lighting : 240 V AC
CABLING:
Fire survival cables, able to withstand 750 degcelcius, of appropriate size & core for
connection of fire detector in parallel shall be used. The test certificates for the cables
shall be submitted.
Fire retardant low smoke AC/DC cable as applicable (FRLS) cable of appropriate Sizes &
core for connection between transformer signal box/marshalling kiosks box to control box
and further from control box to fire extinguishing connection shall be used.
name and address of the customer, indicating the dates of commissioning as well as
performance certificate of successful and satisfactory operation for minimum two years
from the customers.
TESTS
TYPE TEST
Type Test reports including that for detectors along with declared response time shall be
submitted within the tender. The system shall be tested by reputed international testing
body or a national testing body (BIS) recognized laboratory). TAC approval, if any, shall
be submitted with the tender.
FACTORY TEST
Tests will be carried out on individual equipment of the system and the total system in the
supplier’s workshop in presence of purchaser’s representatives.
PERFORMANCE TEST
Performance test of the complete system shall be carried out after complete erection at site
by the supplier’s representatives. These tests shall include simulation and verification of the
response of the complete system without actual draining of the oil and injection of the
nitrogen gas. In addition to above, additional tests as required necessary shall be conducted.
SPARES
One full set of spares nitrogen gas filled cylinder, 50 % of the installed no. of fire detectors
(heat sensing element) shall be provided in addition to additional other recommended
spares. The list of recommended spares is to be submitted along with the proposal of
vendor approval.
3.2 Fiber Optic Winding Hot Spot Temperature Monitor:-
Fiber optical winding hot spot temperature monitor to be provided with transformer
windings connected in parallel of the winding temperature indicator to measure
transformer‐winding hot spots in real time and activate control of the cooling system. The
Fiber to be given high strength casing through rugged jacketing and fiber to be securely
routed till the tank wall plate. Temperature readings shall be available on SCADA and FO
sensor shall have IEC 61850 compliant port to communicate with SCADA.
Page 19 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 20 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
9. The controller shall be housed in cooler cubicle or in a separate enclosure having ingress
protection IP 55.
10. Temperature Rise Test Measurements shall be made with the Fiber Optic Thermometers.
The equipment shall be operational during temperature tests and be demonstrated during
these tests. During probe verification, the hottest probes for each phase shall be
identified, and temperature data for all probes recorded and reported in the test report.
11. All temperatures probes should be compatible with SCADA communicability.
If the employer requires ester oil filled transformer, the contractor shall submit detailed design of
the transformer along with relevant extracts of applicable International/Indian standards. Any
savings in size due to ester oil shall be clearly specified. The contractor shall submit the credentials
to assist proven-ness of the design. Transformer shall be designed with thermally upgraded papers
and OLTC other accessories shall be designed with high temperature rises, so as to minimize the
size of the transformers. The adjustment price of transformer with synthetic ester oil is to be quoted
in pricing/BOQ document(this includes the supply of spare ester oil drums in place of mineral oil, if
ester oil filled transformers are chosen)
Page 21 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 22 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
The contractor shall submit fully filled technical data sheet given in chapter 8B of PS along
with other relevant data during technical approval
Page 23 of 24
DMRC Electrical Standards & Design Wing DMES-
0002/TRANSF-02
Page 24 of 24