Internship Report ON Power Generation, Transmission and Protection System Equipments of Ashuganj Power Station Company Limited
Internship Report ON Power Generation, Transmission and Protection System Equipments of Ashuganj Power Station Company Limited
ON
SUBMITTED BY
MD. IQBAL HOSSAIN
SID: 2008 – 3 – 80 – 014
SUBMITTED TO
INTERNSHIP REPORT
ON
POWER GENERATION, TRANSMISSION AND PROTECTION SYSTEM
EQUIPMENTS OF ASHUGANJ POWER STATION COMPANY LIMITED
SUBMITTED BY
MD. IQBAL HOSSAIN (SID: 2008 – 3 – 80 – 014)
SUBMITTED TO
APPROVED BY
ACADEMIC ADVISOR
ANWARUL AZIM
2
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Approval Letter
3
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Acknowledgement
To begin with, I wish to convey my heartfelt gratitude to Almighty Allah for his help to complete
the Internship successfully. I also thank to the management of Ashuganj Power Station Company
Ltd (APSCL) for providing me such opportunity to accomplish my industrial training. I would
specially thank to Engr. MD. Nurul Alam, Managing director of APSCL who gave me the
permission to do internship work at APSCL.
I would like to thank Anwarul Azim, my advisor for his constant support and many suggestions,
but also for his patience and gentleness in those times, where I had to slug through problems.
I want to thank all those people who helped to complete my internship report successfully. In this
process my special thanks goes to Engr. Lutfurrahman (Principal of Trainnig Center, APSCL)
who coordinated my internship program and helped me to get acquainted with other engineers. I
am very grateful to Engr. Bikash Ranjan Roy, manager (I & C), Engr. Md. Azizur Rahman,
senior engineer (combine cycle power plant), Engr. Noor Mohammad, manager (Sub-station),
Engr. Md. Kamruzzaman, senior engineer (Generator and switchgear protection), Engr. Md.
Anwar Hossain, manager (Operation) for their supportive guidance. They helped me to learn the
scheduled topic which was present in my internship training schedule. I also want to thank each
and every employee of APSCL for their continual support.
I would also like to mention the name of Dr. Anisul Haque, ex Chairperson and Professor of the
Department of Electrical & Electronic Engineering and Dr. Khairul Alam, Chairperson and
Professor, Department of Electrical & Electronic Engineering, for being so kind during the
period of my internship. I am also grateful to all of my teachers and friends for their cooperation
and encouragement throughout my whole academic life in East West University.
4
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Executive Summary
I did my internship at Ashuganj Power Station Company Ltd (APSCL) located on the left bank
of the river Meghna from 26th of Dcember to 11th of January and this internship report is the
result of those 15 days attachment with the APSCL.
Ashuganj Power Station Company Ltd. (APSCL) owns the second largest power station in
Bangladesh. Ashuganj Power Station fulfills about 15% of power requirements of the country.
The installed capacity by its 9 units is 777 MW.
My duration of stay was divided to work in five sections as generator, sub-station, CCPP, I & C
and operation. During my internship I gathered practical knowledge about production of
electricity, operation, CCPP, major equipments e.g. Generator, Transformer and Switchgear
equipments required for distribution and protection of the system.
Protection and controlling of the equipments of the power station is a very important and
complicated task. With the help of the plant engineers I observed the control room and protective
equipments such as: relays (digital and electrical), circuit breakers etc very closely and
understood the functions and controlling system of those equipments.
Substation is an important part of a power station to distribute power and protection purpose. I
acquired knowledge about various types of transformers, bus-bars, circuit breakers (SF6 and
Oil), lightning arresters, CT, PT and other equipments of the substation which were clearly
taught and shown by the senior engineers of the substation of APSCL.
5
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Training Schedule
The following table contains my training schedule in Ashuganj Power Station Company Limited
(APSCL). My internship started on 26 December, 2011 and ended on 11 January, 2012.
Date Division Time Instructor
26-12-11 Eng. Achinta Kumer Sarker
Power Plant Training Center 8am to 5pm
DGM(MM)
27-12-11
Operation Eng. Md Anwer Hossain
to 8am to 5pm
Manager (Operation)
28-12-11
29-12-11 Eng .Bikash Ranjan Roy
Instrumentation and Control
to 8am to 5pm Manager (I&C)
(I&C)
01-01-12
List of abbreviations
6
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
TABLE OF CONTENTS
7
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
2.6 Turbine.............................................................................................................................................................. 22
2.6.1 Sections of steam turbine .......................................................................................................................... 22
2.6.2 Operation and maintenance ...................................................................................................................... 23
3.5 Damper.............................................................................................................................................................. 28
8
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
9
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
7.4 Discussion.......................................................................................................................................................... 55
References: ................................................................................................................................................................. 55
10
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
LIST OF TABLE
Table 1-1: Generation details of APSCL ................................................................................................................. 13
Table 1-2: Financial performance of APSCL .......................................................................................................... 14
Table 1-3: Salient feature of the 225MW future project ........................................................................................ 15
Table 1-4: Salient feature of the 450MW future project ........................................ Error! Bookmark not defined.15
Table 1-5: Salient feature of the 450MW (North) future project .......................................................................... 15
List of Figures
Figure 2-1: Forced draft fan ..................................................................................................................................... 16
Figure 2-2: Gas flow meter ....................................................................................................................................... 17
Figure 2-3: Water filter house .................................................................................................................................. 18
Figure 2-4: Burner room with water tube boiler .................................................................................................... 20
Figure 2-5: Steam turbine ......................................................................................................................................... 22
Figure 3-1: Design diagram of CCPP in APSCL .................................................................................................... 24
Figure 3-2: Combustion chamber in CCPP............................................................................................................. 25
Figure 3-3: Diesel engine of CCPP ........................................................................................................................... 26
Figure 3-4: Fuel annex room in CCPP ..................................................................................................................... 27
Figure 3-5: Design of Steam Generation process in CCPP .................................................................................... 29
Figure 4-1: A typical bus bar of APSCL .................................................................................................................. 30
Figure 4-2: A typical CT ........................................................................................................................................... 31
Figure 4-3: A typical PT ............................................................................................................................................ 31
Figure 4-4: Bushing of transformer ......................................................................................................................... 32
Figure 4-5: Silica gel in a cylinder ............................................................................................................................ 32
Figure 4-6: Insulator used in APSCL ...................................................................................................................... 33
Figure 4-7: Isolator used in APSCL ......................................................................................................................... 33
Figure 4-8: Double bus-bar arrangement ................................................................................................................ 34
Figure 4-9: Double bus bar transmission arrangement of APSCL ....................................................................... 35
Figure 4-10: SF6 circuit breaker .............................................................................................................................. 36
Figure 4-11: Oil circuit breaker ............................................................................................................................... 36
Figure 5-1: Generator in APSCL ............................................................................................................................. 38
Figure 5-2: Over current protection ........................................................................................................................ 39
Figure 5-3: Stator Winding Protection. ................................................................................................................... 40
Figure 5-4: Over current protection ........................................................................................................................ 41
Figure 5-5: Negative sequence protection ................................................................................................................ 42
Figure 5-6: Reverse power Protection use in APSCL ............................................................................................. 42
Figure 5-7: Minimum impedance and Distance protection.................................................................................... 44
Figure 5-8: Stator ground fault protection .............................................................................................................. 44
Figure 5-9: Earth fault protection of field circuit by potentiometer method & the relay used in APSCL ........ 45
Figure 6-1: Total output unit measure meter .......................................................................................................... 46
Figure 6-2: Control unit 1 &2 ................................................................................................................................... 46
Figure 6-3: Control unit 3 & 4 .................................................................................................................................. 47
Figure 6-4: Combine cycle control unit ................................................................................................................... 47
Figure 6-5: Feed water drum level control .............................................................................................................. 48
Figure 6-6: Safety valve used in APSCL .................................................................................................................. 49
Figure 6-7: Typical pressure gauge. ......................................................................................................................... 50
Figure 6-8: Flame detector. ....................................................................................................................................... 51
Figure 6-9: Junction box used in APSCL ................................................................................................................ 52
Figure 6-10: Fire alarm used in APSCL .................................................................................................................. 52
11
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
I did my internship at Ashuganj Power Station Company Ltd (APSCL) from 26th of December
2011 to 11th of January 2012 and this internship report is the result of those 15 days attachment
with the APSCL.
1.1 Introduction
Ashuganj Power Station Company Ltd. (APSCL) owns the second largest power station in
Bangladesh. The installed capacity by its 9 units is 777 MW and present de-rated capacity is 642
MW. Electricity generated in this power station is supplied to the national grid and distributed to
the consumers throughout the whole country. This power station plays a significant role in the
national economic development by generating more than 15% of the total demand of electricity
in the country.
Power Sector Development and reform Program of the Government of Bangladesh, Ashuganj
Power Station Company ltd, has been incorporated under the companies Act 1994 on 28 June
2000. All the activities of the company started formally on 01 June 2003. From that day the
overall activities of the company along with the operation, maintenance and development are
vested upon a Management Team consisting of the Managing Director, the Director (technical)
and the Director (Finance).
In this power station Natural Gas from Titas Gas Transmission and Distribution Company Ltd. is
used as fuel. Water from Meghna is used through in-take channels for steam generation and
cooling of generated steam. Used water (for cooling) is again thrown into the Meghna through
discharge channels. Huge water from the discharge channels is used for irrigation in the dry
season. Approximately 36,000 acres of land of Ashuganj are irrigated by this water. [3], [4]
12
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Particulars of Gas
Unit 01 Unit 02 Unit 03 Unit 04 Unit 05 GT 01 GT 02 ST (cc)
Operation Engine
Brown
Brown Brown Brown Brown
Boveri GEC, GEC,
Make & Boveri Boveri Boveri Boveri GEC,
190 69.6 69.6 Genbac
Capacity of 80 Mva, 80 Mva, 190 Mva, 190 Mva, 43 Mva,
Mva, Mva, Mva, her
Turbo- 11Kv, 0.5 11Kv, 15.75Kv, 15.75Kv, 13.8 Kv
15.75Kv, 13.8 Kv 13.8 Kv
Alternator pf 0.5 pf 0.5 pf 0.5 pf
0.5 pf
Date of
Commissionin 17-08-70 08-07-70 17-12-86 04-05-87 21-03-88 15-11-82 23-03-86 28-03-84 30-04-11
g
Year of Last
1989 1994 2003 2011 2008 2004 2000 n/a n/a
Overhauling
Generated
energy since
installation(G 10575.44 9807.24 22455.89 21306.43 29952.39 5985.33 6662.45 1745.36 5983.88
wh)
Load factor
68.96 68.96 69.24 71.35 84.80 99.42 92.29 98.03 95.00
(in 2011) %
Station heat
rate 11979 11696 12076 11017 10356 18175 18175 0 9366
Kcal/Kwh
Stationary
Thermal
29.97 30.87 29.89 31.75 34.86 19.86 19.86 0 38.54
Efficiency in
2011
Cost of fuel
per unit
0.93 0.87 0.90 0.90 0.79 1.30 1.30 0.00 0.69
generation in
Tk
13
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
14
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Capacity 225 MW
EPC Contract Price USD61,970,240 +EURO60,362,742+BDT2,530,772,664
ECA Backed Project Financer Expecting ECA support
Mandated lead arranger Standard Chartered Bank
Contract Agreement signing Date 05 October, 2011
Expected date of completion April, 2014
Project duration 25 months
Fuel Natural Gas
ii. Ashuganj 450 MW Combine Cycle Power Plant Project: The company has also
initiated the process to install another 450 MW combined cycle power plant using ECA
funding. The evaluation of the Bid is under process. Key information of the project is
placed bellow:
Capacity 450 MW
Estimated Cost of Project BDT 3,333 Crore
Expected project financing ECA backed project finance
Project completion time 27 months
Expected contract agreement June, 2012
Expected date of completion September, 2014
Current status Selection of EPC contractor in progress
Fuel Natural Gas
iii. Ashuganj 450 MW Combine Cycle Power Plant (North) Project: The Company is
also taken up program to install another 450MW Combine Cycle Power Plant, jointly
financed by Asian Development Bank (ADB) and Islamic Development Bank (IDB). A
brief particulars of the project is furnished below:
Capacity 450 MW
Estimated project Cost BDT 3,400.02 Crore
Project finance ADB & IDB
Expected Completion October, 2015
Current status Engagement of Consultant is in process
Fuel Natural Gas
15
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
In this part of my internship training Mr. Bikash Ranjon Roy (Manager of I & C) was my
instructor where I worked 3 days. I visited steam turbine unit, gas distribution, water pump,
water purification process and turbine
16
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
17
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
2.4.1 Pump
In APSCL there are three circulating water pumps for collecting water from river. In every place
there are two pumps one is working and another is standby. There is a discharge valve behind the
pump which is driven by oil. This valve works as either 0% close or 100% open. If it takes time
from 0% close to 100% open more than 90 sec then the pump will trip. This water which collects
from river goes to condenser to condensate steam. Rest of the water goes to purify then goes to
river again.
18
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
In the water filter house there are different type tanks and filters which purify the water. There
are four polyelectrolyte tanks where two is used for checking ph. There are two gravel filters. It
works very effectively by pulling water down through the gravel, where the solid debris is
trapped close to the surface, and the soluble waste is broken down by bacteria that grow on the
gravel surface further down. The clean water is then taken back to the surface. The lower level of
impurities not only reduces corrosion rates in the boiler but also reduces the erosion of the
turbine blades
2.5 Boiler
The basic purpose of a boiler is to turn water into steam, in this case super-heated steam. This
operation sounds relatively simple but is actually more complicated. The boilers utilized on
campus are of the stack drum type, which means there are drums within the boilers and flue gas
through the stack to atmosphere. The upper drum is called a boiler drum and is where saturated
steam leaves the boiler. While the lower drum is called the mud drum and is where liquid feed
water enters. Tubes called rises and down comers are used to connect the two drums. All the
energy required within the boiler is produced by the combustion of a fuel.
19
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
2.5.2 Ignition
The ignition coil is the component that connects directly with electricity line and includes two
transformer windings. The primary winding feeds into the distributor, while the secondary
winding connects to the spark plugs. When enough energy has been created, the spinning cam
opens a breaker, which causes a high-voltage jump in the ignition coil. This voltage surge is
transported to the spark plugs, resulting in the necessary electric spark to begin ignition. At the
beginning of the firing of the burner small amount of natural gas and air is needed. This small
amount of gas is known as ignition gas which is supplied into the burner by ignition pipe or line.
After the burner is on the ignition line is turned off and main line for fuel and air supply is turned
on.
2.5.3 Burner
Burner is the chamber in the boiler where natural gas or coal is burned with the presence of air
for producing heated gas or flue gas. In Ashuganj Power Station Company Ltd (APSCL) natural
gas is burned with the presence of air for generating heat for making steam. In steam turbine
power plant of APSCL each furnace chamber has nine furnaces. The temperature inside the
furnace chamber is 1200-1500°C. The treated water from the feed water tank through
economizer enters into the boiler through tubes and the flue gas produced inside the furnace
passes through the tubes.
20
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
21
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
2.5.8 Stack
Stack or chimney is a passage through which flue gas escape from a fire or furnace. From the
furnace flue gas is produced. This flue gas is used to create the steam for rotating the turbine.
The flue gas passes through several equipments and finally goes into the nature through stack.
2.6 Turbine
A steam turbine is a mechanical device that extracts thermal energy from pressurized and
converts it into rotary motion. The turbine mainly consists of nozzle and rotary and fixed blade
wheel. The steam is expanded from a high pressure to a low pressure either in nozzles or in the
blade where it is transformed into the mechanical work. The steam power plant of APSCL has a
casing around the blades that contains and controls the working fluid.
i. High Pressure Turbine (HP): From the super heater the high speed steam first enters to
the high pressure turbine. The blades in the high pressure turbine are the smallest of all
turbine blades; this is because the incoming steam has very high energy and occupies a
low volume. The blades are fixed to a shaft and as the steam hits the blades it causes the
shaft to rotate.
22
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
ii. Intermediate Pressure Turbine (IP): From the boiler re-heater the steam enter into the
intermediate pressure turbine. The steam has expanded and has less energy when it enters
this section, so here the turbine blades are bigger than those in the high pressure turbine.
The blades are fixed to a shaft and as the steam hits the blades it causes the shaft to rotate.
From here the steam goes straight to the next section of turbine set.
iii. Low Pressure Turbine (LP): From the intermediate pressure turbine steam enters into
the low pressure turbine and continues its expansion. The blades of the turbine of this
section are larger than the previous two sections but the energy of steam is lesser than the
previous two sections.
23
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Ashuganj Power Station Company Ltd. (APSCL) uses gas as fuel to generate the heat. This heat
is used to heat water and create steam. Then the steam passes through turbine which transfers the
thermal energy of the steam to the mechanical energy. A generator rotor is attached with this
turbine and generator transfer mechanical energy to the electrical energy. There are five steam
turbine power plants in APSCL. Installed capacity of steam turbine power plant in APSCL is
578MW.
24
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
heat, and then it is merged with the burned products of combustion. The pressurized mixture,
usually at 1010°F or higher, flows into a reaction turbine. The turbine drives the compressor and
also produces work by driving the generator. A portion of the exhaust gas may be re-circulated
and it is possible to recover heat energy from the waste exhaust.
3.2.1 Compressor
The compressor is driven by the turbine through a common shaft. Air enters the compressor via
an inlet duct. The compressor increases the air pressure and reduces the air volume as it pumps
air to the combustor and through the engine. At the begging of the generation compressor is
routed by diesel engine in APSCL.
25
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
26
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
The system provides the engine with the proper amount of fuel to sustain operation. System
components include filters, a fuel manifold, fuel tubes, and nozzles. Off-engine components
include the fuel control equipment and a supply system. Fuel (in APSCL it is natural gas) enters
the tubular fuel manifold ring via the supply system. The fuel tubes direct the fuel from the
manifold to the fuel nozzles which are mounted in the fuel. In APSCL gas comes from Titas.
27
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
3.4 Economizer
Economizers are mechanical devices intended to reduce energy consumption, or to perform
another useful function such as preheating a fluid. It used for Boiler heating, ventilating, and air-
conditioning purpose.
3.5 Damper
Dampers are often provided in CCPP so the gas turbine exhaust can bypass the heat recovery
boiler allowing the gas turbine to operate if the steam unit is down for maintenance.
Supplementary oil or gas firing is also included to permit steam unit operation with the gas
turbine down.
28
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
230oc 100oc
Boiler HP Deareator
40oc
dram
L.P. Evaporator
HP. Evaporator
3.6.2 De-aerator
In combine cycle power plant it is used as the preserver of feed water which comes from the
condenser by extraction pump. At this stage the temperature of feed water which enters the de-
aerator is 40°C. From de-aerator the feed water is flowed into the low pressure evaporate again
goes to de-aerator. When feed water through the LP Evaporate then it gains heat which is 100°C.
29
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
CHAPTER - 4 Substation
In this part of my internship training Mr. Noor Mohammad (Manager of Substation) was my
instructor where I worked 3 days. I visited sub-station yard, transmission field, sub-station
control room.
30
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
In electrical engineering, a current transformer (CT) is used for measurement of electric currents.
When current in a circuit is too high to directly apply to measuring instruments, a current
transformer produces a reduced current accurately proportional to the current in the circuit,
which can be conveniently connected to measuring and recording instruments. A current
transformer also isolates the measuring instruments from what may be very high voltage in the
monitored circuit. Current transformers are commonly used in metering and protective relays in
the electrical power industry. [1]
31
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
4.2.4 Transformer
Transformer is a static device used to transform power from one voltage level without changing
the frequency. There are different parts of a transformer given below:
i. Bushing: This maintains the incoming and outgoing connection of a transformer.
ii. Radiator: This is used to radiate the heat of a transformer when transformer is heated up
at a certain level.
iii. Oil temperature meter: This meter indicates the temperature of transformer oil. If
temperature crosses a certain level then it makes an alarm.
iv. Temperature meter: This meter indicates the temperature of transformer windings. If
temperature crosses a certain level then it starts the winding fans.
v. Oil level meter: This meter indicates the oil level of transformer. If oil is low than a
certain amount it makes an alarm that means that transformer have to feed oil.
vi. Silica gel: It works like breathing. There have a little amount oil under the silica gel
which suck the moisture of air and further sends this air to silica gel which further sucks
the rest of the moisture of the air.
vii. Exchanger: Regulate voltage through winding selection between primary & secondary
side.
viii. PRD (Pressure relief device): release the oil pressure by releasing oil when oil pressure
is high.
32
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
4.2.5 Insulator
Porcelain or ceramic insulator is used in substation to support the live conductors and bus bars.
4.2.6 Isolator
Islators are used for isolating the circuit when the current has already been interupted. They
allow currents into the circuit until curcuit is repair again. Isolators re used for connecting and
disconnecting parts of electrical installation after de-energizing.
33
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
34
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
APSCL Uses double line bus bar arrangement scheme for their transmission purpose. They
provide their generated power to Shajibazar, Ghorashal, Kishoregonj through double bus bar
system.
35
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
36
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
4.5 Relay
A relay is a device used to control the operation of a magnetic contactor or other device .relay
operate as a function of current ,voltage ,heat .and pressure and supply the “intelligence” that is
necessary to provide automatic acceleration, protect against overload ,under voltage, excessive
speed, excessive torque, etc. At APSCL two types of relay is used. One is electrical relay and
another is electronics relay. [7]
37
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
CHAPTER - 5 Generator
In this part of my internship training Md. Kamruzzaman (Senior Eng. of Generator) was my
instructor where I worked 3 days. I visited Generation control room, generator, and steam
turbine. Here I learned about Generator and different types of protection of generator.
5.2 AC generator
Ac generator also called synchronous generators or alternators. Ac generators are the principal
sources of electrical power throughout the world, and range in size from a fraction of a KVA to
1500 MVA. Alternating voltage may be generated by rotating a coil in the magnetic field or
rotating by magnetic field within a stationary coil. The value of voltage generated depends on –
i. The numbers of turn in the coil.
ii. Strength of the field.
iii. The speed at which the coil or magnetic fields rotate.
38
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
7000/5A
Time delay
(0.9IN)
Timer
Instantaneous relay
(1.2IN)
In APSCL generator unit 3, 4 and 5 uses rated terminal voltages 15.75kv and rated current
6995A. Hear over current relay connect through the CT with the terminal and use CT ratio
70000V/5A. Inversely we can say if 5A current flow the voltages flow 7000V,Over current relay
consists of two types of relay, one is time delay relay which is connect with timer another is
39
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
instantaneous relay. In APSCL timer setting time is 0.5second. When time delay activated than
start time counting and after 5second is breaks contract, on the other hand instantaneous relay
operate instantaneously. Generally nominal current is 5A. If 0.9 times of nominal current flow
through the line then time delay activated or if 1.2 times of nominal current flow through the line
then instantaneous relay activated. In these case time delay activated but it start time counting
where instantaneous relay operate instantaneously.
Suppose fault occurs in the terminal than high current (9000A) appear in the line time delay start
time counting but instantaneous relay trip the breaker instantaneously. In the power r system
time delay relay operate when load increase in the feeder line and instantaneous relay operate
when fault in the line.
6995A
6995A
6995A
5A 2A
3A
40
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
under voltages appear .when in the power system both condition appear then the under voltages
with over current relay activated .if over current relay activated we understands that huge amount
of fault in the system occurred ,if under voltage appear we can are confuse if it is fault or over
load occurred or over voltages.
In the power system main causes of over voltages occur Sudden load rejection, Lightening, Line
fault.
7000V/5A
16KV/110V
1.2IN
0.8IN
over currentwith
under voltages
relay
41
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
6995A
6995A
6995A
42
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
43
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
100% 80%
7000V/5A
16KV/110V
44
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Figure 5-9: Earth fault protection of field circuit by potentiometer method & the relay used in APSCL
45
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
In this part of my internship training Mr. Anwar Hossain (Meneger of Operation) was my
instructor where I worked 2 days. I visited all control rooms where entire power plant can be
controlled and supervised from the centered console and the large display panel in the main
control room.
46
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
47
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
Feed water and, therefore, steam flow is controlled to meet load demand by the turbine and at the
same time maintain the level of water in the steam drum within relatively narrow limits.
Normally, the water level in the drum is maintained half- full up to the diametric plane. High
steam consumption by the turbine, combined with low feed-water supply would lower the water
level in the drum. A three element automatic control system, of which the drum level is one
element, is shown in fig: () The Drum level sensor respond to the error between actual drum
level and its set point, such as in the case of high steam consumption and low feed-water supply,
and acts of the controller to increase the feed-water valve opening to meet the steam flow
demand. This action be too slow and is supplemented by sensor for feed-water and steam flow.
The difference between the signals from these two sensors anticipates changes in drum level and
sends a signal to the controller to actuate the valve in the desired direction.
48
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
On-off controls, the simplest, are used on fire-tube and small water-tube boilers. The on-off
control system supplies a pre- determined amount of fuel and air. On-off controls cannot supply
a steady steam pressure because they work on a cyclic basis.
Positioning controls, used on many boilers, are more flexible and can provide better combustion
efficiency than can on-off controls. These controls operate on a continuous basis, providing
smoother changes in fuel and air feed allowing the boiler to maintain a more uniform steam
pressure. The amount of air and fuel feed can be adjusted manually to change the air to fuel ratio.
49
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
In the APSCL, boiler has several valve, they are set to pop at different pressure. Boilers are
designed to operate at certain maximum pressures. IF the operating pressure is exceeded, the
boiler may explode. Therefore, all boilers are equipped with at least one or more safety valves
will open, releasing steam if the pressure in the drum becomes too high.
Safety valves can also be popped manually by using hand levers. For large boilers, each super-
heater and re-heater will have one or more safety valves. The safety valves are located near the
outlets of these tube sections.
The Bourdon tube is the most common gauge used on a boiler. It consists of a curved tube that is
sealed at one end. The sealed end is connected to a pointer by linkage.
The open end of the gauge is the pressure connection. As pressure increases in the tube, the tube
straightens out, moving the pointer. As the pressure decreases the tube returns to the normal
curved position. Bourdon pressure gauges can measure pressures of steam, air, oil, water, or
other fluids. These gauges require careful handling and proper maintenance to keep them
operating accurately. They should be removed from their mountings, disassembled and cleaned
with a suitable regularly.
Steam gauges for a small boiler are usually mounted on top of the water column. The gauge will
directly read the pressure of the boiler. In many boilers, so that they can easily be reads by the
operator. At this level, the true steam pressure is the value read of the gauge minus the hydraulic
50
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
head. For each foot of vertical distance between the connection at the drum and the ground level,
the gauge reading must be corrected by subtracting a value of 0.433 psi per foot of head.
Gaugescan also be mounted above the point of pressure measurement. In this case the pressure
due to the hydraulic head must be added to the gauge reading.
Flame detectors, or scanners, monitor burner flames on all boilers and ignitors on coal or natural
gas and oil- fired boilers. If the flame in a burner or ignitor goes out, a flame detector sends a
signal to the fuel feed controls that automatically stop the flow of fuel into the boiler. Thus, the
boiler is prevented from operation or igniting while explosive conditions in the furnace exist.
Three flame detectors used of boilers are photocell, ultraviolet, and infrared detectors. Photocells
detect visible light, ultraviolet sensors detect ultraviolet light, and infrared sensors detect infrared
light in the burner flame or ignitor. These devices are installed in the furnace wall as shown in
figure.
51
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
52
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
53
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
CHAPTER - 7 Conclusion
7.1 My achievements
Before internship I knew many theories and working principles of power system and related
equipments but from internship I acquired practical knowledge about power system engineering
and its equipment. Here, I always tried to relate my academic courses with practical participation
of power generation process. Beside I also faced some practical problems which was not taught
in my academic courses. My communication skill also improved through communication with
different instructor. Therefore, I made good achievements with my industrial training which will
help me in my future.
ii. Practical participation in different works of APSCL would give more experience but
practical participation was not allowed for internship student
iii. Company did not provide me enough data for security purpose.
7.3 Recommendations
Some recommendations are given below for the students to do their internship program in a
better way –
i. The internship program should be scheduled in such a way so that it does not clash
with the university classes.
ii. More theoretical knowledge about power generation, protection system, power
equipments should be learnt before going for internship. Hence students must
complete the related courses to their internship before joining the program. Taking
the courses before the internship helps the students understand the topic much better.
54
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
7.4 Discussion
In case of power generation, APSCL is the combination of steam, gas and combined cycle plant.
Last 26th December I went to Ashuganj Power Station Company ltd. for my internship program.
I visited steam power plant, I observed how water is collected, purified and then boiled to
produce steam. There are several switch gear and control rooms to control the overall system of
producing steam and power generation. Various types of relays used for protective purposes that
are also controlled in control room. I visited gas turbine of APSCL. There I have seen how fresh
air and natural gas supplied by TITAS GAS are used as fuel to burn. After burning, produced hot
gas used to rotate the turbine as well as power generation. For protective measures relays are also
used and controlled in switch gear room. After gas turbine, I visited combined cycle power plant
(CCPP). Here the exhausted hot gas is being used to boil water for producing steam. I visited the
distribution section of APSCL. In sub-station, stepped up or down of voltages is being done
using transformers and power is distributed. Different types of isolators are being used for
maintenance purpose of transmission lines.
The authorities in APSCL were very concerned about all kinds of safety. The friendly
environment in APSCL encouraged me to co-operate with each other. I learned a lot and
obtained practical knowledge from my internship at APSCL, which will help me in my future
life.
References:
[1] V.K. Mehta & Pohit Mehta, “Principles of Power system”, 4th Revised Edition, S.Chand
& Company Ltd, 2009.
[2] M.V. Deshpande, “Elements of Electrical Power Station Design”, 3rd Edition,
A.H.Wheeler & Company Private Ltd, 1986.
[3] http://www.apscl.com
[4] http://www.powerdivision.gov.bd
[5] http://www.scribd.com/doc/11911769/Network-Protection-and-Automation-Guide
[6] http://en.wikipedia.org/wiki/circuit_breaker
[7] http://en.wikipedia.org/wiki/relay
55
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
56
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
57
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
58
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
59
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
60
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
61
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
62
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
63
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
64
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
65
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
66
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
67
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
68
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
69
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
70
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
71
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
72
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
73
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
74
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
75
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
76
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
77
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
78
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
79
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
80
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
81
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
82
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
83
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
84
Department of Electrical and Electronic Engineering, East West University
Undergraduate Internship Report
85
Department of Electrical and Electronic Engineering, East West University