Project Progress Report
Project Progress Report
Supervisors:
Mr. Maxwell Jackson, MSc (Internal)
Mr. Richard Thomas (External)
This project proposes a design of an iron removal system for the water supply system
at La Bonne Intention, East Coast of Demerara.
In addition, the presence of dissolved iron enhances the growth of iron bacteria, which
forms dark-coloured slime layers on the inner side of a system's pipes. The slime is then
released into the network through water flow fluctuations, leading to dirt build-up and
damage to the plumbing. Consumers are therefore forced to spend more money to clean
and maintain appliances every year.
The study will involve sampling of the groundwater for laboratory analysis both before
and after the current treatment method (s) to ascertain the levels of iron concentration.
Samples will also be taken from a random residential home within district being
supplied by the pump station. The samples will be tested for soluble iron, insoluble
iron, pH and temperature.
The results will then be analysed for the design of an iron removal/treatment system.
This project will not include any economic calculations, meaning that no information
on prices will be included or researched by the author. The main emphasis will be
placed on the engineering aspect.
The red rectangle borders the area of interest (La Bonne Intention Pump Station). The
blue rectangle borders GWI’s Main Storage Facility. To the north of the rectangles lie
the Railway Embankment (East Coast of Demerara Public Road) whereas to the east
lie La Bonne Intention Road (LBI Estate Road).
Data
Analysis
Design
Results
Conclusion Recommendations
End
Interviews were conducted with the external supervisor so as to gain knowledge on how
to go about executing this project.
Practical works are now expected to be completed on the 29th January 2019.
Note that the total duration of the project is now expected to be 174 working days.
Gantt Chart above illustrating the projected start date and duration.
Practical works have commenced but were delayed due to the final examinations period
and the holiday season. These delays have made a significant impact on the site
investigation, data analysis and the design stages which in turn affected the project
schedule. However, working on weekends and national holidays will fast track the
delayed works and bring the project back on schedule.