YDH FEED Verification
YDH FEED Verification
1
Description
In document "BI-10-02399 YDH, MARAFIQ Interfaces SOW", three metering skids
are required along with junction boxes, RTU panel support etc. But this folder
don’t show any civil drawings related to this.
Sr. No. Drawing Number
1)
Description
1 PI-A00430
2 PI-A00430
3 PI-A00430
4 PI-A00430
5 PI-A00430
6 PI-A00438
7 PI-A00438
8 PI-A00438
10 PI-A00430
11 PI-A00430
12
Description
No architecture drawings for buildings in SAMREF interface are available. Hence it is
considered as an upscope. This include Electrical Room building.
No structural drawings for buildings in SAMREF interface are available. Hence it is considered
as an upscope. This include Electrical Room building.
X40-FS-X003, Foam skid is shown in SASREF interface but no details are provided in Index-Q &
Index-M. Hence it is considered as an upscope.
Custody Metering Shelter Index-M & Index-Q drawings are not available in the SAMREF
interface package. Hence it is considered as an upscope.
Pipe Way is shown in drawing PI-A00430, but no civil strutural information is available about
this. Hence it will be considered as an upscope.
Culvert is proposed but civil details are missing in interface FEED package, hence it will be
considered as an upscope.
Radar Mapping report for civil support missing
Geotechnical report is missing for new support foundation location
Pg-13 clarification required for 50 mm settlement criteria of Mat foundation.
Pg-13 Metering Skid Settlement values are missing
Pg-13 NABC values are very high need to be discussed.
Oily water lift station (X40-S-2104) for SAMREF is missing in the FEED package for SAMREF,
hence this item will be considered as an upscope.
In SAMREF package no road works and site development drawings are included, hence it will
be considered as an upscope.
1)
Drawing STA00032 is marked as foam skid in DCL but shows details of operation building in actual
drawing.