The document discusses several civil/structural items that are referenced in interface scope of work documents for various projects (YDH, MARAFIQ, YASREF, SAMREF) but whose details are missing from the interface packages. Specifically, it notes a lack of civil drawings, geotechnical reports, architecture/structural drawings for buildings, clarification on settlement criteria, and other details. The document identifies these missing items as potential scope upgrades that require further clarification and discussion with the project teams.

Uploaded by

bill
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
252 views10 pages

YDH FEED Verification

The document discusses several civil/structural items that are referenced in interface scope of work documents for various projects (YDH, MARAFIQ, YASREF, SAMREF) but whose details are missing from the interface packages. Specifically, it notes a lack of civil drawings, geotechnical reports, architecture/structural drawings for buildings, clarification on settlement criteria, and other details. The document identifies these missing items as potential scope upgrades that require further clarification and discussion with the project teams.

Uploaded by

bill
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Drawing

Sr. No. Description


Number

Document "BI-10-02399 YDH, YR Interfaces SOW 160816" shows requirement of


1 Pumps, Surge Tanks, New pipe supports etc. But there is no civil package at all in
the same YR interface folder.
Although same document refers to structural scope in page-4.

As mentioned in scope of work document "BI-10-02399 YDH, YR Interfaces SOW


2 160816" Geotechnical study report no 2015/104 & 93/90 is required to carry out
civil works.
Sr. No. Drawing Number Description

1 For YRC interface package, there is no civil/structural work involved


except preparing road crossing details for pipelines.
2 YRC interface scope of work is missing.
Sr. No. Drawing Number

1
Description
In document "BI-10-02399 YDH, MARAFIQ Interfaces SOW", three metering skids
are required along with junction boxes, RTU panel support etc. But this folder
don’t show any civil drawings related to this.
Sr. No. Drawing Number

1)
Description

As per interface scope document "BI-10-02399 YDH, YASREF Interfaces SOW


160816", bullet "3.Notes", on page 1, civil support may be requried for new surge
relief tanks and respective deluge foam system. Please clarify if this will be
considered as an upscope once confirmed.
Sr. No. Drawing Number

1 PI-A00430

2 PI-A00430

3 PI-A00430

4 PI-A00430

5 PI-A00430

6 PI-A00438

7 PI-A00438
8 PI-A00438

9 Geotechnical File No. 2015/104, Rev.1

10 PI-A00430

11 PI-A00430

12
Description
No architecture drawings for buildings in SAMREF interface are available. Hence it is
considered as an upscope. This include Electrical Room building.
No structural drawings for buildings in SAMREF interface are available. Hence it is considered
as an upscope. This include Electrical Room building.
X40-FS-X003, Foam skid is shown in SASREF interface but no details are provided in Index-Q &
Index-M. Hence it is considered as an upscope.
Custody Metering Shelter Index-M & Index-Q drawings are not available in the SAMREF
interface package. Hence it is considered as an upscope.
Pipe Way is shown in drawing PI-A00430, but no civil strutural information is available about
this. Hence it will be considered as an upscope.

Culvert is proposed but civil details are missing in interface FEED package, hence it will be
considered as an upscope.
Radar Mapping report for civil support missing
Geotechnical report is missing for new support foundation location
Pg-13 clarification required for 50 mm settlement criteria of Mat foundation.
Pg-13 Metering Skid Settlement values are missing
Pg-13 NABC values are very high need to be discussed.
Oily water lift station (X40-S-2104) for SAMREF is missing in the FEED package for SAMREF,
hence this item will be considered as an upscope.
In SAMREF package no road works and site development drawings are included, hence it will
be considered as an upscope.
1)
Drawing STA00032 is marked as foam skid in DCL but shows details of operation building in actual
drawing.