Design Problem Updated
Design Problem Updated
A Chinese owner wants to have a truck hub for his truck • AMBF of Industrial Zone
business. He wants it to have its own gas refilling station
it’s a mix of industrial, commercial and residential • AMBF of Residential Zone
development for his 50m by 1 hectare lot
• Total maxISA Table 8.1
The client requires a gas refilling lane of 10meters by
• TLA of the project
7.5 meters with 6 pumps. There will be 5 underground
storage tank for 49.20 x 20.40m. Near the gas refilling • Vol. of concrete of commercial bldg. 2nd floor
lane is the car wash lane that would cater 4 cars at the slab
same time, with dimension of 12mx8m. Adjacent is
covered water and air island of 1m x 3m. Right ahead is • AMBF of the Project
a two storey commercial building that serves as their
multi business office. Both ground and second floor has • PSO of the Project
an area of 28m x 12m. Provide a 6m wide driveway for
• ISA of the Project
industrial and residential. Behind the commercial
building is the light industrial area with 4250 sq. m. • TOSL of the Project
There will be warehouses, 1 will be 28m x 40m and the
second one is for 28m x 30m. There is 200 sq.m. motor
pool, a truck parking for 8mx85m area, loading and
unloading for 640 sq. m. and a generator room and
utility room for 8m x 10m. Up ahead is a 300sq. m.
staff/driver’s house.
Design Objective:
B. Statement of the Problem The office of the bldg. official has approved more than
60% paved front yard each unit of duplex house should
A Newly-wed couple has decided to set up a real estate optimize the use of the lot. It should also have 2
development corporation. They have a lot of inherited carports and should not sacrifice because the
land properties and their initial project is to build a 2 prospective clients are working couples with their cars.
storey duplex house in Davao City Located within Take note that the subdivision developer has loosen
subdivision of low density. With this particular project, upon the use of yards giving away to the needs of time.
they have envisioned to cater markets of working
couples that in junior executive positions.
C. Design Requirements
Objective
B. The 3rd floor will be available for rental while the 4th
floor will be for developer’s firm.
4. Roofdeck
STATEMENT OF THE PROBLEM: openings at the Lunch Counter, the uppermost
classroom of the West Wing and the south end of the
The Scola Guadalupana Extension (P-1) West Wing.
The Scola Guadalupana, or the La Salle Sisters of The southeast corner includes the 5m driveway and
Guadalupe Middle School is planning to offer additional parking spaces, arranged from the east as such: 5
grade levels to Grade 10 within the next five years. The regular parking slots, the 5m access road, and then 1
existing site (Lot 16) is located in a light commercial PWD parking. The site’s paved area includes this area
area beside a mid-rise condominium close to private and an adjacent area that extends inward, forming a
subdivisions. The expansion could involve two separate total depth of 10m from the front of the property. An
phases, with each phases to be executed within 2 to 3 additional 5.8m x 2m paved path connects the south
years. The first phase requires expanding its existing 10- end of the West Wing corridor to this paved area. The
year old two-storey structure which was structurally rest of the open grounds are unpaved, where slides,
designed to accommodate up to 3 storeys by adding swings and see-saws are placed near the lunch counter.
additional classrooms on the third floor. For the second On the southwest area, a pound and garden occupies
phase, the La Salle Sisters are negotiating to purchase a the unpaved ground.
vacant lot (Lot 19) to the left of its existing campus,
having a depth of 62m. 1. AMBF for the Lot 16?
The campus lot (Lot 16) has a frontage of 37m facing a b. 1835 m2
20m RROW oriented in the east-west direction. Its L-
shaped two-storey structure, setback 3m from the c. 1605 m2
property line, has the longer side oriented along the
d. 1950 m2
west property line, while the shorter side rests along
the north property line. On the West wing, four 63m2 2. If lunch counter was reduced in width to farm a
classrooms were built on the second floor. On the setback, what should be the maxISA?
ground floor, three classrooms were built, and the
remaining 63m2 area is occupied by the guidance office a. 573.5 m2
and the clinic towards the south end. U-shaped stairs
with 1.5m width and mid-level storage rooms (at the b. 344.1 m2
landing) are located adjacent to the clinic.
c. 229.4 m2
On the North wing, the ground floor includes the admin
d. 458.8 m2
and faculty room occupying an area equivalent to two
classrooms while the lunch counter at the end of the 3. According to DepEd Facilities Planning Manual, the
North Wing has its right wall resting against a firewall front setback of a two-storey structure in a school
measuring 11.2m at the east property line starting at should be?
2.4m from the northeast center. Two more classrooms
were built on the second floor of the north wing, while a. 8 m
a library was built above the lunch counter with the
exact same dimensions. The corner of the building b. 10 m
towards the northwest has a 70m2 that involves the
c. 6 m
stairs, restrooms, utility rooms plus circulation areas.
Here, the stairs are placed adjacent to the last d. 5 m
classroom at the West Wing, while the restrooms, each
measuring 3.5m x 4m, are located adjacent to the 4. If a new two-storey building would be built for the
admin offices. The same configuration is found on the expansion at Lot 19, how far should it be from the edge
second floor. All classrooms as well as the admin and of the existing building?
guidance offices are facing corridors with a 3m width on
the ground floor and a 2m widths on the second floor a. 5 m
and third floors. Ground floor corridors are bound by
b. 8 m
1.4m high walls on the outer edge, width 3m width
c. 6 m a. 27 m
d. 10 m b. 35 m
Find for :
• AMBF
• PSO
• ISA
• USA
• TOSL
• MACA
• BHL
• FLAR
• GFA
• TGFA
Title: Proposed 3 storey duplex 13. Find the applicable range of the no. of gypsum board if
Problem: installed in the interior ceiling [of 1 unit only
Developer wanted to build model duplex house on a lot in Marikina a. 100-120
City zoned as R-3. Each unit has uniform 198sqm lot with a total area b. 135-155
of 396sqm, the site slopes down 2% towards the street. c. 65-80
To maximize the use of lot, each dwelling unit shall be uniformly d. 160-180
built with a common wall at the middle and will be allotted 91sqm 14. Find the applicable range of the no. of gypsum board if
per floor total ground floor area will be 182sqm for the duplex. installed at the ground floor interior ceiling of 1 unit only
Project site features: a. 60-69
The structure will have a setback of 6.00m at front, 2m at sides and b. 32-39
3m at the rear area. Each unit shall have features c. 47-52
1. Ground floor d. 22-28
a. 7.00 x 6.00 unroofed carport 15. Find the range of gallons of paint needed (3coats using
b. 3.00 x 3.60 entrance foyer and 2.4 x 3.6m stair ratio of 20sqm per gallon) to cover the ground floor
abutting the common wall interior ceiling of the duplex
c. 4.00 x 6.00 living area front carport and the a. 45-50
easement b. 26-32
d. Next to living area is a 6.00 x 7.00 combined c. 8-12
kitchen and dining with 1.5 x 2.4 toilet abutting d. 14-20
the common wall and rear service area 16. Considering a uniform 0.13m slab thickness, find the range
e. Open and service kitchen-laundry area at the in cubic meters of the slab of the interior ground floor of 1
rear yard unit only
2. Second and third floor a. 14-15
a. 2 identical bedrooms occupying an area of 4.6 x b. 1-7
3,5 each located at the front c. 11-12
b. Master bedroom measuring 6.0 x 7.0 located at d. 18-19
the back with 1.5 x 2.4m above and 1.5 x 2.4 17. Considering a uniform 0.15m slab thickness, find the range
toilet at the ground on cubic meters of the slab of the interior ground floor of
c. Common toilet 1.5 x 2.4m 1 unit only
The project is a rectangular inside lot with a total frontage of 18.0m a. 36-38
facing a 14.0m RROW towards north. b. 39-40
c. 20-22
1. AMBF (SQM) of the Project? d. 27-29
2. PSO (actual) of the Project
3. Max. ISA of the Project
4. Min. USA of the Project
5. Actual TOSL of the Project
6. MACA
7. FLAR of the Project
8. What is the BHL (No. of the Storage) of the Project
9. What is the Allowable GFA (sqm) of the Project
10. What is the Allowable TGFA in sqm based on the max. GFA
of the Project?
11. Considering a 1.5m eaves throughout the exterior face of
the house, what is the applicable range of the total ceiling
area (sqm) for this Project?
a. 480-490
b. 724-738
c. 495-500
d. 630-660
12. Find the Applicable range of the no. of 0.60 x 0.60 granite
tiles for all the interior floor of 1 unit only
a. 780-850
b. 410-470
c. 510-550
d. 680-750