FIDIC, Presentation
FIDIC, Presentation
AUSTRIA BENELUX CZECH REP. GERMANY HUNGARY INTER- CROATIA POLAND RUSSIA, ROMANIA SERBIA SLOVAKIA SWITZER- SWEDEN COMPLIANCE PPP
NATIONAL CIS & LAND ,
BALTIC CORPORATE
STATES
S. Müllner G. Koele I. Karfík R. Fuchs D. Kázmér M. Ðenadić M. Brundić A. I. Campbell C. Tampau M.Momcilovic R. Šály M. Cabalzar E. Dalén H. Soldierer R. Allitsch
(Real Estate) Rybicki
C. Genschow
(Civil engineering)
V. Springer
(Road construction)
CML INT: Seven (7) lawyers, four (4) contract managers, and Stand: 15.07.15
Sekretarijat (Secretariat)
Komiteti (Committees)
Forumi
Odnos izmedju FIDIC Ugovora
Prelazak rizika: Glavne razlike po knjgama
The most frequently used and best-known are the Red Book, Yellow
Book, Silver Book and Green Book
FIDIC contracts are neither a legal system, nor are they laws
• Further document (if any) listed in • the Contractor‘s Proposal and any
the Contract or in the Letter of other documents forming part of the
Acceptance Contract
-> this defines the documents which -> this defines the priority order in case
form part of the Contract of ambiguity or discrepancy
-> ugovorne strane mogu u Posebnim
Uslovima dogovoriti drugaciji prioritet
dokumenata
Sta se desava kada strane ne popune Appendix to Tender?
Retention money NO NO
Advance payment NO NO
(Boban Jelic)
Vazne karakteristike Crvene knjige i Zute knjige
Dizajn
Should the Contractor be required The Employer is liable for its own
to design, the Engineer is design [GC 17.3 g], if any (e.g.
responsible for the coordination of Preliminary Design).
each Party’s design.
When achieved, the Works
The Contractor bears the risk that (especially the design) shall be “fit
Works are“fit for their intended for the purposes for which the
purposes”. Works are intended as defined
in the Contract”.
Fitness for purpose means that the Contractor is guaranteeing that, when
completed, the Works will satisfy the functionality and the purposes
defined in the Contract
Fitness for purpose is required irrespective of (i) the level of skill and care
and dilligence expected from the Contractor or (ii) whether or not an
independent professional designer may decline liability for being unable to
procure insurance or limit its liability to reasonable skill and care
Design Liability: Fitness for Purpose (ii)
Please note that by default there is no such definition with the FIDIC
Contract
The degree of additional obligations and risk put on the Contractor by such “fit
for purpose” depends mainly on the way such purpose is defined in the Contract:
To seek the liability of the Contractor or reject the Works, the Employer
does not need to prove any fault but (simply) that the Works are not fit for the
relevant purpose
Errors in the Employer‘s Requirements in Yellow Book
GC 5.1 GC 1.9
During the period stated in GC 5.1 After the period stated in GC 5.1
(starting on receipt of the
notice of Commencement Date)
Time for
Completion
1. Obligation to scrutinize the Employer's 1) Contractor shall send a notice when it
Requirements u roku predvidjenom u discovers any error, fault or defect in the
Appendix to Tender. Employer's Requirements.
1) Errors in the design of the Employer are Employer‘s Risk (GC 1.8 /
17.3.g);
Under Yellow Book the price is by default a lump sum. However, certain
items may be paid according to their actual quantities if so is expressly
stated in the PC.
Both, Yellow Book and Red Book make the difference between:
Accepted Contract Amount (GC 1.1.4.1); and
Contract Price (GC 1.1.4.2).
Price Adjustment
The Contract Price is adjusted in the following events:
Claims (GC 20.1);
Use or not to provisional Sums (GC 13.5);
Variations (GC 13.1);
Price escalation (or Ajdustments for changes in Cost) (GC 13.8); or
For Red Book only, changes in the quantities of an item (GC 12.3) such
as:
(i) the measured quantity of the item is changed by more than 10%;
(ii) this change in quantity multiplied by such specified rate for this
item exceeds 0.01 % of the Accepted Contract Amount;
(iii) this change in quantity directly changes the Cost per unit quantity
of this item by more than 1%; and
(iv) this item is not specified in the Contract as a "fixed rate item“.
Payment procedure under Yellow Book and Red Book
56 days
28 days
The Engineer also can instruct such revision, if considers that “actual
progress is too slow to complete within the Time for Completion” or
“progress has fallen (or will fall) behind the current programme”, in
accordance wit the SC 8.6 [Rate of Progress].
Programme [GC 8.3] and Claims [GC 20.1]
• When claiming Extension of Time, the same is always (in vast majority of the
cases), measured & quantified on the Programme which was valid at the
time of the delay.
• When a (critical) activity uses more time than has been allocated to it in the
Programme, there are four possible scenarios:
1. Use time-contingency of delayed activity (shorten duration) to
eliminate any deviation from Baseline.
2. Re-sequence and/or shorten remaining activities to absorb the
impact/overrun of the potential delay.
3. Agree later date for completion (EOT).
4. Suffer Delay Damages.
Date(s)
Contractor’s intention on how the works will be executed, needs to reflect the
requirements and constraints of the Contract. Generally, in sense of the
POW, these constrains are:
Time for Completion (general or for Sections);
Any milestones defined in Contract (penalized deadlines).
PROGRESS
Contractor’s progress is expected to be in accordance with the POW and with
reference to Time for Completion (SC 8.6 Rate of Progress).
Obligation to proceed “with due expedition and without delay” i.e. show
actual progress as to complete within the Time for Completion.
Keep in mind:
Engineer has no power to reject the POW, simply because he has a different view
as to how the work should be carried out or the work could be carried out in another
way that is more convenient to the Employer.
What Employer owes to us under the Programme? [GC 2.1 &
8.3]
Right of ACCESS to the SITE
Duty to provide access to and possession of the Site by the Employer is in some cases
dependent on the Contractor’s POW. In accordance with the Sub-clause 2.1 [Right of
Access to the Site]:
if no time(s) is stated in the Appendix to Tender, the Employer must give the
Contractor such right of access and possession “within such times as may be
required to enable the Contractor to proceed in accordance with the Programme”
ATTENTION:
Dates of Site Access are an essential part of the POW
But – under FIDIC – Time for Completion starts with Commencement Date.
Claim Procedure
Claim procedure
Failure to do so, the Contractor may have its entitlement reduced or be time-
barred (28-days rule) even if the Contractor has a good entitlement
Do not be afraid to
send notice!
Claim Procedure: General [GC 20.1]
GC 20.1 is the key clause in respect of Contractor’s claims and provides for
the main requirements:
- Notice of claim within 28 days after being aware of the event or on the
date on which it should have been aware of;
and
- Fully detailed claim with supporting particulars within 42 days after
being aware of the event or on the date on which it should have been
aware of (i.e. not the date of the first notice).
However, the Contractor should follow the other requirements provided in the
Contract:
i.e.: Notice of change in standards [GC 5.4];
i.e.: Notice of Unforeseeable Physical Conditions [GC 4.12];
i.e.: Notice of Force Majeure event within 14 days [GC 19.2]; or
i.e.: Notice of any event which may adversely affect the Works or Contract
[GC 8.3].
Claim Procedure: Overview
Settlement YES
of Claim Fair Determination by
Agreement to Successful
Engineer In accordance NO
the Determination Consultation
With Sub-Clause 3.5
Occurence of NO
a dispute
YES
… Settlement
of Claim
Time bar: Notice to be sent within 28 days
In any case, it is key to send a notice of claim within 28 days at the latest to
reserve Contractor’s rights !
If the Contractor fails to give notice of a claim within such period of 28 days, the
Time for Completion shall not be extended, the Contractor shall not be
entitled to additional payment, and the Employer shall be discharged
from all liability in connection with the claim.
IF…
and IF …
and IF …
THEN …
4. this delay or disruption will be a cause under paragraph (b) of Sub-Clause 8.4
[Extension of Time for Completion]
AND
Sub-Clausse 17.3 & 17.4 – Employer’s Risks & Consequences of Employer’s Risks
IF…
1. to the extent that any of the risks listed in Sub-Clause 17.3 above
results in loss or damage to the Works, Goods or Contractor’s Documents,
and IF …
2. the Contractor suffers delay and/or incurs Cost from rectifying this loss or
damage,
THEN …
3. the Contractor shall be entitled to payment of any such Cost*, which shall be
included in the Contract Price.
and IF …
4. In the case of sub-paragraphs (f) and (g) of Sub-Clause 17.3 [Employer’s Risks],
THAN …
• Personnel Costs
• Salary
• Insurance
• Medical Care & Check
• Housing
• Transportation
• Professional Licenses
• Work Permits
• Food
• etc.
• Each month is take as a separate „window“, for which all incurred costs are
calculated in total.
• Than from such total costs, certain amount of costs is taken as compensable by
proportional number of critical delay days incurred in same month.
• Nevertheless, not all delay are giving the entitlement for the Contractor to claim
costs therefore, appropriate adjustment FROM “total critical delays” TO “critical
delays on reasons giving the Contractor entitlement for reimbursement for
costs” needs to be differentiated.
Procedure: Response from Engineer
- with approval;
Then the Engineer will then cancel, confirm or vary the Instruction.
Procedure for Variation [GC 13.3]
for each item of work, the appropriate rate or price for that item
specified in the Contract (usually in the BoQ)
where no such item exists, then item for similar work specified in
the Contract
a new rate or price shall be used if:
no rate or price is specified in the Contract for this item, and
no similar rate applicable as item is not similar or executed
under different conditions
Evaluation of Variation (only Red Book) (ii)
IS………:
RECORDS!
Suspension & Termination
Right of suspension under FIDIC Yellow and Red Books (i)
The Contractor may suspend or reduce the rate of the Works in three (3)
circumstances under GC 16.1:
- the Engineer fails to certify within 28 days from the submission
of the statement;
- the Employer fails to pay within 56 days from the submission
of the statement; or
- the Employer fails to provide reasonable evidence that it has
sufficient financial arrangements to pay the Contract price in a
timely manner
Contractor´s
submission Certification of the IPC Contractor´s notice of
of statement by the Engineer suspension Beginning of
under Sub-Clause 16.1 suspension
56 days 21 days
Beginning of
suspension
28 days 21 days
Contractor´s notice of
suspension
2 cases to issue a notice under Sub- i) Non issuance of the IPC within 28 days from the submission of the Statement
Clause 16.1 ii) Non payment by the Employer within 56 days from the submission of the Statement
Right of suspension under FIDIC Yellow and Red Books (iii)
28 days 21 days
Contractor‘s obligations after end of suspension
The Contractor shall restart the Works even if no express notice was sent by the
Engineer or the Employer
In respect of what Works the Contractor has to do, the Contractor has to
continue to “proceed in accordance with the programme” [GC 8.3].
Contract termination at Contractor‘s risk and fault
Contract provides for, at least, seven (7) grounds for the Employer to terminate
the Contract at Contractor‘s risk and fault [GC 15.2]
(a) fails to issue the Performance Security or comply with a notice to correct a
default,
(b) abandons the Works or otherwise plainly demonstrates the intention not to
continue performance of his obligations,
(c) without reasonable excuse fails to:
(i) proceed with the Works in accordance with Clause 8
[Commencement, Delays and Suspension], or
(ii) comply with a notice issued under Sub-Clause 7.5 [Rejection] or
Sub-Clause 7.6 [Remedial Work] within 28 days
Procedure for termination
Upon termination, the Contractor shall leave the site, deliver all Goods,
Contractor's documents [including design] required by the Engineer
The Engineer shall consult the Parties or, as the case may be, make a
determination on the value of the Works done
The Employer may withhold payment until the cost of completing the
Works is known
The Employer may recover from the Contractor all costs incurred
The Employer may terminate the Contract at any time for convenience
but not for giving Works to other Contractors [GC 15.5] under Yellow
Book and Red Book
Termination takes effect 28 days after (i) the receipt of the notice
and (ii) the return of the Performance Security
FIDIC provides for seven (7) grounds for the Contractor to terminate the
Contract at Employer´s risk and fault [GC 16.2] following a 14 day prior
notice
The most significant events are that a:
(a) Failure of the Employer to pay an amount due within 42 days,
(b) Failure of the Engineer not certify a Statement with 56 days after receiving
payment Statement,
(c) Substantial failure of the Employer to perform its obligations under the
Contract,
(d) Failure of the Employer to provide reasonable evidence of financial
arrangement within 42 days from the notice of suspension under Sub-Clause
16.1.
YES
Settlement
of Dispute
What is a dispute?
either Party may refer the dispute in writing to the DAB for its decision.
Appointment of the DAB
FIDIC Yellow and Red Books proposes to solve any dispute which arose
between the Parties by a Dispute Adjudication Board (“DAB”)
In Red Book, the Parties may jointly request a formal opinion to the
DAB (not provided in the Yellow Book)
DAB Procedure (i)
Employer submits
Statement of Defence
Contractor submits
84 days Statement of Reply
DAB decision
DAB Procedure (ii)
DAB Decision
final and binding
Clause 20.5 „Amicable Settlement“ stage
Arbitration
Clause 20.6 within 56 days Notice of Dissatisfaction
Saveti (ii)
• Troškovi DAB i dužina procesa su značajno niži & kraći od sudskih / arbitražnih.
- Saslusanje strana
(Zakazuje arbitrazni sud)
! Republika Srbija:
• Domaća arbitražna odluka ima snagu domaće pravnosnažne sudske odluke
• Strana arbitražna podleze postupku priznanja od strane nadležnog suda
FIDIC 2017
5 Decembra 2017 u Londonu je objavljen set novih FIDIC
Ugovora: Crvena Knjiga, Zuta Knjiga i Srebrna Knjiga
Tokom jednogodisnjeg „probnog“ perioda, brojne kritike su
upucnene na racun novih izdanja
Praksa ?
Neke od izmena:
a) Znatno je povecan sadrzaj, unete su mnoge nove definicije;
b) Clan 3.7 [Determinations] zamenjuje dosadasnji Clan 3.5, definise detaljno
vremenska ogranicenja i ulogu Inzenjera u vezi sa Claims;
c) Clan 8.3 [Programme] predvidja da Program mora da bude odobren od
strane Inzenjera;
d) Predvidja se standing DAB i dodatna vremenska ogranicenja
e) Clan 20 [Claims, Disputes and Arbitration] je podeljen na Clan 20
[Employer's and Contractor's Claims] and Clan 21 [Disputes and Arbitration]
sa ciljem razgranicenja izmedju uobicajenih Claims i ozbiljnih sporova;
! NASTAVICE SE …
Pitanja?