Project Estimator Tool
Project Estimator Tool
Technical
BASIS BASIS $1,200 0% 0 $0 50% 25 $30,000 90% 76 $90,720 100% 77 $92,400 100% 23 $27,600 201 $240,720
ABAP 1 Conv/Int/Rep $800 0% 0 $0 50% 25 $20,000 90% 76 $60,480 100% 77 $61,600 100% 23 $18,400 201 $160,480
ABAP 2 Conv/Int/Rep $800 0% 0 $0 0% 0 $0 90% 76 $60,480 100% 77 $61,600 50% 12 $9,200 164 $131,280
ABAP 3 Conv/Int/Rep $800 0% 0 $0 0% 0 $0 90% 76 $60,480 100% 77 $61,600 50% 12 $9,200 164 $131,280 $795,040 893.5 7148
ABAP 4 Conv/Int/Rep $800 0% 0 $0 0% 0 $0 90% 76 $60,480 100% 77 $61,600 50% 12 $9,200 164 $131,280
Subtotal 0.0 0 $0 1.0 50 $50,000 4.5 378 $332,640 5.0 385 $338,800 3.5 81 $73,600
Security
Subtotal 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 0 $0 0
Specialists
Travel $85,000 0 0
Travel $0 $25,000 $25,000 $25,000 $10,000
Subtotal 0.0 0 $0 0.0 0 $25,000 0.0 0 $25,000 0.0 0 $25,000 0.0 0 $10,000 85000 $85,000
Grand Totals $584,000 ### ### $234,940
Page 1
Partnering
Project Days
275.00 2% 23% 31% 37% 8%
Consultant Role Lvl Rate PP Alloc PP Days PP Fees Alloc BB Days BB Fees Alloc RZ. Days RZ. Fees Alloc FP Days FP Fees Alloc GOL Days GOL Fees Total 8
10/1/02 5 10/4/02 10/7/02 62 12/31/02 1/2/03 84 4/30/03 5/1/03 101 9/30/03 10/1/03 23 10/31/03 Fees Days Hours
Functional $2,281,223 2,868 22945.21
SAP Tech. Project Lead PM MGR1 $1,400 100% 5 $7,000 80% 50 $69,440 90% 76 $105,840 70% 71 $98,980 100% 23 $32,200
FI Consultant FI FC-4 $1,200 100% 5 $6,000 80% 50 $59,520 90% 76 $90,720 70% 71 $84,840 50% 12 $13,800
CO Consultant(Akzo) CO xxx $0 0% 0 $0 80% 50 $0 90% 76 $0 70% 71 $0 50% 12 $0
MM Consultant MM FC-4 $1,200 100% 5 $6,000 80% 50 $59,520 90% 76 $90,720 70% 71 $84,840 100% 23 $27,600
PP Consultant(Akzo) PP xxx $0 0% 0 $0 80% 50 $0 90% 76 $0 70% 71 $0 100% 23 $0
PM Consultant PM/AM/QM/WM FC-4 $1,200 0% 0 $0 50% 31 $37,200 50% 42 $50,400 25% 25 $30,300 25% 6 $6,900
SD Consultants SD1 FC-4 $1,200 100% 5 $6,000 80% 50 $59,520 90% 76 $90,720 70% 71 $84,840 50% 12 $13,800
SD Consultant (Akzo) SD2 xxx $0 0% 0 $0 50% 31 $0 50% 42 $0 70% 71 $0 50% 12 $0
Subtotal 4.0 20 $25,000 5.8 360 $285,200 6.4 538 $428,400 5.2 520 $383,800 5.3 121 $94,300 $1,216,700 1558.1 12464.8
Technical
BASIS BASIS AC-4 $960 0% 0 $0 49% 30 $28,867 90% 76 $72,576 70% 71 $67,872 100% 23 $22,080
ABAP 1 Reports AC-3 $800 0% 0 $0 49% 30 $24,056 90% 76 $60,480 70% 71 $56,560 100% 23 $18,400
ABAP 2 Interfaces AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
ABAP 3 Conversions AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
ABAP 4 Enhancements AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
Subtotal 0.0 0 $0 1.0 60 $52,923 4.5 378 $314,496 3.5 354 $294,112 3.5 81 $68,080 $729,611 872.14 6977.12
Security
Subtotal 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 $0 0 0
ES / Chg Mgt 0
Training FI Chg Mgt EC-4 $800 0% 0 $0 49% 30 $24,056 90% 76 $60,480 64% 64 $51,308 0% 0 $0
Training MM Document EC-4 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 64% 64 $51,308 0% 0 $0
Training SD Chg Mgt EC-4 $800 0% 0 $0 0% 0 $0 0% 0 $0 64% 64 $51,308 0% 0 $0
Training SD RISK EC-2 $560 0% 0 $0 0% 0 $0 0% 0 $0 64% 64 $35,972 0% 0 $0
Subtotal 0.0 0 $0 0.5 30 $24,056 1.8 151 $120,960 2.5 257 $189,896 0.0 0 $0 $334,912 437.911 3503.288
Specialists 0
QTR4 2002 QTR 1 2003 QTR2 2003 QTR3 2003 QTR 4 2003 TOT 2002 TOT 2003 PROJECT TOTAL
$ 387,179 $647,892 $554,920 $528,852 $162,380 $ 387,179 $1,894,044 2,281,223
Page 2
Staffing
Project Days
275.00 2% 23% 31% 37% 8%
Consultant Role Lvl Rate PP Alloc PP Days PP Fees Alloc BB Days BB Fees Alloc RZ. Days RZ. Fees Alloc FP Days FP Fees Alloc GOL Days GOL Fees Total 8
10/1/02 5 10/4/02 10/7/02 62 12/31/02 1/2/03 84 4/30/03 5/1/03 101 9/30/03 10/1/03 23 10/31/03 Fees Days Hours
Functional $1,539,416 1,614 12909.96
SAP Tech. Project Lead PM MGR1 $1,400 50% 2.5 $3,500 50% 31 $43,400 50% 42 $58,800 50% 51 $70,700 50% 12 $16,100
FI Consultant FI FC-4 $1,200 100% 5 $6,000 80% 50 $59,520 90% 76 $90,720 70% 71 $84,840 50% 12 $13,800
CO Consultant(Akzo) CO xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
MM Consultant(Akzo) MM xxx $0 100% 5 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
PP Consultant(Akzo) PP xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
PM Consultant(Akzo) PM/AM/QM/WM xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
SD Consultants SD1 FC-4 $1,200 100% 5 $6,000 80% 50 $59,520 90% 76 $90,720 70% 71 $84,840 50% 12 $13,800
SD Consultant (Akzo) SD2 xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
Subtotal 3.5 17.5 $15,500 2.1 130 $162,440 2.3 193 $240,240 1.9 192 $240,380 1.5 35 $43,700 $702,260 567.3 4538.4
Technical
BASIS(Akzo) BASIS xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
ABAP 1 Reports AC-3 $800 0% 0 $0 49% 30 $24,056 90% 76 $60,480 70% 71 $56,560 100% 23 $18,400
ABAP 2 Interfaces AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
ABAP 3 Conversions AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
ABAP 4 Enhancements AC-3 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 70% 71 $56,560 50% 12 $9,200
Subtotal 0.0 0 $0 0.5 30 $24,056 3.6 302 $241,920 2.8 283 $226,240 2.5 58 $46,000 $538,216 672.77 5382.16
Security
Subtotal 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 0.0 0 $0 $0 0 0
ES / Chg Mgt 0
Training FI Chg Mgt EC-4 $800 0% 0 $0 49% 30 $24,056 90% 76 $60,480 64% 64 $51,308 0% 0 $0
Training MM Document EC-4 $800 0% 0 $0 0% 0 $0 90% 76 $60,480 64% 64 $51,308 0% 0 $0
Training SD Chg Mgt EC-4 $800 0% 0 $0 0% 0 $0 0% 0 $0 64% 64 $51,308 0% 0 $0
Training SD(Akzo) Risk xxx $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0 0% 0 $0
Subtotal 0.0 0 $0 0.5 30 $24,056 1.8 151 $120,960 1.9 192 $153,924 0.0 0 $0 $298,940 373.675 2989.4
Specialists 0
QTR4 2002 QTR 1 2003 QTR2 2003 QTR3 2003 QTR 4 2003 TOT 2002 TOT 2003 PROJECT TOTAL
$ 226,052 $452,340 $384,090 $387,234 $ 89,700 $ 226,052 $1,313,364 1,539,416
Page 3
Rates
Hours/day 8
Page 4