Short Circuit Guide Example PDF
Short Circuit Guide Example PDF
INTERN EXPERIENCE AT
An Internship Report
by
DOCTOR OF ENGINEERING
December 1981
INTERN EXPERIENCE AT
An Internship Report
by
c g r-
(Member) (Member)
l
| \ X ^ f v v x - -- j V
(Member) (Member)
/ ^ .
December 1981
ABSTRACT
Engineering, Inc. during the period September 1980 through August, 1981
is presented. During this one year internship, the author was assigned
plant. The other was the design of a 8.2 MW induction generator for
cogeneration.
relaying and SCADA systems for the projects. Secondly, he assisted the
work;
All my committee members, Dr. C. W. Brice, Dr. Biman Das, and Dr. G.
internship;
Mrs. Judy Humphrey who graciously provided her competent and profes
Supports 27
Protection 89
REFERENCES 157
APPENDIX I 159
VITA 163
L IS T OF F IG U R E S
PAGE
Devices 19
Basis Devices 21
Generator 60
Direct-Connected 78
Generators 82
Design 100
Transformer 122
Current if 160
L IS T OF T A B LE S
PAGE
INTRODUCTION
to bridge the gap, if any, between the academic and the industrial
environments.
ethical practices, and the interactions between the company and the in
dustrial environments.
ciency of energy usage or to find new energy sources other than petro
Mr. Albert J. Smith and Mr. Thomas C. McMichael, who at that time had
Its first project was the design, construction, and the operation of a
300 MW combined cycle power generation plant, the largest base load
combined cycle gas turbine power plant ever built at that time.
by the shift in fuel cost and availability today, Power Systems Engi
and meet their specific requirements by the most cost effective methods.
generation projects.
neering consultant, the firm always tries its best to employ procedures
and techniques which are cost effective and result in overall savings
for its clients. Power Systems Engineering has designed and built a
wide range of industrial power and utility projects from small to very
installations.
Figures 1.1 and 1.2 show the overall structure of the firm, with
deparmental functions. It is clear that the organization form is of
(1) The project team can respond more quickly and move effective
neers from each discipline as needed are assigned to handle all engi
the project engineer are design, drafting, and logistic teams. Each
individual project engineer also acts as liaison with the client for
engineers.
CHAPTER 2
ally be made on the basis of voltage drop, power loss, maximum allowable
tics will be covered under Sections 2.2 and 2.3 separately. Instrument
transformer performance and the R-X diagram are two key topics in power
2.5 separately. Although this chapter and the following three chapters
is it implied that other aspects are not important and can be neglected.
occurs. On the other hand, other parts of the system should be capable
Law. There are several methods or algorithms for fault current calcu
fault calculation.
asymmetrical wave form whose magnitude varies with time after the
fault. Then a question like "When should the fault current be calcu
(1) The first cycle: First cycle maximum symmetrical values are
always required. They are often the only values needed for low voltage
systems and for fuses in general. These values are usually related to
(2) From 1.5 to 4 cycles: Maximum values are required for high
breakers.
both the maximum and the minimum values are often required. Sometimes,
the minimum values are estimated as fractions of the maximum values for
Power frequency currents which flow during a fault come from elec
the impedance of the machine and the impedance between the machine and
but is complex and varying with time. For purposes of fault current
the terminals.
to the remote and relatively large central station generators, and this
cvi_i ) 2
Z syg (ohm)
Available short circuit level in MVA from
the utility sytem at the point of connection
This diagram should show all sources of short circuit currents and all
under Step 5.
that they are in parallel with other network branches. This is so be
cause system load currents are usually negligibly small compared with
the high fault current. This assumption implies that from a system
voltage (Eo) can be taken as the system nominal voltage at the moment
fault occurs. Therefore, when using the per-unit system, the driving
voltage is equal to 1.0 per unit if the voltage bases are equal to
system nominal voltages. This will greatly simplify the calculation
in Step 5.
line diagram obtained from Step 1. For many short circuit studies at
ratios when applying high and medium voltage circuit breakers, but they
This step is the most straightforward one, but it may be most time con
suming too.
locations.
This step uses different impedances for the rotating machines to calcu
late the short circuit currents depending upon the purpose of the
(a) First cycle duties for fuses and low voltage (below 1 KV)
circuit breaker.
and above).
detail.
For first cycle duties of fuses, switches, and low voltage circuit
with ANSI C37.13, ANSI C37.41, NEMA AB, and NEMA SG latest standards.
reactance is 0.25 p.u. based on the lump sum KVA rating of the machines.
each fault location can be obtained. Then the symmetrical short circuit
^■sym = So p.u.
Z f
For those low voltage circuit breakers whose short circuit ratings
given in terms of total rms currents, the symmetrical short circuit cur
For first cycle duties of high voltage circuit breakers, the cal
After the first four steps stated above, a single impedance Xf for
each fault location can be obtained. Then the first cycle asymmetrical
Itot = — x 1 - (>
Xf
This is the short circuit duties for comparison with high voltage (above
reactance multiplier from Table 2.1. Consider first the duties for
the high voltage circuit breaker rated on the total current basis.
f/Rf correction from curves shown in figure 2.1 [5]. To use the curves
Power S ystem s
ROTATING m a c h i n e reactance multipliers
E ngineering, Inc.
P.O. Box 19398
Houston. Texas 77024
JL JO B NO. N/A DATE
T Y P E OF R O T A T I N G
MACHINE MOMENTARY INTERRUPTING
mines the choice between graphs for fault fed predominantly from local
capability.
Next consider the high voltage circuit breaker rated on the symmet-
F Y
rical current basis. Calculate o/Xf and f/Rf ratios and select the
multiplying factor from Figure 2.2 as in the total current basis case.
calculated as,
3 CY CL E
'C IR C U I T
BREAKER
M ULTIPLYING FACTORS
M u ltip ly in g Factors for Three-Phase Faults Fed Predom inantly from Generators
T hrough No More Than One Transform ation (From IE E E Std 320-1972)
multiplying f a c t o r s
M u ltip ly in g Factors for Three-Phase and Line-tcGround Faults Fed Predom inantly
T hrough Two or More Transformations (From IEEE Std 320-1972)
Figure 2.2 MULTIPLYING FACTORS FOR SYMMETRICAL CURRENT RATING BASIS DEVICES
The short circuit study for time delayed relays, known generally as
and impossible as the size and complexity of the system increase. Digi
tal computers are generally used for major fault studies in the industry.
losses. The cost of the energy losses through resistance is also im
cases, it may pay to use the conductors at less than their ampacity.
classical economic theory is the one that makes the annual cost of the
For substation buses, ampacity and energy loss are two factors
and insulation of the line. Because of the extra high voltage generally
a result, long spans are usually used. For building wires and cables,
other hand, the National Electric Code specifies that the size of
feeder conductors should be such that the voltage drop will not be
more than 3% for power loads and 2% for lighting loads or combined
mined by the tempeature rise resulting from the power loss of conduction
and any other heat gained by the conductor. Since most equipment to
temperature that would cause heat to flow into the apparatus. Such heat
the maximum operating temperature below 80°C for copper conductors, be
low 100°C for aluminum conductors, below 95°C for single layer ACSR
12R + Q, = Qr + Qc
Qc = 0.283 d ^ ’5 at altitudes
(1 0 , 0 0 0 feet and above)
*Q„
>-
= 0.1695 [— DdV ] 0 # 6 K (t C - ta) if 1,000 < DndV
U ___
< 18,000
u u
where D = conductor diameter in inches
conductor.
CMOSPHERICAL DATA FOR AMPACITY CALCULATION Power S ystem s
Engineering, Inc.
P.O. Box 19398
JL N/A Houston, Texas 77024
JO B NO. DATE
TABLE A VISCOSITY, DENSITY AT SEA 1 E V E L T O 15,000 FT, AND THERMAL CONDUCTIVITY OF AIR
M l - ---
THERMAL
T E M PER A T U R E / K \‘ A ESO IU T E DENSITY, d CONDUC-
I _ 1 VISCOSITY, TIVITY,
V io o y SEA LE V tt 5,000 FT 10,000 FT 15,000 FT
K u
■' K !
32 C j ./ 3 55.55 C.C415 0.0807 a ni 71 0.0554 0.0455 0.00739
41 5 273 59.73 0.C42! 0.0793 0.0660 0.0545 0.04.47 0.007 50
‘ 50 ■C 2 63 *4 14 0.04 27 0.0779 0.0648 0.0535 0.0439 0.00762
59 15 2S8 68.80 0.0433 0.0765 0.0636 0.0526 0.0431 0.CC773
68 in 292 7370 0.0439 0.0752 0.0626 0.0517 0.04 24 0 00784
77 25 296 7c. 86 0.0444 0.0740 0.061 6 0.0508 0.04 T7 C.C0795
86 30 303 E*.29 0.0450 0.0728 0.0606 0.0500 0.041 1 0.00807
95 35 305 89.99 0.0456 0.0716 0.0596 0.0492 0.0404 0.0051 e
104 40 313 95.98 0.0461 0.0704 0.0586 0.0484 0.0397 0.00830
113 45 3l 6 102.26 0.0467 0.0693 0.0577 0.0476 0.0391 0.00841
122 50 323 1OS.85 0.0473 0.0683 0.0568 0.0469 0.0385 0.00852
131 55 328 1 15.74 0.0478 0.0672 0.0559 0.0462 0.0379 0.00864
140 60 333 122.96 0.0484 0.0661 0.0550 0.0454 0.0373 0.00875
149 65' 338 130.52 0.0489 0.0652 0.0542 0.0448 0.0367 0.00886
158 70 34 3 138.41 0.0494 0.0643 0.0535 0.0442 0.0363 0.00898
167 75 348 146.66 0.0500 0.0634 0.0527 0.0436 0.0358 0.00909
176 80 353 155.27 0.0505 0.0627 0.0522 0.0431 0.0354 0.00921
185 85 358 164.26 0.0510 0.061 6 0.051 3 0.0423 0.0347 0.00932
194 90 363 173.63 0.0515 0.0608 0.0506 0.041 8 0.0343 0.00943
203 95 368 183.40 0.0521 0.0599 0.0498 0.0412 0.0338 0.00952
212 100 373 193.57 0.0526 0.0591 0.0492 0.0406 0.0333 0.00966
20 62 78 87 0 62 282
25 62 88 88 180 62 272
30 62 98 83 180 62 262
TABLE C TOTAL HEAT RECEIVED BY SURFACE 35 61 107 78 180 61 253
AT SEA LEVEL N O RM A L TO SUN’S RAYS 40 60 1 15 73 180 60 245
45 57 122 68 180 57 238
50 54 128 63 180 54 232
q.. WATTS/SO FT 60 47 137 53 180 22 3
i ^
SO LA R 70 40 143 43 180 | 40 217
ALTITUDE, CLEAR INDUSTRIAL
Hc, DEGREES A TM O SPH ER E A TM O SPH ERE
5 21 J 12.6
10 4 0.2 22.3
15 U .2 30_5
20 64.4 39.2
25 71.5 46.6
30 . 77.0 53.0
35 £ 1_5 57.5
40 £4.5 61.5
45 £7.4 64.5
50 90.0 67.5
60 92.9 71.6
70 9 r-0 75.2
80 95.8 77.4
90 96.4 78.9
tor, 0.23 for new conductor and 0.5 for average oxidized
conductor.
(1) Heat loss carried off by conduction through supports and con
head lines, and cables. For medium voltage substations, the size of
cuit currents. For high voltage buses, where currents are relatively
lower and the phase spacing is larger, the deflection under short cir
cuit of the conductor usually determines the bus size. A good practice
where only two supports are used and qq ~ where three or more supports
are used. For overhead lines, fault currents are more likely to cause
the conductor, than direct mechanical damage. However, the high elec
sign and selection of line supports, spacers, dampers, and other equip
ment. For all insulated wires and cables, heating caused by short
the life of cable and wire insulation is about halved and the failure
operating conditions.
other according to Ampere’s Law. The basic formula for force between
D (107)
Where Ij and 1 2 are current in each wire, D is center-to-center spacing
and are decreasing with time. There are various methods to calculate
very great forces might result. This method involves data on buses,
ance and economy, high voltage substations are generally designed with
the natural frequencies of such high voltage bus systems are normally
much lower than the f r e q u e n c y of the current in the bus. Even for
those applications where resonance might occur, the problem can be eas
developed over a half cycle instead of that delivered by the wave peak.
force [9]. This theory is true only if the average force is maintained
indefinitely and the forces are a series of impulses. Even worse, there
is no clearly defined safety margin for all design based on this
theory.
The use of the first half-cycle peak value of the current wave is
a sound and sensible basis for the worst case design. This gives the
types of fault will result in the maximum short circuit forces available
are derived on the base of peak current value during the first half
wave and the rms value of the corresponding symmetrical current wave
if no offset is present.
have any offset, the peak value of the wave is equal to yfl times the
rms value.
Fs - 5.4 (7? Is ) 2
D(107 )
= 10.8 Ig2
D(107 )
D(107 )
= 43.2 Is2
D(107 )
If the rms asymmetrical value over the first half-cycle is given, the
D(107)
“ 1 4 -4 ! a2
D(107)
short circuit must occur 45° after zero current value in phase B. Any
dition. At the instant of short circuit, phase B current will have the
value of 0.7071 (that is, sin 45°) times the prefault current peak
value; phase A current will have the value of 0.2588 (sin 15°) times
and phase C current will have - 0.9659 (sin 255°) times the prefault
short circuit [10] . Neglecting the decrement during the first half
F» ■ 1 8 -7 v 2
D(107)
In the case where the rms symmetrical value is given, the peak
value equals^ 2 ~ Is
Fs - 18.7 ( /2 Is)2
D(107)
- 3 7 ~* !s2
D(107)
from a three phase fault is v/3/2 times that from a single phase fault,
assuming that the current per phase of the two types of circuits are
the same. However, on the same circuit, the three phase short circuit
currents are usually greater than those of line-to-line faults and the
half-cycle rms value of the fault current, the forces on phase B con
Fg = 14.4 (0.866) Ia 2
D(107 )
" 1 2 ‘5 Xa 2
D(107 )
By a similar analysis, the maximum force on either outside conduc
tor can be derived. Table 2.3 summarizes the maximum forces due to
since the currents are 120° out of phase and no time can be selected so
that all three are simultaneously zero. It should be pointed out that
all formulas are derived on the basis of the following two assumptions:
individually.
cept hydraulic generators, is used for the first cycle duty. Therefore,
short circuit force analysis. On the other hand, if the results from a
SHORT-CIRCUIT FORCE ON BUS CONDUCTORS Power S ystem s
Engineering, Inc.
P O. Box 19398
Houston, Texas 77024
JL JO B NO. N/A DATE
M A X IM U M f,
SHORT-CIRCUIT
FORCE ON IN P O U N D S
CURRENT, /, TYPE OF FAULT C O N FIG U R A T IO N
CO N D U C TO R PER FT.
G IV EN AS
(D in IN C H ES)
A B
o o F_ 5.4 \-
D-C A or B
r— D—H D (107)
Single- A B
o o F _ 10.8 /2
RAAS symmetrical Phase A or B
Symmetrical ~ D (107)
Single- A B
RMS symmetrical Pnase o o F _ 43.2/2
A or B
Asymmetrical h-D -H ~ D (107)
Single- A B
RMS asymmetrical Phase o o A or B /: _ u -4 I s ■
Asymmetrical H— d —-! D (107)
Three- A B C
o. o o F 37.4 /2
RMS symmetrical Phase B
Asymmetrical hD-r-DH D (1 0 7)
Three- A B C
RMS asymmetrical Phase o o o B F_ /2
Asymmetrical H-d -t -d H ~ D (107)
Three- A B C
RMS symmetrical o o o F_ 34.9 I 2
Phase A or C
Asymmetrical k-D-n*-DH ~ D (107)
Three- A B C
RMS asymmetrical o o o F_ n .6 / 2
Phase A or C
Asymmetrical h-d -4*-d H D( I O-)
Three-
V D D / F 37.4 r-
RMS symmetrical Phase A, B or C
Asymmetrical
XO O X ~ D (1 0 7)
A k- d —; c
Three- D ° D F_ 12.5 I 2
RMiS asymmetrical Phase A, B or C
Asymmetrical ~ D (1 0 7)
A —1 C
F=force between two equal long parallel bars before F can be determined.
Fl=force between two long parallel straight round
The above curves have been drawn neglecting skin
conductors (see section on short circuit forces)
effect and assuming that the current density is uniform
To use the curves, F 1 must be computed according to over the section of conductors.
the discussion on forces due to short circuit currents
ductor is also subjected to the loads from its own weight, ice, and
vided into three districts for which standard loading conditions are
specified in National Electric Safety Code [11]. The loading for the
various districts is shown in Figure 2.4. The wind load on the con
ductor is
H = P(D + 2t)
12
Figure 2.4
I = 1.24t (D + t)
the ice weight and the conductor weight are in the vertical direction;
| Fig 250-1
I General L oading Map o f United States w ith Respect
I to Loading o f Overhead Lines
Extreme W ind
L oading Districts L oading
(For use w ith (For use w ith
Rule 250B) Rule 250C)
R ad ial thickness of
ice (in) 0.50 0.25 0 0
H orizon tal wind
pressure in lbs
per sq ft 4 4 9 See Fig 250-2
T em perature (°F ) 0 +15 +30 +60
C onstant to be
added to the re
sultant in pounds
per foot:
All conductors 0.30 0.20 0.05 0.0
F h 2 + Fv 2 + K
During short circuits, the stresses imposed upon the conductor may
(2) Good substation bus design, especially rigid metal bus, re
stresses on the bus support systems. Because the loads to which they
are subjected, that is, bus weight, short circuit forces, ice and
made by using the formulas for a simple beam. If more than two supports
are required for a single length of bus, the formulas for a continuous
beam apply. Formulas for these two cases are summarized in Table 2.4.
fault current flow, (3) the material and cross sectional area of the
short that for most practical purposes it can be assumed that no heat
rise is determined by only the specific heat of the metal, the size of
the conductor and the heat input. The specific heat varies as the
tors, the maximum safe short circuit currents can be easily calculated
for all-aluminum conductors and 645°C for ACSR conductors. For insu
ing application, caution should be given to the fact that the effect of
heating is cumulative.
volts or less), the effect of fault impedance is such that the actual
current resulting from a fault is usually much smaller than that calcu
be such that the relay will operate before any arcing burndown occurs.
either event, the failure usually takes place at the point of ver
the continuous current ratings of the connected relays and of the sec
load current normally flowing through phase relays, the ratio is usually
At the same time there is usually little need to limit the ratio error
to less than 10% and hardly any need to limit the phase angle for
relaying. Consequently, the basis for classification of performance
age ratings, the ANSI standard [12] also uses two letters, C and T,
current by-passed through the exciting branch can be rather easily cal
and any other transformers whose core leakage flux has a negligible
effect on the ratio within the defined limits. On the other hand,
formers and any others whose core leakage flux affects the ratio
appreciably.
terminals.
This can be justified on the basis that the burden at higher current
is usually less and thus the current transformer will perform better
tion and large errors. Two common methods for performance estimation
class method.
(A) Excitation curve method:
following expressions:
sure the ratio error of a Class C transformer being less than 10% with
should be met.
NV + 100 R > Is (Z + R)
system voltage level and the basic impulse insulation level as required
by the system on which they are to be used. ANSI Standard [12] recog
and connections.
true ratio. These accuracies are normally high enough so that any
standard transformer will not create any problem for relaying applica
The answer to this question will be found in the R-X diagram. Before
the relay will respond to at least three of the following four torque-
producing components:
Thus a general torque equation for the relay will look like:
Torque = ± Kj V 2 t K£ I2 t K 3 V I f (r, 6 ) +
variable magnitudes.
Since a good example can serve hundreds of words, the following example
(90° + r-e).
Remember V/l = Z.
than K 3 /K 1 sin (90° r-6 ) in order to operate the relay. From this
example, it is clear that the value of the R-X diagram lies in the
figure is also shown the impedance seen by the relay located at substa
c «
■u
t: u
3
. o a X'O
°
J w 2Z
w z ? ®
o o •» O)
< -
*
O u.
o
—* ©
_ > ■
- - tr o ■<
u
W o U s ft-
vT o
I ©©©©©
a synchronous generator.
been plotted on the same diagram, the proper protective scheme for the
system can be decided from the R-X diagram. This will be illustrated
GENERATOR PROTECTION
practices and improved materials. Yet failure can occur and may result
in severe damage and long outages if not properly protected. The de
no protection were applied, and acccording to the size and the impor
tion. Since there are very few [4] provisions for generator protection,
ing power system will dictate the type of grounding and protective
ground, and the amount of fault current will depend upon the method
failures and may occasionally involve more than one phase. Insulation
failures occur due to overvoltage or reduced insulation strength, or
is usually due to abuse and aging. Both result in drying out and bak
ing the insulation until it loses its elasticity and approaches the
late. All short circuits in the stator require the repair or replace
tant to limit the duration of a stator fault for the following reasons:
in a fire.
which connect the generator to the rest of the system, these breakers
disconnect and collapse the field, and to de-energize the prime mover
of the machine from its source of power. If the neutral of the genera
tripping of this breaker along with the main breaker and the field
circuit will help to limit the duration of arcing at a ground fault.
a u x i l i a r y or lockout relay. This same relay should also shut down the
ments may prevent the use of low current or fast time settings. It
since overcurrent relays must be set above maximum load current and
must also have time settings which should be coordinated with other
tions [4] .
grounded so that a single ground will not damage the machine at all.
However, since a potential second ground may short part of the field
call for running the unit at reduced speed for several hours with the
operation.
equal to the level required for the system protection, the machine
[13]. For installations where the possible ground fault level exceeds
and 150% maximum of full load current by the use of grounding resistance
each machine is isolated from the others and the system. Hence, the
but not less than the minimum necessary to actuate a protective relay
resistor across its secondary between the star point and the ground
unit system is low reactance grounding. The neutral reactor will gen
erally be selected so that ground fault current will not exceed the
prime mover.
rent transformers so that the net input to the relay is the difference
used and the connection of the machine itself. However, in all these
any other equipments such as meters and other relays to these circuits.
Actually, very few current transformers, even though they are commer
This relay has two or more restraint windings which produce opening
torques and desensitize the relay to high external fault currents.
more sensitive and faster on light internal faults, but less sensitive
on heavy external faults. However, it costs about 25% more than a con
applications:
tions will produce DC current flow in the machine. Since the time
circuits in any part of the winding except a small portion very close
ct
Ul
o.
UJ
< Q_
CC
cc
I—
CL
CD
CL
UJ Qc _J CTL
00
Z <
21
(X CD
CH
i- a.
o:
O
5 Z> 00 Gj c c X
< iT) L lI
O O O o
I-
o g
HH
O
H H
O
HH I T
HP
8 2 cr
<
i£>
CD
iS>
CD oo CO O UJ
in 2 :
fcja
Ll I ^
b o
o c r iljJ
CL Ih-
o
o Ll I
Q
> -1 z :
o < z:
r\J p o
z: V
UJ , ,
QC y
UJ > 7
Q <
current-limiting devices are inserted in the neutral, the effective
the winding next to the neutral for which no protection can be provided
is grounded elsewhere and the fault current is greater than the relay
line current, that is, the phasor sum of the line currents, is balanced
faults will not operate the relay and separate phase relays are re
is so because the lower the relay pickup, the higher its burden on the
fault current and the third harmonic current flowing in the neutral.
This third harmonic current may reach 15% of the maximum generator
system. The relay used must be insensitive to the third harmonic volt
age which may normally exist between neutral and ground, and yet still
ground which accompanies a fault. Since the power transformer and the
if used. The general practice is to use the relay to trip the generator
and requires a service interruption. The relay commonly used for such
to the system operation depending upon the relative size of the genera
discussed.
power from the system. If the system is large enough to supply the
deficiency in excitation through the armature, the machine will operate
nous speed. Since synchrous generators are not designed for asynchro
nous operation, the machine output will oscillate as the rotor rotates
relay should trip the unit or sound an alarm. From the standpoint of
generator protection, most modern generators can run two or three min
utes at full load with zero excitation without endangering the genera
disturbance.
in series with the field circuit. However, this type of relay would
for a unit system protection [15]. Figure 3.3(b) shows system behav
obvious from the R-X diagram that a time delay unit or another mho
will have other burdens connected between phases and possibly between
the total burdens connected between that phase and the other phase and
* - * » © » ■ :-£ i t c # 17 £ i f i e ld i t f u t i l c i b
■ - S W 0 tT - 'U » O ilT E 3 r i f i r I T MODERATE LOAD
C - S n e t T - C lt c u n T t* n t L O »T * 0 1 0 * 5 0 * O F f l -
Cl«£li"!t fin e II KO 1,310.
IT S . CQ IIIf.
/ITT_____ | m r m iT r
BUS
f 34 f a u lt
l «* U » |T* * »f :e « I. c t i t i n 11 1 0 * 9 i* > f S » * c { .
tion on a blown primary fuse, a voltage balance relay (Device No. 60)
during a light load period can approach the loss of excitation condition
tripping.
If the turbine throttle or stop valves are closed while the genera
tor remains connected to the system, the generator will run as a motor,
receiving sufficient power from the system to supply friction and wind
age losses in the unit. The approximate power required to motor a gen
of the lack of adequate steam flow to cool the blades and shroud, and
water flow.
widely accepted. Since safe motoring times will usually be in the order
electrical reverse power relay to trip the unit from the system when
rotor iron, slot wedges, and retaining rings, resulting in rotor heat
is satisfied:
a 2 )2t < k,
Type of Machine k
other hand, none of the other relays are designed to protect expressly
and that the relay trip the generator instead of initiating an alarm.
anced current caused by current transformer errors will not trip the
unit.
mination of backup relays are usually more difficult than for first-line
overcurrent relays, the other uses three single phase distance relays
well as system fault backup protection even if the generator main cir
should be used. With such connection, the relays will backup the
system and generator only when the generator main breaker is closed
and there are no other sources of generation in the system. One point
which deserves special caution in the design of external fault backup
to fuse blowing may cause misoperation of the relays. This can be re
tect ground faults only up to and within unit transformer low voltage
ground fault relay fed from a CT in the transformer high voltage neutral
should be used.
the main circuit breaker, the field breaker and also shut down the
prime mover.
ings which will initiate an alarm. Thus, the condition can be corrected
this application, the relay shall be arranged to open the generator and
will disconnect the armature circuit from the system upon loss of volt
voltage dips.
Since most modern generators are equipped with some type of mechan
operation is more direct and does not depend on the presence of alter
current circuits are within the desired limits of frequency and voltage
are only checking these two sources to insure that they have not become
ing action when the beat frequency, voltage deviation and phase angle
reasonably balanced.
tric energy in all these systems. This section will cover the minimum
quite often included to either supply all or part of the total load or
tem energy are operated almost continuously. They are usually turbine
level. Those used to supply emergency power are normally shut down
and are briefly operated when the normal power source fails or during
Figure 3.4 shows the recommended protection for generators that are
fault current to less than the generator full load current. A current-
polarized directional relay may be used for this application, its op
erating coil being connected to the differential circuit and its polar
ffl
£
0
T3
'ffl 'C
&
ci
ltd
1— !! c
m > , , (0
IQ rH '
tji' +J 1— t © H. rH ffll
ffl' >11 0 ©■ 4J a ffli a ;
G iffli i—m X: rH ’ ■H C ffli (X;
■HI •H I »— t u ffl ‘h ©I 1— t irp!
*o
ffl ffll' if) C 0 iHI Amdi. rH td'
IP 0) a ■"H: irfll *H1 fH 4 -J' P (fl £
o f
irO
o
;|. 1.
t-l'
OQ 0 0 rH ■HI ■0 irH
m © j p
£=
V_-‘ m U ffl •.HI
■HI
u jj' •HI nj
JZ
— m 4 -J1
Re
8 IE-*
© t r O' c c * w Q © K
05 iK n 0 © U' tT1 0 ;m C © ■ -iH -MM
© k c £ Q *0' 'MM!
r—fl ltd 1 +J
ro
"-H. >
© 1— ! ii***
.P ■HI CD
©
W'
0 0 (0
tw C[ -iHI: *HI
(k CJ O'
to ■>— I B +J H Q
O ' id
rH rH C O1 4 -» c ip ; Xi O' c iP
1—1! .m c
0 c C ■HI
ss:
q O (d 0 ffll II
ip ft. k 1© '» k ■
■ ■H O p nj >1 e ra + J ■ffl >1: f f l i ffl' IMi + J
J p k P © -P > - i p 1 ,rC , l* rt ir f ll ■H u e fli to O' ( d 11— II
§o c P 4J 0 c O' *H 1© ir— H X I IH ■B-1 ; k JM •H i
O ' c O ,P © 0 ffl -P e ffl' O' © a!' ffli 0 |RJ,
1 2
H u ffll ■
iIM' 'ffli c O' ■--- V lH! a ms 1 " e i l^ll iH I C l > pij. Ipb x x
I, u © C (0 r fij •H ia © H ffl' ■HI iHj C II
P. ffl k > -P' '<4-11 ffll O +j 4 Jt + J' ;> O -IP' H 00 4J 131
S£
,r-J
y
0 3 O u c -H I :rC 0 M U c •HI 4J :P c c:
4 J,
(X rt O 0
4 J.
td
4 JI
c k 5-41 0 © ,rC ’ C b *T3 I 0 ffl' ,p
4J
k ffll 1© P © ffli a; ffl in JZ
0
u CU rC +J IMl tfd. iH I ■0 0
w ■rH © Ei IQ. W ■ to O' £ ,+ ji (C lMl t T ' .0 ' +J ■O' X c: shi
I) 11 I i 1
I
! III III I 1 CP'
I III III i il *
t It ! i I ■ • IP
k
If III I H I
3
III I I
III I:
O ' t7>
III
I > “iHf
1
1
I
II.
II
I ||Z4
II 0 } II
I
!
$
o o 1 > III 1 O '
O' (M O ' H0 O n,C ir -
til m H£« \0 ffl '0 0 CO'
iHII
■**°
2 Z
u k ...
0 0 '<M>: HUH
■H •HI *ir+
.HA
3 irH S =
& m 0 H
© c ETt ■CP iHI
IP O 'U > 10 ufl :>
-"iH' ■ffl X ■*)■ IE
10 41 iiH ; irH1 m
ji—ii^ O z. ,^_1 'Tjr
iflj O' > •I > IP*;
.iHI1 '13 K r«ic
ffll. 1® ■® > . 'ffl
Ik liM' rHf um 0 c irH1 i i i
fflt iHI > m r-r b
HIIIM •cl ® Q ■w (0 .HI
O' * 0 O' > M 0 "0
g «r < H^JI-
*4 xz ® > ffl' ffl
0 «
r» fijl jQ < K II-PI nX-Jl <
c: " t l 1 ifHII > 1—4 :>
zs irH1, < X O O ifHI < X
c P : -HI > 0 O .HI i> 0
5 % 0 ■ ifHI1 3 ' *4 0
m 0 0 0
m s z ■0® 0 ITT+ ■ffll ■IB O ■—i-
Oil k 0 1 > IM O 1
0 O' lull O O uri O '
c lixi. 4J 1. 1 O 4 .a O'
0 ffll ffl! O ' Ufl us 0 C i
Hji 0 1 — Hi
*r+ ■ffll ©,
J> C' ,»— >
!■ C
llU ,J3i D f fl itf '"^1
"W DS?- a©' ""l— ■
■r,i «rj.
05
04
two points. First, where suitable current transformers are available,
the static exciter, if energized from the stator circuit of the genera
operation.
primary protection for faults in the generator leads and in the trans
the bus and the power transformer. Although the station service trans
A Pow er S y ste m s
UNIT GENERATOR TRANSFORMER ARRANGEMENT
E ngineering, Inc.
p.o. Box 19 39 8
JL JOB N O . N/A DATE 1 H ou st on , Tex as 7 7 0 2 4
Sh of
vice LV circuit breaker only as a backup for the circuits on the sta
erator so that protection is required for all of the unit system. The
speed. Since relay designs vary, the relay performance at reduced fre
other form of useful energy such as heat or process steam in the same
or adjoining facilities.
21 Distance Relay
NOTE: ( ) shows number of 40 Loss-of-Excitation Relay
relays required 41 Field Circuit Breaker
46 Negative-Sequence Current Relay
50 Instantaneous Overcurrent Relay
51v/27 Voltage Sensitive Time Overcurrent
Relay
51N Time Overcurrent Relay
64N Voltage Sensitive Ground Fault Relay
64NT Voltage Sensitive Ground Fault Relay
63 Sudden Pressure Relay
87G Generator Differential Relay
87T Transformer Differential Relay
equipment and slip rings as well as voltage regulation equipment are not
erator always assumes the same output voltage and frequency as that of
current type, not the percentage type. The ground fault protection re
lay (50G) is generally fed from the residual of the primary side current
all power factor, the voltage relaying is required to protect the gen
erator against over and under voltage. There are considerable varia
to initiate an alarm but not to trip the unit circuit breaker. Where
DWG. NO. REV.
H I* vJ=5T, c m P M A 6E B A L A tO C t R E L A Y
S o G r j v j£ 5 1 ”. it H i w i T ^ B O J R R e M f F .E lA Y
Z \G c V J tft D V c f i^ O L t A e E F ? £ L A Y
67 | W S 5 1 If H < j£ > i. D t r F E R E U l l A L RELAY
EX> i ^ N 'T C M P c r? A fU 'R £ M O M lfO f?
S o O / c l u J E j T .u J U UXKO l ^£LO Y
k o iC l ' * j E 5 l I'M \w y T O V 6 R C O R R E U T -R E L A Y
< W £ R : \t f L l4 < j£ R iU k y |
{ { iC P , I i* r U R i3 ilo £ S H O f C O w O O R £ L A .y j
should trip the unit circuit breaker and shut down the generator. In
flow into the utility's incoming line. The relay for this purpose is
TRANSFORMER PROTECTION
reliable device, and this is correct as far as the mean failure rate
(1) Winding failures are the most frequent. Reasons for this in
surge protective devices such as rod gaps and arresters. Two principal
laminations.
cluding thermal relays, gas relays, etc., are designed to detect ab
relaying.
fuses are widely used for this purpose. Although fuses have certain
tain, and generally failsafe. This is true for many transformer sizes;
against external short circuit currents under most conditions, but can
impedances.
ance faults.
Where more sensitive protection is required, it can be achieved by
tion due to the factors stated above although it does protect turn-to-
used to detect either the rate of rise of gas pressure (sudden pressure),
fault relaying for fault protection, and to overload relaying for ab
former operation and even for several times full load current when a
short circuit first occurs, because the unbalance due to the magnetizing
current is small compared with the full load current and far below the
relay pickup.
There are two other types of inrush, that is, recovery inrush and sym
one other transformer on the same bus is already energized. The inrush
the same bus may be nearly a sine wave of fundamental frequency. This
generally either the second or the third order which is generally not
of inrush current.
relay during inrush, care shall be taken that means should not delay
monic components of the inrush current from the parallel banks while
stantial exciting current will flow. In this case there are principally
odd harmonics, particularly the third order. This may misoperate sec
either inside the transformer or outside in the terminal leads but with
current. The required percentage may vary between 15% and 50% depending
(a) Its setting should be above the maximum possible inrush cur
moderate sizes located at some distance from the major source of gen
eration [17].
as follows:
The relay is most suitable for large power transformers located near
ential relay utilizes the fact that a voltage dip always accompanies a
former banks rated 1 MVA and above and with 2400 V and above secondary
removed. For transformers from 1 MVA to 2 MVA and below 15 KV, desen
formers rated 2 MVA and above, or having windings rated 15 KV and high
recommended.
transformers are used on the high tension side and are balanced either
against other bushing type current transformers on the low tension side
general answer can be given to this question, but the procedures for
In order that the relay will get as much current as possible, and
will supply the relay with current approximately equal to its tap rat
cause these transformers show a marked departure from the turn ratio
over the range from very low current to that limited by the power trans
rating to use. This is because it is the voltage ratio, not the indi
using a transformer tap at the middle of its range. Thus, with a plus
rest of the system through two breakers, for example a ring bus or
current.
ground faults, and to compensate for the 30° phase shift introduced by
three or more windings, consider any two windings first and connect the
current transformers for those two windings as if they were the only
may occur and cause misoperation of the relay when ground current flows.
"out" currents that are in phase for a balanced load condition. Where
there are more than two windings, all combinations must be considered,
two at a time.
the relay taps should be so selected that the relay ratio is as close
to ensure that the relay taps selected have an adequate safety margin.
total mismatch should include not only M but also load tap changing
values (LTC).
rent transformer ratio error must not exceed a specific limit depending
(h) The total error of the differential scheme equals M plus LTC
and CT ratio error. This value should be smaller than the relay slope
connected on the delta size, external ground faults on the delta side
will cause zero sequence currents to flow in the wye connected CTs.
example.
The relay has a 25% slope and a time current characteristic curve as
shown in Figure 4.3. The continuous and short time current ratings of
Yes!
Figure 4
A THREE-WINDING TRANSFORMER BANK AND CTS' P ow er S y ste m s
CONNECTION FOR DIFFERENTIAL PROTECTION E ngineering, Inc.
P O. Box 19 398
Hous to n. Tex as 7 7 0 2 4
IV JL JO B N O . N/A DATE Sh 1 of 1
4 A
U J ^ 44KV
110 K V A
— m -
i
P A 1 3 .8kv
tr
= 5
la
110 KV
IB
44 KV
*la
13.8 KV
klB
Figure 4 .3 THE TIME-CURRENT CURVES FOR THE TRANSFORMER DIFFER EN TIAL RELAY
the relay are 10 A and 220 A for one second, respectively. Further
more, assume the maximum available fault level for a three phase fault
transformer.
as follows:
TRANSFORMER WINDINGS
110 KV (Y) 44 KV (A) 13.8 KV (Y)
3.0 %
5.01 /
4.27 _ 4.6
Mismatch error between 4.53 5.0' X 1002
110 KV & 13.8 KV 4.6
5.0
•3w
2 r '/o
4.92 _ 5.0
Mismatch error between 4.53 4.6 X 1002
44 KV & 13.8 KV 4.92
4.53
0.082
All are less than 5%, therefore, mismatch error is not excessive
= 1.6 GVA/( J T V ^ )
relay fault currents (A) 181 210 193
Select desired operating time according to the system requirement. From
Figure 4.3, assume the required operating time is less than 3 cycles at
8 times relay tap value. This means that the current transformers
should be able to supply the relay with 8 times rated relay tap current
with an acceptable error. On the other hand, the relay short time cur
rent rating should be at least greater than the fault current supplied
by the C T s . Given short time current rating of 220 A for one second,
( 2 2 0 ) 2 x 1 = ( i ) 2
Therefore, both continuous and short time ratings are not exceeded,
of the CT's are 0.15-ohms for 400/5, 0.12 ohms for 500/5, and 0.09
ohms for 3000/5. Furthermore, assume that there are no other de
4.3.2 Sudden Pressure and Buchholz Gas Protection (Device No. 63)
relays are more sensitive to light internal faults than the differential
relay and generally recommended for all units of 5 MVA or more [16].
should trip a separate lock-out relay from that tripped by the differen
and a single donut type CT can be fitted around all three phases, a
current relay fed from the residual circuit of the phase CTs should be
used.
tem protection for both transformer and system faults. If the coordin
phase and neutral CTs shall be relatively close together. If they are
remote from each other, such as those in a transformer feeder, the po
should be fed from the phase CTs and polarized from an open delta
potential transformer.
protection.
only those circuit breakers connected between all ground fault current
studied and planned for the particular application. If the ground fault
should be used.
of the transformer windings or the oil, are inherent selective and are
These relays can be depended upon to trip the transformer main cir
which can cause transformer failure if the fault is not cleared promptly.
The transformer can be isolated from the fault before damage occurs by
ator protection schemes, the choice between these two types of relays
possi b l e .
far more complicated because of the wide range of load current and more
There are two types of overcurrent relays generally used for trans
relay should have two elements, that is, instantaneous trip and inverse
necessary, the pickup value of the inverse unit should be set above
cooled rating are common, although higher values are sometimes used.
this relay must coordinate with all other relays it overreaches. Con
ground faults.
should be connected to operate when the current flow is into the trans
former. The directional element should be fed from the same CTs as the
overcurrent element and, in addition, a polarizing voltage derived
Of course, the relay should coordinate with other system relays. More
nected to operate when the fault current flows toward the protected
transformer. The setting should reach into, but not beyond, the trans
former .
the schemes given are for illustration only and should not be taken as
is required.
4.5.1 Protection of Generator Transformers
with its delta winding connected to the generator bus. The secondary
winding can be either delta or wye connected depending upon the exter
grounded neutral of the wye winding should be of inverse time type and
considerations.
P o w e r S y stem s
E n gin eerin g, Inc.
P.O. Box 19398
JL JO B NO. N/A DATE Sh
Houston. Texas 77024
fe? KV
m ain windings and overcurrent relays set to protect the main windings
relay (51) , fed from a current transformer in one leg of the delta
protection zones.
connected between the high voltage (above 34.5 KV) power source and
the distribution system or load. The power flow is normally from high
inverse type such that their settings can be co-ordinated with the sec
with the motor protection while obtaining fast clearance tines for high
level faults and a low enough current setting to comply with the NEC,,
lays. Qme set should have a long time inverse characteristic and the
unobtainable with only one set of overcurrent relays. Where the trans
If the motor on the low voltage bus is synchronous rather than in
that 50/51 relays will not operate for a high voltage system, fault*
For the same reason, directional overcurrent relays should also* replace
50/51 relays if the low voltage bus has another infeed and fault cur
relay (67N1) with another ground fault overcurrent relay (51G) should
be used. The 51G relay should be fed from a transformer neutral cur
rent transformer and be coordinated with the high voltage system ground
fault protection.
when the fault current is above its interrupting capacity. This usually
P o w e r S y stem s
E n g in eerin g , Inc.
P.O. Box 19398
Houston, Texas 77024
BY JL JO B NO. N/A DATE Sh 1
F I G U R E 4 ,6 PROTECTION ARRANGEMENT f o r
A W Y E / DELTA T R A N S F O R M E R
d w g .n o . REV .
i
v._ _ _ m
NOTE
1. Relays marked -> are alternative. Relay 50GS is used with a donut CT ■
Relay 50N/51N is used with phase CT's.
P o w e r S y stem s
E n g in e e rin g , Inc.
P O. Box 19398
Houston. Texas 77024
JL JO B NO. N/A DATE
F IG U R E 4 ..9 p r o t ec t io n a r r a n g e m e n t for a w y e / d e l t a
TRANSFORMER WITH A GROUNDING TRANS.
d w g .n o . REV.
P o w e r S y ste m s
.. /'.SI E n gin eerin g , Inc.
P.O. Box 19398
JL JO B NO. N/A date Sh
Houston, Texas 77024
( 1)
PREFERRED a l t e r n a t iv e
CT CT. f
CIRCUIT A
MOTOR
LOAD
generators, power pooling, etc., are widely used. Among these, a proper
scheme should trip all necessary circuits, not more or not less. Con
mission line m a y trip circuit breakers on both ends and interrupt all
loads tapped along the line, which may not be necessary. Breaker
problem.
are nothing more than analog computers designated for individual speci
in detail.
following four arrangements: the single bus, the double bus, the ring
is acceptable. In the event that the loss of all circuits due to any
should be provided.
The ring bus and the breaker and a-half configuration provide both
without more than two circuit outages. The use of the ring bus arrange
beyond the remote bus. Selectivity of this remote backup depends main
flowing from the remote bus. This is true especially when very long
mary relays fail, local secondary relays will trip the local breakers.
In case the local breaker fails, either the primary or the secondary
relays will initiate the breaker failure protection to trip all local
PR!, RELAY
SYSTEM
r --- 1
i SEC. RELAY
circuit breaker and start the timer 62 through auxiliary relays 62X
and 62Y. If the circuit did not open before 62 times out, this indi
cates a failure to clear the fault. Then failure detector (device No.
auxiliary relay 86BF, which in turn will trip all the adjacent breakers.
rent relay 50BF rather than the breaker "a" contact. This is because
the "a" contact may be open while the main contacts in a damaged breaker
are actually closed. Three overcurrent units used can be set below
"a" contact.
and (iii) one timer per breaker be used, rather than one timer per bus.
The time interval between trip energization and current flow cessation
is the breaker interrupting time. If interruption does not occur in
about this much time, the breaker is assumed to have failed and the
Figure 5.2 shows the simplest breaker failure scheme for the single
bus configuration using one timer per bus. In transmission line protec
rent supplies as shown in the figure. Two zener diodes TRB-2 are used
diode inside each overcurrent detector isolates the multiple trip cir
cuits of all overcurrent detectors on the same bus so that only the
Figure 5.3 shows breaker failure relaying for the same bus arrange
ment using one timer per breaker. Although using a separate timer for
each breaker is more costly than a timer for each bus, the following
the common timer must be set to accommodate the slowest breaker. Sep-
another, the common timer might misoperate and strip the bus. As the
properly.
P o w e r S y ste m s
Jkjy E n g in eerin g , Inc.
P.O. Bo* 19398
Houston, Texas 77024
JL JOB NO. DATE N/A
to
D
CQ
1
W
cc
1
—® n
£w■i~s
i2 m
2 5I o2 £o
2, i e>
*X ~ c
•
z
^ C t
o5
£■ u
> ©
to ^ —
S.- 4* 0
D
J
a
fa
Pi
h
53
<<
ZC
3 0>
m
■=r£y O- ? E
S £
'91J* 3 ® »
5 “<-r=5-£ s
CQ
oat?£ ~ " -U. iy. ia <
,
*” 3 3 I I
~ “ V J jiS a
: ; H J u
n O O v = £S S £ ffi ,i
,H
W
CM
-in
a
u
a
* o- ;^ x > Qn,
Q Z • | fcO$£>i£> '<£>
fa
P o w e r S y ste m s
E n g in e e rin g , Inc.
P.O. Bo* 19398
Houston, 77024
JL JO B NO. N / A DATE
(3) With separate timers, the bus can be reconfigured without
Figures 5.4 and 5.5 show breaker failure relaying for the breaker-
and-a-half bus and the ring bus, respectively. The basic functioning
of these schemes is the same as for the single bus, and requires no
scheme for a generator pair is shown in Figures 5.6 and 5.7. The
turn is under the direct control of the S'CADA central processor* Cowr
station; the master station, on the other hand, issues control cooniaads
it « 3 C
Q ED Q j
^ ^^
-S -c 5 o r ij
^ i <V ® rc *J &S cvn
a- 5 fxJ5 -2=1
h < -£S2
a S
3| ut SC <
-©
"Z c
w5 3“fI Sx
O a * <£
o > I « •- U.- u.' < u.' * ©» O
P ' NJ r
IS) O a. co cd cd cb ,- i ^ 5
*- » ?
1 >8
iUULJLJUULJ
;S 03 O '•® COCD ® CD COQ
i t£ o
r 5 ,v *
► lo m c
££«?
„ a
X S oo
fU"*><VCN tD
* l£>< s n a h
C C N -V
oo od co a
o
2
H
<
J
8 £
D 2
*1 <
s s
CQ
& OS
W W
\4 Oh
CQ §
H
Cn H
w
s
o
o
2
M
w
D
CQ
in
a
3
Cn
•H
tn
DWG .NO. REV.
BREAKER F A I L U R E R E L A Y I N G FOR A RING BUS P o w e r S y ste m s
' E n g in e e rin g , Inc.
P.O. Box 19398
Houston. Texas 77024
BY JL JO B NO. N/A DATE Sh of 1
co
D
«
o
S
a
o
Pn
u
2H
s
in
in
0)
u
p
CP
•H
Cn
Thij drawing <s the proo«ny of P o w e r S y lt e m * Engineering, tnc. Neither this d e w in g ncr reor<xiiJClion<,
of i?, nor information derived from it shad tx* gtv*n to others without the t?*or**ssed written .. im sm -w jt
S y ite m a . No us® is to De made of m which >s. or mav De injurious Pow m S y t t e m i
D W G. NO. REV.
the equipment under control and control signal itself. It usually ac
measured by data thruput. To enhance the data thruput, the SCADA sys
from the data thruput point of view, the data base is the heart of the
SCADA system.
accordingly.
plays, alarm generation, data entry, data logging and picture compiler.
(A) Performance Monitoring:
of a RTU system.
ciated with each function- has been programmed and is executed locally
operation, control and for data input to SCADA programs. They should
binary coded decimal and others; (c) analog inputs to maintain a fresh
data.
resources, wiring and space spare for the future addition of new points
processor must decide how, when and to whom the processing resources
firmware are actually an art and should be carefully studied for any
particular application.
cations functions should not use more than 30% of microprocessor re
source time.
as usually required.
microprocessor and the remote scan program stored in ROM. Figure 5.9
points and maintains a queue of all changes. On request from the SCADA
P o w e r S y ste m s
FUNCTIONAL B L O C K diagram - RTU SYSTEM
E n g in e e rin g , Inc.
P O. Box 19398
JL JO B NO. DATE Sh
Sh 1 of, 1 Houston. Texas 77024
s
13
W
w
D
Eh
OS
U
<
H
Q
b
o
CQ
a
EH
00
in
Q)
u
P
Cn
A •H
DWG. NO. REV
P o w e r S y ste m s
C O M M O N C O N T R O L MODULE
s ^M E n g in e e rin g , Inc.
P.O. Bo* 19398
v JL JO B NO. N /A DATE Sh ^ of 1 Houston. Texas 77024
a
o
s
9os
H
£O
o
2O
C\
LO
©
s
Cn
•H
£n
master station, the module can report the number of state changes
address. The module compares these two sets of point address; if they
quence and produce a serial bit pattern for serial transmission* The
from the SCADA master station. As in the control module, two sets of
It is divided into two parts; part one discusses life cycle of engineer
formal design review, and ended with hand over and comp let Ion,. Inter
discussed.
The data collected at this stage is usually quite rough and a decision
program.
above.
.nical baseline for the system defined in the feasibility study and pro
The detailed design phase begins with the concept and configura
should be p r e p a r e d .
Purchasing is one of the key engineering functions. It consists
order.
The completion and hand over phase of a project prepares the pro
ject for phasing out and hand over to another fora of administration*
the legal exposure that it does today. The rapid expansion of technol
ogy has stimulated equally rapid developments in the law. Merely keep
neers from developing familiarity with all the laws that may affect
The engineer must develop a sixth sense that will alert him to
ing three legal theories. These theories, which form the basis for re
techniques.
CHAPTER 7
Gow said in 1932 still holds true. This is largely due to the fact that
and to "older" engineers as well who know these things perfectly well
This chapter is divided into two parts; part one discusses purely
Just one point should be clarified before entering into the con
engineering career.
7.1 Character and Personality Considerations
and much has been taught in schools from the social, ethical, and reli
given and discussed from a purely practical point of view based upon
lity to get along with all kinds of people. This is rather a compre
too hard to get along with everybody merely by being agreeable and
friendly on all occassions. You must earn the respect of your asso
extremely important, especially when you know you are in the right. If
you can be pushed around easily, the chances are that you will be pushed
you do well to start a fight yourself, when your objectives are worth
fighting for.
of character among the members of any group who have been associated for
appearance.
which you tackle your first humble tasks will usually be carefully
you results; go after your results and keep everlastingly after them.
and sit back waiting for the result. In fact, most jobs move in direct
immediately for some way around each obstacle encountered and keep the
rather than a half-baked one. OR you will not get credit for your
great i d e a s .
reports.
get a clear answer out of the answer that its usefulness is thereby
Rule 6 : Don’
t be timid, speak up and express yourself and promote
your i d e a s .
what they are told to do. Of course, there are times when it is very
wise and prudent to keep your mouth shut, but, as a rule, it pays to
This sounds almost as trite as one plus one equals two, but many
habitually guessing when they do not know the answer to a direct ques
tion. Remember next time, if you do not know, say so, but always say,
To get along with your boss, the basic principle is that he must
know what is going on in his territory. From this idea are derived
Rule 1 : Do not overlook the fact that you are working for your
boss.
Sometimes they move a little bit faster that way for a while, but even
take for granted that your boss has good reasons for wanting his job
done now. Also, if you are instructed to do something and you subse
don’
t forget to inform your boss of your intentions and reasons.
developments.
your boss. Try to sell your ideas to him and make contributions.
boss.
less than half the man he ought to be, transfer to some other company
Complaints made to a m a n ’
s superior should be resorted to only
when direct appeal fails. Give the man a fair chance to correct the
authority.
CHAPTER 8
to the firm:
for the 480 MW power plant, microprocessor-based SCADA and SOE systems.
gress control chart and helping the Project Manager to prepare cost
control charts for a project which cost over $1.4 million merely for
engineering.
neers in the firm. This report summarizes and highlights the results
This report is divided into two parts. Part one emphasizes the
R-X diagram.
cal and thermal stresses. The minimum values are needed to check the
tion of system protective devices, both the maximum and the minimum
in Chapter 2.
synchronism.
to protect the system and limit damage in the event of a fault. Abnor
best possible and the three internship objectives have been met. The
internship.
REFERENCES
[3] D. G. Fink e t . a l .
Standard Handbook for Electrical Engineers
10th edition, McGraw-Hill Co., 1969
[5] ANSI Test Procedures for Low Voltage AC Power Circuit Breakers
ANSI Std. C37.50, 1973
[6 ] W. C. H e u n i n g , Jr.
"Interpretation of New American National Standards for
Power Circuit Breaker Applications"
IEEE Trans. Industry & General Applications,
Vol. IGA No. 5, 1969
[7] H. R. Everitt
"Formulas for Conductor Size According to Cost of
Resistance Loss”
[14] Westinghouse
Electrical Transmission & Distribution Reference Book
Westinghouse, 1964
[15] General Electric
"Loss of Excitation Relay" GEK-27887C, 1977
[16] Westinghouse
Applied Protective Relaying, Westinghouse, 1977
[18] Westinghouse
"Type KC-4 Overcurrent Relay",
Westinghouse I.L. 41-776.1J, 1978
[19] C. R. Gow
Elements of Human Engineering
Macmillan Co., New York, NY, 1932
[20] R. E. Shannon
Engineering Management
John Wiley & Sons, Co., New York, NY, 1980
APPENDIX I
the figure, when 0 is the angle between the instant of positive volt
L if = ig(t) = E (coswt + 0)
dt
— ,. if = J L (coswt + 0)
dt L
if (o) = o
constant - _ E
WL
= 0
if (t) = J L [-coswt * 1]
WL
:l Ip = peak of if (t )
= 2y T is
The rms value of if (t) over the first half-cycle after fault occturrMC*
Ip :s= 2 I a * 1*63 l a
yiTi
OlnriiBwiisly,
ia = y ? ! ®
Candidate’
s Full Name: Ting-Zern Joe Lee