Nu - Design Guidelines and Technical Standards1 PDF
Nu - Design Guidelines and Technical Standards1 PDF
AND
TECHNICAL STANDARDS
TABLE OF CONTENTS
Introduction
DIVISION 3 – CONCRETE
DIVISION 4 – MASONRY
DIVISION 5 – METALS
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 22 – PLUMBING
DIVISION 23 – HVAC
DIVISION 26 – ELECTRICAL
DIVISION 27 – COMMUNICATIONS
APPENDIX
INTRODUCTION
General
The Design Guidelines and Technical Criteria included in this manual identify the standards and
preferences of Northwestern University (NU) Facilities Management Department. The Design
Guidelines are organized by subject matter while the Technical Criteria generally follow the
numbering system suggested by the Construction Specification Institute (CSI).
It is intended that these General Guidelines and Technical Criteria serve as a reference for
consultants providing architectural and engineering services for NU design and construction
projects. The Guidelines do not include “standard” or “master” specifications for any
construction material or system.
The translation of these General Guidelines and Technical Criteria into contract documents is
left to the individual consultant. In no instance shall a direct referral to these Design Guidelines
and Technical Criteria be included in contract documents prepared by design consultants, nor
shall any portion of the Technical Criteria be reproduced in project specifications without being
specifically tailored to the individual project.
Since requirements of applicable ordinances, codes, statutes, and regulations are subject to
change, it is the responsibility of the design professional to determine independently that the
project fully complies with all applicable ordinances, codes, statutes, and regulations at the time
of design. If, in the opinion of a design professional working on a specific matter, a requirement
of these guidelines is inconsistent with a requirement of an applicable ordinance, code, statute,
or regulation that compliance with this manual would violate the applicable provision, the design
professional should comply with the applicable ordinance, code, statute, or regulation and
should also advise the NU Project Representative in writing of the apparent inconsistency and
the reasons that the guideline may not be followed.
Users of this guideline, including Facilities Management staff who have suggestions for
modifying or expanding the subject matter covered in these guidelines are encouraged to
submit their suggestions in writing to the Facilities Management representative coordinating
these standards. A form for providing such input is provided in the Appendix to the manual,
although any form of written communication or email is welcome.
Application for waivers to any section of these guidelines shall be made, in writing, by the
Architect/Engineer of Record to the Director of Design and Construction, copying the NU Project
Manager.
The origination date of these standards is January 1, 2014. This guideline is to be reviewed
annually for modification or expansion as determined during the course of the year by Facilities
Management. The period of review of this guideline will be the last quarter of the calendar year.
All modification requests received by October 1 will be reviewed by the Guidelines Review
Committee within 30 to 90 days, with recommendations to be incorporated into this guideline by
the annual date following the origination date.
INTRODUCTION
Page - 1
NORTHWESTERN UNIVERSITY
Design Guidelines and Technical Standards 01.01.14
4. DDC Standards.
1. Products, materials, and equipment described herein establish a guideline for the
required function, dimension, appearance, and quality. When a single item or source is
described, the design professional shall specify only that item.
2. Substitutions are not permitted without written permission from the University.
3. When more than one item is specified or the item is described as “preferred,”
substitutions may be considered by the University, if equal to the specified standards.
4. The University may obtain a written agreement of “lowest commercial price” from single
source vendors, suppliers, or manufacturer’s named in these Design Guidelines and
Technical Standards.
INTRODUCTION
Page - 2
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
1. Sites:
a. Buildings shall integrate with the existing campus, surrounding buildings, long-
term stewardship goals, and the campus master plan.
b. Review historic districts and specific requirements with the NU Project Manager
at the beginning of the project.
b. Design walks with landscape between curbs and walks such that wheel stops are
not required and to allow for favorable ADA access.
DESIGN GUIDELINES
Page - 1
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
6. Site Accessories:
d. Bike Racks: NU Standard bike racks are described in Appendix. See Appendix
for additional information.
7. Storm Drainage:
b. Each project should evaluate the existing systems in place and maximize site
retention back into the soil. Use of the existing City of Evanston system should
be minimized to the extent possible.
a. Existing structures should not allow sedimentation from storm runoff to infiltrate
the campus storm system, sanitary system, or open waters.
9. Sanitary Sewers:
a. The Evanston Campus sanitary sewer system slopes from north campus and
south campus to central campus where it is pumped west via lift stations. The
existing system on the north and central campus is approaching the limits of
good design practice.
b. A new north campus sanitary sewer discharge to the west and associated lift
station should be considered when planning new buildings north of the
Technological Institute Building.
DESIGN GUIDELINES
Page - 2
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
Utility Systems
1. Vaults:
a. General:
i. Vaults are to have stainless steel sump pumps that are alarmed back to
DDC.
ii. Discharge water to pumped to city drain or French drain below frost line.
Areas below lake level need to be pumped to a campus lift station.
2. Steam:
a. General:
b. Evanston Campus: A framework master plan has been developed for steam
utilities on campus and should be referenced with the NU Project Manager prior
to the start of the design phase of the project.
i. Steam produced in the Central Utility Plant (CUP) is available all year,
except for the scheduled annual maintenance shutdown, which typically
occurs over the Labor Day Holiday.
ii. For the Evanston campus central steam is distributed at 230 PSIG and a
second line distributed at 150 PSIG from the Central Utility Plant (CUP).
Steam shall be metered and reduced in pressure after entrance of each
building.
iv. Each building typically has a low pressure pumped condensate return.
Condensate is to be metered returned to the central plant 50 to 75 PSIG.
Condensate metering preferred to steam metering, refer to NU Metering
Standards.
v. Each building and sometimes each department is metered for billing and
management purposes. This should be confirmed prior to the start of the
design phase of the project. See NU Metering Standards for additional
information.
DESIGN GUIDELINES
Page - 3
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
c. Chicago Campus:
i. Steam produced in the heating plant is available all year, except for the
scheduled annual maintenance shutdown, which typically occurs over the
Labor Day Holiday.
ii. For the Chicago campus central steam is distributed from the central
plant 150 to 175 PSIG. Steam shall be metered and reduced in pressure
after entrance of each building.
iii. Each building typically has a low pressure pumped condensate return.
Condensate is to be metered and returned to the central plant 50 to 75
PSIG. Condensate metering is preferred to steam metering, refer to NU
Metering Standards.
iv. Each building and sometimes each department is metered for billing and
management purposes. This should be confirmed prior to the start of the
design phase of the project. See NU Metering Standards for additional
information.
3. Chilled Water:
a. General:
ii. Each of the buildings on both the Evanston and Chicago campuses are
that are connected to the Central Utility Plant (CUP) are to be metered.
iii. Chilled water and heating hot water piping is to have a side stream filter
and pot feeder. A chemical pot feeder shall be installed across the hot
water pump.
ii. Chilled water is currently distributed at 80 psi to 100 psi leaving the
Central Utility Plant with a 6 to 8 psi differential pressure at the
extremities.
DESIGN GUIDELINES
Page - 4
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
c. Chicago Campus:
iii. Project integration into this system shall be reviewed at start of design
process with NU Project Manager and NU FMO Staff Engineer.
4. Geothermal:
b. The costs associated with the installation and energy savings payback as well as
the ability to have steam and chilled water delivered to the site should be
reviewed.
5. Domestic Water:
a. Evanston Campus:
ii. Domestic Water service to buildings must retain and/or create new water
loops to eliminate dead end runs.
iii. Each building and sometimes each department is metered for billing and
management purposes. This should be confirmed prior to the start of the
design phase of the project.
DESIGN GUIDELINES
Page - 5
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
6. Natural Gas:
a. Evanston Campus:
ii. Each new load needs to study the existing systems and potentially plan
for extensions or new distribution and service as necessary.
7. Laboratory Services:
8. Fire Protection:
a. Evanston Campus:
ii. Some existing buildings will require evaluation of existing systems and
requirements for extension and/or new fire pumps.
DESIGN GUIDELINES
Page - 6
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
9. Electrical Service:
a. ComEd: A/E shall work with NU and local utility providers to determine scope of
the project.
b. ComEd will typically provide and install primary wire and equipment and
contractor will typically provide secondary wire and equipment.
c. A/E shall provide bid documents for conduit ductbanks, manholes, and
transformer pads in locations that comply with ComEd design standards for
Contractor to install.
c. Review existing generator loads and capacity for remodeling projects and/or
additions to existing buildings, including the following:
i. Life safety;
Building – General
1. Exterior Campus Palette: Both the Chicago campus and Evanston campus share a
similar palette of exterior materials.
2. Interior Finishes: Both the Chicago campus and Evanston campus share similar
expectations for interior materials and finishes.
DESIGN GUIDELINES
Page - 7
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
as part of the design phase of the project. Additional reviews with the user
group(s) should be anticipated. See the Appendix for additional information.
3. Room Planning Criteria: Both the Chicago campus and Evanston campus share similar
expectations for space planning.
a. General:
i. Exit corridors shall remain clear of any obstructions. Do not plan for items
such as microwave ovens, copiers, or other similar office equipment in
exit corridors.
ii. Structural columns should not be placed in the mid span of interior
demising walls. Maintain an uninterrupted rectangular room shape as
much as possible.
iii. The latch side of doors shall be the typical location for light switches,
occupancy sensors, fire alarm devices or strobes, and thermostats.
c. Restrooms:
i. Wall hung fixtures including water closets, urinals, and lavatories are
preferred.
ii. A shelf or counter shall be provided at each mirror for personal items.
iv. Toilet partitions shall typically be floor to ceiling and hooks shall be
provided in the interior of each stall door.
vi. Trash receptacles shall be free standing and typically provided by NU.
Design bathrooms such that free standing trash cans are located at the
back wall adjacent to the latch side of the door so that paper towels can
DESIGN GUIDELINES
Page - 8
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
be used to open the door and dropped into the trash receptacle at the
door location without blocking the exit path.
viii. Shower stalls shall be either full height tile or other durable materials.
d. Mechanical Rooms:
iii. Provide adequate number of floor drains in mechanical rooms; drains are
to be connected to the sanitary sewer system, not to storm sewer. Locate
drains to avoid running of condensate drains and other similar equipment
across mechanical room floors. Provide trap primers as required per
Code.
DESIGN GUIDELINES
Page - 9
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
i. All data center units are to have N + 1 redundancy for cooling. Units that
are critical need to have domestic water piped for emergency backup.
4. Signage: Signage is typically provided by NU. Review specific requirements with the
NU Project Manager prior to the start of the design phase of the project.
b. Review the specific requirements for elevators and vertical transportation with the
NU Project Manager prior to the start of the design phase of the project.
c. Provide at least one C2 class elevator in each building. Consider tall doors for all
elevators.
d. Passenger elevator locations shall have more than one passenger elevator for
ADA redundancy while one car is out of service or being maintained.’
6. Mechanical Systems:
c. Systems shall be durable and low maintenance with particular focus to be placed
on the operability and maintainability of the installed systems.
d. A Life Cycle Cost Analysis is typically required for major mechanical systems.
Review specific requirements with the NU Project Manager prior to the start of
the design phase of the project.
7. Electrical Systems:
a. General:
DESIGN GUIDELINES
Page - 10
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
b. Coordinate with ComEd early in the design process for both temporary
construction service, conflict relocation, and new permanent service.
d. Review the following basic information with the NU Project Manager and Chief
Electrician prior to the start of the project:
i. General Requirements:
2. System Voltages.
5. Supply Capacity.
8. System Grounding.
1. Switchgear.
2. Transformers.
4. Electrical Motors.
4. MV cables.
DESIGN GUIDELINES
Page - 11
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
5. Grounding.
3. Corridor Lighting.
5. Street Lighting.
6. Sidewalk Lighting.
9. Emergency Lighting.
v. Power Requirements:
1. Convenience Outlets.
2. Metering Equipment.
3. Grounding.
4. Substations.
DESIGN GUIDELINES
Page - 12
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
1. Generators.
4. Essential Systems.
7. Fire Pumps.
8. Fire Alarms.
1. Testing Requirements.
Sustainability
1. Introduction:
a. This portion of the Design Guidelines and Technical Standards includes the
sustainability guidelines to be followed by the Project Managers, Consultants,
Architects, and/or Engineers in the course of a project at Northwestern
University.
DESIGN GUIDELINES
Page - 13
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
c. It is essential that all members of the project team work together and consider all
sustainability categories in order to be aware of the influence of their decisions
on the overall sustainability performance of the building in each category. In
addition, not all strategies suggested here are relevant for every project and
certainly not all strategies will be implemented in every project.
d. These decisions are not made in isolation but rather they should recognize the
interactions and tradeoffs of a particular project. Northwestern University’s
sustainability guidelines outline an integrated design approach. The process
steps are identified to establish performance goals and to ensure that decisions
are made in a collaborative and informed manner. The maximum benefits to the
programmatic mission can be achieved when sustainability is incorporated at
every point along the project delivery process.
b. Incorporate the sustainability initiatives discussed into the Request for Proposal
(RFP) and Owner’s Project Requirements (OPR) outlined in the Design
Guidelines and Technical Standards. Understand any costs or savings that may
be incurred in order to create an more sustainable building.
4. Programming:
DESIGN GUIDELINES
Page - 14
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
b. As the project team develops or verifies the project program, summary schedule,
and preliminary budget, the FM Project Manager should arrange a Sustainability
Working Session (SWS) to review the options and the underlying principles of
sustainability as they relate to the building design, construction, and operation.
5. Schematic Design:
a. The largest resources impacts of the project should be identified, prioritized, and
discussed at design meetings and should include energy, water, materials, and
people. The consultant should be prepared to discuss major mechanical
systems and alternatives like geothermal.
6. Design Development:
a. During the Design Development (DD) phase, the approved schematic design
begins to include a level of detail necessary to work out a clear, coordinated
description of all aspects of the project. Because the DD Phase is one of the last
opportunities for the User Group to become fully involved in the design, it is
crucial that sustainability principles from each of the LEED categories be fully
discussed and implications be understood and integrated as appropriate.
b. Design and construction costs associated with the sustainable attributes of the
project should be clarified. Sustainable component cost metrics (capital and life
cycle) should be developed and cost and/or savings decisions evaluated against
performance and life cycle cost considerations. The results are to be refined
within the BOD document and LEED Checklist.
c. The project team should ensure that the project schedule allows adequate time
for implementing the activities that may lead to a more sustainable project, such
as commissioning, demolition waste diversion, and training.
7. Construction Documents:
DESIGN GUIDELINES
Page - 15
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
50% CD review) along with any update of the BOD document and LEED
Checklist. This review should specifically address materials selection.
8. Construction:
Sustainability Guidelines
1. These guidelines are for use by NU Project Managers and consultants on projects of all
scales. Although Northwestern sets LEED Gold as a target for larger projects, each
project should follow these guidelines when applicable.
a. Sustainable Sites.
b. Energy.
c. Water.
f. Human Centric.
4. The sustainability strategies included here are not comprehensive; these guidelines are
intended to provide ideas and not exclude any from consideration. The project team is
encouraged to develop additional strategies and refer to current documents published by
the United States Green Building Council (USGBC) at www.usgbc.org.
DESIGN GUIDELINES
Page - 16
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
1. Sustainable Sites:
a. Promote development that relates well to both natural systems and existing
infrastructure.
c. Maintain and enhance the biodiversity of natural systems and/or the existing
character of the site.
2. Energy:
ii. Review project specific goals with the NU Project Manager prior to the
start of the project.
c. Achieve energy cost and related savings through infrastructure upgrades and
system design and operation (e.g. labs).
3. Water:
a. Increase the harvesting and recycling of all available water resources in both
buildings and landscape projects.
DESIGN GUIDELINES
Page - 17
NORTHWESTERN UNIVERSITY
Design Guidelines Issuance Date: 01.01.2014
b. Monitor and avoid indoor air quality problems during renovation, demolition, and
construction activities.
c. Provide occupants with operational control of lighting and HVAC systems where
practical.
6. Human Centric:
END OF SECTION
DESIGN GUIDELINES
Page - 18
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section outlines the general requirements and coordination required by
the Architect / Engineer and the NU Project Manager during the design and construction
phases of the project.
a. Bid Form: This form should be reviewed the NU Project Manager and modified
by the Architect / Engineer for the specific project.
3. Standard Warranties: The minimum allowable warranty for materials and equipment
shall be one year from the Date of Substantial Completion. The warranty period shall
not begin prior to the Date of Substantial Completion, regardless of the date of
installation.
4. Special Warranties: Certain systems and/or components may require additional special
warranties. These systems and components shall be reviewed with the NU Project
Manager and modified by the Architect / Engineer for the specific project. Refer to
specific sections for additional information.
a. The receipt of close-out documents, including, but not limited to, as-built
drawings and specifications, O&M manuals, and warranty letters and the
completion of required training for Owner personnel, shall be a condition of the
release of retainage.
b. Close out documents shall include a list of finishes for all building elements with a
finish.
c. Closeout documents shall include copies of all reviewed submittals in pdf format.
GENERAL REQUIREMENTS
01 1000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
7. Temporary Utilities:
b. Contractor shall not utilize temporary power, especially science buildings, for
construction welding. General Contractor to provide separate power for welder
generator remote from any fresh air intake.
END OF SECTION
GENERAL REQUIREMENTS
01 1000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General:
2. Submittals – Photographs:
3. Protection of Existing Conditions: When existing buildings are directly adjacent, provide
survey and monitoring as needed to document movement during construction.
4. Hazardous Materials:
5. Existing Utilities:
SELECTIVE DEMOLITION
02 4119 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Contractor shall not obstruct walks or public ways without the written permission
of Northwestern and/or authorities having jurisdiction.
c. Provide adequate signage for new routes to avoid confusion for pedestrians,
bikes, vehicles, and emergency vehicles.
8. Tree Protection:
b. Trees should be protected at drip-line. When this is not possible, Contractor shall
provide a plainly visible fence at least 5 feet from trunks of individual trees or
around outer perimeter of clumps of trees that are to be protected.
c. Protect drip-line tree roots from excessive compaction, leave free from materials
to allow for air circulation and give the tree ability to benefit from natural rainfall.
d. For long term construction projects where existing plant material is under
extreme duress, auxiliary watering may be necessary during drought/extreme
conditions.
e. Tree surfaces should be periodically cleared of dust and debris and mulched to
help protect roots and maintain available water for the plant.
10. Underground Work: Contractor shall contact utility locating service prior to proceeding
with underground work.
END OF SECTION
SELECTIVE DEMOLITION
02 4119 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 3 – CONCRETE
a. Except for lean concrete, which is typically used for backfill, minimum 28-day
concrete strength shall be 3,000 psi, for below grade construction, and 3,500 psi
for slabs-on-grade and above-grade construction.
b. Concrete exposed to freeze / thaw shall have a minimum air content of 4.5%.
3. Design Considerations:
f. Coordinate brick ledges and exterior grades so that soils are not placed against
exterior façade materials (e.g. stone, precast concrete, or masonry).
g. Form tie depressions shall be patched on all vertically formed concrete surfaces
that are either exposed to view or are to receive damp-proofing or waterproofing.
i. Pipe, conduit, and other penetrations through perimeter basement walls shall be
provided with an appropriate seal as manufactured by Link-Seal or approved
equal.
CAST-IN-PLACE CONCRETE
03 3000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
m. Concrete slabs (exclusive of mud slabs) shall receive a minimum of a float finish;
if indicated to be broomed, the slab shall be floated and then broomed.
4. Tolerances: The University requires proper forming, placement and finishing to meet the
following:
a. Sizes of sleeves, floor openings, and wall openings: Center line of sleeves, floor
and wall openings, +/-1/2”.
iii. Trowel Finish: For surfaces to be exposed to view and slab surfaces to
be covered with resilient flooring, carpet, ceramic or quarry tile, paint, or
other thin film finish coating system: Achieve level surface plane so that
depressions between high spots do not exceed 1/8” under a 10-foot
straightedge.
c. Floor Leveling: Contractor, at his own expense, shall provide floor leveling, to
the satisfaction of the University, in areas where the above tolerances are not
achieved.
5. Quality Assurance:
CAST-IN-PLACE CONCRETE
03 3000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Deliver, store, and handle steel reinforcement to prevent bending and damage.
9. Accessories:
CAST-IN-PLACE CONCRETE
03 3000 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Prepare design mixes for each type and strength of concrete determined by
either laboratory trial mix or field test data bases.
b. Use a qualified independent testing agency for preparing and reporting proposed
mix designs for the laboratory trial mix basis.
12. Embedded Items: Place and secure anchorage devices and other embedded items
required for adjoining work that is attached to or supported by cast-in-place concrete.
c. Granular Fill: Cover vapor retarder with granular fill, moisten, and compact with
mechanical equipment to elevation tolerances of plus 0 inch (0 mm) or minus 3/4
inch (19 mm).
i. Do not cut or puncture vapor retarder. Repair damage and reseal vapor
retarder before placing concrete.
b. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign
materials.
d. Set wire ties with ends directed into concrete, not toward exposed concrete
surfaces.
e. Install welded wire fabric in longest practicable lengths on bar supports spaced to
minimize sagging. Lap edges and ends of adjoining sheets at least one mesh
CAST-IN-PLACE CONCRETE
03 3000 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
15. Joints: Typically joints are to constructed true to line with faces perpendicular to surface
plane of concrete. Special requirements shall be indicated on the drawings.
16. Concrete Placement: Before placing concrete, contractor shall be required to verify that
installation of formwork, reinforcement, and embedded items is complete and that
required inspections have been performed.
a. Filling In: Contractor shall be required to fill in holes and openings left in
concrete structures, unless otherwise indicated, after work of other trades is in
place.
CAST-IN-PLACE CONCRETE
03 3000 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ii. After concrete has cured at least 14 days, correct high areas by grinding.
iv. Correct other low areas scheduled to receive floor coverings with a repair
underlayment.
vi. Repair defective areas, except random cracks and single holes 1 inch (25
mm) or less in diameter, by cutting out and replacing with fresh concrete.
vii. Repair random cracks and single holes 1 inch (25 mm) or less in diameter
with patching mortar.
ii. Aggregate Exposure: Please note that each finish below will have some
percentage of all four finishes. The finish choices are described as:
CAST-IN-PLACE CONCRETE
03 3000 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Sheen:
b. The depth of the grind to achieve the desired results is dependent on the
techniques used for finishing, the concrete mix, and the amount of time between
concrete pouring and grinding. To avoid disputes later, however, it is necessary
to specify a minimum required depth of the grind of at least 1/4-inch. That gives
the contractor a starting point to achieve the desired finish results.
d. Do not grind and polish lightweight concrete. Shale aggregates will be pulled
from the surface resulting in pits.
19. Field Quality Control – Testing Agency: Typically, Northwestern will engage a qualified
independent testing and inspecting agency to sample materials, perform tests, and
submit test reports during concrete placement. Architect/Engineer shall review project
specific requirements with the NU Project Manager during the Design Phase of the
project.
b. Testing Services: The following are recommended minimums for field quality
control and testing. Testing of composite samples of fresh concrete obtained
according to ASTM C 172 shall be performed according to the following
requirements:
i. Testing Frequency:
2. Obtain at least one composite sample for each 100 cu. yd. (76 cu.
m) or fraction thereof of each concrete mix placed each day.
ii. Slump: ASTM C 143; one test at point of placement for each composite
sample, but not less than one test for each day's pour of each concrete
CAST-IN-PLACE CONCRETE
03 3000 - 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Air Content: ASTM C 231, pressure method, for normal-weight concrete;
ASTM C 173, volumetric method, for structural lightweight concrete; one
test for each composite sample, but not less than one test for each day's
pour of each concrete mix.
iv. Concrete Temperature: ASTM C 1064; one test hourly when air
temperature is 40 deg F (4.4 deg C) and below and when 80 deg F (27
deg C) and above, and one test for each composite sample.
vi. Compression Test Specimens: ASTM C 31/C 31M; cast and laboratory
cure one set of four standard cylinder specimens for each composite
sample.
1. Cast and field cure one set of four standard cylinder specimens for
each composite sample.
CAST-IN-PLACE CONCRETE
03 3000 - 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Additional Tests: Testing and inspecting agency shall make additional tests of
concrete when test results indicate that slump, air entrainment, compressive
strengths, or other requirements have not been met, as directed by
Architect/Engineer. Testing and inspecting agency may conduct tests to
determine adequacy of concrete by cored cylinders complying with ASTM C 42
or by other methods as directed by Architect/Engineer.
END OF SECTION
CAST-IN-PLACE CONCRETE
03 3000 - 9
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
CAST-IN-PLACE CONCRETE
03 3000 - 10
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 3 – CONCRETE
1. General: This section outlines the requirements for precast concrete. Specific
requirements shall be reviewed with the NU Project Manager during the design phases
of the project
2. Submittal Requirements:
c. Shop drawings shall specifically identify the locations and magnitudes of loads
that will be imposed on the structure by precast connections.
3. Quality Assurance:
a. Precast pieces that are damaged during shipping, handling, etc. shall be
reviewed by the Architect/Engineer and Owner prior to installation.
b. The Architect/Engineer and Owner shall have the discretion to require that
damaged pieces be repaired to their satisfaction prior to installation.
END OF SECTION
PRECAST CONCRETE
03 4000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PRECAST CONCRETE
03 4000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 4 – MASONRY
1. General: This section outlines the general requirements for unit masonry.
3. Quality Assurance:
4. Face Brick:
5. Ground Face Concrete Masonry Units: Provide in public areas. Ground surfaces filled
with cementitious grout. Apply heat treated acrylic finish in compliance with ASTM C744
after polishing.
a. Acceptable Manufacturers:
6. Mortar and Grout Materials: Portland cement Type I or Type II. Provide Portland
cement of color required to produce approved mortar sample.
7. Mortar and Grout Mixes: Limit cementitious materials to lime and Portland cement. Do
not use calcium chloride additives.
UNIT MASONRY
04 2000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Mortar Colored with Pigments: Use organic pigments only. Do not exceed ratio
of pigment-to-cement recommended by pigment manufacturer.
b. The use of galvanized steel in lieu of stainless steel shall be reviewed with the
NU Project Manager.
c. Provide a permanent weep system for masonry assemblies. Utilize a weep / air
space protective product to prevent obstructions from mortar droppings, etc.
ii. Weeps: Provide permanent system of weeps that will remain free
draining and will not be clogged by mortar.
END OF SECTION
UNIT MASONRY
04 2000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 4 – MASONRY
1. General: This section outlines the general requirements for limestone masonry.
2. Design Considerations: To match existing stone bearing wall construction with modern
cavity wall veneer stone technique, the following notes should be incorporated into the
specifications:
a. Corner pieces shall be “L” shaped units with heights and lengths of pieces given
based on the project specific requirements.
b. Arrange corners with larger stones at the bottom, decreasing in size higher up
the building.
c. Edges of all units shall be hand chipped to remove shelves at mortar joints.
f. Grey hued stone will buff over time. It is best to start a bit grey when trying to
match existing older stone.
g. Most of the stone walls on the Evanston campus are a mixture of stone quarried
from horizontal locations (tan in color) and vertical edge pieces (grey in color).
i. Utilize tern-coated through wall flashings to avoid any shiny stainless steel
edges.
j. Two 5-foot by 7-foot mock-up wall samples shall be made for mortar color, stone
color, and to set the limit on stone unit “rectangleness”.
k. Once in place, the mock-up shall be made to confirm stone layout patterns and
limits on mortar joint uniformity. Once approve, the mock-up can remain in place.
LIMESTONE
04 4600 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Safety factors: Use safety factor of 8. Design with redundant load paths, so that
failure of one element (fastener, anchor, etc.) does not result in failure of any
other element.
c. Horizontal Building Movement: Allow for horizontal building movement from floor
to floor (interstory drift) not more than the floor-to-floor height divided by 400.
e. Stone Testing: Test each variety of stone to show compliance with physical
characteristics specified. Test limestone in accordance with ASTM C 568. For
stone veneer thinner than 2-1/4 inches, perform modulus of rupture tests on
specimens of the smallest thickness and with the finish to be used on the project.
4. Stone pieces that are damaged during shipping, handling, etc. shall be reviewed by the
Architect / Owner prior to installation. The Architect / Owner shall have the discretion to
require that damaged pieces be repaired to their satisfaction prior to installation.
6. Limestone:
j. Color: Buff.
l. ILI Grade: Select preferred, other grades may be used under special conditions.
LIMESTONE
04 4600 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
7. Accessory Materials:
p. Stone Anchors in Direct Contact with Stone: Stainless steel, Type 304 or 316
unless specifically indicated otherwise.
a. Provide internal gutter system for draining water from stone cladding in
accordance with the Indiana Limestone Institute Design Handbook.
END OF SECTION
LIMESTONE
04 4600 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
LIMESTONE
04 4600 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 5 – METALS
1. General: This section outlines the general requirements for structural steel framing.
b. Consideration must be made for effects of hanger loads from M/E/P systems,
hung stairs, etc., on building structure.
d. Stainless steel should be considered for areas that are permanently exposed to
the elements.
e. For multi-story structures, design to a strict deflection limit. The fit & finish of
architectural components, the long term durability and construction delays
associated with elevated slab concrete that would need to be leveled (filled,
patched, bushed, topped, etc.), the additional loading on the structure associated
with increased concrete thickness needed to meet flatness / levelness standards,
etc. should all be considered when determining acceptable deflections.
3. Performance Requirements:
4. Quality Assurance:
a. Contractor shall store materials to permit easy access for inspection and
identification. Keep steel members off ground and spaced by using pallets,
dunnage, or other supports and spacers. Protect steel members and packaged
materials from erosion and deterioration.
b. Contractor shall store fasteners in a protected place. Clean and relubricate bolts
and nuts that become dry or rusty before use.
c. Contractor shall not store materials on structure in a manner that might cause
distortion, damage, or overload to members or supporting structures. Repair or
replace damaged materials or structures as directed.
7. Products:
d. Bolt Holes: Cut, drill, mechanically thermal cut or punch standard bolt holes
perpendicular to metal surfaces.
f. Cleaning: Clean and prepare steel surfaces that are to remain unpainted.
h. Steel Wall-Opening Framing: Select true and straight members for fabricating
steel wall-opening framing to be attached to structural steel. Straighten as
required to provide uniform, square, and true members in completed wall
framing.
i. Holes: Provide holes required for securing other work to structural steel and for
passage of other work through steel framing members.
ii. Base-Plate Holes: Cut, drill, mechanically thermal cut, or punch holes
perpendicular to steel surfaces.
iii. Weld threaded nuts to framing and other specialty items indicated to
receive other work.
8. Shop Connections:
b. Weld Connections: Comply with AWS D1.1 for welding procedure specifications,
tolerances, appearance, and quality of welds and for methods used in correcting
welding work.
i. Remove backing bars or runoff tabs, back gouge, and grind steel smooth.
ii. Assemble and weld built-up sections by methods that will maintain true
alignment of axes without exceeding tolerances of AISC's "Code of
Standard Practice for Steel Buildings and Bridges" for mill material.
iii. Verify that weld sizes, fabrication sequence, and equipment used for
architecturally exposed structural steel will limit distortions to allowable
tolerances. Prevent weld show-through on exposed steel surfaces.
9. Shop Priming:
v. Galvanized surfaces
b. Surface Preparation: Clean surfaces to be painted. Remove loose rust and mill
scale and spatter, slag, or flux deposits.
ii. Apply two coats of shop paint to inaccessible surfaces after assembly or
erection. Change color of second coat to distinguish it from first.
10. Galvanizing:
ii. Galvanize lintels and shelf angles attached to structural-steel frame and
located in exterior walls.
b. Correct deficiencies in Work that test reports and inspections indicate does not
comply with the Contract Documents.
ii. Magnetic Particle Inspection: ASTM E 709; performed on root pass and
on finished weld. Cracks or zones of incomplete fusion or penetration will
not be accepted.
12. Examination:
13. Preparation:
a. Provide temporary shores, guys, braces, and other supports during erection to
keep structural steel secure, plumb, and in alignment against temporary
construction loads and loads equal in intensity to design loads. Remove
temporary supports when permanent structural steel, connections, and bracing
are in place, unless otherwise indicated.
14. Erection:
c. Align and adjust various members forming part of complete frame or structure
before permanently fastening. Before assembly, clean bearing surfaces and
other surfaces that will be in permanent contact with members. Perform
necessary adjustments to compensate for discrepancies in elevations and
alignment.
g. Do not enlarge unfair holes in members by burning or using drift pins. Ream
holes that must be enlarged to admit bolts.
b. Weld Connections: Comply with AWS D1.1 for welding procedure specifications,
tolerances, appearance, and quality of welds and for methods used in correcting
welding work.
d. Correct deficiencies in Work that test reports and inspections indicate does not
comply with the Contract Documents.
END OF SECTION
DIVISION 5 – METALS
1. General: This section outlines the general requirements for steel decking.
2. Design Criteria:
b. Metal decking shall be provided with deck and flute closures, metal edge forms,
etc. as required to contain the wet concrete during slab-on-deck placement.
3. Design Considerations:
END OF SECTION
STEEL DECKING
05 3100 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
STEEL DECKING
05 3100 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 5 – METALS
1. General: This section outlines the general requirements for metal fabrications.
2. Design Criteria:
i. For materials indicated to be painted, the erector shall prime all exposed
steel following grinding.
3. Bollards:
a. Bollards shall be placed sufficiently far apart for bicycle traffic and close enough
to prohibit automobile traffic.
b. Provide removable bollards with handles on each side located in the direction of
traffic.
d. Provide a bank of additional receivers for the removable bollards, equal to the
number of bollards. Locate out of the way of traffic. These may be located in
lawn or mulched areas.
e. Provide two 2-inch wide reflective strips located 2-inches down from the top of
the bollard the second row 2-inches below the first strip.
g. Acceptable Manufacturer:
END OF SECTION
METAL FABRICATIONS
05 5000 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
METAL FABRICATIONS
05 5000 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 5 – METALS
1. General: This section outlines the general requirements for metal fabrications.
2. Design Criteria:
a. Exterior Railings:
ii. The preferred base detail for exterior railings is to use base plates and
fasteners.
iii. If the condition requires a embedment of the bottom of the railing post,
then an epoxy-based setting compound should be utilized. Por-Rok is not
recommended.
v. When mild steel balusters are used, provide stainless steel ends welded
to the mild steel for the embedded portion.
END OF SECTION
DIVISION 5 – METALS
1. General: This section outlines the general requirements for stair treads and nosings.
2. Design Criteria:
a. Stair Nosings: For interior and exterior public stairs, provide full length, non-slip
nosings and treads.
END OF SECTION
2. Design Considerations:
a. Rough Carpentry:
ii. Load bearing lumber shall meet the following minimum working stresses:
f = 1,000 psi, H = 135 psi and E = 1,300,000 psi.
iii. Wood products used in wet locations (windows, roofs, etc.) shall be
moisture-treated. Moisture-treated lumber shall be kiln-dried following
treatment.
v. Electrical rooms and communication closets shall have at least two 4 ft. x
8 ft. plywood backboards; refer to NUIT Standards for requirements at
main telecommunication rooms.
b. Wood Trusses:
ii. Truss calculations shall account for mechanical and electrical utilities
supported from the bottom chord of the trusses.
iii. The minimum bottom chord member size shall be nominal 2x6.
END OF SECTION
ROUGH CARPENTRY
06 1000 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ROUGH CARPENTRY
06 1000 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
2. Quality Assurance:
3. Woodwork:
a. Woodwork: AWI “Custom” grade typical; “Premium” grade for door frames and
sidelights and for laboratory casework.
4. Wood Materials:
END OF SECTION
ARCHITECTURAL WOODWORK
06 4000 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ARCHITECTURAL WOODWORK
06 4000 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
2. Design Considerations:
a. Architect shall perform a dew point analysis of the exterior wall enclosure.
i. Walls: R20
c. Vapor Barriers: Provide a continuous vapor barrier system at the warm side of
building insulation.
END OF SECTION
THERMAL INSULATION
07 2100 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
THERMAL INSULATION
07 2100 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section outlines general requirements for firestopping and smoke
stopping systems.
2. Design Considerations
a. General: Products for fire stopping and smoke stopping shall be by a single
manufacturer throughout the project.
b. Fire Stopping:
c. Smoke Stopping:
i. Use Hilti Foam or other approved joint sealant suitable for the application;
use only fully curing types where accessible in the finished work.
b. Provide a “use matrix” indicating manufacturer and UL label system for each
condition on the drawings or in the technical specifications.
END OF SECTION
BARRIERS
07 2700 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
BARRIERS
07 2700 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
2. Materials:
a. Slate Shingles: ASTM C 406 Grade S2 slate shingles, machine punched for two
nails located for proper head lap and complying with the following requirements:
iii. Colors: To be reviewed with the NU Project Manager during the design
phases of the project.
b. Snow Guards: Prefabricated copper units designed for use with slate shingle
roofing and complete with hook for installation onto slate.
i. Basis of Design:
END OF SECTION
SLATE SHINGLES
07 3126 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
SLATE SHINGLES
07 3126 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section outlines general requirements for modified bituminous membrane
roofing systems.
2. Design Considerations:
4. Roof System:
a. Provide a two-ply system, with a heavy base sheet as the bottom ply. Finish with
Type II flood coat at 70 lbs / square and gravel at 400 lbs / square.
b. Provide APP of SPS base flashings cover with fibrated coating after installation.
d. Accessories:
1. Width: 36 inches.
6. Quality Assurance:
a. Manufacturer's Qualifications:
b. Installer Qualifications:
c. Initial Roofing Meeting: Before start of roof deck construction, a meeting shall be
held with General Contractor, roofing installer; installers of roof deck, roof-
mounted equipment, and other work adjacent to or integral with the roof system;
the architect; the owner and other parties concerned with roofing system
performance.
END OF SECTION
1. General: This section outlines general requirements for EPDM roofing systems.
2. Design Considerations:
4. Roof System:
b. Flashing: Cured EPDM, Nominal 0.060 inch thick except uncured EPDM,
Nominal 0.060 inch thick, for conditions where flashing is formed around corners,
projections, or changes in direction. Match color of membrane material.
c. Insulation System Requirements: Provide type and style of insulation that meets
contract requirements and is approved by the membrane manufacturer for the
indicated installation.
EPDM ROOFING
07 5323– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
6. Quality Assurance:
a. Manufacturer's Qualifications:
b. Installer Qualifications:
c. Initial Roofing Meeting: Before start of roof deck construction, a meeting shall be
held with General Contractor, roofing installer; installers of roof deck, roof-
mounted equipment, and other work adjacent to or integral with the roof system;
the architect; the owner and other parties concerned with roofing system
performance.
EPDM ROOFING
07 5323– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
EPDM ROOFING
07 5323– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
EPDM ROOFING
07 5323– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section outlines general requirements for PVC roofing systems.
2. Design Considerations:
4. Roof System:
i. Membrane Material: PVC sheet, minimum 0.060 inch (60 mils) thick.
Review the option of 0.080 inch (80 mils) thick membrane with NU Project
Manager.
ii. Minimum properties: ASTM D 4434, Type II, Grade I, glass fiber
reinforced, felt backed.
PVC ROOFING
07 5419– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Accessories:
6. Quality Assurance:
b. Manufacturer's Qualifications:
c. Installer Qualifications:
d. Initial Roofing Meeting: Before start of roof deck construction, a meeting shall be
held with General Contractor, roofing installer; installers of roof deck, roof-
mounted equipment, and other work adjacent to or integral with the roof system;
the architect; the owner and other parties concerned with roofing system
performance.
PVC ROOFING
07 5419– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
PVC ROOFING
07 5419– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PVC ROOFING
07 5419– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section outlines general requirements for sheet metal flashing and trim.
2. Materials: Do not use galvanized metal in exterior applications. Use one of the
following:
a. Stainless Steel Sheet: ASTM A 167, Type 316L, non-corroding. Finish: 2D (dull
annealed).
c. Terne Coated Stainless Steel Sheet: ASTM A 167, Type 304 sheet, coated both
sides with terne alloy (80 percent lead; 20 percent tin); FS QQ-T-201F, Type II.
Minimum coating weight: 40 lb., nominal (1.45 ounces per square foot total
coating weight).
a. Fabricate from same material and finish used for adjacent exposed flashings.
b. Provide removable debris screens for gutters, fabricated from 1/4-inch mesh wire
cloth of same material used for gutters or approved compatible material.
c. Provide formed sheet metal frame on 4 sides of each screen unit. Length of
screen units shall not exceed 10 feet.
d. Provide wire basket type strainers at downspouts, fabricated from wire and sheet
metal of same material used downspouts or approved compatible material.
Provide sheet metal baffles 6 inches high with legs 18 inches long at gutter
corners below roof valleys.
e. Provide formed metal splash pans fabricated from same type of sheet metal used
for downspouts. Locate where downspout discharges onto lower roof.
END OF SECTION
1. General: This section outlines general requirements for roof accessories including heat
and smoke vents.
2. Design Considerations:
iii. Curb: Fully welded units, manufacturer's standard height but not less
than 12 inches from base flange to top of frame. Fabricate from same
material and thickness used for cover top.
v. Hinges: Spring lift mechanism, sized to open doors with 10 pounds per
square foot uniform live load applied to exterior.
END OF SECTION
ROOF ACCESSORIES
07 7200– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ROOF ACCESSORIES
07 7200– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
2. Quality Assurance:
a. Field Installation Tests: Before installation, test the adhesion of each sealant to
actual substrates.
5. Materials:
a. Elastomeric Sealants:
i. Non-Sag, two-part, ASTM C 920, Type M, Grade NS, Class 25, Use NT,
plus movement capability of 50 percent in both extension and
compression.
i. Nonsag, two-part, ASTM C 920 for Use T: Type S or M, Grade NS, Class
25, Use T.
JOINT SEALANTS
07 9200– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Solvent-Release-Curing Sealants:
g. Butyl Sealant:
h. Latex Sealants:
i. Noncuring Sealers:
j. Sealant Backers:
i. General: Non-staining.
JOINT SEALANTS
07 9200– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Below-Grade Joints:
d. Exterior Joints Well Protected from Weather and Not Subject to Movement:
f. Interior Floor Joints and Pedestrian Paving Joints, Less than 1-1/2 Percent
Slope:
i. Use one of the following sealants: Silicone sealant for Use T; Two-part
nonsag urethane sealant for Use T.
g. Joints around Pipes, Ducts, and Conduit Penetrating Exterior Walls and Roofs:
Same as used for adjacent substrates.
END OF SECTION
JOINT SEALANTS
07 9200– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
JOINT SEALANTS
07 9200– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 8 – OPENINGS
1. General: This section outlines general requirements for interior and exterior hollow
metal doors and frames.
2. Design Considerations:
a. Paired doors are discouraged. When paired doors are absolutely necessary
provide removable mullions.
c. Solid grout frames, both interior and exterior, at concrete, concrete masonry,
brick masonry, or limestone walls.
d. Provide batt insulation full perimeter of hollow metal frames in interior walls at
drywall partitions.
3. Quality Assurance:
a. Fire Rated Door Assemblies: Comply with SDI 100, Fire-Rated Door Assemblies
and in compliance with NFPA 80 and labeled per ASTM E 152 by UL, FM or
Warnock-Hersey.
5. Steel Doors: Fabricate steel doors in accordance with requirements of SDI 100.
a. Doors: Grade III - Extra Heavy-Duty, Model 1 - Full Flush, 16 ga. min. face skin
for exterior use and 18 ga. min. for interior use. Stiffened with 20 ga. ribs spaced
not more than 6” apart, 14ga. lock rail, 12 ga. continuous channel hinge rail, 16
ga. top and bottom rails, seamless edges. Provide 12 ga. reinforcing for closer at
head.
i. Minimum U-value: 0.24 BTU per hour per square foot per degree F
a. Construction: Mitered and welded corners. Reinforce head with 12 ga. can.
END OF SECTION
DIVISION 8 – OPENINGS
2. Design Considerations:
a. Wood doors are for interior use only and not for exterior applications, with the
following exception:
i. Use of custom wood doors for exterior applications may be required for
historic buildings. Review specific project requirements with NU Project
Manager.
b. Natural finishes are preferred. Opaque finishes shall be permitted under special
conditions.
c. Solid, staved wood core doors with matching hardwood stiles and rails shall be
specified, with the exception that mineral cores shall be used for fire rated doors
where required by code.
2. Warranties:
3. Wood Doors:
a. Solid Core Wood-Faced Doors: Face veneers for transparent finish, Premium
Grade, Premium, 5 ply construction.
c. Stile and Rail Wood Doors: Permitted under special conditions. NWWDA
Premium/Select grade.
a. Steel frames are preferred. Wood frames are permitted only in special situations.
Architect shall review requirements and options with NU Project Manager.
a. Fabricate frames in accordance with AWI Section 900 and casings in accordance
with AWI Section 200. Same grade as door.
END OF SECTION
WOOD DOORS
08 1416– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
WOOD DOORS
08 1416– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 8 – OPENINGS
1. General: This section outlines general requirements for access doors and frames.
2. Design Considerations:
a. Architect to review locations for access doors and access panels with NU Project
Manager during the design phase.
b. If possible, access door and access panel locations shall be shown on the
drawings.
3. Manufactured Units: The following are the minimum requirements for manufactured
access doors and frames. Architect shall review specific requirements with the NU
Project Manager.
c. Door: 14 gage steel flush panel; when fire-rated, provide standard insulated
flush panel/doors with continuous piano hinge.
e. Locking device: Keyed cylinder lock. Supply 2 keys with each lock. Key all
cylinder locks to keying system established for other finish hardware.
5. Exposed Frames: Fabricate frame with nominal 1-inch-wide exposed flange at door
panel perimeter.
6. Doors: Flush panel doors: Fabricate door panel from material and material gage
indicated, with a smooth face, and with door edges installed square with door frame.
7. Shop/Factory Finishing: Prime paint finish: Where indicated, finish door assembly with
manufacturer's standard factory-applied rust-inhibitive primer.
END OF SECTION
DIVISION 8 – OPENINGS
1. General: This section outlines general requirements for aluminum framed entrances and
storefronts.
2. Design Considerations:
a. Kawneer TUFFLINE system is preferred, with 8-1/4” mid rail, 10-1/4” bottom rail,
and 1” insulating glass.
b. Provide all welded construction with back-sealed joints to prevent light leaks.
d. Paired doors are discouraged. When paired doors are necessary, provide fixed
or removable mullions.
b. Structural Performance: Design to withstand all live and dead loads without
deformation and without deflection greater than 1/175 of span.
c. Deflection in Plane of Wall: Not greater than that which would reduce glass edge
clearance to 25 percent of design dimension or 1/8 inch, whichever is greater, or
that which would reduce glass bite to 75 percent of design dimension.
d. Wind Loads:
ii. Design system to withstand 150 percent of design wind load with no
failure or permanent deformation greater than 0.2 percent of span.
e. Air Infiltration:
i. Fixed Framing: Not more than 0.06 cfm per square foot of fixed area
iii. Single Doors: Not more than 0.5 cfm per linear foot of crack
iv. Pairs of Doors (Not recommended): Not more than 1.0 cfm per linear foot
of crack
f. Water Penetration:
g. Condensation Resistance:
5. Materials:
a. Aluminum Members: ASTM B 221 for extrusions, ASTM B 209 for sheet/plate;
alloy and temper recommended by the manufacturer for the strength required, for
corrosion resistance, and for the finish required.
6. Framing Systems:
b. Style: Flush glazed (without projecting stops), with glazing centered in frame
members; see drawings for profiles, dimensions, and arrangement of members.
e. Finish: Review options with NU Project Manager during the design phase.
f. Aluminum Door Frames: Extruded tube or channel frames with welded joints.
7. Swinging Doors:
a. Stile and Rail Doors: Glazed doors with tubular extruded aluminum frame
members.
h. Weather-stripping:
END OF SECTION
DIVISION 8 – OPENINGS
2. Design Considerations:
d. Window Design: Where glazing stops are indicated, design for re-glazing without
removal or dismantling of ventilator/sash or frames.
3. Performance Requirements: As specified in AAMA 101, for window type, grade, and
class indicated.
d. Acceptable field values: Not more than 1.5 times laboratory allowed value.
WINDOWS
08 5000– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
5. Quality Assurance:
b. Field Tests:
8. Hung Windows (for Residence Halls): Vertically sliding sash, with counterbalances.
Provide tilting sash to allow cleaning of both sides of sash from inside of same unit.
b. Grade: DH-HC40
9. Materials:
WINDOWS
08 5000– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Aluminum.
ii. Steel, zinc electroplated after fabrication in accordance with ASTM B 633.
e. Sealants:
ii. For nonworking, metal-to-metal joints within window units: Small joint
sealant conforming to 803.3, as described in AAMA 800.
iii. For joints between other window components: Suitable for application.
iv. For joints between window units and other building components: Provide
products specified in Division 7.
10. Accessories:
b. Insect Screens: Formed or extruded aluminum frames with screen fabric. Design
to fit tightly, but be removable, using as few exposed fasteners or latches as
possible.
iii. Screen Fabric: Aluminum wire fabric complying with FS RR-W-365, Type
VII.
WINDOWS
08 5000– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
11. Field Quality Control: Test for air and water infiltration after installation. Review specific
requirements with NU Project Manager during the design phase.
END OF SECTION
WINDOWS
08 5000– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 8 – OPENINGS
1. General:
b. Door hardware specifications shall be reviewed with the NU Project Manager and
the NU Lock Shop during the design phases of the project.
2. SUMMARY
i. Swinging doors.
b. Door hardware includes, but is not necessarily limited to, the following:
c. Related Sections:
DOOR HARDWARE
08 7100– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Codes and References: Comply with the version year adopted by the Authority
Having Jurisdiction.
iii. ASTM E1886 - Test Method for Performance of Exterior Windows, Curtin
Walls, Doors and Shutters Impacted by Missiles and Exposed to Cyclic
Pressure Differentials.
vi. FEMA 361 2008 - Design and Construction Guidance for Community Safe
Rooms.
vii. ICC 500 - ICC/NSSA Standard for the Design and Construction of Storm
Shelters.
DOOR HARDWARE
08 7100– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
e. Standards: Hardware specified herein shall comply with the following industry
standards:
3. SUBMITTALS
ii. Organization: Organize the Door Hardware Schedule into door hardware
sets indicating complete designations of every item required for each
door or opening. Organize door hardware sets in same order as in the
Door Hardware Sets at the end of Part 3. Submittals that do not follow the
same format and order as the Door Hardware Sets will be rejected and
subject to resubmission.
1. Type, style, function, size, label, hand, and finish of each door
hardware item.
DOOR HARDWARE
08 7100– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
4. QUALITY ASSURANCE
DOOR HARDWARE
08 7100– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Source Limitations: Obtain each type and variety of Door Hardware specified
in this Section from a single source, qualified supplier unless otherwise indicated.
g. Regulatory Requirements: Comply with NFPA 70, NFPA 80, NFPA 101 and
ANSI A117.1 requirements and guidelines as directed in the model building code
including, but not limited to, the following:
3. Thresholds: Not more than 1/2 inch high. Bevel raised thresholds
with a slope of not more than 1:2.
iii. NFPA 101: Comply with the following for means of egress doors:
DOOR HARDWARE
08 7100– 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. Latches, Locks, and Exit Devices: Not more than 15 lbf to release
the latch. Locks shall not require the use of a key, tool, or special
knowledge for operation.
ii. Inspect and discuss electrical roughing-in, power supply connections, and
other preparatory work performed by other trades.
a. Inventory door hardware on receipt and provide secure lock-up and shelving for
door hardware delivered to Project site. Do not store electronic access control
hardware, software or accessories at Project site without prior authorization.
b. Tag each item or package separately with identification related to the final
Door Hardware Schedule, and include basic installation instructions with each
item or package.
DOOR HARDWARE
08 7100– 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
6. COORDINATION
a. Templates: Obtain and distribute to the parties involved templates for doors,
frames, and other work specified to be factory prepared for installing standard
and electrified hardware. Check Shop Drawings of other work to confirm that
adequate provisions are made for locating and installing hardware to comply
with indicated requirements.
7. WARRANTY
iii. Deterioration of metals, metal finishes, and other materials beyond normal
weathering.
iv. Electrical component defects and failures within the systems operation.
DOOR HARDWARE
08 7100– 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
8. MAINTENANCE SERVICE
a. General: Provide door hardware for each door to comply with requirements in
Door Hardware Sets and each referenced section that products are to be
supplied under.
DOOR HARDWARE
08 7100– 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Hinges: ANSI/BHMA A156.1 certified butt hinges with number of hinge knuckles
as specified in the Door Hardware Sets.
4. For doors with heights more than 120 inches, provide 4 hinges,
plus 1 hinge for every 30 inches of door height greater than 120
inches.
ii. Hinge Size: Provide the following, unless otherwise indicated, with
hinge widths sized for door thickness and clearances required:
iii. Hinge Weight and Base Material: Unless otherwise indicated, provide the
following:
iv. Hinge Options: Comply with the following where indicated in the
Hardware Sets or on Drawings:
DOOR HARDWARE
08 7100– 9
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
v. Acceptable Manufacturers:
i. Acceptable Manufacturers:
c. Pin and Barrel Continuous Hinges: ANSI/BHMA A156.26 certified pin and
barrel continuous hinges with minimum 12 gauge (.105) Type 304 stainless steel
hinge leaves, concealed teflon- coated stainless pin, and twin self-lubricated
nylon bearings at each knuckle separation. Fabricate hinges non-handed and
U.L. listed for use on up to and including 3 hour rated doors and U.L. listed for
windstorm components where applicable. Provide hinges with power transfer
cutouts where indicated at electrified openings.
i. Acceptable Manufacturers:
d. Floor Closers: ANSI/BHMA A156.4 certified floor closers provided either center
hung or 3/4" offset hung type complete with top and intermediate pivots (offset
closers only) in quantity according to manufacturer's recommendation. Floor
closers available with options for labeled, lead lined and regular doors. Provide
independent and adjustable valves for closing speed, latch speed, and
backcheck with built-in dead stop and hold open features as specified. Provide
finish cover plates or thresholds as indicated in door Hardware Sets.
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 10
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
ii. Bi-folding Door Hardware: Rated for door panels weighing up to 125 lb.
iii. Pocket Sliding Door Hardware: Rated for doors weighing up to 200 lb.
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 11
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
e. Electric Door Hardware Cords: Provide electric transfer wiring harnesses with
standardized plug connectors to accommodate up to twelve (12) wires.
Connectors plug directly to through- door wiring harnesses for connection to
electric locking devices and power supplies. Provide sufficient number of
concealed wires to accommodate electric function of specified hardware. Provide
a connector for through-door electronic locking devices and from hinge to
junction box above the opening. Wire nut connections are not acceptable.
Determine the length required for each electrified hardware component for the
door type, size and construction, minimum of two per electrified opening.
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 12
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Provide one each of the following tools as part of the base bid contract to the
contractor:
a. Flush Bolts and Surface Bolts: ANSI/BHMA A156.3 and A156.16, Grade 1,
certified automatic, self-latching, and manual flush bolts and surface bolts.
Manual flush bolts to be furnished with top rod of sufficient length to allow bolt
location approximately six feet from the floor. Furnish dust proof strikes for
bottom bolts. Surface bolts to be minimum 8” in length and U.L. listed for labeled
fire doors and U.L. listed for windstorm components where applicable. Provide
related accessories (mounting brackets, strikes, coordinators, etc.) as required
for appropriate installation and operation.
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 13
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Door Push Plates and Pulls: ANSI/BHMA A156.6 certified door pushes and
pulls of type and design specified below or in the Hardware Sets. Coordinate
and provide proper width and height as required where conflicting hardware
dictates.
ii. Straight Pull Design: Minimum 1-inch round diameter stainless steel
bar or tube stock pulls with 2 1/2-inch projection from face of door unless
otherwise indicated.
iii. Offset Pull Design: Minimum 1-inch round diameter stainless steel bar or
tube stock pulls with 2 1/2-inch projection and offset of 90 degrees unless
otherwise indicated.
iv. Push Bars: Minimum 1-inch round diameter horizontal push bars with
minimum clearance of 2 1/2-inch projection from face of door unless
otherwise indicated.
v. Fasteners: Provide machine screws for all metal doors (drill and tap not
self-tapping) and provide manufacture standard for all wood doors.
2. McKinney (MK)
3. Trimco (TR)
d. Locking Pull System: Post-mount style door pulls with integrated deadbolt
locking system in type and design as specified in the Hardware Sets. Pulls
available in multiple head, floor, or combination locking options, with outside
keyed rim cylinder operation and inside turn piece activation. Mounting
applications for aluminum, glass, steel and wood doors, with customized sizing
and configuration options. Pull finishes include brass, bronze, and stainless steel.
Provide pulls standard with dustproof strike and auxiliary door stop as specified.
i. Acceptable Manufacturers:
2. Blumcraft (BL)
DOOR HARDWARE
08 7100– 14
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 15
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Lock Trim Design: LNL, LNJ [LNG or TEG by approval only, if approved no
attic stock required], [WTL by approval only, if approved no attic stock required] .
all other trim must be approved by the owner and provide 20% additional product
in attic stock.
a. Integrated Wiegand Output Mortise Locks: Wiegand output ANSI A156.13, Grade
1, mortise lockset with integrated iClass® elite card reader, request-to-exit
signaling, door position status switch, and latchbolt monitoring in one complete
unit. Hard wired, solenoid driven locking/unlocking control of the lever handle
trim, 3/4" deadlocking anti-friction latch, and 1" case-hardened steel deadbolt.
Lock is U.L listed and labeled for use on up to 3 hour fire rated openings. Keyed
high security cylinder override.
iii. 24VDC operation with iClass® elite reader. Fail safe or fail secure
options.
iv. Installation requires only one cable run from the lock to the access
control panel without requirements for additional proprietary lock panel
interface boards or modules.
DOOR HARDWARE
08 7100– 16
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
a. Strikes: Provide manufacturer's standard strike with strike box for each latch or
lock bolt, with curved lip extended to protect frame, finished to match door
hardware set, unless otherwise indicated, and as follows:
ii. Extra-Long-Lip Strikes: For locks used on frames with applied wood
casing trim.
DOOR HARDWARE
08 7100– 17
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
a. Standard Electric Strikes: Heavy duty, cylindrical and mortise lock electric
strikes conforming to ANSI/BHMA A156.31, Grade 1, UL listed for both Burglary
Resistance and for use on fire rated door assemblies. Stainless steel
construction with dual interlocking plunger design tested to exceed 3000 lbs. of
static strength and 350 ft-lbs. of dynamic strength. Strikes tested for a minimum 1
million operating cycles. Provide strikes with 12 or 24 VDC capability and
supplied standard as fail-secure unless otherwise specified. Option available for
latchbolt and latchbolt strike monitoring indicating both the position of the
latchbolt and locked condition of the strike.
i. Acceptable Manufacturers:
b. Surface Mounted Rim Electric Strikes: Surface mounted rim exit device electric
strikes conforming to ANSI/BHMA A156.31, Grade 1, and UL Listed for both
Burglary Resistance and for use on fire rated door assemblies. Construction
includes internally mounted solenoid with two heavy-duty, stainless steel locking
mechanisms operating independently to provide tamper resistance. Strikes
tested for a minimum of 500,000 operating cycles. Provide strikes with 12 or
24 VDC capability supplied standard as fail-secure unless otherwise
specified. Option available for latchbolt and latchbolt strike monitoring indicating
both the position of the latchbolt and locked condition of the strike. Strike
requires no cutting to the jamb prior to installation.
DOOR HARDWARE
08 7100– 18
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
c. Provide electric strikes with in-line power controller and surge suppressor by the
same manufacturer as the strike with combined products having unlimited lifetime
warranty.
a. General Requirements: All exit devices specified herein shall meet or exceed
the following criteria:
i. At doors not requiring a fire rating, provide devices complying with NFPA
101 and listed and labeled for "Panic Hardware" according to UL305.
Provide proper fasteners as required by manufacturer including sex nuts
and bolts at openings specified in the Hardware Sets.
ii. Where exit devices are required on fire rated doors, provide devices
complying with NFPA 80 and with UL labeling indicating "Fire Exit
Hardware". Provide devices with the proper fasteners for installation as
tested and listed by UL. Consult manufacturer’s catalog and template
book for specific requirements.
iii. Except on fire rated doors, provide exit devices with hex key dogging
device to hold the pushbar and latch in a retracted position. Provide
optional keyed cylinder dogging on devices where specified in Hardware
Sets.
iv. Flush End Caps: Provide heavy weight impact resistant flush end caps
made of architectural metal in the same finish as the devices as in the
Hardware Sets. Plastic end caps will not be acceptable. Prefix on all exit
devices should be 43-.
v. Lever Operating Trim: Where exit devices require lever trim, furnish
manufacturer's heavy duty trim with cold forged escutcheons, beveled
edges, and four threaded studs for thru-bolts.
DOOR HARDWARE
08 7100– 19
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
vi. Vertical Rod Exit Devices: Provide and install interior surface and
concealed vertical rod exit devices as Less Bottom Rod (LBR) unless
otherwise indicated.
viii. Dummy Push Bar: Nonfunctioning push bar matching functional push bar.
ix. Rail Sizing: Provide exit device rails factory sized for proper door width
application.
x. Through Bolt Installation: For exit devices and trim as indicated in Door
Hardware Sets.
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 20
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
a. Wiegand Output Integrated Card Reader Exit Hardware: Wiegand output ANSI
156.3 Grade 1 rim, mortise, and vertical rod exit device hardware with integrated
proximity card reader, latchbolt and touchbar monitoring, and request-to-exit
signaling, in one complete unit. Hard wired, solenoid driven locking/unlocking
control of the lever handle exit trim with 3/4" throw latch bolt. U.L listed and
labeled for either panic or "fire exit hardware" for use on up to 3 hour fire rated
openings. Available with or without keyed high security cylinder override.
DOOR HARDWARE
08 7100– 21
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. 24VDC operation available with iClass® elite reader. 24VDC required for
solenoid operated exit trim. Fail safe or fail secure options.
iv. Installation requires only one cable run from the exit hardware to the
access control panel without requirements for additional proprietary lock
panel interface boards or modules.
a. Door closers specified herein shall meet or exceed the following criteria:
ii. Standards: Closers to comply with UL-10C and UBC 7-2 for Positive
Pressure Fire Test and be U.L. listed for use of fire rated doors.
iv. Closer Arms: Provide heavy duty, forged steel closer arms unless
otherwise indicated in Hardware Sets.
DOOR HARDWARE
08 7100– 22
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Door Closers, Surface Mounted (Large Body Cast Iron): ANSI/BHMA A156.4,
Grade 1 surface mounted, heavy duty door closers with complete spring power
adjustment, sizes 1 thru 6; and fully operational adjustable according to door
size, frequency of use, and opening force. Closers to be rack and pinion type,
one piece cast iron body construction, with adjustable backcheck and separate
non-critical valves for closing sweep and latch speed control. Provide high
impact, non-corrosive plastic covers standard.
i. Acceptable Manufacturers:
1. LCN Closers (LC) - 4041XP Series x TBWMS screw pack for all
closers.
i. Acceptable Manufacturers:
1. LCN Closers (LC) - 1461 Series x TBWMS screw pack for all
closers.
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 23
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Performance Requirements:
h. Features: Operator units to have full feature adjustments for door opening and
closing force and speed, backcheck, motor assist acceleration from 0 to 30
DOOR HARDWARE
08 7100– 24
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
seconds, time delay, vestibule interface delay, obstruction recycle, and hold open
time from 0 up to 30 seconds.
i. Provide outputs and relays on board the operator to allow for coordination of
exit device latch retraction, electric strikes, magnetic locks, card readers, safety
and motion sensors and specified auxiliary contacts.
l. Acceptable Manufacturers:
i. LCN Closers (LC) - 4640 Series x TBWMS screw pack for all closers
a. Single Point Closer Holders: Single point closer holder designed to hold open
fire or smoke rated doors until interruption of signal from fire alarm, smoke
detector or remote release switch. Pull side, push side, or double egress
mounting applications available with non-handed track and closer body and
dual voltage input (24V/120V). Voltage to be 24VDC unless otherwise specified.
Pull side mounted closers to have minimum adjustable hold-open range of 85 to
110 degrees. Auxiliary door stops are required at hold open point.
i. Acceptable Manufacturers:
1. LCN Door Closers (LC) - 4040SE Series x TBWMS screw pack for
all closers.
i. Acceptable Manufacturers:
c. Electrified Holders: Electrified door holders are designed to provide single point
hold open for fire and smoke labeled doors and must be used in conjunction
with a opposite side mounted U.L. listed door closer. Single track arm is non-
handed with detector or non-detector option.
DOOR HARDWARE
08 7100– 25
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
ii. Size: Fabricate protection plates (kick, armor, or mop) not more than 2"
less than door width (LDW) on stop side and not more than 1" less than
door width on pull side. Coordinate and provide proper width and height
as required where conflicting hardware dictates. Height to be as specified
in the Hardware Sets.
a. General: Door stops and holders to be of type and design as specified below or
in the Hardware Sets.
DOOR HARDWARE
08 7100– 26
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Door Stops and Bumpers: ANSI/BHMA A156.16, Grade 1 certified door stops
and wall bumpers. Provide wall bumpers, either convex or concave types with
anchorage as indicated, unless floor or other types of door stops are specified
in Hardware Sets. Do not mount floor stops where they will impede traffic.
Where floor or wall bumpers are not appropriate, provide overhead type stops
and holders.
i. Acceptable Manufacturers:
3. Trimco (TC).
i. Acceptable Manufacturers:
b. Smoke Labeled Gasketing: Assemblies complying with NFPA 105 that are listed
and labeled by a testing and inspecting agency acceptable to authorities having
jurisdiction, for smoke control ratings indicated, based on testing according to UL
1784.
c. Fire Labeled Gasketing: :Assemblies complying with NFPA 80 that are listed
and labeled by a testing and inspecting agency acceptable to authorities having
jurisdiction, for fire ratings indicated, based on testing according to UL-10C.
DOOR HARDWARE
08 7100– 27
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
e. Replaceable Seal Strips: Provide only those units where resilient or flexible seal
strips are easily replaceable and readily available from stocks maintained by
manufacturer.
i. Acceptable Manufacturers:
a. Key Switches: Key switches furnished standard with stainless steel single gang
face plate with a 12/24VDC bi-color LED indicator. Integral backing bracket
permits integration with any 1 1/4" or 1 1/2" mortise type cylinder. Key switches
available as momentary or maintained action and in narrow face plate options.
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
DOOR HARDWARE
08 7100– 28
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturers:
e. Wiegand Test Unit: Test unit verifies proper Wiegand output integrated card
reader lock installation in the field by testing for proper wiring, card reader data
integrity, and lock functionality including lock/unlock, door position, and request-
to-exit status. 12 or 24VDC voltage adjustable operating as Fail Safe or Fail
Secure.
i. Acceptable Manufacturers:
i. Acceptable Manufacturers:
31. FABRICATION
32. FINISHES
DOOR HARDWARE
08 7100– 29
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
standards, but in no case less than specified by referenced standards for the
applicable units of hardware.
33. EXAMINATION
b. Notify architect of any discrepancies or conflicts between the door schedule, door
types, drawings and scheduled hardware. Proceed only after such discrepancies
or conflicts have been resolved in writing.
34. PREPARATION
a. Hollow Metal Doors and Frames: Comply with ANSI/DHI A115 series. B. Wood
Doors: Comply with ANSI/DHI A115-W series.
35. INSTALLATION
DOOR HARDWARE
08 7100– 30
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Provide blocking in drywall partitions where wall stops or other wall
mounted hardware is located.
d. Thresholds: Set thresholds for exterior and acoustical doors in full bed of
sealant complying with requirements specified in Division 7 Section "Joint
Sealants."
e. Storage: Provide a secure lock up for hardware delivered to the project but
not yet installed. Control the handling and installation of hardware items so that
the completion of the work will not be delayed by hardware losses before and
after installation.
37. ADJUSTING
a. Initial Adjustment: Adjust and check each operating item of door hardware and
each door to ensure proper operation or function of every unit. Replace units
that cannot be adjusted to operate as intended. Adjust door control devices to
compensate for final operation of heating and ventilating equipment and to
comply with referenced accessibility requirements.
a. Protect all hardware stored on construction site in a covered and dry place.
Protect exposed hardware installed on doors during the construction phase.
Install any and all hardware at the latest possible time frame.
c. Clean operating items as necessary to restore proper finish. and provide final
protection and maintain conditions that ensure door hardware is without damage
or deterioration at time of owner occupancy.
39. DEMONSTRATION
DOOR HARDWARE
08 7100– 31
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. The hardware sets represent the design intent and direction of the owner and
architect. They are a guideline only and should not be considered a detailed
hardware schedule. Discrepancies, conflicting hardware and missing items
should be brought to the attention of the architect with corrections made prior to
the bidding process. Omitted items not included in a hardware set should be
scheduled with the appropriate additional hardware required for proper
application and functionality.
DOOR HARDWARE
08 7100– 32
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 33
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 34
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 35
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 36
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 37
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 38
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 39
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
Hardware Set 26 – Typical Out Swing Electronic Access Door – Fire Rated
Qty. Item Description / Model No. Finish Man.
2 Hinges TA2714 4 ½ X 4 ½ NRP 652 MC
1 Hinges TA2714 4 ½ X 4 ½ QC6 652 MC
1 Lockset LC 8270/71 LNL 630 SA
1 Mortise Cylinder As Required 626 ME
1 Closer 4041 TBWM REG/PA 689 LC
3 Door Silencers S1M MC
1 Door Stop 480 626 RO
1 Kick Plate KP50 10" x 2" LDW x B4E x CSK 630 MC
DOOR HARDWARE
08 7100– 40
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
DOOR HARDWARE
08 7100– 41
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DOOR HARDWARE
08 7100– 42
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 8 – OPENINGS
1. General: This section outlines the requirements for interior and exterior glazing.
2. Design Criteria:
3. Warranty: Review project specific requirements with NU Project Manager during the
design phase.
c. Review options for low-e coatings, frit patterns, and insulating glass unit
construction with the NU Project Manager during the design phase.
END OF SECTION
GLAZING
08 8000– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
GLAZING
08 8000– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 8 – OPENINGS
1. General: This section outlines the requirements for glazed aluminum curtain wall
systems for exterior applications:
2. Quality Assurance: Architect shall review the following Contractor Required Quality
Assurance and Field Quality Control Testing requirements with the NU Project Manager
during the design phase of the project.
iii. Perform the following tests on mock-up of the size specified by the test
method:
ii. Firm having experience in the testing specified and having the capability to
do the testing specified within the time frame required by the contractor, as
shown by information supplied as required by ASTM E 699
ii. Perform AAMA 501.3 ("static") test on the first area of wall to be completed;
at least 2 bays wide by 2 stories high.
c. Perform AAMA 501.2 ("hose") test on at least 2 additional areas of a similar size at
higher levels.
4. Continue to test an additional area and make repairs on entire installation until an area not
previously tested tests without deficiencies.
END OF SECTION
DIVISION 9 – FINISHES
1. General: This section outlines the requirements for gypsum board systems.
2. Design Considerations:
b. Wonderboard.
END OF SECTION
GYPSUM BOARD
09 2900 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
GYPSUM BOARD
09 2900 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 9 – FINISHES
2. Design Considerations:
a. Tile Finishes: Review materials, colors, and finishes with NU Project Manager
during the design phase.
b. Tile Grouts: Avoid light colored grouts on floors and other horizontal surfaces.
END OF SECTION
TILE
09 3000 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
TILE
09 3000 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 9 – FINISHES
2. Design Considerations:
a. Finishes: Review materials, colors, and finishes with NU Project Manager during
the design phase.
b. Accessories:
c. Architect shall review the following Contractor requirements with the NU Project
Manager and include in the Construction Documents:
i. Initial Cleaning and Sealing: Dry-mop, removing all dust and debris.
Clean surface with a neutral cleaner using green pad and floor machine.
Clean with a fine abrasive where necessary to remove any stains or
cement smears. Clean edges, baseboards, door jambs, and corners
using a Doodle Bug pad and holder with a green pad. Pick up all
solutions using a wet/dry vacuum. Thoroughly rinse twice with clear
water.
ii. Sealing: Where required, apply two coats of water-based sealer and 3
coats of water-based finish using a fine strand rayon mop. Allow a
minimum of 45 minutes between coats. All prior coats shall be dry to the
touch before any subsequent coats are applied. Apply first coat of sealer
and first coat of finish wall to wall. Stop subsequent coats of sealer and
finish 1” from baseboards, door jambs, and other vertical edges.
iii. Protection: Cover floor surface, and protect from soiling, staining,
marring, scratching, and other damage. Construction traffic, including foot
traffic, is strictly prohibited on completed surface. Maintain protection until
final completion unless floor is put into service at time of substantial
completion.
END OF SECTION
RESILIENT FLOORING
09 6500 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
RESILIENT FLOORING
09 6500 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 9 – FINISHES
2. Design Considerations:
a. Materials and Finishes: Review materials, colors, and finishes with NU Project
Manager during the design phase.
b. Architect shall review the following contractor requirements with the NU Project
Manager and include in the Construction Documents:
i. Initial Cleaning and Sealing: Dry-mop, removing all dust and debris.
Clean surface with a neutral cleaner using green pad and floor machine.
Clean with a fine abrasive where necessary to remove any stains or
cement smears. Clean edges, baseboards, door jambs, and corners
using a Doodle Bug pad and holder with a green pad. Pick up all
solutions using a wet/dry vacuum. Thoroughly rinse twice with clear
water.
ii. Sealing: Apply two coats of water-based sealer and 3 coats of water-
based finish using a fine strand rayon mop. Allow a minimum of 45
minutes between coats. All prior coats shall be dry to the touch before
any subsequent coats are applied. Apply first coat of sealer and first coat
of finish wall to wall. Stop subsequent coats of sealer and finish 1” from
baseboards, door jambs, and other vertical edges.
iii. Protection: Cover terrazzo surface, and protect from soiling, staining,
marring, scratching, and other damage. Construction traffic, including
foot traffic, is strictly prohibited on completed surface. Maintain protection
until final completion unless terrazzo is put into service at time of
substantial completion.
END OF SECTION
TERRAZZO
09 6600 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
TERRAZZO
09 6600 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 9 – FINISHES
2. Design Considerations:
a. Finishes: Review materials, colors, and patterns with NU Project Manager during
the design phase.
3. Materials:
a. Glue-Down Installation:
xi. Warranty minimum: 10 yr. wear and edge ravel, 15 yr. tuft bind
b. Tackless Installation:
CARPET
09 6800 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
xi. Warranty minimum: 10 yr. wear and edge ravel/no zipper, 15 yr. tuft bind
c. Provide 38 oz. minimum yarn weight at steps and classroom risers with rubber
nosings.
2. Installation:
a. Provide samples and seaming diagrams for all areas before proceeding with
carpet installation.
END OF SECTION
CARPET
09 6800 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 9 – FINISHES
1. General: This section outlines the requirements for interior and exterior painting.
2. Design Considerations:
i. Decorators White
v. Linen White
3. Submittals: Provide for each coating system, color, and texture; apply to representative
substrate samples. Prepare samples to show bare, prepared surface and each
successive coat. Label each sample with coating name manufacturer type and color,
name and/or number.
4. Manufacturer: Top line products of Benjamin Moore & Company. Pratt & Lambert may
be used for wood finishing products.
a. Colors: For multi-coat systems, apply each coat using a successively darker tint
or shade, unless approved otherwise.
5. Prime Coats:
b. Field apply bottom coats scheduled except where the contract documents require
shop coating of ferrous metals. Ferrous metals that have not been shop primed
shall be field primed promptly after arrival at the site or shall be stored away from
the effects of weather. Repair and retouch damaged prime coats using
approved, compatible primer.
c. Primers for Wood and Wood Products: Apply first coat to wood upon receipt at
the site and before wood is exposed to sun or rain.
PAINING
09 9000 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Concrete and Masonry: As scheduled, Latex, satin or Tile-like epoxy, low gloss.
9. Project Closeout:
END OF SECTION
PAINING
09 9000 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 10 – SPECIALTIES
1. General: This section outlines the requirements for visual display surfaces.
END OF SECTION
DIVISION 10 – SPECIALTIES
1. General:
2. Materials:
b. Steel Sheets for Baked Enamel Finish: ASTM A 591, Class C, galvanized
bonderized, of following minimum thickness.
d. Pilaster Shoes: ASTM A 167, Type 302/304 stainless steel, not less than 3"
high, 20 gauge, finished to match hardware.
e. Hardware:
3. Fabrication:
TOILET COMPARTMENTS
10 2113 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Metal Toilet Partitions: Pressure laminate seamless face sheets to core material
and seal edges with continuous interlocking strip or with lapped and formed
edges. Weld edges and corners, with exposed welds ground smooth.
a. Finishes: Baked Enamel Finish: Clean galvanized steel surfaces after fabrication
and before application of enamel coating system, to remove processing
compounds, oils, and other contaminants. Prime metal with baked on rust
inhibitive primer. Apply two coats of thermosetting enamel finish, applied by
electrostatic process, and baked in accordance with paint manufacturer's
instructions.
END OF SECTION
TOILET COMPARTMENTS
10 2113 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 10 – SPECIALTIES
2. Design Considerations:
b. Review project specific requirements with the NU Project Manager during the
design phase of the project.
END OF SECTION
OPERABLE PARTITIONS
10 2226 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
OPERABLE PARTITIONS
10 2226 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 10 – SPECIALTIES
2. Design Considerations: Architect shall review project requirements for toilet and bath
accessories with the NU Project Manager during the design phases.
3. Products:
a. Typically, the standard paper towel dispensers, soap dispensers, toilet paper
dispensers, and feminine napkin dispensers are provided by Northwestern for
installation by the Contractor.
b. Typically, the grab bars, mirrors, feminine napkin disposals, and other
accessories shall be furnished and installed by the Contractor.
END OF SECTION
DIVISION 11 – EQUIPMENT
1. General: This section outlines the requirements for projection screens that are provided
as part of the project.
2. Design Considerations:
b. Architect/Engineer shall review options with the NU Project Manager during the
design phase of the project and coordinate power and/or data requirements.
3. Quality Assurance: Obtain each type of projection screen required from a single
manufacturer as a complete unit, including necessary mounting hardware and
accessories.
4. Projection Screen Surfaces, General: Obtain screens manufactured from mildew and
flame resistant fabric of type indicated for each type of screen specified and complying
with the following requirements:
a. Normally provide matte white viewing surface with minimum gain characteristics
complying with FS GG S 00172D (1) for Type A screen surface.
b. For larger rooms provide glass beaded viewing surface with minimum gain
characteristics complying with FS GG S 00172D (1) for Type C screen surface.
5. Electrically Operated Front Projection Screens: Single Station Control: Three position,
UL listed control switch for each screen with metal device box and cover plate for flush
wall mounting and for connection to 120 V a/c. power supply.
a. Motor Operated Screens with Automatic Closure: Units designed and fabricated
for recessed installation in ceiling with bottom of case composed of two panels
fully enclosing screen and wiring compartments, one panel hinged and activated
by operation of screen to open and close automatically when screen is lowered
and fully raised and the other panel removable or operable for access to interior
of case.
b. Offset mount bottom panels to case in position where their bottom surfaces will
align flush with finished surface of adjoining ceiling and the bottom edges of case
surrounding panels will be recessed by the depth of, and concealed behind,
overlapping ceiling finish.
PROJECTION SCREENS
11 5213 – 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Spring Roller Operated Projection Screens: Units designed and fabricated for
wall or ceiling installation and complying with the following requirements:
b. Screen Case: Fabricated in one piece from not less than 22 gage steel with flat
back design, vinyl covered or baked enamel finish, and end caps with integral
roller brackets and furnished with universal mounting brackets in finish matching
end caps to enable attachment to wall or ceiling.
END OF SECTION
PROJECTION SCREENS
11 5213 – 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 12 – FURNISHINGS
1. General: This section outlines the requirements for window screens that are provided as
part of the project.
2. Design Considerations:
a. Window treatments shall typically be provided as part of the base bid scope of
work and not part of the furnishings, fixtures and equipment (FF&E).
3. Horizontal Blinds:
a. General: Head rail and blinds shall conform to shape of window. Bottom rail,
tubular steel, designed to withstand twisting or sagging. Contour top surface to
match slat curvature, with flat or slightly curved bottom. Close ends with metal or
plastic end caps of same color as rail. Finish rail in same color as slats.
b. Slats: Spring tempered aluminum (louver blades), rounded corners with forming
burrs removed.
d. Wand Operator: Detachable clear plastic wand, of proper length to suit blind
installation, detachable without tools by raising locking sleeve.
e. Lifting Mechanism: Crash-proof cord locks with cord separators and braided
polyester or nylon lift cords with tassels at ends. Size cord to suit blind type.
Include self-aligning cord equalizers designed to maintain horizontal blind
position.
END OF SECTION
WINDOW TREATMENTS
12 2000– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
WINDOW TREATMENTS
12 2000– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 12 – FURNISHINGS
1. General: This section outlines the requirements for entrance floor grilles.
2. Design Criteria:
a. Foot grilles and frames shall be designed to support a uniform distributed load of
at least 200 pounds per square foot.
3. Quality Assurance: Single Source Responsibility: Obtain foot grilles and frames from
one source from a single manufacturer.
4. Aluminum Foot Grilles: Provide manufacturer's standard extruded aluminum foot grille
with top surfaced tread rails. Framing members and tread rail material, aluminum finish,
tread top surface, and tread rail spacing as indicated.
a. Provide frames for foot grilles of same material as other framing members with
finish to match tread rails.
b. Aluminum: Extruded aluminum, ASTM B 221, alloy 6061 T6 for tread rails and
keylock, where used; alloy 6063 T5 or T6 for framing and connecting members.
c. Tread Rail Spacing: 1-1/2 inches on center with 1/8-inch to 3/16-inch wide
openings between treads.
e. Top Surface: Fusion bonded level cut pile nylon carpet insert; DuPont "Antron
III" filament, 1/4 inch high, 28 oz. per sq. yd.
6. Drainage Pit Applications: Provide special deep pit frame and support extrusion system
with intermediate support beams, sized and spaced as recommended by manufacturer
for indicated spans and equipped with vinyl support cushions.
a. Provide 16 gage stainless steel or 0.060 inch thick aluminum pit liner for each
entrance mat unit, with 2 inch IPS floor drain. Coat bottom of aluminum pan with
zinc chromate paint. Provide joint sealant between the concrete slab and metal
pan.
END OF SECTION
1. General:
1. Submittals:
2. Keys:
a. Contractor to provide Northwestern with a minimum of three (3) sets of all keys at
the time of acceptance.
3. Quality Assurance:
4. Maintenance Service:
iii. Include 24 hours per day, 7 days per week emergency callback service.
e. Door Operation: Minimum Single slide, left hand opening, 3'-6" wide x 7'-0" high.
f. Power Supply: 208 volts, 3 phase, 3 wires, 60 hz, 40 H.P., AC, verify with
sources available.
h. Lighting: LED.
i. Microprocessor electronics.
j. Controllers: Controllers shall be Galaxy (GAL), MCE, Otis and/or other non-
proprietary manufacturer per review and approval by NU Project Manager.
k. Cabling: Provide additional twisted pair and coax for future security or control
use as per Project Manager. Millennium requires 5 sets twisted pair; cameras 1
coax each.
l. Hoistway: Provide a sump pump and sump pump basin if required by applicable
codes and/or engineer/architect/project manager review.
6. Signal Equipment:
provide correctly activated phone jack & patch cord. If required by applicable
code, provide a fireman's telephone cabinet or fireman's telephone jack in main
elevator lobby.
b. Alarm System: Provide security system as required per all applicable codes.
d. Hall Lanterns must be easily visible throughout the elevator lobby, as per code.
a. General: Provide personal protective devices as per all applicable codes and
elevator consultant.
c. Door Edge Protective Device: Provide retractable edge shoe on leading edges
of elevator entrance doors that causes doors to stop and reopen upon contacting
an obstruction in entrance, per all applicable codes.
d. Photo Eye Detection Device: Provide electronic photo eye device with timed
cutout, projecting dual light beams across car entrance at 5 inch and 29 inch
heights, that when interrupted will cause closing doors to stop and reopen.
Provide keyed switch in car operating panel or toggle switch in service cabinet for
disconnecting photo eye protective device, per all applicable codes.
c. Aluminum Sills: Extruded aluminum, with grooved surface, 1/4 inch thickness,
mill finish.
c. Ceilings must be completely accessible from the car top as per applicable codes.
e. Provide scratch and graffiti-proof wall panels. Review options that include
stainless steel or plastic laminate with the NU Project Manager.
f. Provide passenger cab protection blankets for each side of elevator cab.
b. Contractor shall make a final check of each elevator operation with University's
personnel present and just prior to date of Substantial Completion. Determine
that control systems and operating devices are functioning properly. Contractor
must provide Northwestern a copy of all inspection reports and complete
paperwork to provide Northwestern the State Elevator tag before closing the
project.
END OF SECTION
1. General:
1. Submittals:
2. Keys:
a. Contractor to provide Northwestern with a minimum of three (3) sets of all keys at
the time of acceptance.
3. Quality Assurance:
4. Maintenance Service:
HYDRAULIC ELEVATORS
14 2400– 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Include 24 hours per day, 7 days per week emergency callback service.
e. Door Operation: Single slide, left hand opening, 3'-6" wide x 7'-0" high.
f. Power Supply: 208 volts, 3 phase, 3 wires, 60 hz, 40 H.P., AC, verify with
sources available.
i. Microprocessor electronics.
j. Controllers: Controllers shall be Galaxy (GAL), MCE, Otis and/or other non-
proprietary manufacturer per review and approval by NU Project Manager.
k. Cabling: Provide additional twisted pair and coax for future security or control
use as per Project Manager. Millennium requires 5 sets twisted pair; cameras 1
coax each.
l. Hoistway: Provide a sump pump and sump pump basin if required by applicable
codes and/or engineer/architect/project manager review.
6. Signal Equipment:
HYDRAULIC ELEVATORS
14 2400– 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
provide correctly activated phone jack & patch cord. If required by applicable
code, provide a fireman's telephone cabinet or fireman's telephone jack in main
elevator lobby.
b. Alarm System: Provide security system as required per all applicable codes.
b. Door Edge Protective Device: Provide as required per all applicable codes.
c. Photo Eye Detection Device: Provide as required per all applicable codes.
c. Aluminum Sills: Extruded aluminum, with grooved surface, 1/4 inch thickness,
mill finish.
c. Ceilings must be completely accessible from the car top as per applicable codes.
e. Provide scratch and graffiti-proof wall panels. Review options that include
stainless steel or plastic laminate with the NU Project Manager.
HYDRAULIC ELEVATORS
14 2400– 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Provide passenger cab protection blankets for each side of elevator cab for each
elevator. Provide blanket hooks at perimeter of each elevator.
c. Install casings with waterproof seals at pit floor and with waterproof, high
pressure seal at bottom of casings.
d. Provide a second (inner) casing with welded waterproof, high pressure seal at
bottom and set inside outer (initial) casing.
e. Corrosion Protection: The inside of the cylinder shall be treated with rust
preventative and the outside with a suitable heavy duty service bitumastic or tape
wrap.
a. Contractor shall instruct University personnel in proper use, operations, and daily
maintenance of elevators. Review emergency provisions, including emergency
access and procedures to be followed at time of failure in operation and other
building emergencies. Train University's personnel in normal procedures to be
followed in checking for sources of operational failures or malfunctions. Confer
with University on requirements for a complete elevator maintenance program.
b. Contractor shall make a final check of each elevator operation with University's
personnel present and just prior to date of Substantial Completion. Determine
that control systems and operating devices are functioning properly. Contractor
must provide Northwestern a copy of all inspection reports and complete
paperwork to provide Northwestern the State Elevator tag before closing the
project.
HYDRAULIC ELEVATORS
14 2400– 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Hydraulic Elevators are included in the University's Spill Response Plan. All new
elevators must be catalogued with the FMO Staff Engineer.
END OF SECTION
HYDRAULIC ELEVATORS
14 2400– 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
HYDRAULIC ELEVATORS
14 2400– 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General:
2. Design Criteria:
a. NFPA Standards 13 and 14 provide the basic design guidance for automatic
sprinkler systems. Modifications and clarifications that follow must be
incorporated into the design and specifications.
ii. Automatic sprinkler zones shall be coordinated with the smoke control
systems. In no case shall parts of one automatic sprinkler zone be
contained in more than one smoke control zone.
iv. The automatic sprinkler design criterion applies to wet pipe systems.
Increase the area of application in accordance with NFPA Standard 13 for
dry systems.
vi. On the Chicago campus, the Chicago Building Code shall be consulted
for deviations from NFPA standards.
b. The following occupancies shall be reviewed with the NU Project Manager and
the University’s Office of Risk Management to determine the sprinkler system
design basis for the following areas and vaults:
iii. Storage for tires, rolled paper, Group A plastics, or unusual materials of
any height.
END OF SECTION
1. General: This section outlines general requirements for automatic fire sprinkler systems.
2. Design Considerations:
b. Fire pumps shall include a valved bypass city loop and a valved connection to an
outside test header. Valve arrangements shall be such that the fire pumps can
be isolated during testing with the city loop remaining in service.
d. Dry pipe valves should be provided with a dedicated tank-type air compressor.
In no case shall dry pipe valves be connected to an HVAC control air
compressor. Dedicated air compressors must be connected to the emergency
power system.
e. Drains from automatic sprinkler system equipment (dry pipe valves, flow test
valves, RPZ backflow preventers) shall be piped to a floor drain capable of
handling the expected maximum discharge for at least two minutes.
g. A water flow alarm shall be installed in each automatic sprinkler zone at the main
water supply entrance, and at the supply connection to each vertical combined
automatic sprinkler and standpipe riser.
h. Valve supervisory switches shall be provided for each point where the water
supply to the system or parts of the system can be shutoff. Valves grouped at a
common location can be combined into the same zone to a maximum of five. In
no case shall control valves be concealed. External tamper switches or external
wired tamper switches are required. Butterfly sectional and floor control valves
are preferred.
j. Siamese connections shall be of the flush type having a polished chrome plated
finish. Lettering shall indicate dual service.
k. Sprinkler heads located in ceiling tiles should be centered in the tile unless the
head can otherwise be aesthetically located.
END OF SECTION
1. General: This section outlines general requirements for chemical suppression systems.
2. Design Considerations:
a. Dry chemical suppression systems are preferred except in kitchens where wet
chemical systems have typically replaced dry chemical systems. Review specific
requirements with the NU Project Manager.
d. Trouble and alarm signals from fire extinguishing systems shall be connected to
the building's fire alarm control panel. Where not possible, alarm and trouble
signals shall be transmitted to Northwestern’s central monitoring station.
a. The system and agent supplier shall have provided equipment and agent for at
least 50 systems of similar size.
END OF SECTION
1. General: This section outlines general requirements for smoke control systems.
2. Design Considerations:
a. Engineer of record will be required to meet with the Authority Having Jurisdiction
(AHJ) for either Chicago or Evanston Campus for Specific requirements for
smoke control requirements.
3. Definitions:
b. A static system is a system that automatically shuts down (fans OFF) when
smoke is detected in the supply or return air of the HVAC system.
4. Design Guidelines:
a. To meet the Chicago and the City of Evanston codes a static system is required
as a minimum.
b. To meet the Chicago and the City of Evanston Hi Rise codes a dynamic system
is required as a minimum.
c. If a smoke control system is provided to meet code the guidelines herein must be
followed.
d. For the Chicago campus high rise buildings, a stairwell pressurization system
should be considered to enhance life safety.
e. To consider the use of a dynamic smoke control system the smoke control zone
must be sprinkled and the sprinkler and smoke zones must be the same physical
floor area.
5. System Descriptions:
a. General: All smoke control safety devices shall be hardwired into the fan safety
circuit, with auxiliary relay contacts used for notification to BAS platform.
Building Automation System (BAS) software control logic shall not be used for
fire alarm shutdown.
b. Static Systems (Fans OFF). All smoke detectors and Fire Alarm Relay Panels
(FARP) shall be furnished and installed by the fire alarm contractor. The fire
alarm relay panel shall be within 10 ft of each Building Automation System (BAS)
panel.
SMOKE CONTROLSYSTEMS
21 2500 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. The BMS contractor shall provide minimum 1/2 inch EMT conduit
between the BAS control panel and the Fire Alarm Relay Panel (FARP).
Confirm size of conduit with electrical requirements.
ii. Wiring from the smoke detectors to the Fire Alarm Control Panel (FACP)
and from the FACP to the fire alarm relay panels shall typically be by the
fire alarm contractor. Wiring between the BAS panels and fire alarm relay
panels shall typically be by the BAS contractor. Confirm who is
responsible for terminations in each panel and verify project specific
requirements with NU Project Manager and indicate requirements in
Construction Documents.
c. Dynamic Systems (Fans ON). Smoke detectors and Fire Alarm Relay Panels
(FARP) shall be furnished and installed by the fire alarm contractor. Fire Alarm
Relay Panels shall be located within 10 feet of the BAS panels and one for each
smoke zone. The location of the smoke zone FARPs shall be coordinated by the
BAS and fire alarm contractors. Wiring from the smoke detectors to the FACP
(Fire Alarm Control Panel) and from the FACP to the fire alarm relay panels shall
be by the fire alarm contractor.
d. The BAS contractor shall provide (1) the power source and controls for the
smoke dampers or the combination fire/smoke dampers, and (2) 1/2 in. EMT
conduit between the BAS control panels and the nearby FARP. Confirm size of
conduit with electrical requirements. Wiring between the BAS panels and fire
alarm relay panels shall be by the BAS contractor.
END OF SECTION
SMOKE CONTROLSYSTEMS
21 2500 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 22 – PLUMBING
1. General: This section outlines general requirements for domestic water distribution
systems.
2. Design Considerations:
a. Potable water pipe shall be routed so that the circuit terminates at high use
areas, such as washrooms. The purpose is to avoid stagnation leading to a high
bacteria count.
c. Domestic cold water, domestic hot water supply and recirculation, laboratory cold
water, laboratory hot water and recirculation, and fill/makeup water lines shall be
copper.
d. Faucets and fixtures, such as emergency showers, eye wash, dishwashers, and
autoclaves shall have local shutoff valves within five feet of the faucet/fixture.
Valves must be accessible.
e. No piping with a fluid shall be routed over electrical busway housings. For
electrical busway housings provide a minimum 24 inches on top, both sides and
the bottom.
3. Materials:
a. Steel and copper pipe shall be built and stamped to meet ASTM standards.
b. Copper Tubing:
ii. Copper tubing shall be 95-5 soldered. Solder shall be lead free.
i. General:
END OF SECTION
DIVISION 22 – PLUMBING
2. Materials:
a. Ball Valves:
i. Ball valves shall be bronze, 600 psig WOG, full port, with a 316 stainless
steel ball and stem.
2. Neles-Jamesbury, Inc.
b. Gate Valves:
c. Backflow Preventers:
d. P-Traps:
END OF SECTION
PLUMBING SPECIALTIES
22 2114 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PLUMBING SPECIALTIES
22 2114 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 22 – PLUMBING
2. Design Considerations:
a. When possible sinks, urinals and closets should match existing fixtures for
renovation projects.
3. Materials:
i. Acceptable Manufacturers:
2. Crane Company.
3. Eljer Plumbingware.
4. Kohler Company.
2. Kohler.
PLUMBING FIXTURES
22 4000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Acceptable Manufacturer:
i. Toilet flush valves shall have a transformer and shall be hard wired with a
courtesy flush override button. Coordinate power requirements and
indicate on electrical power drawings.
f. Drinking Fountains:
i. Design Considerations:
1. Halsey Taylor.
g. Hand Dryers:
ii. If provided, hand dryers shall be surface mounted equipped with an infra-
red sensor and an automatic 60 second cut-off switch, 120 Vac.
Coordinate power requirements and indicate on electrical power
drawings.
PLUMBING FIXTURES
22 4000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
PLUMBING FIXTURES
22 4000 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PLUMBING FIXTURES
22 4000 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 22 – PLUMBING
2. Materials:
i. Acceptable Manufacturers:
END OF SECTION
PLUMBING EQUIPMENT
22 4500 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PLUMBING EQUIPMENT
22 4500 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
General Criteria
1. General: The Heating, Ventilation, and Air Conditioning (HVAC) systems within
Northwestern’s facilities need to be designed and maintained to provide occupant
comfort and to meet the goals of safety, reliability, serviceability, and efficient operation
as described below:
a. Safety for building occupants during equipment operation and for maintenance
personnel equipment service.
d. Systems efficiency should consider all operating costs, including energy and
maintenance.
2. Redundancy: The design must identify and address points of failure for systems serving
critical spaces, which are to be identified with the owner. Redundancy and/or back-up
systems should be identified. (For example, for an area with critical temperature stability
requirements, a secondary source of cooling may be required as back-up to the central
plant systems).
Sustainability Overview
1. General: Refer to Design Guidelines for Energy Usage Intensity (EUI) requirements.
a. Energy analysis shall be completed in the Schematic Design Phase and updated
during the Design Development Phase utilizing a DOE-2 energy analysis
computer program.
b. The energy analysis shall be used to evaluate energy efficiency measures and
inform design decisions. A final model shall be prepared upon completion of the
construction documents.
3. Refrigerants:
b. Refrigerants that have low impact on both ozone depletion and global warming
shall be chosen.
4. HVAC Systems:
5. Controls:
b. Lighting – Lighting systems shall have local controls and shall include switches,
occupancy sensors, photocells, pre-set controllers and/or other controls as
appropriate. Where daylight dimming is used, the lighting controls may be
integrated into the BAS to maximize energy conservation.
6. Commissioning:
HVAC Criteria
1. General:
a. Investigate the application of condensate reclamation off AHU cooling coils, for
irrigation, cooling tower make-up, etc.
b. Chemical shot feeders only apply to building closed loops. Chemical treatment
on Central Utility Plant (CUP) systems are accomplished at the CUP with no
additional chemical treatment or makeup in the buildings.
3. Hydronic Distribution:
a. Hot water heating systems shall utilize the campus central steam system when
available. If central system steam is not nearby, a life cycle cost analysis will
need to be completed comparing extending campus steam into the building
versus other types of heating systems. Refer to NU Steam Framework Plan.
b. Hot water heating systems shall have standby pumps and heat exchangers sized
for 100% of the load.
5. Process Cooling:
a. Process chilled water (CHW) shall be through plate and frame heat exchanger to
CUP CHW. In no case shall CUP CHW be used directly for process cooling.
Design the heat exchanger for a maximum CUP CHW supply temperature of 52
degrees F.
b. Process cooling loads are to be presented to the NU Project Manager for review
during the design phases of the project.
c. Where process cooling loads are identified in the design, provide hard pipe
connections to the loop. Braided tubing, barbed fittings, etc. are not permitted.
6. Air Distribution:
a. Ductwork and diffuser velocities must achieve the sound criteria developed for
each project. Review project specific requirements with the NU Project Manager.
9. Vibration Monitoring:
b. The design and layout of HVAC equipment shall show flow arrows for each
hydronic system.
c. Floor plans with the design and layout of HVAC equipment shall show the
required service clearance space for each piece of equipment, including, but not
limited to, tube pull space, coil removal, and unit-mounted starter electrical panel
code required clearances.
d. Floor plans with the design and layout of HVAC equipment shall show the
required path for equipment removal and replacement to the exterior of the
building. This equipment is defined as equipment too large to fit through a
standard 30” x 84” door such as AHU sections, pumps, chillers, boilers, large
fans, heat exchangers and electric switch gear, etc.
c. See Comfort Criteria Matrix at the end of this section for additional information.
General Classroom
Mechanical Rooms
Telecomm Rooms
Electrical Rooms
Student Centers
Residence Halls
Research Labs
Administrative
Teaching and
Dining Halls
Comfort Criteria Matrix
Library
Offices
HVAC SYSTEM TYPES
All air variable air volume with code
X X X X X X
minimums with reheat
Displacement air from floor, column
X X X X X X
or low side wall discharge
Chilled beam with code minimum
X X X X X X
outside air
100% Outside air Constant or
Variable air volume with makeup air X
and code minimums with reheat
Heat Recovery unit for laboratory
X
exhaust system
Heat Recovery unit for
kitchen/dishwasher exhaust to
X
exchange with 100% minimum
outside air AHU
Heat Recovery unit for
bathroom/toilet exhaust to exchange
X
with 100% minimum outside air
AHU
Gang hood and general lab exhaust
X
where acceptable
4 pipe fan coil units with code
X
minimum outside air
Provide mechanical ventilation
supply and exhaust as required by
X
code or for cooling or combustion
air
HEATING
Design Temperature 70°F ± 2°F X X X X X X X
Temperature Set Point 68°F X X X X X X X X X X
Reheat for interior rooms & exterior
X X X X X X X
room perimeter walls with no glass
Perimeter fin tube or radiant ceiling
Panel for perimeter with glass X X X X X X X
heights less than 12ft
General Classroom
Mechanical Rooms
Telecomm Rooms
Electrical Rooms
Student Centers
Residence Halls
Research Labs
Administrative
Teaching and
Dining Halls
Library
Offices
Comfort Criteria Matrix
HEATING Cont'd
Perimeter fin tube at multiple levels
or forced hot air from top & bottom
or a combination of the two for X X X X X X X
perimeter with glass height 12 feet
or more
For rooms over 25 feet deep from
window, consider a separate X X X X X
perimeter zone.
Provide Unit Heaters X
Provide electric only Unit Heaters X
COMFORT COOLING
Provide mechanical/electrical
cooling for mechanical rooms that
X X
have electronic controls with
maximum temperature requirements
Provide computer room air
conditioning units for mechanical
X
cooling, heating, dehumidifying and
humidifying the space
AIR DISTRIBUTION
Provide even distribution of air with
X X X X X X X
multiple supply and returns
Avoid supply air directed at or near
X
face of laminar flow of fume hood
HUMIDITY CONTROL EQUIPMENT
ABBREVIATIONS, GENERAL
AI Analog Input
AO Analog Output
BAS Building Automation System
BI (DI) Binary (Digital) Input
BO (DO) Binary (Digital) Output
CUP Central Utility Plant
EMS Energy Management System
FACP Fire Alarm Control Panel
PRS Pressure Reducing Station
SD Smoke Detector
ABBREVIATIONS, DRAWINGS
END OF SECTION
DIVISION 23 – HVAC
2. Design Considerations:
a. Motors driven by a VFD shall not operate into their service factor.
b. Motors within an air handling unit (air stream) shall be Totally Enclosed Fan
Cooled (TEFC).
c. HVAC motors outdoors not in an air stream shall be Totally Enclosed Fan Cooled
(TEFC).
d. HVAC motors indoors not in an air stream shall be open drip proof (ODP).
f. Motors, except those controlled driven by a variable frequency drive, shall have
class B insulation.
h. Motors driven by a VFD shall be provided with shaft grounding brush similar to
AEGIS SGR to prevent bearing from shaft current.
END OF SECTION
MOTORS
23 0513 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
MOTORS
23 0513 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines general requirements for variable frequency drives.
2. Design Considerations:
x. RFI protection.
d. The VFD shall have 110% continuous current capability, 120% overload capacity
for 60 seconds.
f. High motor winding temperatures shall shut down the driven device and alarm.
3. Application
iii. Redundant Pumps: 2 pumps are used, each at 100% or 3 pumps are
used, each at 50%.
4. Acceptable Manufacturers:
c. ABB.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines general requirements for mechanical supporting devices.
2. Design Considerations:
a. Hangers and supports for both interior and exterior use to be steel hot dipped
galvanized coated.
b. Hangers are required to be specific to pipe and ductwork independently and not
shared.
c. Where insulation in not required use similar metal hangers such as copper
hanger for copper pipe and stainless steel hanger for stainless steel pipe.
f. Ductwork: Metal and flexible duct hangers and supports shall be in accordance
with SMACNA “HVAC Duct Construction Standards – Metal and Flexible,” latest
edition.
END OF SECTION
DIVISION 23 – HVAC
2. Design Considerations:
a. All rotating equipment shall have vibration isolation from building structure.
Table 23 0550-1
a. Ducts within 50 feet of the fan discharge shall be isolated by spring hangers with
neoprene cups.
Table 23 0550-2
a. The first three hangers and floor supports from equipment (, pumps) shall be
isolated by spring hangers with neoprene cup for pipe and spring isolated
concrete inertia base mounts respectively.
VIBRATION ISOLATION
23 0550 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Piping passing through equipment room walls, floors, or ceilings shall be all
directional acoustical pipe seals.
d. Concrete bases after the system is in operation shall have a minimum 2 in.
clearance between the floating base and the floor.
5. Acceptable Manufacturers:
a. Amber/Booth Company.
b. Mason Industries.
d. Vibro-Acoustics.
END OF SECTION
VIBRATION ISOLATION
23 0550 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
2. Design Considerations:
a. Provide labels on pipe and ductwork every 20 feet and at every change in
direction.
c. Piping shall be marked in accordance with ANSI Standard A13.1, most current
version.
e. Provide labels for each type of air duct including a flow arrow for direction of flow.
h. Combination fire/smoke dampers can be reset manually. Mark the access panel
from which the damper can be reset by a label not less than 2 inch in height
reading: RESETTABLE FIRE/SMOKE DAMPER. Mark the other access panel
by a label not less than 2 inches in height reading: FIRE/SMOKE DAMPER.
k. Provide equipment labels for air-handling units, fan pumps, chillers, boilers, etc.
Labels shall spell out the system or equipment. Do not use abbreviations.
3. Acceptable Manufacturers:
c. Panduit Corp.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for testing and balancing during
the design and/or construction phases of the project.
2. Design Considerations:
3. Certification:
a. Each TAB technician shall be certified by AABC (Associated Air Balance Council)
or NEBB (National Environmental Balancing Bureau).
b. Certification is required for air systems, hydronic systems, sound, and vibration.
Test procedures shall be in accordance with the latest edition of AABC or NEBB
Standards, ASHRAE - 2011 HVAC Applications Chapter 38.
4. Acceptance Criteria:
a. For most spaces, the total supply air quantity to each space of a system shall be
within -5% to +10% of design. Review project specific requirements with NU
Project Manager.
b. The percent tolerance of each outlet within a space shall be per Table 23 0594-1.
Table 23 0594-1
1 2 3 or More
c. Air quantity of each return air grille and diffuser shall be within ±10% of design.
The design room pressurization must be maintained regardless of the tolerance
at each individual diffuser.
5. Reports:
a. The contractor prior to TAB work shall submit the following data for review.
c. Test procedures.
e. As tests are completed the contractor shall submit test reports with includes an
executive summary. The executive summary shall state extent of system
compliance, system deficiencies, and recommended changes.
6. Approved Contractors:
b. CEPRO.
c. Project Architect / Engineer to confirm with NU Project Manager that testing and
balancing contractors are currently in good standing with NU.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for mechanical system
insulation.
2. Design Considerations:
b. Insulation shall butt to preformed insulation covers furnished with circuit setters.
c. Insulated pipe and fittings outdoors shall be covered by Zeston 300 series fitting
covers and pipe jacketing. Seams and joints shall be waterproof.
d. Insulated pipe fittings indoors shall be covered by Zeston 2000 PVC covers.
i. Density of the insulation shall not be less than 12 lb/ft3; the thermal
conductivity of the material shall not exceed 0.45 BTU·in./(hr·ft2·ºF) at
100ºF.
Table 23 0700-1
0.5 1.0
1.0 2.0
1.5 2.5
2.0 3.5
2.5 4.5
3.5 6.0
iii. Insulation shall have a jacket; either metal or Zeston series 300 PVC.
i. Acceptable Manufacturers:
3. Temptec.
h. Chilled and Low temperature Condenser Water Pumps: Each water pumps shall
be covered by 1 inch thick AP Armaflex applied with a waterproof adhesive.
Removable components shall use Velcro applied to both the Armaflex and the
pump surface with a waterproof adhesive such that the pieces can be removed
for servicing without damage.
i. Chillers: Each chiller shall be covered by 1 in. thick AP Armaflex applied with a
waterproof adhesive. All removable components shall use Velcro applied to both
the Armaflex and the shell surface with a waterproof adhesive such that the
pieces can be removed for servicing without damage.
j. Converters:
i. Shell and tube heating shall be covered by 2-1/2 in thick rigid glass fiber
insulation in accordance with ASTM C612, Type IA and IB, suitable for
temperatures to 450°F,
ii. Plate and frame shall be covered by 1 in. thick AP Armaflex applied with a
waterproof adhesive:
k. Condensate Pump / Receivers: Provide a cover of 2 inch thick rigid glass fiber
insulation in accordance with ASTM C612, Type IA and IB, suitable for
temperatures to 450°F,
END OF SECTION
DIVISION 23 – HVAC
1. General:
a. This section outlines the general requirements for hydronic pipe and pipe fittings,
including valves, unions, and flanges.
b. Specific requirements shall be reviewed with the NU Project Manager during the
design phases of the project.
2. Design Considerations:
b. Provide vents at the high point of piping systems, in accessible locations, to allow
for system venting. Vents shall have isolation valves, pressure gauge, and boiler
drain.
d. Air separators shall be installed in each heating system distribution loop at the
point of lowest air solubility and vented to atmosphere.
i. Each new closed hydronic system shall have full bore strainers and a
particulate side-stream filter rated at 100 microns, unless specified
otherwise.
1. Show on the drawings for each new hydronic system full bore
strainers and a 15% side stream filter. Specify the micron filtration
size for the side-stream filter.
ii. No piping with a fluid shall be routed over electrical busway housings.
For electrical busway housings provide a minimum 24 inches on both
sides and the bottom.
f. Tracer Wire:
HYDRONIC PIPING
23 2113 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ii. Tracer Wire shall be installed on the pipe as shown on the contract
drawings.
iii. Tracer wires shall terminate in each tunnel and manhole where new
utilities penetrate. Tracer wires shall be provided with labels noting what
pipe the wire is affixed to (ie. Chilled Water Supply, Pumped Condensate
Return, etc).
a. Prefabricated ells, loops and tees to be provided where shown on plan drawings
and to consist of pipe, insulation, and conduit conforming to the same pipe and
welding specifications as specified before herein for straight runs. Tees, anchors,
elbows and other fittings shall be factory connected and prefabricated to straight
sections whenever shipping requirements permit.
c. The piping system is designed with both expansion loops and expansion joints.
The piping system shall be designed to accommodate this requirement by
including moment guides as required for the piping system to function properly in
conjunction with expansion joints.
5. Anchors:
b. Concrete block to be cast over plate and conduit and to be large enough for firm
anchorage into undisturbed trench sidewalls and/or bottom. Concrete block to be
at least 36” in length and extend minimum of 12” beyond entire anchor plate. The
piping vendor shall provide detailed instructions to Contractor for oversized
anchors due to expansion joints. The Contractor shall provide oversized anchors
as detailed by the piping vendor.
HYDRONIC PIPING
23 2113 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. All end and gland seals shall be reinforced with 12” long galvanized steel sleeve
at the sealing surface to prevent compression of the outer jacket and insulation
from modular wall sealing devices. The protection sleeve shall be minimum 6
gauge thickness and shall be outside of the HDPE jacket. Where the galvanized
steel sleeve stops on the outside of the manhole, the sleeve shall be shrink
wrapped to the HDPE jacket and sealed water tight.
7. Field Joints:
b. Field joints shall consist of field installed mineral wool insulation banded with
stainless steel bans on the carrier pipe, field applied 10 gauge connector sleeve
on the inner conduit, field applied foam insulation, polyethylene heat shrink wrap
and split HDPE jacket at a minimum. Field joint materials and methods shall be
provided by and approved by the piping manufacturer.
ii. Fittings: ASME B16.4, Class 125, cast iron, threaded or ASME B16.3,
Class 150, malleable iron, threaded.
iii. Unions: ASME B16.29, malleable iron, Class 250. Refer to Unions and
Flanges in this Section.
iii. Flanges: Class 150. Refer to Unions and Flanges in this Section.
HYDRONIC PIPING
23 2113 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Pipe: API-5L, Grade B, Type DSAW, 0.375" wall thickness, carbon steel.
ii. Fittings: ASTM A234, Grade WPB/ASME B16.9, 0.375" wall thickness,
seamless, carbon steel weld.
iii. Flanges: Class 150. Refer to Unions and Flanges in this Section.
4” 0.25”
6” 0.25”
8” 0.25”
10” 0.26”
12” 0.28”
14" 0.30"
16" 0.32"
18" 0.34"
20" 0.36"
24" 0.40"
30” 0.45”
iii. Straight pipe joints and fittings to be restrained joint-type. Joints and
fittings shall be flexible and shall be designed to provide positive restraint
against end-wise separation due to thrust.
iv. All pipe taps shall be drilled and tapped using corporation stop. Saddle
taps will not be allowed.
HYDRONIC PIPING
23 2113 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Pipe Joints:
2. All bolts shall be low alloy, high strength steel bolts having
minimum yield strength of 45,000 PSI and which are cathodic to
the pipe, meeting the requirements of AWWA C111.
i. Type K copper water tube, (drawn) temper, ASTM B88; with copper
drainage fittings (DWV), ANSI B16.23; wrought copper drainage fittings
(DWV), ANSI B16.29; lead free (<.2%) solder ASTM B32; flux, ASTM
B813.
a. Unions:
HYDRONIC PIPING
23 2113 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Flanges:
1. ASTM A105, ANSI B16.5, hot forged steel flanges, welding neck
pattern. Slipon pattern flanges are not allowed. Bore dimension of
welding neck flange shall match inside diameter of connected
pipe. Use raised face flanges for mating with other raised face
flanges with self-centering flat ring gaskets. Use flat face flanges
for mating with other flat face flanges with full face gaskets.
c. Flange Gaskets:
ii. Gaskets shall be equal to Flexitallic Style CG, graphite filler, 304 SS
winding, carbon steel centering ring, 0.175" thickness.
d. Bolting:
ii. Bolts, bolt studs, nuts and washers used on piping systems in Central
Utility Plant (CUP), tunnel and manholes shall have zinc plated finish.
iv. Threaded rods are not allowed as fastening elements on steam systems.
v. For Class 150 and Class 300 flanges at 400°F or lower temperature, use
carbon steel bolts or stud bolts conforming to ASTM A307, Grade B with
nuts conforming to ASTM A307.
vi. For Class 300 flanges at 500°F or lower temperature, use alloy steel bolts
or stud bolts conforming to ASTM A193, Grade B7 or B16, with nuts
conforming to ASTM A194, Grade 2H.
HYDRONIC PIPING
23 2113 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. General: Install valves as shown on plans, details and according to the valve
manufacturer's installation recommendations.
b. Provide chain operators for manually operated valves 4" and larger, located more
than 6'-0" above normal working surface.
a. Butterfly Valves:
ii. Cast iron body ASTM A-126B, Class B, restrained flanged (ANSI B16.1)
ends. Valve shall be furnished complete with joint accessories (bolts,
nuts, and gaskets). Flanging shall be lugged type permitting removal of
downstream piping while using valve for system shutoff.
iv. Valves 20" and smaller shall have the seat bonded directly to the body.
Valve 24" and larger shall have seats that are mechanically retained in
the valve body. Either seat shall be capable of mechanical adjustment in
the field and field replacement.
vi. Valve shaft to be 18-8, Type 304 stainless steel with "V" / "cup" PTF style
self-adjusting packing.
vii. Valve assembly shall be furnished with a non-adjustable factory set thrust
bearing designed to center the valve disc at all times.
viii. Shaft bearings shall be contained in the integral hubs of the valve body
and shall be self-lubricated sleeve type and shall be sealed in place with
"V" / "cup" PTF style self-adjusting packing.
HYDRONIC PIPING
23 2113 - 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
and the first valves that are 24" and larger. Valve manufacturer
shall be responsible for providing transportation and
accommodations for two (2) NU representatives and one (1)
representative of the Architect / Engineer.
x. Provide worm gear operators. Provide rotary hand wheels with adjustable
position stop and position indicators. Size hand wheel operators with no
higher than 40 lb rim pull at full valve pressure rating.
a. Butterfly Valves:
ii. Cast iron body ASTM A-126B, Class B, restrained mechanical joint
(AWWA C-151/ANSI 21.11) or flanged (ANSI B16.1) ends. Valve shall be
furnished complete with joint accessories (bolts, nuts, gaskets and
glands).
iv. Valves 20" and smaller shall have the seat bonded directly to the body.
Valve 24" and larger shall have seats that are mechanically retained in
the valve body. Either seat shall be capable of mechanical adjustment in
the field and field replacement.
vi. Valve shaft to be 18-8, Type 304 stainless steel with "V" / "cup" PTF style
self-adjusting packing.
vii. Valve assembly shall be furnished with a non-adjustable factory set thrust
bearing designed to center the valve disc at all times.
viii. Shaft bearings shall be contained in the integral hubs of the valve body
and shall be self-lubricated sleeve type and shall be sealed in place with
"V" / "cup" PTF style self-adjusting packing.
HYDRONIC PIPING
23 2113 - 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
xi. Refer to drawings for length of shaft extensions and soil pipes.
a. Valve Boxes:
i. Valve boxes shall be 2 - piece cast iron, screw type, 5 1/4" shaft with
stay-put heavy duty traffic weight lid marked “CHILLED WATER” to match
piping system. Boxes shall be equal to Figure UTL 273, as manufactured
by Dewey Brothers, Tyler or Charlotte Pipe and Foundry Co.
ii. Valve boxes to be coated with coal tar for buried service application.
b. Valve Wrenches:
i. Provide T-handle extension wrench with flexible socket for each different
shaft size. Socket shall be sized for gate valve operating nut.
a. 2" and Smaller: bronze body, threaded, stainless steel ball and stem, full port,
teflon seat rings, blowout-proof stem, three piece construction, 600 psi WOG,
150 psi SWP.
a. In Tunnel: Ball valves as specified above with hose thread adapter and cap.
Provide 2" minimum drain valves provided with short threaded nipple and cap. All
vent valves shall be minimum 3/4" in size.
a. Provide check valves at condensate lines at outlet of traps. Install check valve
between trap and gate valve.
HYDRONIC PIPING
23 2113 - 9
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Provide drain valves at all low points of piping systems for complete drainage of
systems.
a. Provide drain valves at all low points of piping systems for complete drainage of
systems. Provide vent valves at high points for venting of air. Locate drains and
vents as indicated on the contract drawings and as required due to actual
installed conditions.
i. High pressure steam (230 psig) shut-off valves 3" and larger for
supervised warm-up.
END OF SECTION
HYDRONIC PIPING
23 2113 - 10
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for hydronic piping specialties.
2. Design Considerations:
a. Provide chain-wheel operators for valves 6 inches and larger mounted over 8
feet above floor.
i. Acceptable Manufacturers:
1. Flowseal.
2. Bray.
3. Neles-Jamesbury.
4. DeZurik.
5. Posi-Seal.
7. Milwaukee.
3. Primary/Secondary Bridge Valves, Hot and Chilled Water: Typically not permitted.
Project specific requirements to be reviewed on a case-by-case basis.
a. For each project the A/E shall submit bridge piping details to NU Project Manager
and NU Project Campus Energy Management System (EMS) Department for
review.
a. Resilient Seat:
i. Isolation valves 2-1/2 inch and 3 inch may be ball or butterfly. Pipe sizes
4 inch and larger shall be butterfly.
1. 6 inch: handle.
b. Butterfly for Control Valve Duty: High Performance with Rubber Seat.
ii. ANSI Class 150 design rated for 275 psi at 100°F
2. Threaded lug type, upper and lower body bearings with thrust
bearings,
3. One piece single or double offset shaft of 316 stainless steel and
center less ground and polished to minimize bearing and packing
wear, PTFE seats.
i. High Performance with Metal seat for steam and condensate only. No
triple offset high performance butterfly valves permitted elsewhere in
system.
6. Ball Valves:
a. Isolation valves 2-1/2 inch and 3 inch may be a ball or butterfly. Pipe sizes 2
inches and smaller shall be ball.
b. Ball valves shall be bronze, 600 psig WOG, full port, with a 316 stainless steel
ball and stem.
d. Acceptable Manufacturers:
8. Circuit Setters:
a. Circuit setters shall be furnished with preformed insulation covers by the circuit
setter manufacturer.
b. Acceptable Manufacturers:
ii. Nexus.
a. Acceptable Manufacturers:
a. Check valves shall be ANSI class 150, minimum depending on the service.
Valve shall be carbon steel body and plate, metal seal, serrated raised face end
connections, and a solid body lug design with threaded holes bolted from each
end.
b. Horizontal:
i. Acceptable Manufacturers:
1. Nibco.
2. Mueller.
c. Vertical:
i. Acceptable Manufacturers:
1. Crane.
2. Nibco.
3. Mueller.
i. Acceptable Manufacturers:
1. Stockham, Style G.
11. Thermometers:
b. Wells shall be brass with a 2.5 inch extension neck. The insertion length shall be
in compliance with Table 23 2116-1.
3 N/A* 8½
4 N/A* 8½
6 4½-5½ 8½
8 4½-5½ 8½
10 4½-5½ 8½
12 and larger 8½ 8½
* Perpendicular mount shall not be used on 3 and 4-in. pipe. Stem cooling
effects may occur.
c. Scale Range:
e. Acceptable Manufacturers:
i. H. O. Trerice Co.
a. Pressure gauges shall have a minimum 4-1/2" diameter die cast aluminum case,
glass or acrylic plastic window, phosphor bronze bourdon tube with bronze
bushed movement, recalibration from front of gauge dial and 1/4" NPT forged
brass socket
b. Gauge accuracy shall meet ANSI B40.100 Grade 1A (±1% full scale).
d. Acceptable Manufacturers:
ii. Weksler.
iii. Weiss.
b. Length shall be adequate to control vibration and noise. The live (flexible portion
of the assembly) and assembly lengths shall be determined by the Piping
Contractor.
c. Acceptable Manufacturers:
ii. Metraflex.
iii. Hyspan.
v. Flexonics
b. For Chilled water flow meter detail and specifications see the NU Direct Digital
Control Standards.
b. Acceptable Manufacturer:
a. Acceptable Manufacturer:
d. Expansion tanks shall be located and piped in compliance with the drawing
details.
e. Acceptable Manufacturers:
i. AMTROL.
iii. Armstrong.
c. Option 2. The vibration isolation manufacturer may provide a split seal consisting
of two bolted halves with 3/4 in. or thicker neoprene sponge bolted to the inner
faces. The seal shall be tightened around the pipe to eliminate clearance
between the inner sponge face and the piping. Concrete may be packed around
the seal to make it integral with the wall or ceiling if the seal is not in place prior
to the construction of the building member. Seals shall project a minimum 1 in.
past either face of the penetration.
d. Acceptable Manufacturers:
i. Amber/Booth Company.
a. Acceptable Manufacturers:
a. Baseboard heaters shall be hot water, minimum 1-1/4 inch copper tubing.
b. A/E shall consider the design for baseboard radiation heaters with a supply water
temperature of 120 degrees F.
a. Install on building closed loops only, not on Central Utility Plant (CUP) distributed
utilities.
c. Expansion tanks shall be located and piped in compliance with the drawing
details.
d. Acceptable Manufacturers:
i. AMTROL.
iii. Armstrong.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for mechanical pumps.
2. Design Considerations:
c. For pump piping details see drawings. Strainers shall be full bore.
d. Nameplates shall include impeller diameter, rated capacity (gpm), rated head (ft)
rpm, motor horsepower, and rpm.
e. Pump suction diffusers shall be provided when the pump suction pipe is 90
degrees.
f. Status Switch: The piping contractor shall install the differential pressure switch
status (proof) switches provided by the BAS (Building Automation System)
contractor.
g. Gauges:
v. Provide temperature indicators on the supply and return side of all heat
exchangers, chillers and boilers. All gauges shall have consistent
temperature ranges.
vi. Provide pressure gauges on the supply and discharge sides of all pumps
and heat exchangers.
3. Acceptable Manufacturers:
a. Motors up to 25 hp:
iii. Armstrong.
PUMPS
23 2123 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Peerless.
v. Gould.
iii. Armstrong.
iv. Peerless.
v. Gould.
END OF SECTION
PUMPS
23 2123 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General:
a. This section outlines the general requirements for steam pipe and pipe fittings,
including valves, unions, and flanges.
b. Specific requirements shall be reviewed with the NU Project Manager during the
design phases of the project.
2. Design Considerations:
b. Tracer Wire:
ii. Tracer Wire shall be installed on the pipe as shown on the contract
drawings.
iii. Tracer wires shall terminate in each tunnel and manhole where new
utilities penetrate. Tracer wires shall be provided with labels noting what
pipe the wire is affixed to (ie. Chilled Water Supply, Pumped Condensate
Return, etc).
3. High Pressure Steam in CUP and Manholes (100 and 230 PSIG):
ii. Fittings: ASTM A105 Grade II/ASME B16.11, 3000 lb. forged steel, socket
weld.
iii. Unions: Forged steel, 3000 lb., socket weld. Refer to Unions and Flanges
in this Section.
ii. Fittings: ASTM A234 Grade WPB/ASME B16.9, extra strong, seamless,
carbon steel weld.
HYDRONIC PIPING
23 2113 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Flanges: Class 300. Refer to Unions and Flanges in this Section.
4. Pumped Condensate and Steam Trap Condensate in CUP (100 And 230 PSIG):
ii. Fittings: ASTM A105 Grade II/ASME B16.11, 3000 lb. forged steel, socket
weld.
iii. Unions: Forged steel, 3000 lb., socket weld. Refer to Unions and Flanges
in this Section.
ii. Fittings: ASTM A234 Grade WPB/ASME B16.9, extra strong, seamless,
carbon steel weld.
iii. Flanges: Class 300. Refer to Unions and Flanges in this Section.
ii. Fittings: ASTM 182, Gr. F304, ASME B16.11, 3000 lb socket-weld.
ii. Fittings: ASTM A403, Gr. WP, Class S or Class W, ASME 16.9.
iii. Flanges: ASTM A182, Gr. F304, ASME B16.5, 150 lb std. with 1/16"
raised face, serrated face finish and welding neck.
HYDRONIC PIPING
23 2113 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. The high pressure piping design shall be based on 230 psig steam at 410
degrees F. The condensate piping design shall be based on 230psig at 410
degrees F.
c. All straight sections, fittings, anchors and other accessories shall be factory
prefabricated to job dimensions, and designed to minimize the number of field
welds. The design shall be computer analyzed by the piping system
manufacturer to determine stresses and movements of the service pipe and to
ensure that the system design is in strict conformance with ANSI B31.1 latest
edition, and stamped by a registered professional engineer licensed in the state
of Illinois. The analysis shall include piping and structures inside the manholes.
e. Contractor shall perform a computerized pipe stress analysis for the piping
systems in the underground steam system. Submit stress analysis report
including input data, system graphics, output data including: system forces and
moments, system deflections, system stresses, hanger, support and anchor
loading summary and other pertinent data. Analysis shall consider actual
materials of construction and a system pressure and temperature of 250 PSIG
and 450°F, base temperature is 50°F. Analysis output data shall be utilized to
select proper supports, guides and anchors to resist actual loads calculated. Pipe
stress analysis calculations to be submitted to the Engineer for review along with
the re-engineered piping system shop drawings.
7. Pipe Support Guides: Piping shall be spaced and supported at a maximum of 10 foot
intervals in conduit by insulating support-guides and to permit pipe to expand and
contract freely without stress or wear on pipe or insulation as well as provide for
drainage and free air circulation.
a. Prefabricated ells, loops and tees to be provided where shown on plan drawings
and to consist of pipe, insulation, and conduit conforming to the same pipe and
welding specifications as specified before herein for straight runs. Tees, anchors,
elbows and other fittings shall be factory connected and prefabricated to straight
sections whenever shipping requirements permit.
c. The piping system is designed with both expansion loops and expansion joints.
The piping system shall be designed to accommodate this requirement by
including moment guides as required for the piping system to function properly in
conjunction with expansion joints.
HYDRONIC PIPING
23 2113 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
9. Anchors:
b. Concrete block to be cast over plate and conduit and to be large enough for firm
anchorage into undisturbed trench sidewalls and/or bottom. Concrete block to be
at least 36” in length and extend minimum of 12” beyond entire anchor plate. The
piping vendor shall provide detailed instructions to Contractor for oversized
anchors due to expansion joints. The Contractor shall provide oversized anchors
as detailed by the piping vendor.
b. All end and gland seals shall be reinforced with 12” long galvanized steel sleeve
at the sealing surface to prevent compression of the outer jacket and insulation
from modular wall sealing devices. The protection sleeve shall be minimum 6
gauge thickness and shall be outside of the HDPE jacket. Where the galvanized
steel sleeve stops on the outside of the manhole, the sleeve shall be shrink
wrapped to the HDPE jacket and sealed water tight.
b. Field joints shall consist of field installed mineral wool insulation banded with
stainless steel bans on the carrier pipe, field applied 10 gauge connector sleeve
on the inner conduit, field applied foam insulation, polyethylene heat shrink wrap
and split HDPE jacket at a minimum. Field joint materials and methods shall be
provided by and approved by the piping manufacturer.
a. Steam:
HYDRONIC PIPING
23 2113 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
3. Unions: Forged steel, 3000 lb., socket weld. Refer to Unions and
Flanges in this Section.
b. Pumped Condensate
3. Flanges: ASTM A182, Gr. F304, ASME B16.5, 150 lb std. with
1/16" raised face, serrated face finish and welding neck
HYDRONIC PIPING
23 2113 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ii. The insulation shall be secured to the pipe by stainless steel bands.
Insulation thickness shall be as specified herein with a thermal
conductivity of not more than 0.33 at 200°F mean temperature. The
insulation shall be installed such that joints are staggered preventing a
continuous joint between the carrier pipe and the inner conduit.
d. Inner Conduit:
i. 10 gauge for conduits 26” and smaller. 6 gauge for conduits above 26”.
All conduit shall be either electric resistance welded pipe conforming to
ASTM A-135 or electric fusion welded pipe conforming to ASTM A-139.
Conduit shall be finished in prime coat finish. Where field welds and
connections are made, Contractor shall field install prime coat finish.
ii. The outer jacket shall be High Density Polyethylene (HPDE) with a
minimum wall thickness of 150 mils.
f. System Description:
ii. All piping inner conduit shall be insulated with 1.0” polyurethane foam
insulation with HDPE outer jacket as specified above.
HYDRONIC PIPING
23 2113 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Manufacturers:
a. Unions:
b. Flanges:
1. ASTM A105, ANSI B16.5, hot forged steel flanges, welding neck
pattern. Slipon pattern flanges are not allowed. Bore dimension of
welding neck flange shall match inside diameter of connected
pipe. Use raised face flanges for mating with other raised face
flanges with self-centering flat ring gaskets. Use flat face flanges
for mating with other flat face flanges with full face gaskets.
c. Flange Gaskets:
ii. Gaskets shall be equal to Flexitallic Style CG, graphite filler, 304 SS
winding, carbon steel centering ring, 0.175" thickness.
d. Bolting:
ii. Bolts, bolt studs, nuts and washers used on piping systems in CUP,
tunnel and manholes shall have zinc plated finish.
HYDRONIC PIPING
23 2113 - 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Threaded rods are not allowed as fastening elements on steam systems.
v. For Class 150 and Class 300 flanges at 400°F or lower temperature, use
carbon steel bolts or stud bolts conforming to ASTM A307, Grade B with
nuts conforming to ASTM A307.
vi. For Class 300 flanges at 500°F or lower temperature, use alloy steel bolts
or stud bolts conforming to ASTM A193, Grade B7 or B16, with nuts
conforming to ASTM A194, Grade 2H.
a. General: Install valves as shown on plans, details and according to the valve
manufacturer's installation recommendations.
b. Provide chain operators for manually operated valves 4" and larger, located more
than 6'-0" above normal working surface.
15. High Pressure Steam Pumped Condensate and Steam Trap Condensate System Valves
(100 TO 230 PSIG/450°F):
a. Isolation Valves:
i. Apollo 83-540-64-04.
HYDRONIC PIPING
23 2113 - 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Jamesbury/Metso/Neles LI/SD.
i. 2” and Smaller: ASTM B62, cast steel body, threaded ends, regrinding, Y-
pattern swing type, renewable TFE seat disc, Class 300 (300 psi WOG),
conforming to MSS SP-80.
c. Globe Valves:
i. 2" and Smaller: ANSI Class 600, steel body, stainless steel disc & seat
ring, threaded ends.
ii. 2-1/2" and Larger: ANSI Class 300, steel body, stainless steel disc & seat
ring, butt weld ends, constructed in accordance with ASME B16.34
ii. Use 2" globe valve for use on valves larger than 12".
HYDRONIC PIPING
23 2113 - 9
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
e. Drain Valves:
i. Gate valves as specified above with hose thread adapter and cap.
Provide 1" minimum drain valve except strainer blowdown valves to be
blowdown connection size. Drain valves shall be provided with short
threaded nipple and cap.
i. High pressure steam (230 psig) shut-off valves 3" and larger for
supervised warm-up.
END OF SECTION
HYDRONIC PIPING
23 2113 - 10
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for steam piping specialties.
2. Design Considerations:
a. Provide chain-wheel operators for valves 6 inches and larger mounted over 8
feet above floor.
c. Isolation valves 2-1/2 inch and 3 inch may be a ball or butterfly. Pipe sizes 2
inches and smaller shall be ball valves.
3. Butterfly Valves:
a. Butterfly for Critical Shutoff Duty: High Performance with metal seat for steam
and condensate only. No triple offset high performance butterfly valves permitted
elsewhere in system.
5. Pressure Gauges:
a. Pressure gauges shall have a minimum 4-1/2" diameter die cast aluminum case,
glass or acrylic plastic window, phosphor bronze bourdon tube with bronze
bushed movement, recalibration from front of gauge dial and 1/4" NPT forged
brass socket
b. Gauge accuracy shall meet ANSI B40.100 Grade 1A (±1% full scale).
d. Acceptable Manufacturers:
ii. Weksler.
iii. Weiss.
a. The maximum sound pressure level of a valve shall not exceed 92 dBA.
8 90
6 92
4 95
a. General: The justification for a single stage PRS is space and cost.
b. Preferred. Each PRS shall be two stage with the main and bypass valves in
each stage as follows, and piped in compliance with the drawing details.
i. Main Valve: Fisher type 667-E-4160K globe valve with cast iron body,
SST trim, PTFE packing, fail closed diaphragm actuator, and a pneumatic
controller with proportional plus reset control. Low bleed assembly
(MIZER) shall be included with the controller.
ii. Bypass Valve: Fisher type 92B pilot-operated regulator with a cast iron
body, and SST trim.
c. Alternate. Each PRS shall have one main valve in parallel with one bypass valve
piped in accordance to the drawing details.
i. Two inch and smaller valves shall be screwed; 3-inch and larger valves
shall be class 250 flanged.
d. Approved Manufacturers:
8. Ball Valves:
a. Ball valves shall be bronze, 600 psig WOG, full port, with a 316 stainless steel
ball and stem and 250 psi steam trim.
c. Acceptable Manufacturers
b. Pump motors shall be TEFC, 1800 rpm maximum (3600 rpm not acceptable).
d. Acceptable Manufacturers:
i. Peerless.
ii. Domestic.
iii. Skidmore.
iv. Weinman.
v. Sterling.
vi. Hoffman.
vii. Mepco.
viii. Shipco.
d. Acceptable Manufacturers:
a. For condensate meter detail and specifications see the NU Direct Digital Control
(DDC) Standards.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for ductwork. Specific
requirements shall be coordinated with the NU Project Manager during the design
phases of the project.
2. Design Considerations:
d. Laboratory exhaust ductwork shall be 316 stainless steel and not 304 stainless
steel. Engineer of Record shall evaluate other ductwork material options based
on use and dilution of system.
e. Duct systems must be designed, not just sized by use of the Trane Ductulator or
the friction chart. Procedures to follow are the 2013 ASHRAE Handbook of
Fundamentals, Chapter 21 (Duct Design), page 21.21 (HVAC Duct Design
Procedures).
3. Ductwork Construction:
a. Round, flat oval and rectangular ductwork shall be fabricated in accordance with
SMACNA “HVAC Duct Construction Standards - Metal and Flexible,” Third
Edition, 2005, except as follows:
i. General:
ii. Round:
DUCTWORK
23 3114- 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Where 1.5 radius elbows do not fit use 1.0 radius elbows.
iii. Rectangular:
4. Transverse (girth) joints T-4, 9, 17, 18, 19, 20, and 23 not
permitted.
5. Mitered elbows with turning vanes are not permitted. Use radius
elbows.
4. Ductwork Installation:
DUCTWORK
23 3114- 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. SMACNA HVAC Duct Construction Standards, 1995, Figure 2-15: Flexible duct
elbows at the diffuser as shown is not permitted. Elbows must be sheet metal
(see drawing details).
5. Sealing:
a. Ductwork shall be sealed at the factory and remain sealed at all times until
installed. Ductwork must be sealed at all times even if being worked on. Seals
can be removed only during immediate installation and must be restored
immediately upon non-work activity. Ductwork being worked on shall be sealed
at the end of each work day.
Outdoors A A A A
Unconditioned B A B B
Spaces
Conditioned C B B B
Spaces
(concealed
ductwork)
Conditioned A A B B
Spaces
(exposed
ductwork)
DUCTWORK
23 3114- 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a
6. See Table 23-3114-2 for definition of seal level.
a
Transverse joints are two ducts orientated perpendicular to flow.
Longitudinal seams are joints orientated in the direction of airflow.
Duct wall penetrations are openings made by screws, fasteners,
Round and flat oval spiral lock seams need not be sealed prior
assembly, but may be coated after assembly to reduce leakage. All
other connections are considered transverse joints, including but
not limited to spin-ins, taps, and other branch connections, access
door frames, and duct connections to equipment.
a. Gasketed flanges (SMACNA Joints T-24, T-25, and proprietary slip-on flanges)
shall be sealed with a mastic.
b. Acceptable Products: United Duct Sealer (United McGill Corp.) Hardcast, McGill
AirSeal, Ductmate, Mon-Eco Industries or H.B. Fuller/Foster
7. Leakage Tests:
a. Leakage tests shall be conducted in accordance with the SMACNA HVAC Air
Duct Leakage Test Manual, 1st edition, 1985. Section 3 (General Procedures),
Section 5 (Test Apparatus, and Section 6 (Test Reports). Positive and negative
pressure ductwork shall be tested in the positive mode.
b. Tests shall be completed before insulation is applied and ducts are concealed by
building enclosures. Tests may be conducted in sections.
DUCTWORK
23 3114- 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a
Supply Ductwork: Ductwork downstream of VAV/CAV Terminals
Return Ductwork: Ductwork upstream of VAV/CAV Terminals.
b
Supply, Return, and Exhaust Ductwork.
END OF SECTION
DUCTWORK
23 3114- 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DUCTWORK
23 3114- 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for ductwork specialties and
accessories.
2. Flexible Duct:
b. Acceptable Manufacturers:
ii. Casco.
d. Dampers shall have a Leakage Class III label. Seals shall be metal-to-metal.
h. Combination smoke/fire dampers shall have access panels on each side of the
damper in compliance with the drawing details. Access panels shall have a
single pane Plexiglas viewport.
DUCTWORK SPECIALTIES
23 3314 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Greenheck.
iv. Nailor.
v. Cesco.
vi. Ruskin.
j. The maximum sizes for UL listed 1 1/2 hour rated fire/smoke dampers is
tabulated below. For 3 hour rated dampers the maximum vertical damper is 30”
x 30”. No multiple sizes or horizontal dampers are UL listed as of the date of this
standard.
4. Fire Dampers:
a. Fire dampers shall be installed at all duct penetrations through fire rated walls
and floors.
b. Fire dampers shall be multi-blade, UL 555 labeled. Curtain dampers are not
permitted.
c. Fire dampers shall have a either a 1-1/2 or 3-hour rating depending on the rating
of the wall.
DUCTWORK SPECIALTIES
23 3314 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Fire dampers shall have access panels on each side of the damper in
compliance with the drawing details. Access panels shall have a single pane
Plexiglas viewport.
5. Smoke Dampers:
a. Smoke dampers shall be installed at all duct penetrations through smoke zone
boundaries not having a fire resistance rating.
c. Dampers shall have a Leakage Class III label. All seals shall be metal-to-metal.
g. Combination smoke/fire dampers shall have access panels on each side of the
damper in compliance with the drawing details. Access panels shall have a
single pane Plexiglas viewport.
6. Flexible Connections:
a. Flexible connections shall be 0.024 in. thick, 30 oz/yd2 glass fabric double-
coated with polychloroprene.
b. Acceptable Product:
7. Access Panels:
v. between the VAV terminal units and the reheat coil, and downstream of
the VAV terminal unit reheat coils.
DUCTWORK SPECIALTIES
23 3314 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
8. Louvers:
c. The water penetration of outdoor air intake louvers shall be less than 0.2
oz/SF/0.25 hour based on laboratory tests in compliance with AMCA Standard
500.
d. The face velocity of individual louvers or each louver in a bank of louvers should
not exceed the following values (Source: ASHRAE Handbook of Fundamentals,
2013, Table 6, Page 21.17. Review project specific requirements with NU
Project Manager and take into consideration snow infiltration.
1. 7000 cfm and greater: 400 fpm maximum (Peak velocity not
average velocity).
ii. Exhaust:
Table 23-3314-1
DUCTWORK SPECIALTIES
23 3314 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
Table 23-3314-1
9. Sound Attenuators:
a. A noise calculation is required for both the supply and return ductwork of all air
handling units, and the supply and return ductwork of all return/exhaust fans.
b. For each system the minimum attenuator DIL (Dynamic Insertion Loss) in each
octave band shall be in compliance with Table 23 3314-2. The self-noise of the
attenuator must be at least 5 dB less than the silenced sound power level in
each octave band. A schedule should be issued with the drawings specifying
the noise attenuation required in each of the following octave band frequencies
(Hz): 125, 250, 500, 1000, 2000, 4000, and 8000, similar to the following:
d. Acoustical lined round ductwork is permitted, but the duct must have an inner
perforated liner.
DUCTWORK SPECIALTIES
23 3314 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Aeroacoustic.
v. Commercial Acoustics.
viii. Dynasonics.
END OF SECTION
DUCTWORK SPECIALTIES
23 3314 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General:
2. Design Considerations:
4. Centrifugal Fans:
a. Fans with wheel diameters 36 inches and smaller shall be Class II minimum.
Fans greater than 36 inches shall be Class III minimum.
d. Fan ratings shall be tested and certified in accordance with AMCA Standards
211 and 311 and fans shall bear AMCA Seal
e. Provide OSHA Compliant belt and shaft guards for belt driven fans.
f. Acceptable Manufacturers:
i. Barry Blower.
iv. Greenheck.
v. Industrial Air.
FANS
23 3400- 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
5. Plenum Fans:
a. Plenum Fans may be used for static pressure 6 inches SP and below.
b. Fans shall be airfoil centrifugal type designed for industrial duty and suitable for
continuous operation. Fans shall be single width, single inlet, arrangement 3.
c. Air handling quality, heavy-duty, grease lubricated, pillow block, self-aligning ball
or roller type. Bearings shall be selected for minimum life (ABMA L10) of not
less than 100,000 h operation at maximum cataloged operating speed.
d. Acceptable Manufacturers:
i. Barry Blower.
iii. Greenheck.
6. Fan Array:
a. Fan array system shall consist of multiple, direct driven, arrangement 4 plenum
fans constructed per AMCA requirements for duty specified. Fans shall be
selected to deliver scheduled airflow quantity at scheduled operating total static
pressure and scheduled fan/motor speed. Fan array shall be selected to operate
at system total static pressure that does not exceed 90% of scheduled fan’s peak
static pressure producing capability at scheduled fan/motor speed.
b. Fan intake wall, inlet funnel, and motor support structure shall be powder coated
for superior corrosion resistance. Motors shall be standard pedestal mounted
type, T-frame motors selected at specified operating voltage, rpm, and efficiency
as needed to meet performance requirements. Motors shall include isolated
bearings or shaft grounding. Each fan/motor cartridge shall be dynamically
balanced to meet AMCA standard 204-96, category BV-5, to meet or exceed
Grade 2.5 residual unbalance.
i. Fan array shall provide uniform air flow and velocity profile across entire
air way tunnel cross section. Airflow and velocity shall not exceed
scheduled cooling coil and/or filter bank face velocity when measured at
a point 12 inches from intake side of fan wall array intake plenum wall,
and distance of 48 inches from discharge side of fan wall intake plenum
wall.
iii. Provide structural frame to support upper fans with solid floor panel
partition between fans as shown on drawings to minimize system effect.
FANS
23 3400- 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Each fan in array shall be provided with back flow prevention means that
produces less than 0.10 inches wc of static pressure drop and/or system
effect when that fan is enabled. Any such system effects and/or pressure
drops shall be submitted and included as component in determining fan
system total static pressure as submitted. Manufacturer's pressure drop
ratings of any such equipment, developed from straight run test
conditions will not be accepted.
v. Provide 2 separate variable frequency drives for fan array. Each VFD
shall control half of fans in array. Provide one backup VFD for air
handling unit.
vi. Fan array shall be sized such that upon single fan failure, remaining fans
could ramp up and provide same 100% design capacity.
ix. Contractor shall provide all wiring to air handling unit components that
require power.
c. Acceptable Manufacturers:
i. AcoustiFLO.
ii. Greenheck.
a. Lab Fume hood fans shall be with coating recommended for application, drive
arrangement 10 or 1, AMCA Class C spark resistant construction
b. Air handling quality, heavy-duty, grease lubricated, pillow block, self-aligning ball
or roller type. Bearings shall be selected for minimum life (ABMA L10) of not
less than 100,000 h operation at maximum cataloged operating speed.
FANS
23 3400- 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Acceptable Manufacturers:
i. Barry Blower.
iii. Greenheck.
END OF SECTION
FANS
23 3400- 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for air terminal devices.
2. Design Considerations:
a. Fan powered terminals are not generally permitted. Fan powered terminal for
final diffuser filtering applications may be considered with NU Project Manager
approval.
b. VAV terminals shall have a reheat coil with access panels upstream and
downstream.
3. VAV Terminals:
b. Terminal unit shall be furnished with a hot water reheat coil. The reheat coil
control valve shall be DDC controlled by the terminal box controller. For reheat
coil piping details see drawings.
c. The box casing shall be 22 gauge minimum; the damper assembly shall be 16
gauge minimum.
d. Box manufacturer shall provide an access door between the terminal unit and
the reheat coil.
e. The box manufacturer shall furnish the multi-point, center averaging sensor.
f. The control contractor shall furnish the control components to the terminal box
manufacturer for factory mounting. The box manufacturer shall include the cost
to mount the control components.
g. Acceptable Manufacturers
i. Price.
ii. Nailor.
b. Acceptable Manufacturers:
i. Price.
ii. Nailor.
5. Diffusers:
a. The diffuser style and color shall be reviewed by the NU Project Manager.
b. Grilles, not diffusers, shall be specified, and duct dampers used for balancing.
Show all balancing dampers on the drawings.
5000-IV -- RC
5800A -- DA
-- TMRA P3
5800 -- DM
e. Acceptable Manufacturers:
iv. Price.
v. Krueger.
vii. Nailor.
END OF SECTION
DIVISION 23 – HVAC
1. General:
2. Design Considerations:
a. General:
i. It is preferred that air handling units have the following filter sections,
where efficiency is the ASHRAE atmospheric dust-spot efficiency
determined by ASHRAE Standard 52.2-2007.
4. Final Filters: Final filters shall be extended surface, non-supportive pocket type.
Efficiency shall be 80-90% minimum, MERV 13 where efficiency is the atmospheric dust
spot efficiency determined by ASHRAE Standard 52.2-2007.
6. Filters on 100% OA units for before and after the preheat coil depending on winter and
summer (Snow loading)
7. Use Slide out filter racks when total CFM is 5000 CFM or under, Use Lift out filter
frames for units above 5000 CFM.
8. For slide out filter racks, each housing shall have door on both sides to facilitate
changing filters. Doors shall have perimeter gaskets to minimize air leakage, shall be
hinged, and shall have cam-lock or lever handle latches to secure the door
9. For lift out filter frames, the frames shall be minimum 16 gauge galvanized construction
with provisions for assembly in a bank. Frames shall be suitable for filters scheduled
and incorporate gaskets and spring clips to prevent air bypass.
FILTERS
23 4114- 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
10. Three (3) sets of pre-filters shall be provided, one (1) set for use during construction,
one (1) set for building turnover to owner, and one (1) spare set. Two (2) sets of after
and final filters shall be provided: one (1) set for building turnover to owner and one (1)
spare set.
11. Bag-In / Bag-Out filter housings shall be provided with isolation dampers/valves on each
side.
12. Filter pressure drop gauges shall be across each bank of filters.
END OF SECTION
FILTERS
23 4114- 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for primary heating equipment.
2. Design Considerations:
a. Fired boilers are used in the Central Utility Plant (CUP) for both the Chicago and
Evanston campuses. The primary heating equipment is for convertors from
steam to heating hot water.
i. Shell and tube type with removable copper U-tube bundle, steel shell,
tube sheets, and heads.
iii. Heat exchangers shall have tube side working pressure of125 psi and
test pressure of 250 psi with shell side working pressure of 150 psi and
test pressure of 195 psi.
c. Acceptable Manufacturers:
ii. Armstrong.
iii. Adamson.
iv. Taco.
END OF SECTION
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for packaged air-handling units
(AHU).
b. Systems shall be constant air volume (CAV). Engineer of Record shall evaluate
the use of Variable Air Volume (VAV) with Life cycle analysis.
c. Air handling units are to be designed with 20 percent additional capacity for
future expansion.
e. The base shall be welded 2-1/2 in. minimum structural channel construction with
full walk-on G-90 galvanized steel floors in all sections. No paint is permitted.
f. Unit shall have a double wall casing with 2 in. insulation minimum and in
compliance with ASHRAE/IES Standard 90.1-2010, “Energy Efficient Design of
New Buildings Except New Low-Rise Residential Building,” Table 9-2. The fan
section shall have a perforated liner. All other sections shall have a solid inner
liner.
g. The condensate drain pan shall be 16 gauge, 304 stainless steel. Drain pans are
to be insulated double bottom construction.
i. The humidifier control valves , strainers and valves shall be outside of the
AHU (outside of the airstream)
m. Access Sections:
i. Access sections shall be 24 in. minimum and shall have access doors on
both sides.
ii. Access doors shall have a single pane Plexiglas viewport. Access panels
are not permitted.
iii. Actual height of view port window to consider concrete pad height and be
5’-0” above finished floor to bottom of view port window. View port
window to be 12 inch x 10 inch minimum size.
n. The housekeeping pad shall be adequate to install the cooling coil drain pan trap
in compliance with the drawing details.
o. Acceptable Manufacturers:
i. AAON.
iii. ETL.
v. Ventrol.
END OF SECTION
DIVISION 23 – HVAC
1. General:
a. This section outlines the general requirements for factory-fabricated custom air
handling units (AHU’s).
2. Design Considerations:
a. Air handling units greater than 3500 cfm shall be factory built-up air handling
units.
b. Air handling units shall be double wall, 4-in. thick, acoustically lined, with a 22-
gage minimum galvanized steel inner liner. The fan section shall be perforated;
the other sections shall be solid. Perforated fan section with stand-offs for
insulation liner with Tedlar film thickness of 1.0.
c. Cooling coils shall have a 16 gauge, 304 stainless steel drain pan. Drain pans
are to be insulated double bottom construction.
d. The cooling coil drain pan shall have a trap in compliance with the drawing
details. When the housekeeping pad is not adequate for the trap, the cooling
coil(s) shall be mounted on a 304 stainless steel stand to permit installation of
the trap.
e. Coils shall have slide out racks and not face bolted.
f. Seal coat mechanical room concrete floors and equipment pad underneath AHU.
a. The humidifier control valves , strainers and valves shall be outside of the AHU
(outside of the airstream)
b. Do not locate the humidifier upstream of the fan section. The preferred location
for the humidifier section is downstream from the fan section.
c. When the humidifier is located in the air handling unit it should be located 18
inches downstream of the heating coil and a minimum 3 ft upstream of the
cooling coil.
6. Plenums:
a. Each plenum between components shall have an access door with a view port
on both sides of the unit. Doors shall open against pressure and the view port
shall be 12 inch x 12 inch minimum size, double wire thermal pane. Actual height
of view port window to consider concrete pad height and be 5’-0” above finished
floor to bottom of view port window.
1. Cesco Products.
2. Semco Inc.
c. Plenums shall have outside each door a 120 VAC outlet with waterproof cover.
7. Dampers:
b. Basis of Design – Outside Air Dampers: Outside air dampers shall be equal to
Tamco Series 9000 thermally insulated dampers
c. Acceptable Manufacturers:
i. Tamco.
ii. Ruskin.
d. Frame:
ii. Material. The frame shall be 13 gage (0.0934 in.) galvanized sheet steel
or 0.125 (actual web thickness) 6063-T5 extruded aluminum.
e. Blade:
i. The blade shape shall be airfoil symmetrical to the axle pivot point.
h. Axle: Axles shall be plated steel and both ends 3/8 in. square minimum for
positive linkage attachment.
i. Linkage:
i. Plated steel.
ii. Linkage shall be dual and concealed in the jamb (out of the air stream).
j. Bearings: Axle bearings shall be bronze oilite. Blade seals shall be accessible
for removal and replacement at the blade edges.
i. Air Enterprise.
ii. Buffalo.
iv. TMI.
v. Ventrol.
8. Leakage Testing:
a. Built-up units must be leak tested at 12 in. wg. Tests shall be conducted in
compliance with SMACNA’s HVAC Air Duct Leakage Test Manual, 1st edition,
1985.
b. Draw-thru units shall be tested under negative pressure. Blow-thru units shall be
tested under positive pressure.
c. Inlets and outlets shall be sealed. The leakage rate of the unit shall not exceed
0.5% of the total Scheduled AHU CFM.
END OF SECTION
DIVISION 23 – HVAC
2. Design Considerations:
a. For both the Evanston and Chicago campuses the supply chilled water
temperature is 42 degrees F. The coil should be selected for a minimum 16
degrees F temperature differential.
b. For the Evanston campus central chilled water system primary and secondary
(distribution) piping, consult the NU Facilities Management Office (FMO).
c. For the Chicago campus central chilled water system piping, consult the NU
Facilities Management Office (FMO).
i. Coils shall be slide out style and not face bolted so that they can be
removed without affecting the structural integrity of the unit.
iii. Vent and drain connections shall be stainless steel pipe and extend to
the exterior of the unit.
i. Heat Recovery:
4. Acceptable manufacturers:
a. Buffalo.
COILS
23 8216- 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Marlo.
c. Heatcraft.
d. Aerofin.
e. Temtrol.
4. Acceptable manufacturers:
a. Buffalo.
b. Marlo.
c. Heatcraft.
d. Aerofin.
e. Temtrol.
4. Acceptable manufacturers:
a. Buffalo.
b. Marlo.
c. Heatcraft.
d. Aerofin.
COILS
23 8216- 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
e. Temtrol.
END OF SECTION
COILS
23 8216- 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
COILS
23 8216- 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 23 – HVAC
1. General: This section outlines the general requirements for humidification equipment.
2. Design Considerations:
a. Central Utility Plant (CUP) steam must not be used for humidification.
3. Do not locate steam humidifiers immediately upstream of a fan. The preferred location
is downstream of the supply fan. Observe manufacturer’s free distance downstream of
steam injectors.
a. In AHU:
ii. Each dispersion tube shall be fitted with steam discharge tubelets
inserted into tube wall. Each tubelet shall be made of thermal-resin
material designed for high steam temperatures. Two rows of tubelets in
each dispersion tube shall discharge steam in diametrically opposite
directions, perpendicular to airflow
1. Armstrong.
2. Dri-Steem.
3. Carel.
b. In Ductwork (Booster).
HUMIDIFICATION EQUIPMENT
23 8413- 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ii. Each dispersion tube shall be fitted with steam discharge tubelets
inserted into tube wall. Each tubelet shall be made of thermal-resin
material designed for high steam temperatures. Two rows of tubelets in
each dispersion tube shall discharge steam in diametrically opposite
directions, perpendicular to airflow
1. Armstrong.
2. Dri-Steem.
3. Carel.
a. For small units use Dri-Steem model STS (all Stainless steel).
b. For larger units use Cemline unfired boilers (all Stainless steel).
8. Make up water to the clean steam generators to use RO water and DI water.
a. After coolers shall be constructed of 304 stainless steel and furnished with inlet,
vent and drain connections and stainless steel striking plate
i. DriSteem.
c. Consider air cooled condensate coolers for humidifiers in custom air handling
units to save water versus domestic water cooled condensate coolers.
END OF SECTION
HUMIDIFICATION EQUIPMENT
23 8413- 2
NORTHWESTERN UNIVERSITY
Technical Criteria Issuance Date: 01.01.2014
END OF SECTION
INTEGRATED AUTOMATION
25 0000 - 1
NORTHWESTERN UNIVERSITY
Technical Criteria Issuance Date: 01.01.2014
INTEGRATED AUTOMATION
25 0000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 26 – ELECTRICAL
2. Safety: Electrical safety is paramount in any facility and that begins with a design that is
safe to operate and maintain. Electrical equipment should be specified and located with
emphasis placed on reduced maintenance exposure, manageable short circuit and
ground fault current, and arc-flash safety.
3. Reliability: Reliability in the electrical system is also critical to meeting the goals of the
University to provide world class technical and health research capabilities. Electrical
systems that are reliable also require less maintenance, have lower operating costs, and
produce less waste.
4. Redundancy: The design must identify and address points of failure for systems serving
critical spaces, which are to be identified with the owner. Redundancy and/or back-up
systems should be identified.
Sustainability Overview
1. Sustainability is not just about energy efficiency and energy savings. From the
Advanced Lighting Guidelines: “Lighting is primarily provided for people, not for the
buildings or roadways or objects illuminated. Peoples’ needs should determine what
kind of lighting is provided. Meeting those needs is important because a good visual
environment is critical to health, productivity, comfort, aesthetics, safety, communication
and mood. Lighting designers have an opportunity and responsibility to support and
improve the quality of life for everyone. Recently, lighting has become a subject of much
greater interest than for many years. This is for three reasons:
a. The ageing of the population in many developed countries. As the human visual
system ages, its capabilities deteriorate. Lighting can be used to help older
people to see well and hence to live active lives for longer.
c. The recognition that exposure to light can have significant non-visual effects on
human health. The potential for exposure to light to cause tissue damage has
been known for many years, but now its influence on the human circadian
d. Taken together, these developments mean that the number of factors that should
be considered when determining if a lighting installation is fit for purpose has
increased. However, one factor that will almost always need to be considered is
how well the lighting enables people to see.”
2. Lighting energy efficiency shall be a significant consideration for all lighting designs. The
following shall be taken into consideration:
1. Service entrance types vary depending on campus location, building size and type of
use.
a. Transformer Vaults:
vi. Vaults are to be lighted with low maintenance, all-weather lighting fixtures
connected to the building essential power system and switched at the
entrance. Adequate lighting is to be provided to allow identification of all
component and raceway markings from the entrance to the vault.
vii. Vault man doors are to open in the direction of egress with panic
hardware.
viii. Vault equipment doors are to be sized to allow the largest single piece of
equipment to be removed for replacement.
ix. A 6-inch concrete dike is to be cast onto the floor to prevent leaking
transformer oil from escaping vault. An integral transformer leak basin
can be used in lieu of a dike. The basin is to be sized large enough to
contain the liquid contents of the transformer.
xi. Where allowed by the AHJ, water fire suppression is not to be used in
transformer vaults.
xii. For transformer vaults and/or main distribution rooms located below
grade, provide high water alarms connected to the Building Automation
System (BAS).
xiii. Electrical vaults and gear rooms shall be painted with white walls and
battleship gray epoxy floors.
b. Transformers:
iii. Air-insulated transformers are to have forced air cooling with a core
temperature indicating display.
c. Duct Banks:
i. Service Entrance (MV and LV) duct banks are to be concrete encased.
Duct banks are to terminate in a service entrance switchboard or
switchgear within 5’ of entering the building or are to remain in concrete
and painted red until terminated in a service entrance rated disconnect.
d. Service Disconnect:
ii. LV service disconnecting means rated over 1200 amperes will be in either
a service entrance rated switchboard or switchgear. Laboratory and
research facility services will utilize switchgear equipment with power
style circuit breakers.
Distribution
1. Equipment:
b. Equipment is to be selected to allow for growth of the facility within reason and
meeting the goals of the University. See specific equipment sections for space
requirements.
f. Energy conserving and Energy Star listed equipment should be used as the
design basis for all facilities.
2. Electrical Rooms:
a. Rooms are to be designed to allow growth within the electrical system and safe
maintenance of components within the room. Space allowed for growth will
depend on the facility type and type of equipment in the room. Space for future
panels and transformers is to be discussed with NU during the design. At a
minimum, provide 30% of clear wall space in all electrical rooms for future panels
and equipment.
c. Electrical rooms are to be free of foreign systems such as ductwork, piping and
other equipment.
d. The room is to be fire rated based on the equipment that is located in the room.
e. Electrical rooms should be stacked from floor to floor and located with attention
given to the noise, heat, and magnetic interference caused by the room.
f. The room air is to be exhausted to keep the space below 104F in conditioned
buildings.
Lighting
1. Lighting methods and requirements vary depending on the facility type. An emphasis on
energy conservation and controllability are to be included in each design. The latest
lighting methods and technologies are to be researched and their applications explained
during the design review process.
2. The goals of energy reduction, energy code compliance, and LEED certification are a
priority to the University and efficient lighting designs and controls are a key part in
meeting those goals.
3. The University maintains a stock of lamp types, and new lighting designs should utilize
stocked lamps whenever possible. When designs include lamps that are not NU-
stocked items, advise Facilities Management of this condition early in the process.
1. The goal of the required engineering calculations for each project is to provide a safe,
reliable design that can be easily revised or added to in the future with complete
knowledge of the existing system’s capacities and limitations.
2. Engineering calculations and studies that are required for every system design for both
new facilities and renovations/additions shall include the following:
a. Short Circuit
b. Time-Current Coordination
c. Arc-Flash
d. Voltage Drop
f. Lighting Photometrics
4. Preliminary short circuit calculations are to be provided for review during the design
phase.
5. Time-current coordination for all new overcurrent protective devices and existing devices
where connections are made as part of the project is to be performed after the Design
Engineer has been given the circuit breaker and fuse submittals for the project. The
Design Engineer is responsible for correcting devices that do not coordinate with the
manufacturer. The installing electrical contractor is responsible for providing feeder
length and routing deviations from the design to the Design Engineer as these affect the
calculations. Adjustable device setting will be provided to the installing electrical
contractor who will make the device adjustments.
7. Lighting power density calculations for each area to show compliance with the energy
code are to be shown on the lighting plan drawings.
9. Four (4) copies of a binder with final versions of the power calculations listed above for
the project are to be submitted by the Design Engineer to NU with the record drawings at
the end of the project.
1. The Contractor, after inspecting the premises and the drawings, shall call to the attention
of the Architect/Engineer and NU Supervising Electrician any lack of space or clearance
required by the various equipment before the contract is signed.
2. Electrical projects are not considered complete until as-built drawings with home runs
identified are received by the NU Project Manager and the NU Supervising Electrician.
3. An over-current protection device coordination study using SKM Power Tools and
following ANSI standards for over-current device settings, transformer and cable
damage curves will be included in the engineering documents for all new electrical
power systems. For renovation projects, the study is to include coordination with all
devices in the existing source panel where the new work is added. Device trip settings
will be adjusted by the installing electrician and verified before the system is energized.
4. An arc-flash study of all new electrical power systems using SKM Power Tools will be
conducted by the engineer of record in accordance with NFPA 70E requirements. For
renovation projects, the study is to include the source equipment where the new work is
added. The results of the study will be provided to the installing electrician who will
furnish and install arc-flash safety labels on all new system components where
applicable.
5. Provide a minimum of a 2-year warranty on labor and materials unless stated otherwise
in the Project General Requirements. The warranty period begins on the date the
project is completed.
6. Provide complete functional testing, start-up services, and owner training for each
system component installed.
7. Prior to project completion, all electrical system areas and components are to be
cleaned, painted, and returned to like-new condition.
8. Coordinate electrical system outages with campus Chief Electrician, Building Manager
and General Contractor. Provide a minimum of 2-week notice before outage is to occur.
9. Installing Electrician is responsible for electrical connections and testing for electrical
equipment provided by other trades or the University such as motors, motor control
devices. Coordinate with other trades and the University for requirements and
responsibilities for equipment provided by others.
1. The Contractor and/or supplier shall alert the University of any specified items that
require long lead times for parts replacement (excess of 48 hours).
2. Electrical materials shall be UL approved for the type of use being applied.
3. Provide a 4-inch high concrete housekeeping pad for floor mounted equipment above
grade. Use a 6-inch high concrete housekeeping pad for locations below grade.
4. Steel anchors or toggle bolts shall be used for supporting equipment, pipe, and lights
from the ceiling. The use of plastic anchors is prohibited.
5. See list of materials not allowed in Northwestern facilities. Materials are to be RoHS
compliant were applicable. Non-RoHS compliant materials are to be reviewed on an
individual basis.
7. Material manufacturer’s and types are to match current Northwestern warehouse stock
where applicable.
8. Other system components (i.e. ductwork, piping, etc.) are not allowed to be located
within electrical rooms, electrical closets, or over electrical equipment.
Technology Systems
http://www.it.northwestern.edu/
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for medium and low voltage
conductors. Specific requirements are to be reviewed with the NU Project Manager
during the design phases of the project
2. Design Considerations:
c. Cable for primary and/or secondary distribution for voltage applications in excess
of 2400 volts shall adhere to the following criteria.
i. Cable shall be suitable for use in wet and dry locations in underground
encased duct systems.
ii. Cable shall be rated for 105 degree centigrade for normal operation, 130
degree centigrade for emergency overload and 250 degree centigrade for
short circuit conditions. Use of 90 degree centigrade rated cable is to be
approved by the Supervising Electrician.
d. Wire and cable for secondary power and light distribution shall be new 600 volt
insulated copper conductor.
f. Wire and cable in dry locations shall be THHN (copper) or THWN (in areas of
high moisture); in damp locations, such as crawl spaces or below grade, shall be
XHHW, THWN or XLP-USE type (copper).
120/208 480/277
j. Minimum size conductors for power and lighting loads shall be #12 AWG.
Minimum size for control wiring will be #14 AWG. All power and control
conductors are to be stranded copper.
l. Signal and communication wiring can be installed in a cable tray system for non
plenum areas, when allowed by code.
m. Twist-on connectors are allowed for #10 AWG and smaller conductors. Only
mechanical compression type connectors shall be used on conductors larger
than #10 AWG.
n. Conductor splices are not allowed unless the circuit run exceeds 500 feet.
Splices are to be made with mechanical compression connectors only. Insulation
of the splice is to be the same as the conductor being spliced. Splices are to be
located in dry locations only and inside pull or junction boxes with “SPLICE”
identified on the cover.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for raceways and boxes.
Specific requirements are to be reviewed with the NU Project Manager during the design
phases of the project
2. Design Considerations:
i. Essential circuits.
xi. Class I circuits; remote control and signaling circuits, less than 600V.
xii. Class II circuits; remote control and signaling circuits fed from a Class II
limited power supply, 150V and less.
b. Types of Conduit:
i. Electric metallic tubing “EMT” shall be utilized for concealed interior work,
except as described herein.
ii. Intermediate grade conduit “IMC” shall be utilized for interior feeders in
wet areas, damp areas, exterior, exposed in mechanical rooms and
vertical drops to equipment. Review potential wet or damp areas with
Chief Electrician.
iii. Galvanized Rigid Steel Conduit “GRSC” shall be utilized in areas subject
to physical damage in wet areas, exterior, within masonry walls, hollow
tile walls, and all hazardous areas.
iv. PVC schedule 40 conduit shall be used in concrete slab and encased in
3" of concrete. In no case shall conduit be direct buried below slab.
Provide PVC coated GRSC for all underground elbows. Use long sweep
elbows for feeders above 600V.
v. Flex conduit shall be used only for chasing existing walls, suspended
lights in drop-in in suspended ceilings and connections to equipment
subject to vibration, etc. Flexible conduit shall have green ground wire.
Flexible conduit shall not exceed 6 feet in length.
c. Conduit Colors:
i. Yellow:
ii. Orange: Feeders 277V – 600V in vaults, gear rooms, electrical rooms, or
electrical closets.
iii. White: Feeders 120V – 240V in vaults, gear rooms, electrical rooms, or
electrical closets.
vii. Where conduit is exposed in public or finished areas, the conduits shall
typically be painted to match the adjacent wall or ceiling color. The
associated junction box covers shall be painted to match the
Northwestern standard conduit color code above.
d. Conduit Size:
ii. 1/2-inch above grade allowed for controls, and some low voltage
systems. Review specific requirements with NU Project Manager.
iv. 3/4-inch minimum for all security system conduits, including CCTV and
access control systems.
e. Conduit Installation:
iii. Where conduits follow the same run, trapeze hangers (unistrut) may be
utilized with provisions made for proper spacing and the use approved
conduit straps. Suspending conduit from the bottom of a unistrut support
is not permitted.
iv. Trapeze hangers shall utilize two 3/8” minimum threaded rods per cross
member strut. Rod size is to be increased to match trapeze load with a
30% design safety factor.
vi. PVC and PVC coated GRSC will be used in concrete. All PVC must have
ground wire installed, minimum #12.
vii. Provide conduit sealing bushings for conduits 1-1/2 inches or greater and
at all points where conduits enter the building from the outside or from
below grade. Sealing fitting are to be used at all points where conduits
enter air handlers and cold rooms.
viii. Before any cutting or coring of walls and floors, the Engineering and
Electrical Department must be notified at least 2 weeks in advance.
ix. When coring through fire-rated walls and floor, fire - stop fittings and
sealers must be installed.
xiii. Raceways terminating to cable tray are to be bonded to the tray using
approved fittings and bonding conductor.
xiv. See Electrical Systems Identification Section of this Standard for raceway
identification requirements.
f. Conduit Fittings:
ii. EMT or Thin wall: Compression type, steel with insulated throats in
connectors.
iii. Wiremold #500 series or smaller shall not be used on either campus.
iv. Provide wiremold entrance fittings only. Do not drill surface raceway.
h. Manholes:
3. Cast steel solid cover with lifting shackle and cover support
complying with ASTM A 48/A 48M. The word “ELECTRIC” is to
be cast into the lid face.
4. Minimum of four external lifting rings and four internal pulling rings
cast into manhole body.
ii. Provide Tier 22 or A-16 rated cover, minimum. Cover is to have non-skid
surface with system identification cast into lid face. Lid is to have
structural integrity matching that of the body.
iii. Designed for flush burial with tapered sides that prevent heaving.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for identification for electrical
systems. Specific requirements are to be reviewed with the NU Project Manager and
NU Chief Electrician during the design phases of the project.
2. Design Considerations:
a. General:
b. Labeling for medium voltage shall be Charlie number, voltage, fuse size,
etc. Junction boxes shall match this requirement.
c. In finished areas, labels can be clear with black lettering. Each label shall
include panel and circuit number.
d. In areas where conduits are exposed in public areas, the conduits should
be painted to match the ceiling color. The associated junction box covers
shall be painted and labeled to match the NU standard conduit color
code.
c. Colors:
iv. Emergency (EM) & Essential (ES) 480/277V – Red letters w/black outline
on Orange background. Differentiate EM from ES (Chicago) and EM, LR,
OS, and CS (Evanston).
d. Motors and other pieces of electrically operated apparatus shall be identified with
suitable painted or stenciled lettering.
e. Panel directories shall be type written under a plastic or glass protective cover on
panel door. Hand printed directory and stick on type labels are not acceptable.
When panelboard directories are installed or updated, the date shall be identified
on the directory. The name of the installing or updating contractor shall be
indicated on the directory.
f. Three spare type panel directories will be provide along with As-Built drawing to
the University. Provide one spare directory located at each panel.
g. Prior to typing directories, room numbers and area designation must be reviewed
by the university architect and university supervising electrician in case of conflict
with construction drawing designations.
h. Laboratory raceway receptacles shall display source panel and circuit numbers.
j. Junction box covers are to be marked with the source panel and circuit numbers
for conductors found within the junction box. Use the same color coding as with
raceway identification.
k. Receptacles, switches and disconnects are to be labeled with the voltage, phase
and amperage in addition to the source panel and circuit number/s.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for low voltage transformers.
Specific requirements are to be reviewed with the NU Project Manager and NU Chief
Electrician during the design phases of the project.
2. Design Considerations:
a. Transformers are to have the following maximum rated rise temperatures over a
40°C ambient:
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for low voltage switchgear.
Specific requirements are to be reviewed with the NU Project Manager and NU Chief
Electrician during the design phases of the project.
2. Design Considerations:
a. Locations:
iii. Mechanical ducts, water pipes, drain pipes, etc. will not be permitted in
electrical switchgear room.
i. Each switchgear vertical section is to be labeled with the vertical bus voltage,
amperage, phase, and fault current bracing rating. Each switchgear circuit
breaker is to be labeled with the load identification, breaker amperage, voltage
and phase.
k. All switchgear circuit breakers are to be power style UL1066 listed, ANSI C37.13
air frame or insulated-case type with electronic trip in draw-out cubicles, 800A
frame size minimum. Electronic trip modules are to have adjustments for long
time pickup and delay, short time pickup and delay, instantaneous pickup and
delay. All circuit breakers are to be 100% rated. Main circuit breakers are to
have an arc flash maintenance switch that minimizes the instantaneous delay to
allow for lower required PPE level during maintenance.
m. If ground fault protection is required on the main circuit breaker/s, two levels of
ground fault protection is required to allow coordination of ground fault devices
and avoid complete system outages due to ground faults.
r. Rear covers shall be hinged door with Corbin #4T3142 key lock. Lock type shall
be same for both campuses.
s. Front covers shall be formed and mounted with thumb screws. All front covers
over draw out devices or with meters mounted on them shall be hung with loose
pin hinges.
t. An overhead breaker trolley with hoist is to be provided for each switchgear line-
up. Trolley rails are to be installed to allow pull boxes to be installed above
switchgear without interfering with the trolley.
v. A mimic bus made from laminated plastic is to be attached to the front of the
switchgear with screws. The mimic bus is to indicate the bus pattern as it passes
through the switchgear. The mimic bus is to show both the horizontal and
vertical buses and all overcurrent devices.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for switchboards. Specific
requirements are to be reviewed with the NU Project Manager and NU Chief Electrician
during the design phases of the project.
2. Design Considerations:
a. Location:
iii. Mechanical ducts, water pipes, drain pipes, etc. will not be permitted in
electrical switchboard room.
c. All bus joints shall be bolted and be visible with switchboard energized for
inspection and readily accessible with the board de-energized for maintenance.
Windows shall be provided for infrared capability at joint locations.
d. Main switchboards are to be UL listed dead front (UL891) with silver plated
copper bus, size based on 1000 amperes per square inch current density. An
interior ground bus and terminals are to be provided along with a jumper to the
system neutral. All ground terminations must be cadwelded.
f. Circuit breakers are to be used for protective devices including main disconnect.
Fuses are to be avoided. Where fault currents warrant, current limiting devices
are to be specified. All breakers are to be identified and a complete index
provided. All circuit breakers to have threaded bolts on bus connections. Circuit
breakers employing plug-in, finger type bus connections are not acceptable.
SWITCHBOARDS
26 2413 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
Blank spaces shall be provided and shall not be less than 25% of the
switchboard spaces in each frame size.
g. Each switchboard vertical section is to be labeled with the vertical bus voltage,
amperage, phase, and fault current bracing rating. Each switchboard circuit
breaker is to be labeled with the load identification, breaker amperage, voltage
and phase.
h. Main and Tie Breakers are to be insulated-case type with electronic trip in draw-
out cubicles. Branch breakers 600A trip and above are to be individually
mounted insulated-case type with electronic trip. 800A frame size minimum.
Electronic trip modules are to have adjustments for long time pickup and delay,
short time pickup and delay, instantaneous pickup and delay. All insulated-case
breakers are 100% rated. Other options: Arc flash maintenance switch, arch
flash detection and control relay.
k. Branch breakers rated below 600 amps to 400 amps are to be molded-case,
current-limiting type with electronic trip including adjustable trip settings. No
circuit breakers with trip ratings below 400 amps are to be installed in service
entrance switchboards except to feed surge protection devices.
o. Rear covers shall be hinged door with Corbin #4T3142 key lock. Lock type shall
be same for both campuses.
p. Front cover shall be formed and mounted with thumb screws. All front covers
over draw out devices or with meters mounted on them shall be hung with loose
pin switchboard type hinges.
SWITCHBOARDS
26 2413 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
s. Switchboard bays shall be individual, free standing units with steel angles and
fully welded construction.
ii. Interiors brackets and supports to be #10 gauge steel arc welded frame.
Brackets by means of bolting will not be accepted.
iii. Top and sides plates shall be 12 gauge or better steel, buss bar shall be
copper, 98% conductivity, size based on 1000A per sq inch current
density.
iv. All bus joints to be silver plated all bolts shall be grade 5 bolts. All
equipment shall bear the UL INC dead front switchboard label.
END OF SECTION
SWITCHBOARDS
26 2413 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
SWITCHBOARDS
26 2413 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for panelboards. Specific
requirements are to be reviewed with the NU Project Manager and NU Chief Electrician
during the design phases of the project.
2. Design Considerations:
d. Neutral bus ampacity shall be rated 200% for panels feeding harmonic type
loads.
e. 100 ampere panelboards shall contain space for a maximum of 30 circuits, 125
ampere panelboards shall contain space for a maximum of 36 circuits; 225
ampere panelboards shall contain space for a maximum of 42 circuits.
f. Include in each panel one spare 20 ampere, 1 pole circuit breaker a minimum of
25% of the total number of circuit breakers in panel.
i. Busses shall be copper and must be located in the rear of the panelboard
cabinet.
PANELBOARDS
26 2416 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. Breakers shall be bolt-on type and shall be removable without disturbing
the bussing and/or other branch protective devices. No plug-in breakers
allowed.
v. Panelboards shall be keyed alike with Corbin #4T3142 key lock in each
building and attention must be given additions and revisions to existing
buildings; all keying must be cleared with university lock shop.
vi. Panelboard covers to be hinged with piano style hinges with door-in-door
construction.
vii. Panelboard tubs are to have fully welded construction and not to have
concentric knock-outs.
xi. There are numerous Northwestern buildings with electrical feeders and
risers exceeding 80% capacity. Existing loads must be confirmed prior to
adding any additional load. New lighting or power panels installed on
existing risers must be approved by Northwestern Supervising Electrician.
END OF SECTION
PANELBOARDS
26 2416 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for motor control centers.
Specific requirements are to be reviewed with the NU Project Manager and NU Chief
Electrician during the design phases of the project.
2. Design Considerations:
a. Motor starters and overload protective devices shall be provided for all motors ½
HP or larger. Receptacles may be used for disconnects only on motors less than
1/2 HP and only as allowed by the Chicago Electrical Code and the N.E.C. and is
recommended for all hot water circulating pumps.
b. Motors shall be 480V, 3 phase except for motors less than 1/2 HP.
c. Starters shall be grouped into motor control centers. Individual starters except in
isolated cases are to be avoided. Each starter shall have a hand/off/automatic
selector switch pilot light (run), two normally open and two normally closed
auxiliary contacts.
d. Control power for starter must originate from MCC cubicle to maintain voltage
continuity with disconnection of power to starter or MCC.
e. Heater overloads will be sized at no more than 130% of running load of motor.
h. Motors over 30 HP shall have reduced voltage or solid-state starting and power
factor correction.
l. Provide minimum 500va control power transformer in each starter cubicle. Size
larger transformers as needed with 100% spare capacity.
m. Motor starters are to have phase loss/under voltage detection relays and shall
open contactor upon a loss of any one or two phases or voltage that is 30%
below rated system voltage with a 5 second adjustable delay.
n. Arc-flash labels are to be applied to all motor control devices including VFDs.
p. Motor control centers shall have fully welded construction, welded frames, and
infrared windows.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for metering of electrical
systems. Specific requirements are to be reviewed with the NU Project Manager and
NU Chief Electrician during the design phases of the project.
2. Power Meters:
i. Meter shall support 3- Element Wye, 2.5 Element Wye, 2 Element delta, 4
wire Delta systems.
ii. Surge shall conform to IEEE C37.90.1 and ANSI C62.41 (6 kV)
iii. The meter shall be user programmable for voltage range to any CT or PT
ratio.
iv. Meter shall have a burden of not more than 0.36VA per phase, Max at
660V, 0.01VA and 120 Volts.
v. Meter shall have a burden of not more than 0.005VA per phase, Max at
11 Amps.
vi. The meter shall accept a voltage input range from 20 up to 576 Volts Line
to Neural, and a range from 0 up to 721 Volts from Line to Line.
c. Power meter shall use a dual input method for current inputs. Method one shall
allow the CT to pass directly through the meter without any physical termination
on the meter, ensuring the meter cannot be a point of failure on the CT circuit.
The second method shall provide additional termination pass-through bars,
allowing the CT leads to be terminated on the meter. The meter must support
both termination methods.
i. Fault Current Withstand shall be 100 Amps for 10 seconds, 300 Amps for
3 seconds and 500 Amps for 1 second.
iii. All inputs and outputs shall be galvanically isolated to 2500 Volts AC.
ELECTRICITY METERING
26 2713 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iv. The meter shall accept current inputs of class 10: ( 0 to 10) a, 5 Amp
Nominal and class 2 (0 to 2) A, 1 A Nominal Secondary.
d. The meter shall have an accuracy of +/- 0.1% or better for volts and amps, and
0.2% for power and energy functions. The meters shall meet the accuracy
requirements of IEC687 (Class 0.2%) and ANSI C12.20 (Class 0.2%)
ii. The meter shall calculate RMS readings, sampling at over 400 samples
per cycle on all channels measured readings.
e. The meter shall provide a simultaneous voltage and current waveform recorder.
i. The meter shall be capable of recording 512 samples per cycle for a
voltage sag or swell or a current fault event.
ii. The meter shall provide pre- and post-even recording capability.
iii. The meter shall have a programmable sampling rate for the waveform
recorder.
iv. The meter shall have an advanced DSP design that allows power quality
triggers to be based on a 1 cycle updated RMS.
vi. The meter shall store waveform data in a first-in, first-out circular buffer to
insure that data is always being recorded.
f. The meter shall include a three-line, bright red, .56" LED display.
i. The meter shall fit in both DIN 92 mm and ANSI C39.1 round cut- outs.
ii. The meter must display a % of Load Bar on the front panel to provide an
analog feel. The % Load bar shall not have less than 10 segments.
g. The meter shall be available in transducer only version, which shall not include a
display.
i. The meter shall mount directly to a DIN rail and provide RS485 Modbus
or DNP 3.0 output.
ELECTRICITY METERING
26 2713 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
h. Power meter shall include virtual measurement upgrade packs, which shall allow
user to upgrade in field without removing installed meter.
1. Volts, Amps, kW, kVAR, PF, kVA, Freq, kWh, kVAh, kVARh, and
I/O expansion- V1.
iii. Meter shall be a traceable revenue meter, and shall contain a utility grade
test pulse allowing power providers to verify and confirm that the meter is
performing to its rated accuracy.
i. The meter shall include 2 independent communications ports on the back and
face plate with advanced features.
iii. The meter shall provide an optical IrDA port (through faceplate), as the
second communication port, which shall allow the unit to be set up and
programmed using a PDA or remote laptop without the need for a
communication cable.
iv. The meter shall have Pocket PC based software available for remote
programming and integration.
j. The meter shall provide user configured fixed window or rolling window demand.
This shall allow the user to set up the particular utility demand profile.
i. Readings for kW, kVAR, kVA and PF shall be calculated using utility
demand features.
ii. All other parameters shall offer max and min capability over the user
selectable averaging period.
ELECTRICITY METERING
26 2713 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Voltage shall provide an instantaneous max and min reading displaying
the highest surge and lowest sag seen by the meter.
iv. The Meter shall provide upgrade rate of 6 cycles for Watts, Var and VA.
All other parameters shall be 60 cycles.
k. The meter shall support power supply of 90 to 265 Volts AC and 100 to 370 Volts
DC. Universal AC/DC Supply shall be available and shall have burden of less
than 11VA.
l. The meter shall provide Limits Alarms and Control Capability as follows:
m. The meter shall have data-logging capability with the 2, 3, and 4 Megabyte
memory upgrade (Upgrade packs 2-6). The meter shall have a real-time clock
allow for time stamping of all the data in the meter when log events are created.
The meter with Upgrade packs 2-4 shall have six logs; the meter with Upgrade
packs 5 and 6 shall also have the Waveform Log:
i. The meter shall have three historical logs for trending profiles. Each log
shall be capable of being programmed with up to 64 parameters. The
user shall have the ability to allocate memory between the three
historical logs in order to increase or decrease the memory allotted to
each of the logs.
ii. The meter shall have a log for Limits Alarms. The Limits log shall provide
magnitude and duration of an event, time-stamp and log value. The log
must be capable of recording 2048 events.
iii. The meter shall have a log for System Events. The System Events log
shall record the following occurrences with a time-stamp: Demand
Resets, Password Requests, System Startup, Energy Resets, Log
Resets, Log Reads, Programmable Settings Changes.
iv. The meter shall have a log for I/O changes. The I/O Change log shall
provide a time-stamped record of any Relay Outputs and any Input Status
changes. The log must be capable of recording up to 2048 events.
v. The meter with Upgrade packs 5 and 6 shall have a log which is capable
of recording a waveform both when a user-programmed value goes out of
limit and when the value returns to within a limit.
ELECTRICITY METERING
26 2713 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
n. The meter shall have I/O expandability through two Option card slots on the
back.
i. The cards shall be capable of being installed in the field, without removing
the meter from installation.
ii. The meter shall auto-detect the presence of any I/O Option cards.
iii. The Option card slots shall accept I/O cards in all of the following formats:
100BaseT Ethernet Communication Card; Four Channel Bi-directional 0-
1mA Output Card; Four Channel 4-20mA Output Card; Two Relay
Outputs/2 Status Inputs Card; Four Pulse Output/4 Status Inputs Card;
Fiber Optic Card.
v. The Ethernet Option Card shall provide the meter with the 100BaseT
Ethernet functionality. The Ethernet Option card shall:
vi. The 1mAO Option Card shall provide the following features:
vii. The 20mAO Option Card shall provide the following features:
ELECTRICITY METERING
26 2713 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
viii. The Relay Output/Status Input Option Card shall provide the following
features:
ix. The Pulse Output/Digital Input Option Card shall provide the following
features:
4. Can function for manual relay control and limit based control (with
upgrade pack 4).
x. The Fiber Optic Option Card shall provide the following features:
1. Built in logic to mimic RS485 half- duplex bus, allowing the user to
daisy chain meters for low installation cost.
2. ST Terminated Option.
o. (o) The meter shall have transformer loss, line loss, and total substation loss
compensation.
i. Substation losses shall be programmable for Watts and VARs, and for
Ferris and copper losses.
ELECTRICITY METERING
26 2713 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
Shark 200 -50: 50 Hz -10: 10A -V1: -D2: 90- -X: None -X: None
Meter/Transducer System Secondary Multifunction 265 Volts
Meter only AC/DC
Shark 200T -60: 60 Hz -2: 2A -V2: Above & -D: 18-60 -INP100S -INP100S;
2 Megabytes Volts DC 100BaseT
Transducer System Secondary 100BaseT
Data- logging
Ethernet
Ethernet
memory
-FOSTS: -FOSTS:
Fiber Optic Fiber Optic
Output ST Output ST
Terminated Terminated
-FOVPS: -FOVPS:
Fiber Optic Fiber Optic
Output Output
Versatile Versatile
Link Link
Terminated Terminated
ELECTRICITY METERING
26 2713 - 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
ELECTRICITY METERING
26 2713 - 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for wiring devices. Specific
requirements are to be reviewed with the NU Project Manager and NU Chief Electrician
during the design phases of the project.
2. Design Considerations:
i. Where subject to physical abuse - use nylon type devices and plates.
Use in all dorms and housing facilities. Use stainless steel cover plates
elsewhere in laboratory spaces.
iii. Where subject to water spray, high humidity, acid fumes, etc., specify
corrosion resistant devices with in-use weatherproof cover plates.
b. Provide cleaning outlets in corridors and stairs at least every 40'. Provide
receptacles in corridors so that no point along the corridor is greater than 40 feet
from a receptacle. Corridor receptacles shall be on an independent circuit from
other rooms or equipment. Maximum of six receptacles per circuit. Light
switches and convenience receptacles shall be rated for 20 amperes.
c. Receptacles within six feet of sink, tub, shower, etc. shall be GFI type.
d. A 120 volt receptacle on essential power (red in color) shall be provided in each
mechanical and switchboard room. Provide emergency lighting in each
mechanical and switchboard room.
vi. Consult with project architect to match device color with facility finish
requirements.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for switches and disconnects.
Specific requirements are to be reviewed with the NU Project Manager and NU Chief
Electrician during the design phases of the project.
2. Design Considerations:
a. Switches shall be provided for disconnects and switching. Circuit breakers shall
not be used for switching.
d. Switches and disconnects used where the available fault current is higher than
10kA shall have fuses.
e. Motor disconnects located downstream from starters or VFDs will use auxiliary
contacts to open starter or e-stop VFD prior to the knife blades opening the
circuit when the handle is placed into the off position.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for engine generators and
transfer switches. Specific requirements are to be reviewed with the NU Project
Manager and NU Chief Electrician during the design phases of the project.
2. Design Considerations:
i. Exit signs.
e. Enclosures and silencers for outdoor generators are to be critical grade, sound
attenuating type.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for Uninterruptable Power
Supplies (UPS). Specific requirements are to be reviewed with the NU Project Manager
and NU Chief Electrician during the design phases of the project.
2. Design Considerations:
b. UPS systems are to use batteries for the DC source. Flywheels can be provided
as an alternate for systems supported by a generator.
d. UPS input is to create less than 5% THD from no load to full load.
f. UPS systems shall have the ability of connectivity to the device it is backing up or
IP to the software. Provide SCADA connections for monitoring.
END OF SECTION
DIVISION 26 – ELECTRICAL
1. General: This section outlines the general requirements for interior and exterior lighting.
Specific requirements are to be reviewed with the NU Project Manager and NU Chief
Electrician during the design phases of the project.
2. Design Considerations:
a. Light sources in interior areas shall be fluorescent with electronic ballasts (less
than 10% distortion in use), with T-8 lamps or compact fluorescent lamps.
Remote ballasts must be reviewed with the NU Project Manager and Chief
Electrician before installation.
i. LED lighting fixtures are acceptable for use based on review of the
application by the University. Lamps over 50,000 hours shall be LED.
b. High ceiling areas (spaces over 12 feet) in finished areas not subject to frequent
switching shall be metal halide (MH). High ceiling spaces in unfinished areas
shall be pulse start metal halide (PSMH) or fluorescent type.
e. Reflectors:
f. Electronic Ballasts:
ii. Output frequency shall be greater than 20KHZ with no detectable flicker.
iii. Provide constant light output over and above 10% operating voltage
range.
LIGHTING
26 5100 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
vii. Use program-rapid start for fixtures controlled by occupancy sensors, light
controller systems, or dimming controls.
g. Fluorescent Lamps:
i. Three foot and four foot lamps shall T8 diameter with a 75 CRI, medium
bi-pin base and 4100°K color temperature.
h. Exterior Lighting:
iii. Provide convenience outlet in exterior light poles. See appendix for
standard outdoor fixture specifications.
i. Electrical Rooms.
vi. Other areas identified by the owner as being hazardous when dark.
LIGHTING
26 5100 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
k. Time clocks or Lutron Quantum lighting control panels are to be used in open
areas or classrooms where after-hours sweep is required by the energy
conservation code or LEED. Local area override is to be provided for after-hours
operation.
l. Where electronic time clocks are specified, they shall be manufactured by Tork,
Paragon, Intermatic, or BRK or included in the lighting control.
m. Exterior lighting systems and lighting control shall be controlled by single photo
cell actuated contactors for large areas or across the line photo cell control for
individual luminaries. The lighting control system shall be dimmable or switched
all electrical lighting and day light weather through manual or automatic control of
light and shades. Systems shall easily integrate with SCADA. Provide
emergency lighting at points of discharge as required by authorities having
jurisdiction.
LIGHTING
26 5100 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
p. Lighting Fixtures:
iii. Flush and recessed fixtures installed in furred ceilings shall be provided
with junction boxes located at least 1 foot from fixture.
q. Corridor Lighting:
r. Emergency Lighting:
ii. Exit and directional lighting shall be on the emergency system. Exit signs
for the Evanston Campus shall be equipped with LED type lamps for
longer life. Exit signs for the Chicago Campus shall be Chicago approved
type.
LIGHTING
26 5100 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
vii. In buildings where generators and/or life safety equipment exists, the
design and construction shall connect to the existing systems.
s. Unfinished Areas:
ii. Panels and associated feeders for shell spaces will be sized to provide
adequate power for maximum future lighting requirements.
END OF SECTION
LIGHTING
26 5100 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
LIGHTING
26 5100 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 27 – COMMUNICATIONS
END OF SECTION
DIVISION 28 – SECURITY
2. Design Considerations:
a. Raceways:
c. Lightning Protection:
iv. Door security device power supplies are to have internal back-up
batteries. Refer to Section 28 1000 Access Control for power supply
requirements.
END OF SECTION
DIVISION 28 – SECURITY
1. General: This section outlines general requirements for security systems. Specific
requirements are to be reviewed with the Northwestern Project Manager during the
design phases of the project
2. Design Considerations:
a. Access control entry hardware, monitoring and control shall be selected by the
NU Physical Security Department.
c. Electrified mortise locks are the preferred locking mechanisms. Door hardware is
to be coordinated with Project Architect and NU Physical Security Director.
3. Equipment
a. System Controller:
b. Serial Multiplexer:
c. Door Controller:
ACCESS CONTROL
28 1000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Evanston Campus:
iv. Green and red LED indicator to signal acceptance or rejection of card.
e. Door Contacts:
g. Power Supplies:
i. General:
ACCESS CONTROL
28 1000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
a. Loss of power.
b. Tamper.
2. Model: PS-1.
1. Manufacturer: Alarm-SAF.
2. Model: 10036.
h. Conductors:
iv. All conductors shall be routed in metallic raceways when installed indoors.
i. Rough-In Diagrams: The following diagrams are for information and reference
only. Specific requirements shall be reviewed with the Northwestern Project
Manager.
ACCESS CONTROL
28 1000 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ACCESS CONTROL
28 1000 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
ACCESS CONTROL
28 1000 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
ACCESS CONTROL
28 1000 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 28 – SECURITY
1. General:
a. This section outlines general requirements for fire detection and alarm systems.
c. Review the Life safety Systems Checklist in the Appendix. Copies are available
from the Northwestern Project Manager.
2. Design Considerations:
a. General:
i. Fire alarm systems shall provide full and complete coverage per NFPA
and include mass notification with a connection to the NUPD system.
i. Most fire alarm requirements are contained within two separate sections
of Group 9, Chapter 15-16 of the City of Chicago Building Code. In
addition, careful research in other chapters pertaining to occupancy is
required to identify special fire alarm needs.
ii. On a general basis, two distinct types of fire alarm system requirements
exist: Class I and Class II and equipment must be City of Chicago
approved for use in the alarm system class being installed. Review and
approval of fire alarm plans usually includes both the Fire Prevention
Bureau and Electrical Inspection Bureau.
iii. In the Building Code, references to NFPA fire alarm and detection
standards covers a range of years from 1984 to 1993 requiring careful
coordination in the specifications. (Note: the example specification needs
considerable revision for use on a City of Chicago project.)
v. And there are special fire resistance requirements for initiating and
signaling circuit risers.
vi. There are other unique requirements that may not be specifically
contained in the Building Code but are encountered in the review
process.
a. The fire detection and alarm system (including the conduit) shall be a separate
bid item and not part of the general electrical contract for typical FMO projects.
b. The contractor responsible for installing the conduit, wiring and devices shall
have completed at least five similar fire alarm projects.
c. Training for University technicians must consist of more than a description of the
equipment and its operation. Tuition for two attendees at manufacturer
sponsored and taught service schools shall be included in the contract.
4. Spare Capacity:
a. The fire alarm control panel, and its back box enclosure, shall accommodate a
minimum of 25 percent additional zones for hardwire and 25 percent additional
initiating points for addressable systems.
c. For voice alert/speaker systems, speakers shall be designed with a tap setting
not to exceed 2 watts at any single speaker. In calculating spare circuit capacity,
all speakers shall be assumed being at their highest available power setting
except that 4 watts shall be the maximum required at any speaker in this
calculation.
5. Equipment:
c. Fire alarm control panels shall be located in a secure location having a minimum
1 hour fire resistance rated enclosure for any building. A 2 hour fire resistance
rated enclosure is required for major facilities having command centers or voice
alert. Rooms shall have clean conditioned air with a temperature range of 50 to
80 degrees F and without wide fluctuations in humidity. Floor space and wall
space shall provide room to install and maintain all systems and equipment
located within. At least three feet of clear space shall be provided in front of all
cabinets.
e. Fire alarm control panels and remote control modules shall not exceed 6 feet
above finished floor to the top of the cabinet. Annunciators shall not exceed 5.5
feet above finished floor to the top of the cabinet. This is to assure that
messages and controls can be readily accessed.
f. Voice alerting systems shall have a digitally synthesized recording (no tape
drives) and messages shall use female voices. The system shall use the
University's standard message and it must be reviewed and approved by the
University before recording. Finished voice messages shall be installed and
tested prior to building occupancy and final acceptance testing of the system.
g. System printers shall be full 80 column impact printers provided with a stand and
paper catch tray. After final acceptance testing of the system, the printer shall be
provided with a new ribbon and at least 1,000 sheets of continuous feed paper.
h. Duct type smoke detector should be limited to the return air side of fans and on
supply fans downstream of all filtering and conditioning equipment. These
detectors shall not cause a building wide fire alarm signal but will cause a trouble
supervisory signal on the fire alarm system. Means shall be provided for
bypassing these signals when the fan system is being operated in the smoke
control mode.
j. The fire alarm control panel will be connected by the University to the campus
wide central supervisory system. Requirements for this connection can be
obtained from Facilities Management Operations (FMO).
k. Door frame mounted combination smoke detectors and door holders are not
permitted in University buildings. Door frame mounted holders require special
University approval prior to their use.
l. Provide a minimum of two sets of keys to equipment locks and two sets of
special tools to access flow switches and tamper switches. These shall be
turned over to the Supervising Electrician during final acceptance testing.
m. Status lights shall be provided on fire alarm control panels to identify the smoke
control zone operation and the elevator recall. Other special functions shall also
have status lights.
n. Where voice alerting is used, provide a minimum of one back-up amplifier that
can be switched to take the place of any three primary amplifiers without
rewiring. Additional back-up amplifiers shall be provided on the ratio of one for
each three primary amplifiers.
o. Provide fault separation modules in large and complex systems to limit the
number of devices affected.
6. Design Considerations:
a. General: Review requirements with the latest version of the NU Design Checklist
for Life Safety Systems.
c. Zone smoke door closure by smoke control zones and/or by floor. Stairway door
closure and unlocking shall take place throughout the entire building upon fire
alarm signal.
d. Each laboratory suite/room over 500 square feet shall be provided with at least
one audio/visual alerting device and manual pull station. A visual alerting device
shall be installed in all public washrooms.
e. Electric powered magnetic door holders shall be 24 volt dc supplied from the fire
alarm system.
f. Wire nuts are not acceptable for joining wires. Either crimp connections or wire
terminal strips shall be used to join wires. Wire terminal strips shall be
permanently mounted inside junction boxes with wires neatly bundled and
arranged. Junction box cover is to be labeled “splice”.
ii. Smoke detectors shall be installed at the top of each stairway and
elevator shaft.
iii. Smoke detector(s) shall be installed in the room housing the main and
auxiliary fire alarm control panels, elevator machine room, telephone
rooms, main electrical switch gear room and computer rooms over 500
square feet in area.
iv. Smoke detectors installed for elevator recall and control will also activate
the building and/or zone alarm signals.
vi. Only double action type manual pull stations shall be specified.
viii. Each laboratory suite/room over 500 square feet shall be provided with a
manual pull station inside the suite/room at the entrance/exit door. This is
to assist in notification of emergencies.
h. Color Coding:
NOTES:
The lighter color shall always be used to indicate the positive wire.
Earth ground wires shall always be identified by a green wire with a
yellow stripe. These grounds are to be supplied and wire per
manufacturer's specifications. (Applies to both tables)
iii. The address of each initiating device shall be recorded in the fixed, non-
removable base as a minimum.
iv. The audio amplifiers shall be labeled as to each speaker zone and
channel being supplied.
v. Wiring:
Annunciator
#18 TSP FPLR
City Circuit
#14 Stranded
Door Control
#12 Stranded
Network RS232
#18 TSP FPLR
Communication RUI
#18 TSP
Fire Phone
#18 TSP FPLR
Audio Riser
#18 TSP FPLR
Audible
#12 THHN Stranded
Phone Riser
#18 TSP FPLR
Remote Test
#14 THHN Stranded
Remote LED
#14 Stranded
Addressable Alarm SLC
#18 TSP FPLR
Relay
#14 Stranded
Speaker
#18 TSP FPLR
Visual
#12 THHN Stranded
Initiating (Non-Addressable)
#14 THHN Stranded
7. Spare Parts:
a. The following spare parts list and quantities shall be used in the specification.
Printer Ribbons 4
b. The spare parts shall be turned over to Northwestern Supervising Electrician and
receipt acknowledging this shall be required before final payment to contractor.
a. NFPA Standard No. 72 provides guidance for conducting acceptance testing and
documentation of the results. It is critical that each device be fully tested on a
functional basis including the annunciation and operational interface with other
building functions. Where the project is phased or partial occupancy and
acceptance is made, full testing of the system must still be conducted prior to
final acceptance. In this case, a written work plan shall be developed by the
installing contractor and the design engineer and accepted by the University to
assure complete acceptance testing.
b. Acceptance test records shall include all of the information requested by NFPA
Standard No. 72, Figure 7-5.2.2. The contractor shall submit test record forms
prior to acceptance testing for review and comment by the University. Deficient
or lacking information shall be attached to the contractor's forms. Preliminary
test record submission shall be made for systems installed or tested in phases.
Final records shall be provided at the completion of testing.
c. As-built drawings shall be provided before acceptance of the work and final
payment. A reproducible set and four (4) copies are required. Submit a CD
ROM copy of all CAD files in addition to the drawings. File format shall be
suitable for use with AutoCad. Confirm the revision requirements with the
Northwestern University Project Manager.
f. The FACP room shall have the following document containers provided by the
fire alarm system vendor:
iv. Inspection certificates, service work tickets, etc. This box shall have a
recordable device for updates and program changes.
END OF SECTION
DIVISION 31 – EARTHWORK
1. General: This section includes general requirements for site clearing and removal of
existing above- and below-grade improvements as indicated and as necessary to
facilitate new construction, including the following:
3. Material Ownership: Except for stripped topsoil or other materials indicated to remain
NU’s property, cleared materials shall become Contractor's property and shall be legally
removed from the project site and legally disposed of.
a. Traffic: The City of Chicago and the City of Evanston have specific requirements
for traffic control and load limits. Minimize interference with adjoining roads,
streets, walks, and other adjacent occupied or used facilities during site-clearing
operations.
SITE CLEARING
31 1000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Utility Locator Service: Identify requirements for Contractor to notify utility locator
service for area where Project is located before site clearing.
5. Products:
a. Soil Materials: Obtain approved borrow soil materials off-site when satisfactory
soil materials are not available on-site.
ii. Place fill material in horizontal layers not exceeding a loose depth of 8
inches, and compact each layer to a density required for the proposed
condition.
SITE CLEARING
31 1000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Topsoil Stripping:
i. Remove sod and grass before stripping topsoil. Strip topsoil to whatever
depths are encountered in a manner to prevent intermingling with
underlying subsoil or other waste materials.
END OF SECTION
SITE CLEARING
31 1000 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
SITE CLEARING
31 1000 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 31 – EARTHWORK
1. General: This section includes minimum project requirements for earth moving, including
the following:
a. Preparing subgrades for walks, pavements, lawns and grasses and exterior
plants.
2. Definitions:
b. Initial Backfill: Backfill placed beside and over pipe in a trench, including
haunches to support sides of pipe.
d. Base Course: Course placed between the subbase course and hot-mix asphalt
paving.
e. Bedding Course: Course placed over the excavated subgrade in a trench before
laying pipe.
f. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.
g. Drainage Fill:
h. Course placed over the excavated subgrade before laying subdrainage pipe and
placed around and over the subdrainage pipe.
EARTH MOVING
31 2000 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
o. Subbase Course: Course placed between the subgrade and base course for
hot-mix asphalt pavement, or course placed between the subgrade and base
course for a cement concrete pavement or a cement concrete or hot-mix asphalt
walk.
3. Quality Assurance:
4. Project Conditions:
a. Existing Utilities: Contractor shall not interrupt utilities serving facilities occupied
by Owner or others unless permitted in writing by NU and then only after
arranging to provide temporary utility services according to requirements
indicated.
i. Notify NU not less than fourteen (14) days in advance of proposed utility
interruptions.
ii. Do not proceed with utility interruptions without NU’s written permission.
EARTH MOVING
31 2000 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
iii. Contractor shall contact utility-locator service (J.U.L.I.E.) for area where
Project is located before excavating. A private utility locating service may
be required for non-public utilities.
iv. Contractor shall demolish and completely remove from site existing
underground utilities indicated to be removed. Coordinate with utility
companies to shut off services if lines are active.
5. Products:
a. Soil Materials:
ii. Satisfactory Soils: ASTM D 2487 Soil Classification Groups GW, GP,
GM, GC, SC, SW, SP, ML, CL and SM, or a combination of these groups;
free of rock or gravel larger than 3 inches in any dimension, debris,
waste, frozen materials, vegetation, and other deleterious matter.
iii. Unsatisfactory Soils: Soil Classification Groups MH, CH, OL, OH, and PT
according to ASTM D 2487, or a combination of these groups.
Unsatisfactory soils also include satisfactory soils not maintained within 2
percent of optimum moisture content at time of compaction.
i. Where possible try to match NU sandy loam soil conditions with topsoil
re-use or importing similar soil structure.
ii. Topsoil shall be free of all deleterious material that may adversely affect
the use of the planted surface including any metal, wood, plastic, glass or
other manmade materials not intended specifically as a soil supplement.
iii. Topsoil shall be free of obnoxious weeds and invasive plants or other
undesirable organisms and disease-causing plant pathogens. Topsoil
shall be free of chemicals and pesticides, farm crop seeds, with
documentation on topsoil origin and soil testing.
iv. Topsoil particle sizes shall fall in the following ranges as percentages by
mass both separately and in combination:
EARTH MOVING
31 2000 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Geotextiles:
EARTH MOVING
31 2000 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
EARTH MOVING
31 2000 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Red: Electric.
ii. Paved and Building Slab Areas: At subgrade and at each compacted fill
and backfill layer, at least 1 test for every 3500 sq. ft. or less of paved
area or building slab, but in no case fewer than 2 tests.
iii. Trench Backfill: At each compacted initial and final backfill layer, at least
1 test for each 250 feet or less of trench length, but no fewer than 1 tests.
iv. When testing agency reports that subgrades, fills, or backfills have not
achieved degree of compaction specified, contractor shall scarify and
moisten or aerate, or remove and replace soil to depth required;
recompact and retest until specified compaction is obtained.
EARTH MOVING
31 2000 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
c. Proof-Rolling: Contractor shall proof-roll subgrade below the building slabs and
pavements with heavy pneumatic-tired equipment to identify soft pockets and
areas of excess yielding. Review requirements and additional compensation for
authorized additional excavation and replacement material with NU during the
design phase.
e. Storage of Soil Materials: Contractor shall stockpile borrow soil materials and
excavated satisfactory soil materials without intermixing. Contractor shall place,
grade, and shape stockpiles to drain surface water and cover to prevent
windblown dust. Contractor shall stockpile soil materials away from edge of
excavations. Do not store within drip line of remaining trees.
f. Protection:
END OF SECTION
EARTH MOVING
31 2000 - 7
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
EARTH MOVING
31 2000 - 8
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section includes general requirements for hot asphalt paving, including the
following:
f. Pavement-marking paint.
g. Traffic-calming devices.
2. Project Conditions:
d. Imprinted Asphalt Paving: Proceed with coating imprinted pavement only when
air temperature is at least 50 deg F and rising and will not drop below 50 deg F
within 8 hours of coating application. Proceed only if no precipitation is expected
within two hours after applying the final layer of coating.
ASPHALT PAVING
32 1216 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
3. Products:
a. Aggregates:
ii. Coarse Aggregate: ASTM D 692, sound; angular crushed stone, crushed
gravel.
v. Mineral Filler: ASTM D 242, rock or slag dust, hydraulic cement, or other
inert material.
b. Asphalt Materials:
iii. Tack Coat: IDOT SS-1, SS-1hP, CSS-1, CSS-1hP, emulsified asphalt or
cationic emulsified asphalt, slow curing, diluted in water, per Section 1032
of the Standard Specifications for Road and Bridge Construction and of
suitable grade and consistency for application.
ASPHALT PAVING
32 1216 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
f. Joint Sealant: ASTM D 6690 or AASHTO M 324 Type II or III Type II Type IV,
hot-applied, single-component, polymer-modified bituminous sealant.
i. Wheel Stops:
i. Locate sidewalks away from curbs to avoid the need for wheel stops.
ii. Top Coating: Epoxy-modified acrylic polymer blended with sand and
aggregate, formulated for exterior application on asphalt paving surfaces.
ASPHALT PAVING
32 1216 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
m. Mixes:
ii. Binder Course Mixture N50, IL-19.0, Surface Course Mixture N50, IL-
9.5,Mix “C” designed in accordance with Sections 1030 and Sections 406
and 407 of the Standard Specifications for Road and Bridge Construction
and the special provision, “Quality Control/Quality Assurance of
Bituminous Concrete Mixtures.”
5. Disposal: Except for material indicated to be recycled, remove excavated materials from
Project site and legally dispose of them in an EPA-approved landfill. Contractor shall not
allow milled materials to accumulate on-site.
END OF SECTION
ASPHALT PAVING
32 1216 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section includes general requirements for concrete paving, including the
following:
b. Parking lots.
d. Walkways.
2. Definitions:
3. Project Conditions:
a. ACI Publications: Comply with ACI 301, "Specification for Structural Concrete,"
unless modified by requirements in the Contract Documents.
4. Products:
a. Forms:
b. Steel Reinforcement:
ii. Epoxy-Coated Welded Wire Fabric: ASTM A 884, Class A, plain steel.
CONCRETE PAVING
32 1313 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
v. Joint Dowel Bars: Plain steel bars, ASTM A 615, Grade 60. Cut bars
true to length with ends square and free of burrs.
vi. Epoxy-Coated Joint Dowel Bars: ASTM A 775; with ASTM A 615,
Grade 60 , plain steel bars.
viii. Hook Bolts: ASTM A 307, Grade A, internally and externally threaded.
Design hook-bolt joint assembly to hold coupling against pavement form
and in position during concreting operations, and to permit removal
without damage to concrete or hook bolt.
ix. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing,
supporting, and fastening reinforcing bars, welded wire reinforcement,
and dowels in place. Manufacture bar supports according to CRSI's
"Manual of Standard Practice" from steel wire, plastic, or precast concrete
of greater compressive strength than concrete, and as follows:
c. Concrete Materials:
CONCRETE PAVING
32 1313 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
d. Curing Materials:
i. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute
or kenaf, weighing approximately 9 oz./sq. yd. dry.
vi. Concrete Sealer: Water based USEPA VOC compliant penetrating sealer
for concrete. Cured concrete to conform to ASTM C309.
e. Joint Filler: Two types of joint filler are listed below. Confirm use of sealant with
NU.
CONCRETE PAVING
32 1313 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
i. Types I and II, non-load bearing IV and V, load bearing, for bonding
hardened or freshly mixed concrete to hardened concrete.
i. Chemical Surface Retarder: Water-soluble, liquid-set retarder with color dye, for
horizontal concrete surface application, capable of temporarily delaying final
hardening of concrete to a depth of 1/8 to 1/4 inch.
k. Pavement Markings:
l. Wheel Stops: Two types of wheel stops are described below. Review
requirements with NU.
CONCRETE PAVING
32 1313 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
5. Concrete Mixtures:
a. Prepare design mixtures, proportioned according to ACI 301, for each type and
strength of normal-weight concrete determined by either laboratory trial mixes or
field experience.
6. Concrete Mixing:
CONCRETE PAVING
32 1313 - 5
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
b. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete
according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-
type batch machine mixer.
END OF SECTION
CONCRETE PAVING
32 1313 - 6
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General: This section includes general requirements for unit pavers set in aggregate
setting beds.
a. Precast concrete pavers and curbs shall be manufactured within 500 miles of
Project site from aggregates and cement extracted and manufactured within 500
miles of Project site.
b. Granite and natural stone curbs shall be manufactured within 500 miles of
Project site from materials extracted and manufactured within 500 miles of
Project site.
3. Warranty Requirements: Warranty shall include filling of paver joints 1 year after
installation at no additional cost.
4. Materials:
a. Review use of materials including precast concrete, clay pavers, and natural
stone with NU Project Manager.
5. Products:
END OF SECTION
UNIT PAVING
32 1400 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
UNIT PAVING
32 1400 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General:
2. Design Considerations:
b. Irrigation should contain rain-sensors, soil moisture sensors, solar clocks where
applicable and/or other sustainable friendly measures. When possible irrigation
water source should be derived from site water collection and re-use such as a
cistern.
c. Maximum velocity of water through piping and equipment = 5ft per second all
piping shall not exceed 75% of it rated GPM or psi capacity. Metallic pipe for any
exposed piping, PVC pipe Sch40 1-1/2-inch and smaller SDR21 for 2-inch and
larger 1-inch to 1-1/2-inch polyethylene may be used for lateral piping.
d. Rotary heads are only allowed on areas exceeding 16’ spacing the rotor must be
equipped with the stainless steel riser models for areas with head spacing up to
50’ Hunter I-20stainless for areas with head spacing exceeding 50’ or heavy
use areas such as sports fields or open activity areas use Toro 640 series.
e. Pop-up spray heads only. Use 4-inch pop-ups for turf areas and 12-inch pop-ups
for plantings.
f. The angel of trajectory of the sprinkler head should be calculated so that the
spray will be above the expected mature plant elevation use Rainbird 1800
series.
PLANTING IRRIGATION
32 8400 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
h. All sprinklers heads within a zone to operate at no more than a maximum loss of
3 psi from solenoid valve to farthest sprinkler head. The zone to have 25%
available capacity for higher GPM nozzles or additional sprinklers.
i. The spray of the sprinklers shall not intentionally reach or spray over walk or
pavement. Sprinkler heads spacing, only triangular or square sprinkler head
spacing is to be used (signal row spacing is not allowed) 8' maximum spacing for
landscape planting areas. Detail all pipe sizes from the point of connection and
all irrigation pipe sizes. Include a minimum of one quick coupler valve per 70'
hose can reach all areas.
k. Show all details of tap, meter, meter pit, RPZ valve, RPZ enclosure, blowout
connection and all other related details. Give a detailed description of
winterization procedures and spring start-up, the description shall be detailed so
Northwestern University can perform these procedures.
m. Sleeves: Pipes under walks or pavement to be sleeved with the sleeve shall be
2 times larger than the pipe size all wire shall be in a separate conduit or sleeve.
2. Project Considerations:
a. Submittals: Shop drawings and submittals are required shall be submitted and
approved prior to starting work. Design drawings and submittals are to be
prepared by an Illinois registered Professional Engineer or State of Illinois
licensed Plumbing Contractor detailing the entire layout of the planed irrigation
system.
ii. The design shall include calculations indicating gallons per minute,
pressure all water calculations are to be indicated at point of connection
solenoid valves, sprinkler heads and any other pertinent equipment.
PLANTING IRRIGATION
32 8400 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
END OF SECTION
PLANTING IRRIGATION
32 8400 - 3
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PLANTING IRRIGATION
32 8400 - 4
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
1. General:
2. Project Conditions:
END OF SECTION
1. General:
2. Project Conditions:
END OF SECTION
PLANTS
32 9300 - 1
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
PLANTS
32 9300 - 2
NORTHWESTERN UNIVERSITY
Technical Standards Issuance Date: 01.01.2014
DIVISION 33 – UTILITIES
d. Backwater valves.
e. Cleanouts.
g. Manholes.
2. Definitions:
4. Performance Requirements:
a. Pressure pipe pressure ratings: At least equal to system operating pressure, but
not less than 150 psig.
5. Project Conditions:
iii. Calking Materials: ASTM B 29, pure lead and oakum or hemp fiber.
i. Push-on-Joint Piping:
1. Pipe: ASTM D 3034, SDR 26 PVC Type PSM sewer pipe with
bell-and-spigot ends for gasketed joints.
1. Pipe: ASTM F 679, T-1 wall thickness, bell and spigot for
gasketed joints.
1. Pipe: AWWA C900, Class 150 Class 200 PVC pipe with bell-and-
spigot ends for gasketed joints.
2. Fittings: AWWA C900, Class 150 Class 200 PVC pipe with bell
ends.
h. Ductile-Iron Deflection Fittings: Compound coupling fitting with ball joint, flexing
section, gaskets, and restrained-joint ends complying with AWWA C110 or
AWWA C153. Include rating for 250-psig minimum working pressure and for up
to 15 degrees of deflection.
i. Backwater Valves:
ii. PVC Backwater Valves: Horizontal type; with PVC body, PVC removable
cover, and PVC swing check valve.
j. Cleanouts:
ii. PVC Cleanouts: PVC body with PVC threaded plug. Include PVC sewer
pipe fitting and riser to cleanout of same material as sewer piping.
v. Resilient Pipe Connectors: ASTM C 923 rubber boot, cast or fitted into
manhole walls, for each pipe connection. Boot shall result in a water tight
connection conforming to the performance requirements of ASTM C 443.
m. Manhole Frames and Covers: Include indented top design with lettering cast into
cover, using wording equivalent to "SANITARY SEWER."
i. Type: Solid.
o. External Chimney Seal: Rubber sleeves shall be extruded from a high grade
rubber compound meeting the applicable requirements of ASTM C923. Sleeves
shall be double or triple pleated with a minimum unexpanded vertical height of 8
inches, a minimum thickness of 3/16 inch, capable of expanding not less than 2
inches vertically when installed.
i. Screws, bolts and nuts: Stainless steel, ASTM F-593 and 594 Type 304.
ii. Expansion Bands shall be16 gauge thickness, 1-3/4 inches wide and
made of stainless steel meeting the requirements of ASTM A240, Type
304.
iii. Contractor shall replace defective piping using new materials, and repeat
inspections until defects are within allowances specified.
iv. Contractor shall reinspect and repeat procedure until results are
satisfactory.
b. Testing: Contractor shall test new piping systems, and parts of existing systems
that have been altered, extended, or repaired, for leaks and defects.
i. Contractor shall not enclose, cover, or put into service before inspection
and approval.
vii. Force Main: Perform hydrostatic test after thrust blocks, supports, and
anchors have hardened. Test at pressure not less than 1-1/2 times the
maximum system operating pressure, but not less than 150 psig.
ix. PVC Piping: Test according to AWWA M23, "Testing and Maintenance"
Chapter.
xi. Leaks and loss in test pressure constitute defects that must be repaired.
c. Replace leaking piping using new materials, and repeat testing until leakage is
within allowances specified.
END OF SECTION
DIVISION 33 – UTILITIES
2. Definitions:
4. Project Conditions:
5. Products:
i. Hub-and-Spigot, Cast-Iron Soil Pipe and Fittings: ASTM A 74, gray iron,
for gasketed joints.
ii. Ductile Iron Pipe and Fittings: AWWA C151, for push-on joints.
vi. PVC Pressure Pipe: AWWA C900/C905, Class 150, for gasketed joints.
1. PVC Sewer Pipe and Fittings, 15” and Smaller: ASTM D 3034,
SDR 26, gasketed joints.
viii. PVC Sewer Pipe and Fittings, 18”and Larger: ASTM F 679, T-1 wall
thickness, bell and spigot for gasketed joints.
xi. Reinforced-Concrete Arch Pipe: ASTM C 506, Class IV, for banded
joints.
xii. Reinforced-Concrete Elliptical Pipe: ASTM C 507, Class III, for banded
joints.
ii. Sleeve Materials: ASTM C 1173, rubber or elastomeric sleeve and band
assembly fabricated to mate with OD of pipes to be joined, for
nonpressure joints.
ii. Steps: Steel Reinforced Plastic or Cast Iron, individual steps. Wide
enough to allow worker to place both feet on one step and is designed to
prevent lateral slippage off step. Cast or anchor steps into sidewalls at
12- to 16-inch intervals. Omit steps if total depth from floor of manhole to
finished grade is less than 60 inches
iii. Manhole Frames and Covers: ASTM A 536, Grade 60-40-18, ductile-iron
castings designed for heavy-duty service. Include indented top design
with lettering "STORM SEWER" cast into cover.
iv. Resilient Pipe Connectors: ASTM C 923, cast or fitted into manhole
walls, for each pipe connection.
iii. Frames and Covers: ASTM A 536, Grade 60-40-18, ductile-iron castings
designed for heavy-duty service.
iv. Pipe Connectors: ASTM C 923, resilient, of size required, for each pipe
connecting to base section.
e. Stormwater Inlets:
ii. Gutter Inlets: Made with horizontal gutter opening, of materials and
dimensions according to utility standards. Include heavy-duty frames and
grates.
iii. Combination Inlets: Made with vertical curb and horizontal gutter
openings, of materials and dimensions according to utility standards.
Include heavy-duty frames and grates.
f. Cleanouts:
ii. PVC Cleanouts: PVC body with PVC threaded plug. Include PVC sewer
pipe fitting and riser to cleanout of same material as sewer piping.
iii. Gray-Iron Area Drains: ASME A112.21.1M, round, gray-iron body with
anchor flange and round, secured, gray-iron grate. Include bottom outlet
with inside calk or spigot connection, of sizes indicated. Use units with
top-loading classifications according to the following applications:
6. Identification:
a. Requirements include installing green warning tapes directly over piping and at
outside edges of underground structures.
ii. Use detectable warning tape over nonferrous piping and over edges of
underground structures.
a. Contractor shall clear interior of piping and structures of dirt and superfluous
material as work progresses. Maintain swab or drag in piping, and pull past each
joint as it is completed.
ii. Place plug in end of incomplete piping at end of day and when work
stops.
iii. Flush piping between manholes and other structures to remove collected
debris, if required by authorities having jurisdiction.
iii. Contractor shall replace defective piping using new materials, and repeat
inspections until defects are within allowances specified.
iv. Contractor shall reinspect and repeat procedure until results are
satisfactory.
c. Testing: Contractor shall test new piping systems, and parts of existing systems
that have been altered, extended, or repaired, for leaks and defects.
i. Contractor shall not enclose, cover, or put into service before inspection
and approval.
v. Contractor shall replace leaking piping using new materials, and repeat
testing until leakage is within allowances specified.
END OF SECTION
APPENDIX
A. Division 01 – General:
C. Division 26 – Electrical:
D. Division 27 – Communications:
CIVIL LAYERS
C-BLDG Built elements 2 Cont Black
C-COMM Site Communication/Telephone Poles, Boxes, Towers 2 Cont Black
C-ELEC Underground Electric 2 Hidden2 Black
C-FIRE Fire Protection-Underground Lines 3 Dashdot2 Black
C-IT IT Communication Lines-Underground 4 Cont Black
C-NGAS Natural Gas-Pipes, Manholes, Meters, Storage Tanks 3 Cont Black
C-PKNG Parking Lots 3 Cont Black
C-PROP Property Lines, Survey Benchmarks 1 Phantom2 Black
C-ROAD Roads 3 Cont Black
C-SDWK Sidewalks & Alleys 3 Cont Black
C-STEAM Steam & Condensate 3 Cont Black
C-SSWR Sanitary Sewers-Manholes, Pumping Stations 3 Cont Black
C-TOPO Contour Lines and Elevations 5 Cont Black
C-WATR Domestic Water-Underground Lines 3 Hidden2 Black
C-TUNL Underground Tunnel 3 Cont Black
Page 1 of 2
ELECTRICAL LAYERS
E-COMM Telephone, Communication Outlets 3 Cont Black
E-CTRL Electric Control Systems 3 Cont Black
E-FIRE Fire Alarm, Fire Extinguishers 3 Cont Black
E-LITE Lighting 3 Hidden2 Black
E-LTNG Lightning Protection System 3 Cont Black
E-POWR Power 3 Hidden2 Black
E-SERT Security 3 Cont Black
E-SITE-UNDR Underground Electrical lines 3 Hidden2 Black
FIRE PROTECTION
F-PROT Fire System 3 Cont Black
LANDSCAPE LAYERS
L-IRRG Irrigation Systems 2 Hidden2 Black
L-PLNT Plant & Landscape Materials 151*** Cont Black
L-PLNT-BEDS Rock, bark and Other Landscaping Beds 3 Cont Black
L-PLNT-TURF Lawn Areas 3 Cont Black
L-SITE Site elements 2 Cont Black
L-SITE-FURN Site Furnishings 2 Cont Black
L-SITE-LITE Exterior Site Lighting 3 Cont Black
L-SITE-REC Athletic and Recreational Fields 4 Cont Black
L-SITE-SIGN Signage and Donor Info 3 Cont Black
L-WALK Walks and Steps 3 Cont Black
MECHANICAL LAYERS
M-CONT Controls & Instrumentations 3 Cont Black
M-DUST Dust & Fume Collection Sys (and Riser Diagram) 3 Cont Black
M-ELHT-EQPM Electric Heat Equipment (and Riser Diagram) 3 Cont Black
M-HVAC HVAC System 3 Cont Black
M-MDGS Medical Gas Systems 3 Hidden2 Black
PLUMBING LAYERS
P-FIXT Plumbing Fixtures 5 Cont Black
STRUCTURAL LAYERS
S-GRID Column Grid 4 Hidden Black
* denotes that layer prints in color, otherwise, all layers print as black (see gradient note below)
** denotes that the plotted color is defined by the FM Space program
***L-PLNT-Color 4 revised to 151 because it read too dark. (revised July 20 by Dana)
*** A-AREA-IDEN - Color #40 is set by FM Space. Change color in AutoCAD to color #7 (white) (revised 29 April 2004)
***A-FLOR-TPTN-Color #4 changed to 151, read too dark for bathrooms, (revised July 21 by Dana)
Gradient Note: Color numbers 1-5 denote a gradient from darkest (1) to lightest (5) when plotstyle "NU plotstyle 1.ctb" is
used. See document R:\CAD Layer Documentation\NU Using Color.dwg for notes about plotted colors and
lineweights.
Page 2 of 2
NORTHWESTERN UNIVERSITY
Appendix A2 – Interior Finishes Issuance Date: 01.01.2014
The following is a summary of recommended interior finishes for the most common space types. Review project specific requirements with the NU
Project Manager. Review requirements for specialty spaces including auditoriums, research labs, residential spaces, and food service with the NU
Manager.
Entrances / Vestibules High Volume Traffic Review options with NU Review options with NU Acrylic latex paint Gypsum ceiling board;
Project Manager Project Manager
Slip Resistance Low VOC Review alternatives with
NU Project Manager
Walk-off mats Satin Finish
Acoustic Considerations Review alternatives with
NU Project Manager
STC 45-50 Separation
Lobbies High Volume Traffic Review options with NU Review options with NU Review options with NU Review options with NU
Project Manager Project Manager Project Manager Project Manager
Slip Resistance
Acoustic Considerations
STC 45-50 Separation
Corridors High Volume Traffic Resilient tile or sheet; 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
Slip Resistance Patterned carpet Low VOC
9/16-inch suspended
Acoustic Considerations Satin Finish
ceiling grid
STC 50 Separation
Acoustic ceiling panels
0.65 NRC / 0.85 LRV
Stairways High Volume Traffic Concrete or terrazzo stair Review options with NU Epoxy paint Suspended acoustic ceiling
treads Project Manager system
Slip Resistance Low VOC
Review alternatives with 9/16-inch suspended
Acoustic Considerations Eggshell Finish
NU Project Manager ceiling grid
STC 45-50 Separation Wall protection
Acoustic ceiling panels
0.65 NRC / 0.85 LRV
Page - 1
NORTHWESTERN UNIVERSITY
Appendix A2 – Interior Finishes Issuance Date: 01.01.2014
Classrooms Medium Volume Traffic Resilient tile or sheet 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Low VOC
9/16-inch suspended
STC 50 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Computer Labs Medium Volume Traffic Resilient tile or sheet; 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Patterned carpet Low VOC
9/16-inch suspended
STC 50 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Labs – Dry Medium Volume Traffic Resilient sheet; 4-inch high rubber; Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Epoxy Integral epoxy wall base Low VOC
9/16-inch suspended
STC 45-50 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Labs – Wet Medium Volume Traffic Resilient sheet; 4-inch high rubber; Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Epoxy Integral epoxy wall base Low VOC
9/16-inch suspended
STC 45-50 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Slip Resistance / Spills /
Chemical Staining
Page - 2
NORTHWESTERN UNIVERSITY
Appendix A2 – Interior Finishes Issuance Date: 01.01.2014
Offices Low Volume Traffic Patterned carpet 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
STC 45-50 Separation Low VOC
9/16-inch suspended
Dimmable / Controllable Satin Finish
ceiling grid
Lighting
Acoustic ceiling panels
0.65 NRC / 0.85 LRV
Conference Room Low Volume Traffic Patterned carpet 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Low VOC
9/16-inch suspended
STC 50-55 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Audio/Visual Systems
Copy Room Medium Volume Traffic Resilient tile or sheet; 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
Acoustic Considerations Patterned carpet Low VOC
9/16-inch suspended
STC 45-50 Separation Satin Finish
ceiling grid
Dimmable / Controllable
Acoustic ceiling panels
Lighting
0.65 NRC / 0.85 LRV
Chemical Staining
Storage Room Low Volume Traffic Resilient tile or sheet; 4-inch high rubber Acrylic latex paint Suspended acoustic ceiling
system
STC 50 Separation Patterned carpet Low VOC
9/16-inch suspended
Built-in shelving vs. Satin Finish
ceiling grid
furniture
Acoustic ceiling panels
0.65 NRC / 0.85 LRV
Page - 3
NORTHWESTERN UNIVERSITY
Appendix A2 – Interior Finishes Issuance Date: 01.01.2014
Public Restroom High Volume Traffic Ceramic Tile; Ceramic Tile; Ceramic Tile; Gypsum ceiling board;
STC 50 Separation Porcelain Tile; Porcelain Tile; Porcelain Tile; Suspended acoustic ceiling
system
Slip Resistance / Spills Terrazzo; Terrazzo;
9/16-inch suspended
ceiling grid
Acoustic / moisture
resistant ceiling panels
0.65 NRC / 0.85 LRV
Janitors Closet Low Volume Traffic Sealed concrete; 4-inch high rubber Epoxy paint Suspended acoustic ceiling
system
STC 50 Separation Resilient tile or sheet Low VOC
9/16-inch suspended
Slip Resistance / Spills / Eggshell Finish
ceiling grid
Chemical Staining
Wall protection
Acoustic ceiling panels
0.65 NRC / 0.85 LRV
Mechanical / Electrical Low Volume Traffic Sealed concrete 4-inch high rubber Epoxy paint Exposed construction,
Rooms painted
STC 50 Separation Low VOC
Review specific Eggshell Finish
requirements in Technical
Standards
Page - 4
NORTHWESTERN UNIVERSITY
Design checklist and guidance to Life Safety Systems
(10-Feb 2014)
1. Building Name:__________________________________
2. Building Address:_____________________
6. Building height:____________________
10. Does the building have a full sprinkler system? YES NO PARTIAL
1. Circle one:
A. New construction
B. Demolition
C. Remodel (cosmetic)
D. Modest renovation
E. Renovation (major room/system modifications
1
2. What rooms of the existing building are involved? (list or provide plan)
______________________________________________________________
10. Are there any smoke evacuation systems (atriums) in the project? YES NO
11. Is any existing gas detection system getting modified? YES NO N/A
14. Are any fossil fuels being used in the project area? YES NO
16. Will fire department connections or fire hydrants be changed for this project?
YES NO N/A
17. Are there adjacent occupied buildings within 30 feet of the new building?
YES NO N/A
18. Are the areas adjacent to the renovation occupied? YES NO N/A
19. What is the rating of the construction zone boundary walls? 1hr 2hr NONE
20. Will the HVAC system be turned off in the construction zone? YES NO
21. Are the adjacent and vertically adjacent FA zone strobes visible and do they
need to be synched to the renovation area? YES NO
2
22. Will gas or diesel equipment be used adjacent to occupied buildings?
(Provide equipment scrubbers and carbon filters in AHU’s if YES) YES NO
5. Does the FA system have central station voice alert capabilities? YES NO
13. The existing FA circuits for the construction area run through a junction box
located in room ____________________.
14. For non-battery powered systems, is there enough EM power for the EM lighting
in the renovated space? YES NO
1. What is the percentage of new or renovated space to the total square feet in the
building? ___________
3
3. How much longer will the existing FA system model be supported by the
manufacturer? _________________
FA Bidding Guidance:
(The option taken below will be stated in the drawing notes)
5. Where existing systems are used or modified, a predesign walk through will be
scheduled between the existing FA manufacturer, Risk Management and the
Electrical Shop.
1. A building permit is required when a project area changes use, changes the exit
path or affects a life Safety system.
4
2. The new or renovated area must be designed in accordance with IBC 2012, the
Illinois Accessibility Code, 2010 NFPA 72 and 2010 NFPA 13.
3. An alarm or sprinkler permit is required for any modification to the life safety
system. The NU Electrical Shop and Risk Management must review the drawings
prior to submission to the City.
6. Only one safety system (FA or FS) can be shut-down at a time in occupied
structures unless a fire watch plan is pre-approved by the Fire Marshall.
7. Modifying or adding less than 20 sprinkler heads does not require a hydro test
(visual test is required to clear permit).
8. All final room, area of rescue assistance, stair level of exit, and standard exiting
signage including Braille where required must be installed prior to the TCO
inspection.
11. Fire hose stations must have pressure reducing valves with 2.5”x 1.5” NST
reducers.
12. All student residence halls shall have NFPA 72 and NFPA 13 full and complete
coverage.
15. Each building will have a Knox box with all building keys at the front entrance and
other locations requested by EFD.
16. New structures and major renovation projects larger than 5,000 square feet shall
have a sprinkler system installed. The sprinkler requirement for minor renovation
projects of this size shall be reviewed individually by EFD.
5
17. An outside line accessible phone shall be provided in each fire command center.
Fire command centers required by code shall be 200 square feet and have a
minimum dimension of 10 feet.
18. Provide a lighted concrete pad and outside strobe over the STORZ type building
Fire Department Connection.
19. All building exits shall have a paved illuminated path to a public way.
20. Audible devices shall provide a minimum sound pressure level of 15 decibels
above ambient noise in all areas of any building (70 dba minimum or 15 dba
above ambient at the pillow in residential occupancies with the door shut). The
maximum sound pressure level is 110 decibels.
21. It should be noted that upon completion of Fire Alarm hardware modifications
and/or programming modifications, a FA test of at least 10% of the existing
unmodified system will have to be performed in addition to the complete project
area as required by the code.
22. Temporary winter heating propane tanks must be kept 25 feet away from any
building. Gas supply hoses must be kept off of the floor or ground. (requires site
approval from EFD)
23. ABC rated fire extinguishers greater than or equal to Classification 10A: 60B:C
shall be placed at a maximum travel distance of 75 feet in occupied spaces and
50 feet in construction areas.
24. All doors on hold opens will be released and closed and any stairway door shall
be unlocked throughout the entire building upon fire alarm signal.
25. Smoke detectors shall be installed at the top of each stairway and elevator shaft.
27. Smoke detectors installed for elevator recall and control will also activate the
building and/or zone alarm signals.
28. During a full fire alarm, silencing the alarm panel shall not turn off the visual
alarm devices (strobes) in the building or at the exterior strobe for the Fire
Department connection.
29. All visible visual devices shall be synchronized. This may require older strobes
on multiple floors to be replaced.
6
Northwestern University General Requirements (Synopsis)
(include in design drawings as notes)
1. Hot work permits are managed through the NU Facilities Management Shops.
2. Risk Management shall inspect the open ceiling prior to the City inspection.
3. Existing rated walls adjacent to the construction zone shall be fire caulked.
4. Existing non rated walls adjacent to the construction zone shall be caulked to
prevent smoke migration.
7. Combination safety shower/eye washes shall comply with ANSI code Z358.1
8. When required at the level of discharge on an exit stair, stair barriers (gate) shall
be 42” high
9. Stairs and elevator cabs shall be numbered and labeled both inside and out.
10. Security cameras shall be placed at all exits and large occupancy areas.
2. Contact the Electrical Shop for the approved list of fire alarm shop drawing
symbols.
3. Offices shall be assumed to have two occupants and require a visual device.
4. New construction shall be designed with voice capable devices for mass
notification direct from University Police. This requires a fiber optic cable
connection between the FA panel and data closet and include the programming
to interface with the NUPD system.
7
8. "T-tapping" of intelligent (addressable) fire alarm initiating circuits is not
permitted.
9. Any new fire alarm control panel, and its back box enclosure, shall accommodate
a minimum of 25 percent additional zones for hardwire and 25 percent additional
initiating points for addressable systems.
10. For non-code required Fire Command Centers, fire alarm control panels shall be
located in a secure location having a minimum one hour fire resistance rated
enclosure for any building. A two hour fire resistance rated enclosure is required
for major facilities having command centers or voice alert. Rooms shall have
clean conditioned air with a temperature range of 50 to 80 degrees F and without
wide fluctuations in humidity. Floor space and wall space shall provide room to
install and maintain all systems and equipment located within. At least three feet
of clear space shall be provided in front of all cabinets.
11. Any new fire alarm control panels will be connected by the University to the
campus wide central ADT supervisory system. New ADT installations require
both analog telephone and standard data connections directly adjacent to the
ADT panel.
12. Smoke detectors, manual pull stations and heat detectors may be combined on
the same addressable zone. Flow switches, valve tamper switches, and duct
smoke detectors shall each be on separate zones.
13. Each laboratory suite/room over 500 square feet shall be provided with at least
one audio/visual alerting device and one manual pull station at the exit.
15. Electric powered magnetic door holders shall be supplied with24 volt dc from the
fire alarm system.
16. Wire nuts are not acceptable for joining wires. Either crimp connections or wire
terminal strips shall be used to join wires. Wire terminal strips shall be
permanently mounted inside junction boxes with wires neatly bundled and
arranged.
17. .Smoke detector(s) shall be installed in the room housing the main and auxiliary
fire alarm control panels, elevator machine room, telephone rooms, main
electrical switch gear room and computer rooms over 500 square feet in area.
18. .Fixed temperature 195 degree heat detectors will be installed in sheltered
outside electrical vaults and emergency generator rooms.
8
19. .Residential buildings will have hard wired single station smoke detectors in the
rooms with system connected photoelectric type smoke detectors in the
corridors.
20. . Rate-of-rise heat detectors shall be provided in Janitor's closets with sinks.
21. Conduit for the alarm system will be a minimum of ¾” and be pre-painted red for
concealed conditions. In exposed areas, the conduit shall be site painted to
match the back ground color with only the junction box covers being painted red.
22. Conduits shall use only compression type connectors and be sized for a
maximum 30% fill in new or renovation projects.
23. All wiring shall be color coded as to function as stated in the separate
Northwestern University Design Standards book. Color codes shall be
continuous from the fire alarm control panel to and through the last device.
Initiating loops on addressable systems are an exception to the requirements.
24. Provide a Minimum 14 AWG stranded wire for all addressable circuits.
26. The lighter color shall always be used to indicate the positive wire. Earth ground
wires shall always be identified by a green wire with a yellow stripe. These
grounds are to be supplied and wire per manufacturer's specifications.
27. .Tags on wiring shall be of a permanent means and shall be subject to University
approval. Stick-on wire tags are not acceptable as a means of permanent
marking.
28. .The address of each initiating device shall be recorded on the fixed, non-
removable base.
29. .The audio amplifiers shall be labeled as to each speaker zone and channel
being supplied.
30. All electrical equipment rooms shall have combination heat/smoke detector
devices installed in them.
32. When making general announcements, strobes shall flash throughout the
structure.
9
33. Flow switches shall be replaced and re-timed of all as a part of all fire alarm
replacement projects and whenever an individual FS zone is more than 50%
reconfigured.
34. Smoke detectors inside the construction zone boundary and any other adjacent
areas shall be changed temporarily to heat detectors for the duration of the
construction period.
35. Fire alarm shut down and testing procedures are to be included in the section 01-
5000 and 01-1000 sections of the specifications.
36. In addition to regular exit signs, low level exit signs shall be considered for all
residential buildings.
1. All projects will be reviewed with the Building Department and the Fire Prevention
Bureau at the schematic design stage.
3. Temporary FA system layout for renovations during the construction period will
be designed or sketched by the existing FA manufacturer or general contractor. It
is best if this sketch can be included in the renovation design drawings for permit.
If it is not in the bid package, the sketch will be reviewed and approved by both
the NU Electrical Shop and Risk Management. Upon approval, the sketch will be
forwarded to EFD for approval. The temporary system will be tested by the
Electrical Shop and witnessed by Risk Management. Once the temporary system
layout which may include fire extinguishers, mast mounted pull stations,
audio/visual devices and heat detectors (may be similar to the air wired “safety
station” below) is tested the existing FA and FS systems can be taken out of
service. The temporary system must be active until the final FA and FS systems
have been tested and approved. The Electrical Shop will confirm the removal of
the temporary system with a copy to EFD.
10
Testing Requirements
Special noise limiting testing precautions must be taken in and around residential
spaces, CCM areas, classroom schedules and clinic schedules.
Operational test
11
Fire Alarm
• Fire Alarm devices - manual pulls, strobes, horns, smokes, heats, etc.
o Strobes have to be synchronized
o Doors on magnetic hold opens work properly
o Devices report correctly to the FA panel and are labeled with correct room ID's
o Main panel talks to the ADT panel
o ADT panel talks to University police
Electrical
• Power drop
o Transfer switches
o Emergency lighting
o Exit lights
Communications
Area of rescue
EFD radio coverage
Oxygen Depletion Alarm
Test connection to ADT
Atriums
Smoke Evacuation HVAC system
o Full functional test to see If the system does what Is designed to do
Fire Alarm activation
Devices - beam detectors, smoke detectors, dampers
Pre-action system
Hot smoke test
General
Fire Shutter operation
Fire extinguishers tags
Final Room Signage
Rated Doors latch and close
12
Safety Station
This is an example of a temporary fire alarm “Safety Station”. These stations will be
placed at a rate of not less than one for every 2,500 square feet of renovation area.
13
NU DDC Standards
Table of Contents
Attributes shall be separated by “_” and will go from the building name (four letter
abbreviation) down to point type (ending in _STP, _CMD, etc where applicable). Equipment tags
shall not contain “-“or “/”, and shall be double-digits (i.e. AHU-1 is AHU01 in point name).
The naming convention shall be slightly modified depending on if the point is for a piece of
equipment, virtual point, meter, etc
Examples:
CAMPUS_BUILDING_EQUIPMENTTAG_POINTIDENTIFIER_POINTTYPE
E_COOK_AHU01_DA_TMP_STPT
E_COOK_AHU01_VAV020100:XXX
VAV Box point names shall include AHU tag serving the VAV box (or EF tag for exhaust VAV
boxes)
FOR VAV’S THE FIRST TWO DIGITS AFTER “VAV” WILL REPRESENT THE FLR NUMBER,
FOLLOWED BY A FOUR DIGIT ROOM NUMBER. WHERE MORE THAN ONE VAV BOX SERVE A
SINGLE ROOM THE VAV TAG SHALL END IN “A”, “B”, “C”, ETC FOR EACH BOX. WHERE A VAV
BOX SERVES MULTIPLE ROOMS, THE ROOM NUMBER SHALL BE THE LOCATION OF THE
THERMOSTAT.
Will all equipment tags other than VAVs be two digit number (i.e. AHU01, CHLR02, etc)?
DESCRIPTION ABBREVIATION
Building Abbreviations
Chicago Campus
P102 Chestnut Parking Garage, E-Lot 275 E Chestnut ELOT
P100 Huron Parking Lot, C-Lot 222 E Huron CLOT
P101 Erie Parking Lot, D-Lot 321 E Erie DLOT
8816 Rubloff 375 E Chicago RUBL
8798 Gary Law Library 357 E Chicago GARY
8796 Levy Mayer 357 E Chicago LVMY
8797 McCormick Hall 350 E Superior MCMK
8795 Wieboldt 340 E Superior WBLT
8794 Searle 320 E Superior SRLE
8793 Morton 310 E Superior MORT
8792 Ward 303 E Chicago WARD
8791 Tarry 300 E Superior TARY
8602 Abbott 710 N Lake Shore ABBT
0511 Heating Plant 410 E Huron CCUP
8846 Lurie 303 E Superior LURE
8799 Olson 240 E Huron OLSN
Alarm Levels
Alarm message shall include timestamp, type of alarm, full point name, and value of point
(including units) causing alarm.
Alarm Class
Link users to alarm type acknowledgement
Alarm Class (in order of least to Notified User Group Alarm Routing
most critical)
Alert DDC Technician Logfile on server
Non-critical DDC Technician Console
Critical* DDC Technician, DDC Foreman E-mail, Pager, and Console
Emergency* DDC Technician, DDC Foreman E-mail, Pager, and Console
Nuclear* DDC Technician, DDC Foreman, E-mail, Pager, and Console
Facilities Director
*Critical, Emergency, and Nuclear alarms shall pop-up on any screen the user is logged into
AHU Trends
Description Trend Interval
Discharge Air Temperature
Mixed Air Temperature
Return Air Temperature
Exhaust Air Temperature
Return Air Humidity
Discharge Air Humidity
10 min., Boolean points shall be COV
Damper Commands
Duct Static
Fan Speed
Valve Position Command
Valve Position Feedback (if available)
Coil Entering/Leaving Water Temperature
Occupied/Unoccupied Mode
Fan Status COV
Heating Coil Pump Status
VAV Trends
Description Trend Interval
Zone Temperature
Airflow
Airflow Setpoint
Damper Position 30 min., Boolean points shall be COV
Perimeter Valve Position
Reheat Valve Position
Leaving Air Temperature
Occupied/Unoccupied Mode COV
Boiler Trends
Description Trend Interval
Boiler HWS Temperature
Boiler HWR Temperature
System HWS Temperature
System HWR Temperature
HWS Temperature Setpoint
10 min., Boolean points shall be COV
Boiler % Fire or High/Low Fire (where
applicable)
System HWS Flow (GPM)
3-way Mixing Valve Position
HW Pump Speed
System Differential Pressure COV
NU Home Screen (Opening screen with picture of NU Campus and links to Evanston,
Chicago, and Off-Campus)
o Evanston Campus (points beginning with “E”, “F”, “S”, and “H”)
List of buildings by type (Science, Academic, Athletic, Housing, Fraternity,
Sorority, Utilities)
Individual Building Home Screen (Dashboard for: instantaneous
meter data, alarm statuses, outside air temp/humidity/enthalpy)
o Floor Plan Graphic
Detailed Floor Plan Graphic
Dynamic space temperature
Occupancy Status (where applicable)
Link to VAV graphic
o Equipment Graphics (boilers, chillers, converters, AHUs,
etc.)
o Detailed Meter Graphic
o AHU status table (valve positions, discharge temps,
damper positions, fan speeds, etc.)
o VAV status table(s) (valve position, damper position,
airflow, discharge air temp)
o “Other” Graphics
Misc. equipment
Utilities
o Evanston CUP Home Screen (status only)
o System Meters Screen
o One-line diagrams (CHW, Steam, Condensate, etc)
o Chicago Campus (points beginning with “C”)
List of buildings by type (FSM, Law, Academic, Utilities)
Individual Building Home Screen (Dashboard for: instantaneous
meter data, alarm statuses, outside air temp/humidity/enthalpy)
o Floor Plan Graphic
Detailed Floor Plan Graphic
Dynamic space temperature
Occupancy Status (where applicable)
Link to VAV graphic
o Equipment Graphics (boilers, chillers, converters, AHUs,
etc.)
o Detailed Meter Graphic
o AHU status table (valve positions, discharge temps,
damper positions, fan speeds, etc.)
o VAV status table(s) (valve position, damper position,
airflow, discharge air temp)
o “Other” Graphics
Misc. equipment
Formatting
The default font for words in graphics shall be Tahoma. The minimum font size shall be
12 pt.
Graphic background color shall not be white/shall be lighter color to contrast graphics
(coordinate with Owner)
Commandable points shall have a background color (rather than transparent); non-
commandable points shall be transparent
Any points in override mode shall appear in different color on the graphic (coordinate
with Owner)
At campus-level screens, display status of campus-wide emergency fan shut-down,
chiller plant load shedding program, power loss (via “pop-up” alarm status)
Piping shall be color-coded
o HWS: bright red
o HWR: darker red
o CHWS: bright blue
o CHWR: darker blue
o Steam: white
o Condensate: orange
o CWS: bright green
o CWR: darker green
Graphics shall be designed for screen resolution of 1280x800 (most commonly issued
laptop in FM). Useable graphic area will be smaller due to the space needed for the
graphic header, upper window bar, and left navigation tree. See below for
recommended maximum pixels for graphic header, upper window bar, tabs, and left
navigation tree:
Future graphics: graphic for tablets shall be designed using HTML, not Java
Setpoint the operator can change should appear as a button (defined by user access)
Main header – top of screen (banner)
o NU logo
o OA conditions (temp, %RH, enthalpy)
o Building Name/Equipment tag/Plant description/Service/Location (where
applicable) – located center of banner
o Standard Drop-down menu to links
Link to NU BAS home screen
Link to NU Campus home screens
Link to NU Building abbreviations
Link to NU Std. Point Names
o Secondary Drop-down menu (personalized to user)
All setpoints shall be located in upper right corner
All alarm points shall be shown on graphic next to associated device (freeze, hi-static,
smoke detector)
Units shall be shown next to all values suing the Standard Units outlined earlier in this
document
All points being trended (per Trend Standards) shall have small graphical image of a line
chart next to point value that is a button linking the user to 24-hr trends for that point.
Descriptions for points will be typed into background, similar to JCI graphic
All equipment graphics (including terminal equipment) shall include a link to:
o Sequence of Operation in .pdf format
o Equipment O&M manuals in .pdf format
o Wiring diagram and parts list in .pdf format
Piping graphics shall be 2D, not isometric
NO VENDOR LOGOS
User shall have ability to leave text notes on graphic
Graphic shall display correct type of equipment (centrifugal chiller vs screw chiller,
counter-flow vs. cross-flow cooling tower, inline vs. base-mounted pump, etc)
Equipment with VFDs shall have VFD button on graphic that links user to VFD table
showing information available from VFD via BACNET. The VFD table shall include the
following parameters:
The NU home screen graphic will be similar to the existing Siemen’s NU home screen graphic
shown above. The NU home screen graphic will include links to Evanston, Chicago, and Off-
campus graphics that each have a list of the buildings associated with that campus.
1. The Evanston home screen graphic shall have alphabetical lists of buildings by the
following building types: Science, Academic, Athletic, Housing, Fraternity, Sorority,
Utilities
2. The Chicago home screen graphic shall have alphabetical lists of buildings by the
following building types: FSM, Law School, Academic, Utilities
3. The Off-campus building home screen shall have a single alphabetical list of all off-
campus buildings
Individual building’s home screen graphics will be similar to Norris’s existing home screen graphic. Per
the graphic hierarchy, there shall be links to:
The building home screen graphic shall include a dashboard showing current utility meter
readings for that building, along with current outside air temperature/humidity conditions. The
graphic shall include a picture of the building, and display the address of the building.
Overall floor plan shall be color-coded/hatched by AHU zones (see Figure 3 below).
There shall be a legend with a list of the AHU tags and associated color.
If user clicks on the AHU tag (in the legend), it shall route them to that AHU graphic. If
user clicks on AHU region in floor plan it shall take them to detailed floor plan (see
Figure 4 on pg. 26) of that AHU service area.
If area served by an AHU is large and must be split up into several detailed floor plan
graphics, then all zones served shall remain one color, but there shall be a boundary
(showing the detailed floor plan graphic boundary) that highlights when the user places
their mouse in the zones that link to a given detailed floor plan graphic.
Link to as-built floor plan of ductwork/piping
The above floor plan graphic example shows AHU service zones color-coded by AHU (existing
Tech Building graphic). Per this standard, the above graphic will also have a legend showing
AHU tag and associated color. If the user clicks on the AHU tag in the legend it shall route them
to the AHU graphic. If the user clicks on the AHU service zone in the hatching it shall take them
to a detailed floor plan graphic displaying VAV service zones, room temp/humidity.
The above detailed floor plan graphic example shows VAV service zones color-coded by VAV box. The
detailed floor plan graphic shall display:
Space temperature
Relative humidity (where applicable)
Occupancy status
Space Pressure sensor probe location (where applicable)
If space temp, relative humidity (where applicable), or space pressure (where applicable), is out of
range, the background color of the point value box shall turn red.
If the user clicks on the VAV service zone it shall route them to the VAV graphic.
Converter Graphics
Setpoints in upper right corner (main virtual points, occupied mode, reset schedules).
Clicking on occupied mode or reset schedules shall take user to additional graphic
showing AHU occupancy schedule or reset schedule.
Graphic shall include override buttons for related to terminal equipment served by the
AHU that allows user to:
o Override all terminal equipment heating valves fully open
o Override all VAV dampers fully open
o Override all VAV dampers to max scheduled airflow
o Override all VAV dampers to min scheduled airflow
o Override all VAV dampers closed
Animation on fans (based on status, not output), not on dampers
For systems that are interconnected (energy recovery, EFs, DOAS, etc), but do not all fit
on one graphic, include link on graphic to interconnected system’s graphic
Supply and return airflow shall always be shown from right-edge of graphic (include
label)
Exhaust and outside airflow shall always be shown from left-edge of graphic (include
label)
Transfer button shown for terminal device graphics
Transfer button for related plant equipment (local chiller, boiler, pumps, converters, etc)
Graphic shall display both command and feedback points
Use standard units and point names described in sections above
Each facility shall have a link to an AHU status table. The table shall contain (at
minimum) the following columns (given in order from left to right):
If AHU has multiple supply fans (i.e. fan row) then the AHU row shall be taller and the
cell for the supply fan status shall be split into several rows so that all fan status and
speeds can be displayed clearly.
Setpoints in upper right corner (main virtual points). Shall include min. heat, min. cool,
max heat, max cool CFM, space temperature setpoint (where applicable)
Room name and number shall be included in the VAV object name. Coordinate final
room numbers with owner. Where VAV box serves more than one room, the room
number shall be the room where the thermostat is located.
Where more than one VAV serves a single room there shall be a typical VAV graphic at
the top of the screen with a table below showing values for airflow, damper position,
discharge air temp, etc. Table shall include room airflow totals at bottom row of the
table. Any exhaust dampers associated with a VAV box shall also be shown on the
graphic, included in the tables
Include link to AHU graphic serving VAV box
The purpose of this document is to describe the Enterprise Level Server at Northwestern
University, and the separation of roles between the System Integrator and the Building
Automation System Contractor.
The Enterprise Server consists of the Honeywell Tridium WebsAX running on three Marathon
redundant servers. Two servers are located on the Evanston Campus, and one server is located
on the Chicago Campus. Both the JCI and Siemens head end servers currently reside on this
Marathon redundant server. The long term plan is these two software packages are used for
high level programming only, and will not be used for day to day operations of the JCI or
Siemens BAS.
All new DDC system controllers, terminal device controllers, VFDs, and any other intelligent
control device shall be BTL Certified and shall communicate using BACNET MS/TP. All network
controllers shall communicate to lower level controllers using BACNET MS/TP. Network
controllers shall communicate to each other, and BAS Servers, using BACNET/IP.
The control contractor shall provide a complete DDC system, which interfaces with both the
control vendors "head end" server, and the Northwestern University Tridium Enterprise Server.
The Owners' normal day to day interface will be with the Tridium Enterprise Server. The
configuration of graphics for the Tridium Enterprise Server will be done by the Owner's System
Integrator. The BAS contractor is responsible for coordinating with the System Integrator to
verify all points are properly transmitted to the Enterprise Server including alarm values and
links to trend files. Provide sufficient manpower to work with the System Integrator to do a
point to point test of alarms, trending, setpoint overrides, etc.
Page 1 of 5 1/15/2014
Northwestern University
Scope of BAS Contractor
Page 2 of 5 1/15/2014
Northwestern University
Scope of BAS Contractor
Page 3 of 5 1/15/2014
Northwestern University
Scope of BAS Contractor
iii. All network controllers shall include a lifetime license for free software
upgrades.
iv. The network controllers shall be provided with no connectivity restrictions
on which brand stations or tools can interact with the system. The
station and tool “NiCS” would be as follows:
Value
Property
STATION COMPATIBILITY IN ALL
STATION COMPATIBILITY OUT ALL
TOOL COMPATIBILITY IN ALL
TOOL COMPATIBILITY OUT ALL
d. Delta Controls:
i. Northwestern University does not have a standard developed for Delta
Controls at the time of publication.
e. Automated Logic
i. Provide most current controller compatible with existing ALC campus
infrastructure.
ii. Communications to field control devices shall be through BACNET MS/TP.
7. Point to point checkout.
8. Verify all physical alarms.
9. Setup alarms in the network controller in accordance with the Northwestern
University DDC Standards document. Coordinate with Owner on alarm distribution.
Work with the SI to make sure the Enterprise Server is receiving the alarms.
10. Setup trends in the BASC’s associated server in accordance with the Northwestern
University DDC Standards document. Work with the SI to make sure the Enterprise
Server is receiving the trends.
11. Accessing controllers via PCAnywhere, Telnet or similar software is not allowed.
Remote access shall be through Northwestern’s SSLVPN.
12. Any software required for controller configuration shall be included as a leave-behind
tool with enough license capability to support the installation. Provide the
appropriate quantity of legal copies of all software tools, configuration tools,
management tools, and utilities used during system commissioning and installation.
All tools shall be generally available in the market. No closed and/or unavailable
tools will be permitted. Contractor shall convey all software tools and their legal
licenses at project close out.
Page 4 of 5 1/15/2014
Northwestern University
Scope of BAS Contractor
Page 5 of 5 1/15/2014
Our Purpose Is To Enrich Outdoor Spaces
Woodbench Specifications
Available backed or backless. Backed version available with two armrest Interior woods are finished with Landscape Forms’
styles — loop or ornamental. Offered in 72" or 96" lengths. Freestanding, exclusive LF-80 wood finish, a clear, catalyzed acrylic
surface mounted, or wall mounted styles offered. Available in a variety of catalyzed acrylic lacquer.
woods or PolySite ™ recycled timbers (PolySite not offered in 96" length).
Exterior woods are unfinished and will weather to a soft
Gretchen Picnic Table pewter gray, requiring no future maintenance.
Wheelchair accessible from either end. Available in a variety of woods or Metal is finished with Landscape Forms’ proprietary
PolySite™ recycled timbers. Freestanding or surface mounted. Umbrella hole Pangard II ® polyester powercoat, a hard yet flexible
available. ADA compliant style available. Contact Landscape Forms for details. finish that resists rusting, chipping, peering and fading.
Call for standard color chart. A wide array of optional
Gretchen Litter Receptacle and Ash Urn
colors may be specified for an upcharge.
Large 30-gallon capacity receptacle with liner. Choose from side or top
Consult Landscape Forms price list for complete
opening receptacle styles. Sand pan available for side opening receptacle.
specifying information. Visit landscapeforms.com; click
Available in a variety of woods or PolySite ™ recycled timbers. Coordinating
Design Tools, Materials/Colors link for standard offer-
ash urn available.
ings, including FSC wood options.
Balustrade
Constructed of 2" x 3" wood rails individually fastened to steel bands. Available
backed or backless. Backed bench offered in 72" and 96" lengths, backless
in 72" only. End loop arm available on backed bench. Freestanding, embed-
ded, surface mounted or wall mounted styles offered. Available in a variety
of woods or PolySite ™ recycled timbers (PolySite ™ not offered in 96" length).
Metal is the world’s most recycled material and is fully recyclable. Powdercoat finish
on metal parts contains no heavy metals, is HAPS-free and has extremely low VOCs.
Consult our website for recycled content for this product.
Landscape Forms is proud to specify FSC and Green-e certified paper. This paper meets 800.521.2546 269.381.3455 fax
the Forest Stewardship Council’s standards for responsible forest management and is 431 Lawndale Avenue, Kalamazoo, MI 49048
made using certified renewable energy.
www.landscapeforms.com
VICTOR STANLEY, INC. DYN-342 and DYN-242 Dynasty Series™
-Manufacturers of Quality Site Furnishings since 1962- MegaCan Recycling Stations and Litter Receptacles
P.O. Drawer 330, Dunkirk, Maryland 20754 USA Patents Pending
www.victorstanley.com