1) Qp-01 Contract Review
1) Qp-01 Contract Review
(TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
AS RCS OA
Rev. No. Issue No. Issue Date Reviewed by: Prepared by: Reviewed by: Recommending Approved by:
Approval
Page 1 of 8
TANMIA FOR OIL AND CONSTRUCTION LIMITED. (TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
Table of Contents
1...................................................................................................... PURPOSE
3
2. SCOPE................................................................................................................................................ 3
3. REFERENCES.................................................................................................................................... 3
4. DEFINITIONS...................................................................................................................................... 3
5. PROCEDURE...................................................................................................................................... 3
5.1 Proposal Stage........................................................................................................................... 3
5.2 At Contract Award...................................................................................................................... 4
5.3 Handover to Projects................................................................................................................. 4
5.4 Meeting Preparation.................................................................................................................. 5
5.5 Contract Review Meeting.......................................................................................................... 6
5.6 Follow-up Action........................................................................................................................ 7
6. DOCUMENTATION............................................................................................................................. 8
Page 2 of 8
TANMIA FOR OIL AND CONSTRUCTION LIMITED. (TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
1. PURPOSE
2. SCOPE
That all Contract requirements are clearly understood by the Project Team
disciplines lead staff and any supporting Corporate Supervisors involved in
the project initiation.
That any changes to standard work practices are recognized and accepted by
the Project Manager and all affected corporate supervisors.
That any clarification or outstanding information required from Saudi Aramco
are identified and action by the Project Manager
3. REFERENCES
None.
4. DEFINITIONS
Definitions relevant to this procedure are listed in the front of the Quality Plan and
ISO-9000 (Latest) – Quality Management Systems-Fundamentals and
Vocabulary.
5. PROCEDURE
5.1.1 Where practical, intended Project personnel will be involved with the
evaluation of Saudi Aramco’s Invitation to bid and the preparation of'
documents for the Proposal
Page 3 of 8
TANMIA FOR OIL AND CONSTRUCTION LIMITED. (TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
5.2.2 Upon award of the Contract: The Project Manager will be advised by the
Proposal & Engineering Manager and/or Commercial Department of any
special requirements he should comply with regarding Project execution
arising since Proposal Submission. He will meet, as necessary, with the
Proposal & Engineering Manager and relevant team members to discuss
any questions he may have with regard to the Contract specifications,
errors or omissions and Client involvement.
5.3.1 The Project Manager will receive from the Proposals & Engineering
Manager a complete Package of Proposal documentation, including all
subsequent submissions and correspondence. Collectively, this now
comprises the "contract documentation package", and is passed over by
the Proposal & Engineering Manager under cover of a completed Project
Handover Meeting Report
5.3.5 The Project Manager will thoroughly review the documentation and
become familiar with the contents of the Contract and all related
documents
The activities listed below should preferably be started before the Effective
Date of the contract but in any case, not later than 5 working days after the
effective date
5.4.1 The Project Manager, having acquired a sound knowledge of' the
Contract requirements and the relevant Proposal documentation, will
allocate his Project Team responsibilities.
5.4.2 The Project Manager will uniquely identify parts of' the Contract
documentation package plus TANMIA for Oil and Construction Ltd.
Contract Execution Strategy (if prepared for inclusion in the proposal) and
determine the necessary distribution as appropriate to all project team
members using the transmittal.
5.4.4 The Project Manager will arrange for the distribution in accordance with
5.4.3 above.
5.4.5 Each recipient will critically review the supplied documents, listing any
items not fully understood or where a possible misunderstanding may
arise and any information or clarification is required from Saudi Aramco.
5.4.6 These listings will be made in the form of written specific queries.
Page 5 of 8
TANMIA FOR OIL AND CONSTRUCTION LIMITED. (TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
5.4.7.2 Interfaces - That these are clearly defined understood and include
interfaces of disciplines with each other, with third parties and with the
Client.
5.4.7.3 Work Scope – That the Design Criteria including the Scope of Work
which will constitute the design database, are established, agreed with
Client and issued and understood by those responsible for the work.
For projects with, a large multi -volume Contract Documentation
Package a member(s) of the Project Team will extract the Design Data
Base utilizing the Contract documentation package, in logical
sequence, related to the overall process basis and engineering
disciplines involved. A full index to identify the location of each data
category will be prepared if not included in the Client's documentation.
5.4.7.4 This Design Data Base will be issued to all attendees of the
Contract Review meeting, supplementing information distributed direct
from the Contract Documentation Package (as 5.4.4 above).
5.4.7.5 That the issued Execution Strategy, if prepared and Quality Plan
clearly indicate where the Contract work instructions differ from
standard working practices.
5.4.7.7 That any identified needs for the development of procedures, work
instructions and design briefs are identified and included in the agenda
for the Meeting.
Page 6 of 8
TANMIA FOR OIL AND CONSTRUCTION LIMITED. (TANMIA-QP-01)
REV:01
DATE: 18 MARCH 2017
5.5.2 The Contract Review Meeting will be chaired by the Project Manager,
who will ensure that the minutes of meeting are taken.
5.5.4 The agenda for the meeting will either be based on the responses
received in advance (if requested by the Project Manager, as per 5.4.3
above, or will be tabled by the Project Manager.
5.5.5 All assigned lead proposal Staff will have prepared a statement of all
criteria for their discipline prior to the start of any project (contract)
activities.
5.6.4 Each department and or discipline will maintain a file of, or have
access to, the relevant documents i.e. works scope, Saudi Aramco
specific actions, Saudi Aramco philosophies, regulatory requirements,
relevant national and international standards, and TANMIA for Oil and
Construction Ltd. standards and procedures which are applicable to
their Scope of Work.
6. DOCUMENTATION
None
Page 8 of 8