ID WBS Task Mode Task Name Duration Start 1 2 3

This project summary outlines the construction and finishing of a dentistry building in Islamabad, Pakistan from August 2016 through August 2018. It involves over 660 days of work organized into tasks focusing on site preparation, structural concrete work through 5 floors, masonry, and roof treatment. The tasks are broken into start and end dates to track progress over the duration of the project.

Uploaded by

TariqMahmood
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views

ID WBS Task Mode Task Name Duration Start 1 2 3

This project summary outlines the construction and finishing of a dentistry building in Islamabad, Pakistan from August 2016 through August 2018. It involves over 660 days of work organized into tasks focusing on site preparation, structural concrete work through 5 floors, masonry, and roof treatment. The tasks are broken into start and end dates to track progress over the duration of the project.

Uploaded by

TariqMahmood
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec

Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
1 1 Construction & finishing project SZAB PIMS dentistry building Islamabad
663.7 days Fri 8/19/16

2 1.1 Mobilization and site preperation 43 days Fri 8/19/16 Oct 8 '16

3 1.1.1 Mobilization of offices,accomodations containers utilitise 10 days Fri 8/19/16 Aug 30 '16
connections and site preperation

4 1.1.2 Mobilization of site staff labours equipments 4 days Aug 30 '16


Tue 8/30/16 Sep 4 '16

5 1.1.3 Excavation for lower ground floor and foundations. 14 days Sep 4 '16
Sun 9/4/16 Sep 20 '16

6 1.1.4 Termite proofing 15 days Tue 9/20/16 Sep 20 '16 Oct 8 '16

7 1.2 RCC Structual work 374.1 days Tue 11/1/16 Nov 1 '16 Jan 11 '18

8 1.2.1 P.C.C 1:4:8 in foundation 15 days Tue 11/1/16 Nov 1 '16 Nov 18 '16

9 1.2.2 R.C.C 1:2:4 (3000PSI) foundation,cloumns upto planth and planth 20.1 days Tue 12/6/16 Dec 6 '16 Dec 29 '16
beam

10 1.2.3 R.C.C 1:1:2 (4000PSI) in cloumns including form work in 15 days Thu 12/29/16 Dec 29 '16 Jan 15 '17
basement

11 1.2.4 R.C.C 1:2:4 (3000PSI) in roof slab landing walls beams and stair 20 days Tue 1/10/17 Jan 10 '17 Feb 2 '17
cases ramps including electric conduit fans box in basement floor
PART I

12 1.2.5 Part II 20 days Sat 1/21/17 Jan 21 '17 Feb 14 '17

13 1.2.6 R.C.C 1:1:2 (4000PSI) in cloumns including form work at ground 15 days Sat 2/4/17 Feb 4 '17 Feb 22 '17
floor

14 1.2.7 R.C.C 1:2:4 (3000in PSI) roof slab landing wall beams and stair 24 days Fri 2/10/17 Feb 10 '17 Mar 10 '17
cases including electric conduit fan box at ground floor PART I

15 1.2.8 Part II 23 days Wed 2/22/17 Feb 22 '17 Mar 21 '17

16 1.2.9 R.C.C 1:1:2 (4000PSI) in cloumns including form work at 1st floor 15 days Sun 3/12/17 Mar 12 '17 Mar 30 '17

17 1.2.10 R.C.C 1:2:4 (3000PSI) in roof slab landing walls beams and stair 20 days Sun 3/12/17 Mar 12 '17 Apr 5 '17
cases including electric conduit fan box at 1st floor PART I

18 1.2.11 Part II 20 days Tue 3/21/17 Mar 21 '17 Apr 13 '17

19 1.2.12 R.C.C 1:1:2 (4000PSI) in cloumns including form work at 2nd floor 15 days Wed 4/5/17 Apr 5 '17 Apr 22 '17

20 1.2.13 R.C.C 1:2:4 (3000PSI) in roof slab landing walls and stair cases 20 days Sat 4/15/17 Apr 15 '17 May 9 '17
including electric conduit at 2nd floor PART I

21 1.2.14 PART II 20 days Tue 4/25/17 Apr 25 '17 May 18 '17

Page 1
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
22 1.2.15 R.C.C 1:1:2 (4000PSI) in cloumns including form work at 3rd floor 15 days Tue 5/9/17 May 9 '17 May 26 '17

23 1.2.16 R.C.C 1:2:4 (3000PSI) in roof slab landing walls stair cases 11 days Tue 5/9/17 May 9 '17 May 21 '17
including electric conduit fan box at 3rd floor PART I

24 1.2.17 PART II 12 days Sat 5/20/17 May 20 '17 Jun 3 '17

25 1.2.18 R.C.C 1:1:2 (4000PSI) in cloumns including form work at 4th floor 12 days Sun 5/21/17 May 21 '17 Jun 4 '17

26 1.2.19 R.C.C 1:2:4 (3000PSI) in roof slab landing walls stair cases 20 days Sun 5/21/17 May 21 '17 Jun 14 '17
including electric conduit fan box at 4th floor PART I

27 1.2.20 PART II 20 days Sat 6/3/17 Jun 3 '17 Jun 27 '17

28 1.2.21 R.C.C 1:1:2 (4000PSI) in cloumns including form work at 5th floor 15 days Wed 6/14/17 Jun 14 '17 Jul 1 '17

29 1.2.22 R.C.C 1:2:4 (3000PSI) in roof slab landing walls stair cases 15 days Sat 6/17/17 Jun 17 '17 Jul 5 '17
including electric conduit fan box at 5th floor PART I

30 1.2.23 PART II 20 days Fri 6/30/17 Jun 30 '17 Jul 23 '17

31 1.2.24 STRUCTURE ABOVE 5th FLOOR 20 days Sun 7/23/17 Jul 23 '17 Aug 16 '17

32 1.2.25 Roof treatment and water slope work at top roof 25 days Thu 9/14/17 Sep 14 '17 Oct 13 '17

33 1.2.26 PCC hollow block and bricks masonry work in basement 20 days Thu 3/9/17 Mar 9 '17 Apr 1 '17

34 1.2.27 PCC hollow blocks and bricks masonry work at ground floor 20 days Sun 4/2/17 Apr 2 '17 Apr 26 '17

35 1.2.28 PCC hollow blocks and bricks masonry work at 1st floor 20 days Sat 4/22/17 Apr 22 '17 May 16 '17

36 1.2.29 PCC hollow blocks and bricks masonry work at 2nd floor 20 days Thu 6/1/17 Jun 1 '17 Jun 24 '17

37 1.2.30 Bricks masonry work at 3rd floor 20 days Wed 6/14/17 Jun 14 '17 Jul 7 '17

38 1.2.31 Bricks masonry work at 4th floor 25 days Fri 7/7/17 Jul 7 '17 Aug 5 '17

39 1.2.32 Bricks masonry work at 5th floor 25 days Fri 7/28/17 Jul 28 '17 Aug 26 '17

40 1.2.33 PCC hollow blocks masonry work at top roof 15 days Fri 9/8/17 Sep 8 '17 Sep 26 '17

41 1.2.34 Backfilling with sand foundations tranches plinth or under floor 25 days Wed 1/4/17 Jan 4 '17 Feb 2 '17
etc.

42 1.2.35 Construction of tube well building and finishing work 118 days Fri 6/23/17 Jun 23 '17 Nov 8 '17

43 1.2.35.1 Excavation and PCC work 10 days Fri 6/23/17 Jun 23 '17 Jul 5 '17

Page 2
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
44 1.2.35.2 R.C.C 1:2:4 (3000PSI) in foundation and cloumns 10 days Wed 7/5/17 Jul 5 '17 Jul 16 '17

45 1.2.35.3 R.C.C 1:2:4 in roof slab landing walls beams 10 days Sun 7/16/17 Jul 16 '17 Jul 28 '17

46 1.2.35.4 Bricks masonry work 10 days Fri 7/28/17 Jul 28 '17 Aug 9 '17

47 1.2.35.5 Internal external plastering,flooring and paint work 70 days Wed 8/9/17 Aug 9 '17 Oct 29 '17

48 1.2.35.6 Installation of doors and windows work 8 days Sun 10/29/17 Oct 29 '17 Nov 8 '17

49 1.2.36 Construction and finishing work Compound wall main gate and guard
118 days
room Sat 8/26/17 Aug 26 '17 Jan 11 '18

50 1.2.36.1 Excavation and PCC work 10 days Sat 8/26/17 Aug 26 '17 Sep 7 '17

51 1.2.36.2 R.C.C 1:2:4 (3000PSI) in foundation and cloumns 10 days Thu 9/7/17 Sep 7 '17 Sep 19 '17

52 1.2.36.3 R.C.C 1:2:4 (3000PSI slab landing walls beams 10 days Tue 9/19/17 Sep 19 '17 Sep 30 '17

53 1.2.36.4 Pre coast block and bricks masonry work 10 days Sat 9/30/17 Sep 30 '17 Oct 12 '17

54 1.2.36.5 Internal external plastering,flooring and paint work 70 days Thu 10/12/17 Oct 12 '17 Jan 2 '18

55 1.2.36.6 Installation of doors and windows work 8 days Tue 1/2/18 Jan 2 '18 Jan 11 '18

56 1.3 Internal External Finishing work 305 days Wed 4/19/17 Apr 19 '17 Apr 10 '18

57 1.3.1 Installation of MS doors frame and Internal external plastering work


136 days Wed 4/19/17 Apr 19 '17 Sep 24 '17

58 1.3.1.1 Installation of MS doors frame and walls stair case room and 20 days Wed 4/19/17 Apr 19 '17 May 12 '17
roof plastering work in basement

59 1.3.1.2 Installation of MS doors frame and walls stair case room 20 days Sat 5/13/17 May 13 '17 Jun 6 '17
palstering work at ground floor

60 1.3.1.3 Installation of MS doors frame and walls stair case room 20 days Fri 6/2/17 Jun 2 '17 Jun 25 '17
plastering work at 2nd floor

61 1.3.1.4 Installation of MS doors frame and walls stair case room 20 days Wed 7/12/17 Jul 12 '17 Aug 4 '17
plastering work at 3rd floor

62 1.3.1.5 Installtion of MS doors frame and walls stair case room 20 days Tue 7/25/17 Jul 25 '17 Aug 17 '17
plastering work at 4th floor

63 1.3.1.6 Installation of MS doors frame and walls stair case room 20 days Wed 8/23/17 Aug 23 '17 Sep 15 '17
plastering work at 5th

64 1.3.1.7 Installtion of MS doors frame and walls stair case room plaster 10 days Wed 9/13/17 Sep 13 '17 Sep 24 '17
work at top roof

65 1.3.1.8 External plastering work all building 87.1 days Wed 5/24/17 May 24 '17 Sep 2 '17

66 1.3.2 Internal Floor finishing work 136 days Fri 5/12/17 May 12 '17 Oct 18 '17

67 1.3.2.1 Terrazzo,porcelain tiles floor work in basement 20 days Fri 5/12/17 May 12 '17 Jun 4 '17

68 1.3.2.2 Terrazzo,porcelain and marble floor work at ground floor 25 days Tue 6/6/17 Jun 6 '17 Jul 5 '17

69 1.3.2.3 Terrazzo,porcelain tiles floor work at 1st floor 20 days Sun 6/25/17 Jun 25 '17 Jul 19 '17

70 1.3.2.4 Terrazzo,porcelain tiles floor work at 2nd floor 20 days Fri 8/4/17 Aug 4 '17 Aug 27 '17

Page 3
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
71 1.3.2.5 Terrazzo,porcelain tiles floor work at 3rd floor 20 days Thu 8/17/17 Aug 17 '17 Sep 9 '17

72 1.3.2.6 Terrazzo,porcelain tiles floor work at 4th floor 20 days Fri 9/15/17 Sep 15 '17 Oct 8 '17

73 1.3.2.7 Terrazzo,porcelain tiles floor work at 5th floor 20 days Sun 9/24/17 Sep 24 '17 Oct 18 '17

74 1.3.2.8 Granite tiles work for stair at all floors 33 days Sun 9/3/17 Sep 3 '17 Oct 11 '17

75 1.3.3 False ceiling work 156 days Thu 6/22/17 Jun 22 '17 Dec 21 '17

76 1.3.3.1 False ceiling work in basement 40 days Thu 6/22/17 Jun 22 '17 Aug 8 '17

77 1.3.3.2 False ceiling work at gound floor 40 days Sat 7/22/17 Jul 22 '17 Sep 7 '17

78 1.3.3.3 False ceiling wrok at 1st floor 40 days Sat 7/22/17 Jul 22 '17 Sep 7 '17

79 1.3.3.4 False ceiling work at 2nd floor 40 days Thu 9/14/17 Sep 14 '17 Oct 31 '17

80 1.3.3.5 False celing work at 3rd floor 40 days Wed 9/27/17 Sep 27 '17 Nov 12 '17

81 1.3.3.6 False ceiling work at 4th floor 40 days Thu 10/26/17 Oct 26 '17 Dec 12 '17

82 1.3.3.7 False ceiling work at 5th floor 40 days Sat 11/4/17 Nov 4 '17 Dec 21 '17

83 1.3.4 Dry walls partition and SS doors work 80 days Tue 8/8/17 Aug 8 '17 Nov 9 '17

84 1.3.4.1 Gypsum board walls partitions work at all floors 40 days Tue 8/8/17 Aug 8 '17 Sep 23 '17

85 1.3.4.2 Installation of SS doors 40 days Sat 9/23/17 Sep 23 '17 Nov 9 '17

86 1.3.5 Internal external paint work 240 days Tue 7/4/17 Jul 4 '17 Apr 10 '18

87 1.3.5.1 Paint for roof plaster ceiling walls staire case room steel wood 90 days Tue 7/4/17 Jul 4 '17 Oct 17 '17
in basement

88 1.3.5.2 Paint work for plaster & ceiling walls stair case room steel and 90 days Fri 7/28/17 Jul 28 '17 Nov 10 '17
wood at ground floor

89 1.3.5.3 Paint work for plaster and ceiling walls stair case room steel 90 days Tue 9/26/17 Sep 26 '17 Jan 9 '18
and woodat 1st floor

90 1.3.5.4 Paint work for plaster & ceiling walls stair case room steel 90 days Thu 10/19/17 Oct 19 '17 Feb 1 '18
wood at 2nd floor

91 1.3.5.5 Paint work for plaster & ceiling walls stair case room steel 90 days Wed 11/1/17 Nov 1 '17 Feb 14 '18
wood at 3rd floor

92 1.3.5.6 Paint work for plaster & ceiling walls stair case room steel 90 days Thu 11/30/17 Nov 30 '17 Mar 15 '18
wood at 4th floor

93 1.3.5.7 Paint work for plaster & ceiling walls stair case room steel 90 days Sat 12/9/17 Dec 9 '17 Mar 24 '18
wood at 5th floor

94 1.3.5.8 Paint work for parapet wall stair case roo at top roof 90 days Wed 10/18/17 Oct 18 '17 Jan 31 '18

95 1.3.5.9 External paint work all building 90 days Tue 12/26/17 Dec 26 '17 Apr 10 '18

96 1.3.6 Installation doors 179 days Thu 7/27/17 Jul 27 '17 Feb 21 '18

97 1.3.6.1 Supply and Installation of doors in basement 20 days Thu 7/27/17 Jul 27 '17 Aug 19 '17

Page 4
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
98 1.3.6.2 Suplly and Installation of doors at ground floor 20 days Sat 8/19/17 Aug 19 '17 Sep 12 '17

99 1.3.6.3 Supply and Installation of doors at 1st floor 20 days Tue 9/12/17 Sep 12 '17 Oct 5 '17

100 1.3.6.4 Supply and Installation of doors at 2nd floor 20 days Thu 10/5/17 Oct 5 '17 Oct 28 '17

101 1.3.6.5 Supply and installation of doors at 3rd floor 20 days Sat 10/28/17 Oct 28 '17 Nov 21 '17

102 1.3.6.6 Supply and installtion of doors at 4th floor 20 days Tue 11/21/17 Nov 21 '17 Dec 14 '17

103 1.3.6.7 Supply and installtion of doors at 5th floor 17 days Thu 12/14/17 Dec 14 '17 Jan 3 '18

104 1.3.6.8 Supply and installation of doors at top roof stair case room 17 days Wed 1/3/18 Jan 3 '18 Jan 23 '18

105 1.3.6.9 Supply and installation of windows wardrobe and cabinet 65 days Thu 12/7/17 Dec 7 '17 Feb 21 '18

106 1.3.7 Supply and installation of aluminum doors,windows and ventilators


85 days Sat 10/14/17 Oct 14 '17 Jan 20 '18

107 1.3.7.1 Supply and installation aluminium doors,windows and 10 days Sat 10/14/17 Oct 14 '17 Oct 25 '17
ventilators in basement

108 1.3.7.2 Supply and installation of aluminium doors,windows and 10 days Wed 10/25/17 Oct 25 '17 Nov 5 '17
vetilators at ground floor

109 1.3.7.3 Supply and installtion of aluminium doors,windows and 10 days Mon 11/6/17 Nov 6 '17 Nov 17 '17
vetilators at 1st floor

110 1.3.7.4 Supply and installtion of aluminium dorrs,windows and 10 days Sat 11/18/17 Nov 18 '17 Nov 29 '17
vetilators at 2nd floor

111 1.3.7.5 Supply and installation of aluminium doors,windows and 15 days Wed 11/29/17 Nov 29 '17 Dec 16 '17
vetilators at 3rd floor

112 1.3.7.6 Supply and installation of aluminium doors,windows and 15 days Sun 12/17/17 Dec 17 '17 Jan 3 '18
ventilators at 4th floor

113 1.3.7.7 Supply and installtion of aluminium doors,windows and 15 days Wed 1/3/18 Jan 3 '18 Jan 20 '18
ventilators at 5th floor

114 1.3.7.8 Installtion of SS railing with stair at all floors 25 days Tue 10/31/17 Oct 31 '17 Nov 29 '17

115 1.3.7.9 Installation of MS railing with emergncy eixt way at all floors 20 days Wed 11/29/17 Nov 29 '17 Dec 22 '17

116 1.4 Electrical work stage one (1) 68 days Fri 11/3/17 Nov 3 '17 Jan 21 '18

117 1.4.1 Conduit and installtion electric sewitches sockets box and pannel 10 days Fri 11/3/17 Nov 3 '17 Nov 15 '17
box and cable tray in basement

118 1.4.2 Conduit and installtion of PVC electric switches sockest box and 10 days Wed 11/15/17 Nov 15 '17 Nov 26 '17
cable tray at 1st floor

119 1.4.3 Conduit and installti on of PVC electric switches sockets box and 10 days Sun 11/26/17 Nov 26 '17 Dec 8 '17
cable tray at 2nd floor

Page 5
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
120 1.4.4 Conduit and installation of PVC electric switches sockets box and 10 days Fri 12/8/17 Dec 8 '17 Dec 20 '17
cable tray at 3rd floor

121 1.4.5 Conduit and installation of PVC electric switches sockets box and 10 days Wed 12/20/17 Dec 20 '17 Dec 31 '17
cable tray at 4th floor

122 1.4.6 Conduit and installation of PVC electric switches sockets box and 10 days Sun 12/31/17 Dec 31 '17 Jan 12 '18
calbe tray at 5th floor

123 1.4.7 Conduit and installation of PVC electric switches sockets box at 8 days Fri 1/12/18 Jan 12 '18 Jan 21 '18
top roof stair case room

124 1.5 Electrical work stage two (2) 120 days Sat 10/28/17 Oct 28 '17 Mar 17 '18

125 1.5.1 Cables wiring and Installation of main panel sub panel DB box 15 days Sat 10/28/17 Oct 28 '17 Nov 15 '17
switches sockets boards lights ceiling wall bracket exhaust fans
in basement

126 1.5.2 Cables wiring and Installation of DB and sub panel box switches 15 days Wed 11/15/17 Nov 15 '17 Dec 2 '17
sockets boards lights ceiling bracket exhaust fans at ground floor

127 1.5.3 Cables wiring and installation of DB box switches sockets boards 15 days Sat 12/2/17 Dec 2 '17 Dec 20 '17
lights ceiling bracket and exhaust fans at 2nd floor

128 1.5.4 Cables wiring and installation of DB box switches sockets boards 15 days Wed 12/20/17 Dec 20 '17 Jan 6 '18
lights ceiling bracket and exhaust fans at 3rd floor

129 1.5.5 Cables wiring and inatallation of DB box switches sockets boards 20 days Sat 1/6/18 Jan 6 '18 Jan 30 '18
lights ceiling bracket and exhaust fans at 4th floor

130 1.5.6 Cables wiring and installation of DB box switches sockets boards 20 days Tue 1/30/18 Jan 30 '18 Feb 22 '18
lights ceiling bracket and exhaust fans at 5th floor

131 1.5.7 Cables wiring and installation of switches sockets board and 20 days Thu 2/22/18 Feb 22 '18 Mar 17 '18
lightd at top roof stair case room

132 1.5.8 Telephone and network system work at all floors 90 days Wed 11/15/17 Nov 15 '17 Feb 28 '18

133 1.5.9 Fire alarm smoke detector heat detector system work at all floor 90 days Wed 11/15/17 Nov 15 '17 Feb 28 '18

134 1.5.10 Public address system work 90 days Wed 11/15/17 Nov 15 '17 Feb 28 '18

Page 6
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
135 1.5.11 C.C.T.V system work 90 days Wed 11/15/17 Nov 15 '17 Feb 28 '18

136 1.6 Mechnical Work 372 days Tue 7/4/17 Jul 4 '17

137 1.6.1 Internal Water sewage and rain water system work stage one (1)90 days Tue 7/4/17 Jul 4 '17 Oct 17 '17

138 1.6.1.1 water and sewage pipes work at groung floor 45 days Tue 7/4/17 Jul 4 '17 Aug 25 '17

139 1.6.1.2 Water and sewage pipes work at 1st floor 45 days Fri 8/25/17 Aug 25 '17 Oct 17 '17

140 1.6.1.3 Installation of UPVC pipes for rain water 45 days Sun 7/9/17 Jul 9 '17 Aug 31 '17

141 1.6.2 Internal Water and sewage system work stage two (2) 105 days Thu 8/31/17 Aug 31 '17 Dec 31 '17

142 1.6.2.1 Installation of sanitry in toilets and connection at ground floor 35 days Thu 8/31/17 Aug 31 '17 Oct 11 '17

143 1.6.2.2 installatio of sanitry in toilets and connection at 1st floor 35 days Wed 10/11/17 Oct 11 '17 Nov 21 '17

144 1.6.2.3 Installation of sanitry in toilets and connection at 2nd floor 35 days Tue 11/21/17 Nov 21 '17 Dec 31 '17

145 1.6.3 External water and sewage system work 85 days Sun 12/31/17 Dec 31 '17 Apr 10 '18

146 1.6.3.1 Excvation and civil work 25 days Sun 12/31/17 Dec 31 '17 Jan 30 '18

147 1.6.3.2 laying RCC pipes fitting connection and testing 30 days Tue 1/30/18 Jan 30 '18 Mar 6 '18

148 1.6.3.3 Drilling for water well GI pipe pump isntallation connection 30 days Tue 3/6/18 Mar 6 '18 Apr 10 '18
and testing

149 1.6.4 Fire fighting system work 120 days Tue 9/12/17 Sep 12 '17 Jan 30 '18

150 1.6.4.1 G.I pipes fitting work at all floors 30 days Tue 9/12/17 Sep 12 '17 Oct 17 '17

151 1.6.4.2 Installtion of house cabinet,pump,jet nozzle,fire extinguisers 90 days Tue 10/17/17 Oct 17 '17 Jan 30 '18
and external fire hydrants

152 1.6.5 Elevators work 118 days Sat 1/6/18 Jan 6 '18 May 24 '18

153 1.6.5.1 Cleaning wall surface and prepairing in shaft 10 days Sat 1/6/18 Jan 6 '18 Jan 18 '18

154 1.6.5.2 3 no of elevators steel structure work in shaft 70 days Thu 1/18/18 Jan 18 '18 Apr 10 '18

155 1.6.5.3 Installation electromechanical equipments 30 days Tue 4/10/18 Apr 10 '18 May 15 '18

156 1.6.5.4 Electrical connection power supply testing, align doors and 8 days Tue 5/15/18 May 15 '18 May 24 '18
equipment

157 1.6.6 Road path ways & car parking area construction work 117 days Fri 4/27/18 Apr 27 '18

158 1.6.6.1 demolishing old structure cutting removing cleaning and 10 days Fri 4/27/18 Apr 27 '18 May 9 '18
transportation material

159 1.6.6.2 Excavation work 15 days Wed 5/9/18 May 9 '18 May 26 '18

160 1.6.6.3 R.C.C foundation,bricks,Pavers and kerbs stone masonry work 40 days Sat 5/26/18 May 26 '18 Jul 12 '18

Page 7
ID WBS Task Task Name Duration Start Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 2027 3 101724 1 8 152229 5 121926 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 11
161 1.6.6.4 Plastering work 20 days Thu 7/12/18 Jul 12 '18 Aug 4 '18

162 1.6.6.5 Steel work 20 days Sat 8/4/18 Aug 4 '18

163 1.6.6.6 Paint work 12 days Tue 8/28/18 Aug 28 '18

164 1.6.6.7 Power generator 69 days Fri 4/27/18 Apr 27 '18 Jul 17 '18

165 1.6.6.7.1 Civil work 20 days Fri 4/27/18 Apr 27 '18 May 20 '18

166 1.6.6.7.2 Installation of 2 no of power generators work 25 days Sun 5/20/18 May 20 '18 Jun 19 '18

167 1.6.6.7.3 Electrical connection power supply testing 24 days Tue 6/19/18 Jun 19 '18 Jul 17 '18

168 1.7 Final inspection and handover project 8 days Tue 9/11/18 Sep 11 '18

169 1.7.1 Final inspection and handover project 8 days Tue 9/11/18 Sep 11 '18

170 1.8 Demobilization 10 days Thu 9/20/18 Sep 20 '18

171 1.8.1 Final cleaning removing and transportation all rubush from site 5 days Thu 9/20/18 Sep 20 '18

172 1.8.2 Demobilization of offices accomodation equipment and site staff 5 days Wed 9/26/18

Page 8