Flow Chart For Availing Solar Net Meter

This flow chart outlines the process for roof top net metering with TSSPDCL in 3 steps: 1) Apply for net metering by downloading and filling out an application form from the TSSPDCL website and submitting it with payment. 2) Within 21 days of application, the feasibility will be determined and the consumer can install solar panels from approved suppliers. 3) Once installation is complete, an inspection will be done and the old meter replaced with a net meter within 5 days to begin billing and reconciliation.

Uploaded by

rama krishn
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
155 views

Flow Chart For Availing Solar Net Meter

This flow chart outlines the process for roof top net metering with TSSPDCL in 3 steps: 1) Apply for net metering by downloading and filling out an application form from the TSSPDCL website and submitting it with payment. 2) Within 21 days of application, the feasibility will be determined and the consumer can install solar panels from approved suppliers. 3) Once installation is complete, an inspection will be done and the old meter replaced with a net meter within 5 days to begin billing and reconciliation.

Uploaded by

rama krishn
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Start

Flow chart for Roof top NET METERING

Download Application form from www.tssouthernpower/ Solar


Rooftop Netmetering/ Application Form or Online Register in
TSSPDCL Website

Obtain DD of Rs. 2500 + GST for LT & 15000 + GST for HT


Consumers from any Scheduled bank in favor of TSSPDCL or pay
online for online application

Fill the application & Submit at nearest CSC/ICSC Center along with
DD for offline

Obtain the Acknowledgment from CSC operator with unique


registration number for further reference for offline/ online

Application automatically forward to ADE/op login in case of LT &


DE/Op Login in case of HT for technical feasibility

Application Should be check properly and intimate to Consumer


with in 7 days in case of discrepancy In Case of any DTR
capacity enhancement
required, separate
Technical feasibility report should be approved by Concern officer
application should be
with in 21 days from the date of registration(Proper receipt of
submitted and
application) after site inspection necessary payments
should be paid (if
Required)

SMS Alert and email will be Data will flow to SAP for
received by consumer about preparation of estimation
Technical feasibility

ADE/ DE prepares estimate and


Consumer can approach release in SAP with in 5 days
empanelled suppliers for
installation of solar panel
available in
www.tssouthernpower.com/
www.tnredcl.telangana.gov.in
website Net Meter should be issued to the
concerned Nodal officer from CSC/
ICSC on the same day of receipt of
Consumer should submit work work Completion report from
completion report with in 4 months consumer
from the date of technical feasibility
at CSC/ICSC (Format
Available at TSSPDCL website)

ADE/ DE Should inspect the site and


replace the old meter with Net
For any queries and grievances Meter and update the test report/
mail us at Meter change report in CSC with in
[email protected] 5 days
or Call us @8333904715
Reconciliation with ERO by AE/ICSC or
Data will be sent to EBS for billing
ADE/Op before end of Month and update
and SAP
the Net Meter status by AAO/ ERO

End