0% found this document useful (0 votes)
231 views

2018 1 Linear Programming

The document describes a linear programming problem faced by Ebel Mining Company. Ebel owns two mines with different production capacities and costs. It needs to determine how many days per week each mine should operate to fulfill contracted ore quantities in a way that minimizes total costs. The objective is to minimize costs of $20,000 per day for mine 1 and $16,000 per day for mine 2. There are constraints on the quantity of high, medium, and low grade ore produced. The optimal solution determined through linear programming is for mine 1 to operate 1 day per week and mine 2 to operate 3 days per week, with a minimum total cost of $68,000.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
231 views

2018 1 Linear Programming

The document describes a linear programming problem faced by Ebel Mining Company. Ebel owns two mines with different production capacities and costs. It needs to determine how many days per week each mine should operate to fulfill contracted ore quantities in a way that minimizes total costs. The objective is to minimize costs of $20,000 per day for mine 1 and $16,000 per day for mine 2. There are constraints on the quantity of high, medium, and low grade ore produced. The optimal solution determined through linear programming is for mine 1 to operate 1 day per week and mine 2 to operate 3 days per week, with a minimum total cost of $68,000.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Linear Programming

for Optimization
Ade Febransyah
[email protected]
Where, when, how many, how?
Linear Programming
Characteristics

1. Problems seek to maximize or minimize


an objective: Objective Function
2. Constraints limit the degree to which
objective can be obtained
3. Mathematical relationships are linear
Example: Ebel Mining Company
It owns two different mines that produce a given kind of ore. The
mines are located in different parts of country and hence have
different production capacities and ore quality. After crushing, the
ore is graded into three classes: high, medium, and low.

Ebel has contracted to provide its parent company’s smelting plant


with 12 tons of high-grade, 8 tons of medium-grade, and 24 tons
of low-grade ore per week. It costs Ebel $20,000 per day to run
the first mine and $ 16,000 per day to run the second.

However, in a day’s operation the first mine produces 6 tons of


high-grade, 2 tons of medium-grade, and 4 tons of low-grade,
while the second mine produces daily 2 tons of high-grade, 2 tons
of medium-grade, and 12 tons of low-grade ore. How many days a
week should each mine operated in order to fulfill Ebel’s
commitment most economically?

5
Solution Ebel Mining Co.

 Number of production days per week mine 1= M1


Number of production days per week mine 2= M2
 Objective Function
Min 20,000 M1 + 16,000 M2
 Constraint
6 M1 + 2 M2  12 (High-grade ore requirement)
2 M1 + 2 M2  8 (Med-grade ore requirement)
4 M1 + 12 M2  24 (Low-grade ore requirement )
M1, M2  7 (Days in a week)
M1 0, M2  0

6
Graphical Solution of Linear
Programming Models

 Graphical solution is limited to linear


programming models containing only two
decision variables.
 Graphical methods provide visualization of
how a solution for a linear programming
problem is obtained.
Solution: Ebel Mining

M2
8
: 0.0 M1 + 1.0 M2 = 7.0
7

6
: 1.0 M1 + 0.0 M2 = 7.0

5
Payoff: 20000.0 M1 + 16000.0 M2 = 68000.0
4

3
: 6.0 M1 + 2.0 M2 = 12.0
2
: 4.0 M1 + 12.0 M2 = 24.0

1
: 2.0 M1 + 2.0 M2 = 8.0
0
M1
0 1 2 3 4 5 6 7 8

Optimal Decisions(M1,M2): ( 1.0, 3.0)


: 6.0M1 + 2.0M2 >= 12.0
: 2.0M1 + 2.0M2 >= 8.0 Optimal solution : M1= 1, M2= 3
: 4.0M1 + 12.0M2 >= 24.0
: 1.0M1 + 0.0M2 <= 7.0 Optimal Value : 68,000
: 0.0M1 + 1.0M2 <= 7.0

You might also like