1. The document provides instructions for replacing the X-ray tube on an Aquilion CT scanner. It describes removing the old tube, installing a tube replacement jig, and mounting the new tube. 2. Steps are outlined for adjusting the position of the new tube using front/back and left/right alignment procedures with imaging tests. Alignment screws and plates must be adjusted. 3. Notes are provided on checking tube rotation, avoiding overtightening connectors, and performing seasonal and image quality checks after replacing the tube.

Uploaded by

thanh tong Tieu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
417 views

Aquilion

1. The document provides instructions for replacing the X-ray tube on an Aquilion CT scanner. It describes removing the old tube, installing a tube replacement jig, and mounting the new tube. 2. Steps are outlined for adjusting the position of the new tube using front/back and left/right alignment procedures with imaging tests. Alignment screws and plates must be adjusted. 3. Notes are provided on checking tube rotation, avoiding overtightening connectors, and performing seasonal and image quality checks after replacing the tube.

Uploaded by

thanh tong Tieu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

Aq_TubeChange, 2 December 2010

Aquilion
X-ray tube replacement

1
Delivery of new tube

art
re P
Spa

2
Delivery of new tube

3
Tube replacement jig

4
New Tube Replacement Jig

5
Remove 8 bolts
CAUTION
CAUTION
The
The tube
tube can
can move
move in-
in- or
or outwards!
outwards!

Mark the position of the old tube, with a permanent marker.


This helps to install the new tube close to where it should be.
6
Tube mounting plate

F/B

L/R
Tube

Tube change:
Remove marked
screws (8x)

7
Remove F/B adjustment plates

remove

8
Disconnect cooler hoses
• To disconnect cooler hose, put heat exchanger at
7’oclock position
– (if fluid leaks it will be to the bottom of the gantry)

• To remove the Heat exchanger, put it at 5 o’clock


position
• Dry connector ends
– Connectors may corrode if left wet and then fail to work

• When re-installing do not push Heat exchanger all


the way in. Gantry will not be able to rotate.
9
Disconnect hoses

10
Move tube to 90° and insert pin

1) Remove Wedge
unit Shield Cover

2) Remove
Reference
Detector
(slide tube a
little out)

11
X-ray tube replacement
• Move the tube to 90º (or 270º) position.
• Remove the relevant patient positioning laser assy.
• If tube on 270º: Remove the L/R alignment bracket from tube mounting plate.
• Mount the connection-plate for the Tube-replacement-cart
to the gantry.
• Mount the tube-supporting-base to the cart.
• Connect the cart to the connection-plate.
• Adjust the cart height to the tube position.
• Slide the tube on the tube-supporting-base.
• Make sure you have disconnected
the Ref detector
• Move the base backwards on the cart,
lower the cart, disconnect the cart.
• Change tube, follow procedure backwards.

12
Mount cart-connection plate

13
Adjust cart-height to tube
OLD TYPE

NEW TYPE
(more space
for hoses)

14
Move tube on cart
Exchange mounting plate and
15

collimator with new tube.


X-ray tube F/B alignment.
• Front/Back alignment is done with Polaroid film
(Type 52 or 400).
• Put the couch-top just above the dome cover (lower than
normal).
• Put the film on the couch and make a scan with 120kV,
150mA, 2 mm, 1sec, M field.
– (Film on couch will minimize film movement caused by rotation).

16
X-ray tube F/B alignment 1/2
MultiSlice:without use of film
c With this method we use a 4x0.5mm X-ray beam on the
detector switched to 4x1mm (if row 1 and 4 give the same
values as row 2 and 3 → use detector 4x 2mm)
d The 2mm beam which is in practice more than 2 will in this
way also partly expose Row 1 and 4 .
e The amount of signal on Row 1 and 4 determines the tube
position.
f When the signal on Row 1 equals 4 the alignment perfect.
x-ray (4x 0.5mm)

SSMD (4x 1.0mm)


4 3 2 1 17
X-ray tube F/B alignment 2/2
MultiSlice:without use of film

c Warm-up the tube to 50% OLP


d Make a scan in DCA using :
120kV, 50mA, 1sec, SF, 4x0.5 slit, 4x1(or 4x2) slice
width
e Change pre-processing to : through, decode, offset
f Use Calc(scan data) : channel 438-458 → All.
g Compare signal from Row 1 with 4 and move
(about 17.000)
the tube until values are equal within approx. 500 counts.
(Row1 is at the front)

18
X-ray tube F/B alignment: screws

19
X-ray tube L/R alignment.
• Use a pin-phantom (PX16-56067 Gr.3)
• Align the pin-phantom (Must be centered)
– horizontally with 90 º Scano (check with square ROI)
– vertically with 0º Scano (check with square ROI)
– center the pin using a FOV of 40mm (check with
centered circle ROI)

ROI

ROI
pin
ROI

Vertical Horizontal Center


20
X-ray tube L/R alignment.
• Use L/R alignment software
– (adjust SF by tube shift, correct LF by software)
– Use Scan Time : 0.75 sec.

1 Check
alignment

Correction
data limit

2 Register
correction
values
21
X-ray tube alignment.
• Refer to figure 1.7.3-4 in the Service Manual for
the correct bolts to loosen.
’ If L/R alignment is difficult (tube does not
move), loosen also the middle F/B bolts.
(sometimes all F/B bolts must be loosened)
’ L/R alignment program → Gantry Power OFF
→ Move Tube → Gantry Power ON → make 1
rotation by KGTS Maintenance Panel
(otherwise: L/R alignment program: hang-up)

22
X-ray tube L/R alignment: screws

23
X-ray tube L/R alignment: adjustment

Older systems: New systems:


L/R adjustment L/R adjustment
plate. plate.

24
Tube change Notes:
• Check tube anode rotation by sound or by touch
before exposure!
• System checks for over mA current flow to servo not current in
all three phases.
• With a faulty phase connection current will still flow in two
phases and no error indicated
• In the future system will check current limits
– Rotor cable may be misaligned
• (insert with care)
– Rotor cable may have a broken connection
• Do not push very hard on heat exchanger
connectors without supporting them. They can
break internally
25
CXB-750: HV-connector
• Insert HV-connector carefully
– HV-connector has no key (as normal x-
ray tubes).
– feel pins entering connector
– Do not insert and rotate
• Do not apply too much grease
– Apply grease sparingly on sides only
– Silicone grease is only to allow cable
to slide in
– It may result in a cracked receptacle
• Tighten down connector all the way
– Tighten in star pattern
– If cable does not have 4mm of
compression pack with silicone grease
until you can replace cable

26
Tube change Notes:
• Following replacement
– If adjust for 80kV and 100kV
• See If adjustment
– Season tube
• From menu (using menu there is a 30min wait until
SF scans, system has not hung up)
• From laptop SF scans must be done with gantry
rotation
– Check all If’s
– F/B alignment (while tube is cooling)