Analysis of Multi-Storey RC Building Subjected To Blast Load Using Time History Method
Analysis of Multi-Storey RC Building Subjected To Blast Load Using Time History Method
ISSN No:-2456-2165
Abstract:- The impact of the blast load on the structure explosion based on the standoff distances as Air Blast, Free
due to the increase of terrorist activities is a serious Air Blast and Surface Air Blast.
issue causing failure of the buildings and loss of life.
Depending upon the location of blast within or nearby M.T.R Jayasinghe et al. (2010) studied the non-linear
buildings the structure undergoes ravaging failure due dynamic response of the tall buildings with and without
to explosion. In the present study, G+5 storeyed setbacks. The 20 storey buildings is considered for the
building is subjected to 200, 400 and 600 kg charge study which is designed for imposed load, dead load and
weight of the blast load with a standoff distance of 20, wind load. Time history analysis is carried out using SAP
40 and 60m. IS:4991 – 1968 is used to determine the 2000 for the buildings with 500kg charge weight of the
blast parameters. The time history analysis is carried blast. Storey drift, peak deflection, acceleration and
out using ETABS 2016 software. The response of the bending moments are obtained. Great variations are
structure is determined in terms of displacement v/s observed in the response near the setback storey level due
time, velocity v/s time and acceleration v/s time, storey to the blast load. Placement of the shear wall in the face of
drift, column forces and storey displacement. the building effecting by the blast load improves the
Depending on the source of the blast load and the strength of the building decreasing the damage of the
charge weight of the explosive, response of the building structure. Aditya C. Bhatt et al. (2013) have conducted a
and safe standoff distance is found. To make the comparative study of four storey building subjected to both
building more resistible for blast load, various blast load and earthquake load using ETABS software.
structural systems like shear wall and steel bracings are Linear time history method is carried out for the analysis.
implemented. Displacement of the structure subjected to blast load is very
high due to high intensity of blast load compared to the
Keywords:- Blast load; Standoff distance; Charge Weight; earthquake load and very high variation in different storeys.
ETABS 2016. In case of structures subjected to earthquake load,
displacement proportionally increases. Quantity of concrete
I. INTRODUCTION used for EQ resisting building is 40% less than blast
resisting building. Safe standoff distance and charge
Due to the increase in terrorist and explosion explosive for earthquake resistant RC building is obtained
activities and even the natural activities, their effect on the using trial and error method. Helen Santhi.M et al. (2013)
structure has become a serious issue which leads to damage have investigated the dynamic response of the space
of the structures, death of people and economical loss as framed structure due to blast load. A type of fibre
well. An explosion is a chemical response that releases reinforced concrete (FRC) with high fibre content is used
large amount of energy and hot gases consisting of loud as an alternative of RCC which is SIFCON (Slurry
sound and a bright flash. It occurs within a few seconds of Infiltrated Fibre Reinforced Concrete) having high strength,
duration resulting in release of high temperature and ductility and energy absorbing capacity. Using SAP2000
pressure. In many countries, considering blast effects in the software the models are developed and time history
structural analysis and other techniques are initiated in analysis is carried out for blast load. The displacement time
order to protect the structures and build environment. An history response of the model with SIFCON and RCC was
explosion, depending on the occurrence of blast i.e., near or compared and the capacity of the SIFCON frame was
far from the structure, can cause ruinous damage to the observed to be better than RCC frame under blast load with
internal or external frames of the structure. Thus, special the reduction in displacement of about 25 to 30%. A.V.
care should be taken in designing the structures considering Kulkarni and Sambireddy G, (2014) studied the response of
the blast load effect. the high rise building subjected to blast load. SAP 2000
software was used for the modelling of the building and to
The classification of blast loads is done based on the know the lateral stability of the building due to blast load.
confinement of explosives as two types; Two different charge weights of around 400kg and 800kg
Confined Explosion and Unconfined Explosion. The were considered with 5m and 10m standoff distances. Non-
confined explosion is further classified into three types linear modal analysis was carried out to know the response
depending on the area of confinement as Fully vented of the building. The primary parameters obtained were total
explosion, Partially vented or confined explosion and Fully drift and inter-storey drift. The standoff distance and blast
confined explosion. There are three types of unconfined source point was the important parameter in the study. The
II. BLAST LOAD PHENOMENA AND Fig. 1:- Blast Wave Propagation
INTERACTION
A blast wave generated during an explosion spreads
When the blast occurs at a location there will be a through the surrounding air and due to which a shock front or
huge amount of hot gases released which is the compresses wave is created. This shock wave created surround the entire
the surrounding gases and travels away from the blast building subjected to blast pressure.
source with higher velocity. The distance between the blast
source point and the structure is called as the standoff The factors affecting the blast load are the material type,
distance. As the blast wave travels away from the blast weight of the explosive, amount of the energy released during
source the pressure or the intensity of the wave goes on the blast, distance between the detonation point and the structure
reducing and due to this the effect on the building with called as standoff distance and intensity of the pressure released.
higher standoff distance will be less and the time duration The Fig.2 below shows the interaction of blast wave with the
required to reach the building is reduced. The Fig.1 shows building.
the blast wave propagation curves depending on the
pressure and distance from the explosion or the blast source.
2.1 Typical Blast wave Pressure-Time history curve in the standoff distance from the blast source. And this
Fig. 3 shows the typical blast wave pressure-time eventually becomes equal to the ambient pressure with time
history curve. Initially, when the explosion takes place duration (tA + to + to) which is called as negative phase
during the arrival time of the blast wave, the pressure duration which is longer than the positive phase duration.
present in the surrounding is equivalent to the Ambient During this negative phase duration, the building or the
pressure (Po) and then it suddenly rises to Peak pressure structure is subjected to suction forces which results in
(Pso) in the fraction of second which is in the time (tA) failure of façade of the building such as glass segments or
when blast wave reaches the structure. To achieve the peak windows lying outside the building. This negative phase of
pressure the time required is very small and thus it is taken the curve is neglected during the design as its effect on the
as zero during the design. This peak pressure is also called structure is less when compared to the positive phase of the
as side-on overpressure and it decreases with the increase pressure time history.
P P P F
Joint F.L Z (20m) Z (40m) Z (60m) A m2 F (20m) F (60m)
(20m) (40m) (60m) (40m)
1 34.2 68.4 102.6 317 73 38.8 7.00 2219 511 271.6
2 & 4 GL 34.9 68.7 102.8 300 72.5 38.7 6.13 1839 444.4 237.2
3 & 5 36.2 69.4 103.3 271.8 71.3 38.5 2.63 714.8 187.5 101.3
1 34.7 68.7 102.8 305 72.5 38.7 13.0 3965 942.5 503.1
2 & 4 1 35.4 68.9 102.9 289 72.2 38.7 11.38 3288.8 821.6 440.4
3 & 5 36.7 69.7 103.5 264 70.8 38.5 4.88 1288.3 345.5 187.9
1 36.0 69.3 103.2 275 71.5 38.6 12.0 3300 858 463.2
2 & 4 2 36.6 69.6 103.4 265.6 71 38.5 10.5 2788.8 745.5 404.3
3 & 5 37.9 70.3 103.8 245 69.8 38.4 4.50 1102.5 314.1 172.8
1 37.9 70.3 103.8 245 69.8 38.4 12.0 2940 837.6 460.8
2 & 4 3 38.5 70.6 104.1 235.8 69.3 38.3 10.5 2475.9 727.7 402.2
3 & 5 39.7 71.3 104.6 220.7 68.1 38.1 4.50 993.15 306.5 171.5
1 40.3 71.6 104.8 214.5 67.6 38.1 12.0 2574 811.2 457.2
2 & 4 4 40.9 71.9 105.0 208.3 67.2 38.0 10.5 2187.2 705.6 399
3 & 5 42.1 72.7 105.5 195.9 65.8 37.8 4.50 881.55 296.1 170.1
1 43.3 73.4 105.9 183.5 64.6 37.7 12.0 2202 775.2 452.4
2 & 4 5 43.8 73.7 106.2 178.4 64.1 37.6 10.5 1873.2 673.1 394.8
3 & 5 44.9 74.3 106.6 167 63.1 37.5 4.50 751.5 284.0 168.8
1 46.6 75.4 107.4 155.3 61.4 37.2 6.00 931.8 368.4 223.2
2 & 4 6 47.1 75.7 107.6 152 61.0 37.1 5.25 798 320.3 194.8
3 & 5 48.1 76.3 108.0 145.4 60.2 37.0 2.25 327.2 135.5 83.3
Table 1:- Pressure and Joint load acting on the front face of the building due to explosive weight of 200kg at 20m, 40m and 60m
standoff distance
P P P F
Joint F.L Z (20m) Z (40m) Z (60m) A m2 F (20m) F (60m)
(20m) (40m) (60m) (40m)
1 27.14 54.3 81.4 573 112.7 54.7 7.00 4011 788.9 382.9
2 & 4 GL 27.7 54.6 81.6 543.4 111.4 54.6 6.13 3331 682.9 334.7
3 & 5 28.8 55.1 82.0 484.4 109.2 54.3 2.63 1274 287.2 142.8
1 27.6 54.5 81.6 548.8 111.8 54.6 13.0 7134.4 1453 709.8
2 & 4 1 28.1 54.8 81.7 521.9 110.5 54.5 11.38 5939.2 1257 620.2
3 & 5 29.1 55.3 82.1 468.3 108.4 54.2 4.88 2285.3 528.9 264.5
1 28.9 55.0 82.0 479 109.6 54.3 12.0 5748 1315 651.6
2 & 4 2 29.1 55.3 82.1 468.3 108.4 54.2 10.5 4917.2 1138 569.1
3 & 5 30.1 55.8 82.5 417.5 106.2 54 4.50 1878.8 477.9 243
1 30.0 55.8 82.5 420 106.2 54 12.0 5040 1274 648
2 & 4 3 30.5 56.1 82.6 407.5 104.9 53.9 10.5 4278.8 1101 565.9
3 & 5 31.5 56.6 83.0 382.5 102.7 53.6 4.50 1721.3 462.1 241.2
1 32.0 56.9 83.2 370 101.4 53.5 12.0 4440 1216 522
2 & 4 4 32.5 57.1 83.4 357.5 100.7 53.4 10.5 3753.8 1057 560.7
3 & 5 33.4 57.7 83.7 335.6 99.1 53.2 4.50 1510.2 445.9 239.4
1 34.3 58.2 84.1 314.6 97.8 52.9 12.0 3775.2 1173 634.8
2 & 4 5 34.8 58.5 84.3 303 97 52.7 10.5 3181.5 1018 553.4
3 & 5 35.6 59.0 84.6 284.3 95.6 52.4 4.50 1279.4 430.2 235.8
1 37.0 59.8 85.2 259.3 93.5 51.8 6.00 1555.8 561 310.8
2 & 4 6 37.4 60.1 85.4 253 92.7 51.6 5.25 1328.3 486.6 270.9
3 & 5 38.2 60.6 85.7 240.5 91.4 51.3 2.25 541.2 205.6 115.4
Table 2:- Pressure and Joint load acting on the front face of the building due to explosive weight of 400kg at 20m, 40m and 60m
standoff distance
Similarly, Joint load, F acting on the building is The response of the building in terms of joint
calculated for charge weight of 600kg with 20m, 40m and displacement, velocity and acceleration is obtained when
60m standoff distances. the building is subjected to the blast load of different
charge weight with varying standoff distances. The
IV. RESULTS AND DISCUSSION following Figures 8, 9 and 10 represents the plot of joint
displacement (mm) verses time (sec), joint velocity (m/sec)
The behavior of the building subjected to blast load verses time (sec) and joint acceleration (m/sec2) verses time
acting on the front face of the building with various charge (sec) respectively.
weight and standoff distances is discussed in this chapter.
The response of the building is obtained as storey
displacement, storey drift, joint displacement v/s time, joint
velocity v/s time, joint acceleration v/s time and column
forces. These results extracted are tabulated and discussed
as shown below.
Displacement in mm 452.158 192.994 136.067 611.232 256.298 160.144 771.334 308.268 188.441
Velocity in m/s 3.94 1.75 1.24 5.47 2.32 1.46 6.9 2.78 1.71
Acceleration in m/s2 96.55 43.45 30.27 139.52 57.83 36.08 176.87 69.77 42.43
Table 3:- Comparison of joint displacement, velocity and acceleration of the building subjected to various charge weight and
standoff distances
In order to make the building as blast resisting when compared with bare frame building and the building
structure, various structural system such as shear wall and with corner X steel bracings reduces displacement and drift
steel bracings are provided at the corner periphery of the by 23.6% and 13% respectively when compared with bare
building. frame building.
Thus, it can be concluded that implementation of
shear wall is more effective in the building against blast
load when compared with bare frame building and corner X
steel bracing building.
V. CONCLUSIONS
ACKNOWLEDGMENTS
Fig. 12:- Storey Drift of bare frame building, building with
corner shear wall and steel bracings The authors thank Professor and Head, Dr. Nalini
Elizebeth Rebello, Department of Civil Engineering and Dr.
From Fig.11 and 12, it is observed that the R Srinivasa Rao Kunte, Principal, Sahyadri College of
displacement and drift in the building with shear wall and Engineering and Management, Mangalore for their support
steel bracings is less than conventional bare frame building. and advise in carrying out this research as a part of M.Tech
project.
The building with corner shear wall reduces the
displacement and drift by 53.51% and 30.04% respectively
REFERENCES