Detailed Sub-Estimateproviding Ci Pipes & Specials To Ohsr at Bapunagar (V) of Yedapally (M)
Detailed Sub-Estimateproviding Ci Pipes & Specials To Ohsr at Bapunagar (V) of Yedapally (M)
2 S/d of 80 mm dia x0.90 m CI D/F pipes 3 Nos 872.11 1.00 Each 2616.00
3 S/d of 80 mm dia x0.60 m CI D/F pipes 3 Nos 666.70 1.00 Each 2000.00
5 S/d of 80 mm dia CI sluice valve PN - 1.0 2 Nos 4553.34 1.00 Each 9107.00
TOTAL 45000.00
1) INTRODUCTION:- The Habitation is located in Armoor mandal and is _____ km from the mandal
head quarters. The population of the village as per 2001 cencus is __________
4) DEVIATIONS- Pipe line provided with HDPE pipes in place of PVC pipes
a) Distribution with 110& 90 mm dia 4Kg/cm2 PE-80 Grade HDPE Pipe line
b) Construction of RCC Valve chambers
c) HDPE & GI Specials
d) Provision for 0.50% QC inspection & 0.50% QC investigation Charges
5) CONCLUSION:- With the above Items of work, the working estimate is preapared with common
SSR 2004-05 worked out to Rs 1.50 Lakhs.
AEE/AE
(PR) RWS Mandal:Armoor
GENERAL ABSTRACT ESTIMATE FOR PROVIDING
___________________________________________________________
AT __________________________________ (V) _____________________________ (M)
1 2 3 4 5 6
TOTAL
AEE/ AE
(PR) RWS Mandal: ______________________
DETAILED SUB - WORKING ESTIMATE FOR PROVIDING DISTRIBUTION TO PWS SCHEME
AT RAMPUR (V) ARMOOR( M )
110mm dia 4 Kg/cm2 PE-80 HDPE Pipe line 405.00 m 205.87 1 Rmt 83377.00
75 mm dia 4 Kg/cm2 PE-80 HDPE Pipe line 165.00 m 103.84 1 Rmt 17134.00
TOTAL 100511.00
AE/AEE
(PR) RWS Mandal: Armoor
DATA SHEET FOR CONSTRUCTION OF RCC VALVE CHAMBERS
AT RAMPUR (V) ARMOOR MANDAL.
Sl. Description of work N L B D Qty Rate Per Amount
1 2 3 4 5 6 7 8 9 10
1 Earth Work Excavation depositing on bank with an intial lead and intial lift
of 2 mts in ordinary soils etc complete
For foundation II/4x7 1.20 1.20 1.00 1.13
1.13 cum 43.68 1.00 10 cum 49.00
2 Fiiling founds with Cement Concrete In CM(1:4:8) prop. Using with 40mm
guage HG broken stone metal including cost and conveyance of all labour
and metrilas charges etc complete
For foundation II/4x7 1.20 1.20 0.15 1.19
1.19 cum 1427.92 1.00 1 cum 1695.00
3 RCC in cm(1:2:4) prop using 20mm guage metal including cost and conveyance
of all charges including of all charges. But excluding cost and conveyance of steel
and fabrication charges etc., complete.
Sidewalls IIx7 0.90 0.10 0.90 1.78
Roof slab over chambers II/4x7 1.20 1.20 0.10 0.79
2.57 cum 2418.28 1.00 1 cum 6219.00
5 Add cost of steel and fabrications charges. 70.00 Kgs 33.28 1.00 Kg 2330.00
6 CI Manhole frame with cover Ix7 7.00 Nos 480.00 1.00 Each 3360.00
TOTAL= 14186.00
Assistant Engineer,
(PR) RWS Mandal: Armoor
DATA SHEET (SSR-2004-05)
Sl.N0. Quantity Description of Item Rate Per Amount
1 2 3 4 5 6
1 1.00 Cum Earth work excavation and depsiting on bank with 28.00 1 Cum 28.00
an initial lead of 10M and lift 2M in ordinary
gravetly soils etc., complete as per S.S. 20-B
1 2 3 4 5 6
Assistant Engineer
(PR) RWS Mandal:Armoor
LEAD STATEMENT AS PER 2004-2005 SSR
Add Deduct Add machine
Place of Availability Lead in Conveyance Initial cost Add S/
Sl.No. Name of the Material Unit blasting stacking crushing Total
of Material kM charges of Material charges
charges charges charges
1 2 3 4 5 6 7 8 9 10 11
1 Sand for mortar 1 Cum Jankampet 20 139.90 71.00 0.00 3.70 0.00 36.00 243.20
2 40MM Metal 1 Cum Munipally 14 132.20 269.00 53.00 6.10 0.00 45.00 493.10
3 20 MM Metal 1 Cum Munipally 14 132.20 470.00 53.00 6.10 117.50 45.00 811.60
4 Bricks 1000Nos Local 5 168.30 1250.00 0.00 5.90 0.00 35.00 1447.40
*NOTE* 1) The above quaries are nearer to site to the best of my knowledge.
2) The above leads are correct to the best of my knowledge.
3) The quaries requires full blasting.
Assistant Engineer
(PR) RWS Mandal:Armoor