This document provides a list of items and quantities for erection work. It includes erecting structures like a DP structure and transformer. It also includes laying cables of various sizes both underground and overhead in trays. Other items listed are panels, earthing, distribution boards, lighting work for pump house and filter house, wiring, and fan points. The overall work involves installation of electrical infrastructure for power distribution and lighting.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
480 views8 pages

Electrical Erection Work

This document provides a list of items and quantities for erection work. It includes erecting structures like a DP structure and transformer. It also includes laying cables of various sizes both underground and overhead in trays. Other items listed are panels, earthing, distribution boards, lighting work for pump house and filter house, wiring, and fan points. The overall work involves installation of electrical infrastructure for power distribution and lighting.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

ERECTION WORK

SI No Description of item of work Qty


1 Erection of DP structure as per particular specification 1
2 Erection of outdoor type VCB 3 Panel 1
3 Erection of 1000KVA Transformer 11 KV / 433V, 1
4 Erection of 1600A Busduct
Out door 1
Indoor 1
Coupler 1
5 Laying of 3 Cx 185 sqmm XLPE - E - AL for 1
6 Laying of 3 C x 240 sqmm XLPE - E - AL 1
7 Erection of cable end terminations for 3 C 185 sqmm XLPE AL 1
8 Erection of cable end terminations for 3 C 240 sqmm XLPE AL 1
9 Laying of 4C 1.5 sqmm 1
10 Laying of 19C 2.5 sqmm 1
11 Erection of cable end terminations for 4C 1.5 sqmm 1
12 Erection of cable end terminations for 19C 2.5 sqmm 1
Laying cables directly in ground complete with:
i) excavation (upto hard murram)
ii) sand filling below & above the cable upto 300mm
13 1
iii) layer of cement tiles
iv) back filling
v) cable markers (@ 15m CC)
14 Erection of Main MV Panel 1
15 Erection of APFC panel 1
16 Erection of LIGHTING PANEL 1
17 Erection of MCC-1 1
18 Erection of MCC-2 1
19 Erection of MCC-3 1
20 Erection of PDB 1
21 Filter Console conforming to SLD 1
Laying of 2Rx 3C x 240 sqmm XLPE-AL,AR for laying between Main MV panels to
22 pump motors, MCC-1 and APFC Panels as per SLD (Cable laying within pump 1
room shall be in Cable Trench)

2Rx3.5 C x 300 sqmm XLPE-AL for laying the cable from Main panel to MCC-1 &
23 1
MCC-2 as per SLD

24 1Rx3 Cx 400 sqmm XLPE-AL for laying between main Panel and APFC Panels 1

25 1Rx 3.5 C x 95 sqmm XLPE-AL for laying between Main Panel and Lighting panel, 1
MCC-1 to MCC-2
26 Laying of 4 C 16 sqmm XLPE-AL 1
27 Laying of 3 C 16 sqmm XLPE-AL 1
28 Laying of 3 C 10 sqmm XLPE-AL 1
29 Laying of 4 C 6 sqmm.Cu.Ar 1
30 Laying of 4 C 4 sqmm Cu.Ar 1
31 Laying of 4 C 2.5 sqmm Cu.Ar 1
32 Laying of 3 C 1.5 sqmm Cu.Ar 1
33 Erection of 3.5 C 300 sq.mm & 3 C 240 sqmm XLPE-AL,AR 1
34 Erection of 3 C 400 sqmm XLPE-AL 1
35 Erection of 3.5 C 95 sqmm XLPE-AL 1
36 Erection of 3 C 25 sqmm XLPE-AL 1
37 Erection of 4 C 16 sqmm XLPE-AL 1
38 Erection of 3 C 16 sqmm XLPE-AL 1
39 Erection of 3 C 10 sqmm XLPE-AL 1
40 Erection of 4 C 6 sqmm.Cu.Ar 1
41 Erection of 4 C 4 sqmm Cu.Ar 1
42 Erection of 4 C 2.5 sqmm Cu.Ar 1
43 Erection of 3 C 1.5 sqmm Cu.Ar 1
Cable Trays
44 150 x 50 mm wide (perforated GI tray) 1
45 200 x 50mm wide (perforated GI tray) 1
46 300 x 50 mm wide (perforated GI tray) 1
47 450 x 50 mm wide (perforated GI tray) 1
48 300 x 50 mm wide (ladder GI tray) 1
49 450 x 50mm wide (ladder GI tray) 1
50 600 x 75 mm wide (ladder GI tray) 1
51 750 x 75mm wide (ladder GI tray) 1
DISTRIBUTION BOARD
52 Erection of 8 Way DB 1
53 Erection of MCB DB double door 1
54 Erection of VTPN MCB DB double door 1
55 Erection of MCB DB double door type, 1
EARTHING
Earthing with Copper earth plate 600mm x 600mm x 3mm thick including
accessories and providing masonary enclosures with cover plate having locking
56 1
arrangement and watering pipe of 3 mtrs long etc., with charcoal or coke &
complete as required.
Earthing with G.I. earth pipe 3 metre long, 65 mm dia including accessories, and
57 providing masonry enclosure with cover plate having locking arrangement and 1
watering pipe etc. with charcoal/ coke and salt as required.

Providing and fixing following sizes of GI / copper Flat / wire on surface or in


recess for connections etc. as required. 1

58 50 x 10 mm Copper Flat 1
59 50 x 6 mm GI Flat 1
60 25 x 6 mm GI Flat 1
61 8 SWG GI Wire 1
62 8 SWG Cable Wire 1
PUMP HOUSE and FILTER NOUSE lighting
63 a) 40W – 1200mm single box type fluorescent tube lamps with electronic choke 1
inside the filter house near each filter unit
64 b) 40W – 1200mm single box type fluorescent tube lamps with electronic choke 1

65 c) 40W – TWIN fluorescent tube lamps with electronic choke to be fixed within 1
buildings
66 d)15/5 Amps 3 pin plug with socket. 1

67 e) Portable inspection lamp with 100W bulb lamp guard wooden handle and 25m 1
long flexible wire.

68 f) Water proof 150 Watts sodium vapour lamp with choke and other fittings to be 1
erected outside pump house
69 g)300mm Exhaust Fans including allied civil works. 1

h) Bulk type fittings with lamps of 100 watts to be fitted outside Pump House,
70 chlorine building, chemical building and filter house with 3m long GI post with 1
control switches in weather proof box and wiring.
71 i) Fan with regulator 1200 mm 1

72 j) Ornamental fittings with 20 W lamps to be fixed on compund wall with control 1


switches

Wiring with 3R x 1.5 sq.mm PVC insulated FRLS multi strand copper wires of
650V grade for the light point as shown in the drawing in heavy duty PVC pipe of
size 20/25 mm concealed in ceiling/wall/partitions with MS switch box of suitable
size including providing 16 SWG GI fish wire for each light point . The rate shall
be inclusive of laying and jointing all accessories like PVC pipe, bend, coupling,
clamps, screws and adopter boxes, wall chasing and making good of PVC pipe,
bend, coupling, clamps, screws and adopter boxes, wall chasing and making
good of concealed portion with chicken mesh wherever necessary and cement
mortar etc. The following are the controls light points:

One light controlled by Modular 6A switch.( Pump house 12+ Filter house
73 1
30+Chemical house 12+ chlorination room 6)
Two light controlled by Modular 6A switch (pump house 2+ chemical 2+chlorine
74 1
1)
75 Three light controlled by Modular 6A switch.( Out door unis) 1
WIRING - FAN POINT

Wiring with 3R X 1.5 sq mm PVC insulated FRLS multi strand copper wires of
650V grade in heavy duty PVC pipe of size 20/25 mm in concealed
ceiling/wall/partitions and to provide Fan hook box, 16 SWG GI fish wire for each
Fan point as shown in the drawing. The rate shall be inclusive of laying and
76
jointing all accessories like PVC pipe, bend, coupling, clamps, screws and Adopter
boxes,wall chasing and making good of concealed portion with chicken mesh
wherever necessary and cement mortar etc. The following are the controls light
points:
Ceiling fan point controlled by 1 No. 6A Modular switch with stepped fan
76 regulator. 1

77 One exhaust fan point controlled by a 6A Modular switch. (Pump house 1


2+Chemical 4+Chlorine 4)

78 One light point controlled by 2Nos. 6A modular two way switch.(pump house 1
1+Chemical 1)
LIGHTING CIRCUIT MAIN
79 2Rx2.5sqmm(P & N) + 1Rx1.5sqmm(earth), multistranded copper wire. 1
80 2Rx1.5sqmm(P & N) + 1Rx1.5sqmm(earth), multistranded copper wire. 1
81 25 mm dia with 1.8 mm thick heavy duty PVC conduit. 1
82 20 mm dia with 1.8 mm thick heavy duty PVC conduit. 1
POWER CIRCUIT MAIN

Supply and installation of 25mm dia heavy duty PVC conduits with 1.8 mm thick
sturdy in concealed ceiling/wall/partitions and to provide 18 SWG GI fish wire and
fixing accessories etc., as required complete. The rates shall include chasing of
walls, floors etc, plastering the chased portion as required. And to cost of
83
providing PVC insulated stranded copper conductor earth wire in each conduit
along with other circuit main wires and to provided adopter boxes etc., Power
circuit wiring from lighting power distribution board to respective power point
shall be measured and paid in this item.

2Rx4sqmm + 1Rx2.5sqmm(earth) multi stranded copper wires in 25/20 mm dia


84 1
PVC conduit.
85 25 mm dia with 1.8 mm thick heavy duty PVC conduit. 1
20 mm dia with 1.8 mm thick heavy duty PVC conduit. Note:
86 1
Payment will be made for actual length measured for the above wiring.
Supply and Erection of key type operated emergency stop push button NC,Start
87 1
push button NO with Indoor type enclosure for pump.motors
RA
UOM TOTAL
TE
set 90000 90000
set 75000 75000
No 30000 30000
0
m 2000 2000
m 2000 2000
m 2000 2000
m 1000 1000
m 1000 1000
No 500 500
No 500 500
m 50 50
m 200 200
Set 100 100
Set 500 500
0
200 0
100 0
m
300 0
100 0
50 0
set 25000 25000
set 10000 10000
set 5000 5000
set 5000 5000
set 5000 5000
set 5000 5000
set 10000 10000
No 3000 3000

m 300 300

m 300 300

m 150 150
m
150
150
m 150 150
m 150 150
m 100 100
m 100 100
m 100 100
m 75 75
m 75 75
set 500 500
set 300 300
set 300 300
set 200 200
set 150 150
set 150 150
set 150 150
set 200 200
set 200 200
set 200 200
set 100 100
0
m 1270 1270
m 1838 1838
m 2194 2194
m 3320 3320
m 3000 3000
m 3500 3500
m 4000 4000
m 5000 5000
0
set 1500 1500
set 2000 2000
set 2500 2500
set 2000 2000
0

set 15000
15000

set 10000
10000

2500
2500
m 1000 1000
m 100 100
m 100 100
m 100 100
m 300 300
0
No.
50
50
No. 50 50
No.
75
75
No. 50 50
No.
50
50

No.
1000
1000
No. 500 500

No. 500
500
No. 100 100
No.
400
400

No.
600
600
No. 100 100
No. 100 100
0

No. 0
No. 0

No. 0
0
m 0
m 0
m 0
m 0
0

m 0
m 0
m 0

No. 0

You might also like