III 1 Epoxy Coatings and Cement Mortar Lining - Cleaned
This document summarizes a presentation on epoxy coatings and cement mortar lining for pipe rehabilitation. It discusses the history of pipe rehabilitation technologies, including CIPP which has been used for over 40 years. Options for rehab include slip lining, pipe bursting, cement mortar lining, epoxy coatings, polyureas, and CIPP. Unlined cast iron pipes need rehab to improve water quality, flow capacity, and reduce breaks and corrosion. Cement mortar lining and polyurethane/polyurea coatings are applied through spray rigs. The rehab process requires access pits, bypass, cleaning, curing, and restoration.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
55 views17 pages
III 1 Epoxy Coatings and Cement Mortar Lining - Cleaned
This document summarizes a presentation on epoxy coatings and cement mortar lining for pipe rehabilitation. It discusses the history of pipe rehabilitation technologies, including CIPP which has been used for over 40 years. Options for rehab include slip lining, pipe bursting, cement mortar lining, epoxy coatings, polyureas, and CIPP. Unlined cast iron pipes need rehab to improve water quality, flow capacity, and reduce breaks and corrosion. Cement mortar lining and polyurethane/polyurea coatings are applied through spray rigs. The rehab process requires access pits, bypass, cleaning, curing, and restoration.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17
PIPELINE REHABILITATION
UCT – 2017 Conference
Epoxy Coatings & Cement Mortar Lining
(and the Technical Talk)
Presenters – Lenny Assard & David Rosenberg, Michels Corporation
History & Evolution of Pipe Rehabilitation • Overview of Pipe Rehabilitation CIPP more than 40 years old for sewer mains Definition – same pipe, same trench, uses the existing host pipe CIPP for drinking water applications – more than 10 years old CML has been used for more than 70 years Epoxy / Spray-on coatings more than 20 years in the US
• New Technologies – Continued enhancements to existing technologies –
including UV liners & Geopolymers Why Unlined cast iron host pipes need to be rehabbed? • Improve Fire Flow Capacity • Increase Hazen Williams Coefficient • Improve Water Quality • Reduces Energy Cost • Reduces potential for water main breaks • Reduction of corrosion to host pipe Where or When to Rehabilitate Mains? • Poor water quality areas – heavy tuberculation • Low flow areas • Older neighborhoods • Look where past water main breaks have occurred (develop a scoring system) • Evaluate open areas versus established neighborhood • Dig & replace versus rehab? Cement Mortar • Non Structural • Spray Applied • Used mainly for water quality • AWWA STD C-602 – Performance Standard • Used for mains over 3 inches in diameter • In the US since 1933, 24” and above • Since 1950, smaller diameters • Thickness varies depending on host pipe & diameters – 3/16 to 5/16 inches Polyurethane/Polyureas • Non Structural – Semi Structural • Spray Applied • Calibration of rig required to maintain proper thickness • Temperatures, mixing rations, weights of material critical • Will be used in host pipes 3 inches and above • Thickness depends on application & host pipe material Other Rehab Options • Pipe Bursting • Upsizing may be possible • PVC, HDPE, DI materials can be used • Service issues • Slip Lining • PVC, HDPE • Smaller diameter • Service Issues Additional Processes Required to Perform Work • Install temporary bypass • Create access pits to the host pipe • Clean & CCTV the host pipes prior to performing the work • May require a dry host pipe prior to performing the work Continued –Additional Processes Required to Perform Work • Cure is required to set the product • Restore existing services • Perform pressure testing • Chlorinate the mains – perform BAC-T tests • Flushing of water mains • Site restoration Project Steps • Provide access to the main – similar for all rehab options • Clean & CCTV similar for all rehab options • Temporary by-pass – dependent on lining rehab option • Traffic control • Apply lining & cure • Cement Mortar – 24 Hrs • Epoxy - 16 Hrs • Polyurethanes - Less than 30 minutes • Polyureas - Less than 30 minutes • Site restoration Temporary By-Pass Spray Rig - CML Spray Rig Resources • American Water Works Association (AWWA) – M28 3rd Edition • United States Environmental Protection Agency (EPA) – May 2002 • Hazen and Sawyer – Buried Assets Article 2011 Questions?
Thank You Michels Corporation Lenny Assard David Rosenberg