Karnataka Neeravari Nigam Ltd. Singatalur Lift Irrigation Scheme

The document appears to be a rate analysis for construction of an anganwadi building in Bidralli Rehabilitation Center under the Singatalur Lift Irrigation Scheme. It includes analysis of rates for various construction materials from 2012-13 to present considering factors like transportation costs, contractor profit, and overhead charges. Materials included are cement, steel, sand, metal stones, murrum, and black cotton soil. The sources identified for these materials are within 56km. The rate analysis will be used to determine appropriate costs for items in construction of the anganwadi building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
319 views18 pages

Karnataka Neeravari Nigam Ltd. Singatalur Lift Irrigation Scheme

The document appears to be a rate analysis for construction of an anganwadi building in Bidralli Rehabilitation Center under the Singatalur Lift Irrigation Scheme. It includes analysis of rates for various construction materials from 2012-13 to present considering factors like transportation costs, contractor profit, and overhead charges. Materials included are cement, steel, sand, metal stones, murrum, and black cotton soil. The sources identified for these materials are within 56km. The rate analysis will be used to determine appropriate costs for items in construction of the anganwadi building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 18

Karnataka Neeravari Nigam Ltd.

Singatalur Lift Irrigation Scheme

KARNATAKA NEERAVARI NIGAM LIMITED


SINGATALUR LIFT IRRIGATION SCHEME
RATE ANALYSIS FOR THE CONSTRUCTION OF ANGANWADI BUILDING AT BIDRALLI REHABLITATION
CENTER COMING UNDER SUBMERGENCE OF BARRAGE OF SLIS

Details for Difference in cost of cement: -

Rate of cement in SR (2012-13) = 290.00 / bag

Rate of cement applicable as per present quarter issue rate = 312.00 / bag

Difference in cost of cement = 312.00 - 290.00 = 22.00 / bag


Add 10% contractor's profit & 5% overhead charges = = 3.30 / bag
= 25.30 / bag

ii) Details for Difference in cost of steel: -

Rate of steel in SR (2012-13.) = Rs 43000.00/MT

Rate of steel applicable = Rs 46500.00/MT

Difference in cost of steel = 46500.00 - 43000.00 = Rs 3500/MT

E I Technologies Pvt. Ltd. LBMC III Reach - Rate Analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

KARNATAKA NEERAVARI NIGAM LIMITED


SINGATALUR LIFT IRRIGATION SCHEME

LEAD STATEMENT FOR CONSTRUCTION OF LEFT BANK MAIN CANAL - REACH III
(10.00 to 11.00) Km
Deduct Initial
Sl Total Lead Loading Unloading
Materials Name of Quarry Lead Charges Lead Charges Total Charges
No in Km Charges Charges
(Rs.)
Tungabhadra river near 0.00 54.20 10.20 540.70 / cum
1 Sand 56 76.20 + 25 x 8.10 + 26 x 7.60 = 476.30
Gumgola village 41.40 434.90 / cum
Metal / Size 0.00 64.00 32.00 381.20 / cum
2 Baradur 29 93.20 + 24 x 8.00 = 285.20
stone 58.40 226.80 / cum
7 67.30 + 2 x 5.00 = 77.30 0.00 59.70 59.70 196.70 / cum
3 Cement Gadag
6 67.30 + 1 x 5.00 = 72.30 0.00 59.70 59.70 191.70 / cum
7 67.30 + 2 x 5.00 = 77.30 0.00 59.70 59.70 196.70 / MT
4 Steel Gadag
6 67.30 + 1 x 5.00 = 72.30 0.00 59.70 59.70 191.70 / MT
0.00 54.20 130.40 / cum
5 Murum Local Quary 5 76.20 = 76.20
41.40 34.80 / cum
6 Murum Excavated stuff 0.5 41.40 = 41.40 41.40 / cum
0.00 54.20 130.40 / cum
7 B.C.Soil Local Quary 5 76.20 = 76.20
41.40 34.80 / cum
CERTIFICATE:
This is to certify that the leads considered for the above materials are from the nearest source and sufficent quantity of good quality is available at source.
There are No other sources near than the above sources.

Consultant Assistant Executive Engineer Executive Engineer Superintending Engineer


E I Technologies Pvt. Ltd., KNNL, SLIS R&R Sub- Division KNNL SLIS Division No.2 WRD, TBP Circle
Bangalore Mundaragi Huvinahadagali Munirabad

EI Technologies Pvt. Ltd., Bangalore LBMC Reach III Rate Analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

KARNATAKA NEERAVARI NIGAM LIMITED


SINGATALUR LIFT IRRIGATION SCHEME
RATE ANALYSIS FOR THE CONSTRUCTION OF ANGANWADI BUILDING AT BIDRALLI
REHABLITATION CENTER COMING UNDER SUBMERGENCE OF BARRAGE OF SLIS

Item no. 1
KSRB 2-1.1 : Earthwork in surface excavation in ordinary soil for levelling and lowering the ground manually ( other than
foundation of buildings, culverts, road drains and trenches of pipe lines and cables ) and removing the excavated stuff to
a distance not exceeding 50m and lift upto 1.5m, excavated surface levelled and neatly dressed, disposed earth to be
levelled after breaking of clods and neatly dressed as per specifications. specification. No. KBS 2.1(a) / 2.3.1

(SR Item No.2.1, page 5 of PWD SR, Dharwad Circle for 2014-15)
Basic Rate = Rs 136.00/ cum
Add 3% Area Weightage = Rs 4.08/ cum
Total = Rs 140.08/ cum
Err:511

Item no. 2
Earthworh excavation for foundation of buildings, culverts, water supply, sanitary lines and electrical conduits either in
pits or in trenches 1.50m and above in width, in ordinary soil not exceeding 1.50m in depth including dressing the
bottom and sides of pits and trenches, stacking the excavated soil clear from edges of excavation with lead upto 50m
after breaking of clods complete as per specifications. specification . No KBS 2.1(a) 2.3.5

(SR Item No.2.3, page 5 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 163.00/ cum
Add 3% Area Weightage = Rs 4.89/ cum
Total = Rs 167.89/ cum
Err:511

Item no. 3
KSRB 2-1.1 : Excavation1.5 m and above in width insoft rock by blasting for foundation of buildings, water supply,
sanitary lines and electrical conduits either in pits or in trenches 1.50 m depth, stacking the excavated stuff from edges
of excavation with lead upto 50m including cost of explosives, labuor and HOM of equipment complete as per
specifications. No KBS 2.1.C / 2.3.5 / 2.18 / 2.19

(SR Item No.2.5, page 5 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 439.00/ cum
Add 3% Area Weightage = Rs 13.17/ cum
Total = Rs 452.17/ cum
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 4
KSRB2.8:Providing and Filling in foundation with granite/trap broken metal100mm.and downsize,with approved sand
including hand packing,ramming,watering,including cost of all material sand labour with all lead and lift.complete as
perspecifications. specification. No. KBS

(SR Item No.2.15, page 6 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 1831.00/ cum
Add 3% Area Weightage = Rs 54.93/ cum
Total = Rs 1885.93/ cum
Err:511
Item no. 5
KSRB 4-1.7 : Providing and laying in position plain cement concrete of mix M10 with OPC cement @ 220kgs, with
20mm and down size graded granite metal coarse aggregates @0.84cum and fine aggregtes @ 0.56cum, machine
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation,plinth and cills, ncluding cost
of all materials, labour, HOM of machinery, curing complete as per specifications. Specification No. KBS 4.1, 4.2

(SR Item No.4.7, page 13 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 5195.00/ cum
Add 3% Area Weightage = Rs 155.85/ cum
Total = Rs 5350.85/ cum
Err:511

Item no. 6
KSRB 4.2.8: Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
320kgs, with 20mm and downsize graded granite metal coarse aggregates @ 0.69cum and fine aggregates @
0.46cum, with superplastisiser @ 3Its confirming to IS 9103-1999 Reaffirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in ground floor level for roof slabs, staircase, lintels, and beam
retaining walls, return walls, walls (any thickness) including attached plasters, columns, pillars, posts, struts, buttresses,
string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window cills, fillets etc.; including cost of all
materials, labuor, HOM of machinenery, curing, complete as per specifications. Secificatin No. 4.1, 4.6

(SR Item No.4.13, page 13 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 6056.00/ cum
Add 3% Area Weightage = Rs 181.68/ cum
Total = Rs 6237.68/ cum
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 7
KSRB 5.2-2: Providing and constucting granite/trap/basalt size stone masonry in foundation cement mortar 1:6 ,stone
hammered dressednin courses not less than 20 cms high, bond stones of 2 m .apart in each course including cost of
materials, labour, curing complte as per specifications. KBS 5.1.13

(SR Item No.5.6, page 23 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3173.00/ cum
Add 3% Area Weightage = Rs 95.19/ cum
Total = Rs 3268.19/ cum
Err:511
Item no. 8
Providing and constucting granite/trap/basalt size stone masonry in basement with cement mortar 1:6 ,edges of stones
chistle dressed in courses not less than 15 cms high, bond stones at two m .apart in each course including cost of
materials, labour, curing complte as per specifications. KBS 5.1.13

(SR Item No.5.9, page 23 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3681.00/ cum
Add 3% Area Weightage = Rs 110.43/ cum
Total = Rs 3791.43/ cum
Item no. 9
KKSRB 4.1.6 : Providing and laying in position reinforced cement concrete of mix M15 with cement @ 240kgs, with
20mm and down size graded granite metal coarse aggregates @ 0.878cum and fine aggregtes @ 0.459cum, machine
mixed, concrete laid in layers not exceeding 15 cms thick, well compacted, in foundation, plinth and cills, including cost
of all materials, labour, HOM of machinery, curing, complete as per specifications. Specification No. KBS 4.1, 4.2

(SR Item No.4.6, page 12 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 5258.00/ cum
Add 3% Area Weightage = Rs 157.74/ cum
Total = Rs 5415.74/ cum
Err:511

Item no. 10
KSRB 2.3 : Filling available excavated earth(excluding rock) in sides of foundation upto plinth in layers not exceeding
20cms. in depth, compacting each doposited layer by ramming after watering with lead upto 50m. and lift upto 1.5m.
including cost of all labour complete as per specifications. No. KBS 2.9

(SR Item No.2.10, page 6 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 110.00/ cum
Add 3% Area Weightage = Rs 3.30/ cum
Total = Rs 113.30/ cum
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 11
Providing and constructing burnt brick masonry for superstructure with approved quality of non-modular bricks of
standard size of class designation 35 with cement mortar 1:6 including cost of materials, labour charges scaffolding,
curing complete as per specifications. Specification No. KBS 6.2

(SR Item No.6.3, page 27 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 4860.00/ Cum
Add 3% Area Weightage = Rs 145.80/ Cum
Total = Rs 5005.80/ Cum
Err:511

Item no. 12
KSRB 4.2.10 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
24kgs, with 12mm and down size graded granite metal coarse aggregates @0.5175cum and fine aggregtes @
0.345cum, with superplastisiser @0.225lts, machine mixed, well compacted for plain chajja of 7.5 cms. average
thickness, upto ground floor level, including cost of all materials, labour, HOM of machinery, finishing, curing, complete
as per specifications. Specification No. KBS 4.1, 4.6

(SR Item No.4.19, page 14 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 441.00/ sqm
Add 3% Area Weightage = Rs 13.23/ sqm
Total = Rs 454.23/ sqm
Err:511

Item no. 13
KSRB 4.2.2 : Providing and laying in position reinforced cement concrete of design mix M20 with OPC cement @
320kgs, with 20mm and down size graded granite metal coarse aggregates @0.878cum and fine aggregtes @
0.459cum, with superplastisiser @3lts confirming to IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials, labour, HOM of machinery, curing, complete as per specifications.
Specification No. KBS 4.1, 4.6

(SR Item No.4.11, page 13 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 5929.00/ Cum
Add 3% Area Weightage = Rs 177.87/ cum
Total = Rs 6106.87/ Cum
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 14
KSRB 9.4-2 : Providing Honne wood frames of Doors, Windows, Ventilators and other frames , wrought, framed or
assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of
all materials, labour, HOM of machinaries complete as per specifications. specification No KBS 9.33

(SR Item No.9.11, page 51 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 75854.00/ cum
Add 3% Area Weightage = Rs 2275.62/ cum
Total = Rs 78129.62/ cum
Err:511

Item no. 15
KSRB 7.8 : Providing and fixing in position in cement concrete 1:3:6 steel glazed windows and ventilators side hung/top
hung 2/3 openable 1/3 fixed as per approved drawings using Z angles of 25x33x3mm, weighing 1.419 kg/m both for
outer and inner frames and central mullion section of size 25x46x3mm, weighing 2.28kg/m all duly providing T section
19x19x3mm weighing 0.839 kg/m for glazing of windows, not more than 34 cms. c to c including providing and fixing
4mm. thick reeded glass with teakwood beading of required size, all steel sections should confirm to I.S 7452:1990,
4nos. of holdfasts of approved size, section should be cut to length welded and grinded electrically subdividing frames of
unit shall be tenonned and revetted into the frames electrically. All the steel surface shall be throughly cleaned free of
rust and painted with one coat of anti-corrosive paint and finishing two coats of ready mix paint of approved colour and
make including cost of materials, fixtures, labour charges and HOM of machinery complete as per specifications.

(SR Item No.7.8, page 32 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3088.00/sqm
Add 3% Area Weightage = Rs 92.64/sqm
Total = Rs 3180.64/sqm
Err:511

Item no. 16
KSRB 9-7.2 : Providing and fixing in position fully panelled Honne wood shutters for doors, styles and rails of 30mm.
Thick with bottom and lock rails 180mm wide top rail and styles 100mm wide as per drawing and panels of 25mm thick
including cost of all materials, labuors, HOM of machineries complete as per specifications. (excluding cost of fixtures)

(SR Item No.9.21, page 52 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3229.00/sqm
Add 3% Area Weightage = Rs 96.87/sqm
Total = Rs 3325.87/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 17
KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for
foundations, footings, bases of columns, for mass concrete including cost of all materials, labuor, complete as per
specification No. KBS 4.6.2

(SR Item No.4.28 page 15 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 223.00/sqm
Add 3% Area Weightage = Rs 6.69/sqm
Total = Rs 229.69/sqm
Err:511

Item no. 18
KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for flat
surface such as suspended floors, roofs, landings, balconies and likes, thickness upto 200 mm including cost of all
materials, complete as per specifications.

(SR Item No.4.29.2, page 15 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 530.00/sqm
Add 3% Area Weightage = Rs 15.90/sqm
Total = Rs 545.90/sqm
Err:511

Item no. 19
KSRB 4-6.5 : Providing and removing centering, shuttering, strutting, propping etc., for columns ,pillars, piers,
abutments ,post and struts, square/ rectangular /polygon in plan including cost of all materials, complete as per
specifications. No KBS 4.6.2

(SR Item No.4.32, page 15 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 346.00/sqm
Add 3% Area Weightage = Rs 10.38/sqm
Total = Rs 356.38/sqm
Err:511

Item no. 20
KSRB 4-6.7 : Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides
and soffits of beams, beam haunchings, cantilever girders, bressumers and lintels not exceeding 1m in depth including
cost of all materials, lauor complete as per specifications.

(SR Item No.4.34, page 16 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 248.00/sqm
Add 3% Area Weightage = Rs 7.44/sqm
Total = Rs 255.44/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 21
KSRB 4-6.10 : Providing and removing centering, shuttering, strutting, propping etc., for chajjas, corbels etc., including
edges of includng cost of all materials, labuor complete as per specifications. No. KBS 4.6.2
(SR Item No.4.37, page 16 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 247.00/sqm
Add 3% Area Weightage = Rs 7.41/sqm
Total = Rs 254.41/sqm
Err:511

Item no. 22
KSRB 15-3.8 : Providing rough cement plastering 18mm thick in single coat with cement mortar 1:4, to brick masonry
including rounding off corners wherever required smooth rendering, :Providing and removing scaffolding, including cost
of materials, labuor, curing complete as per specifications.

(SR Item No.15.16, page 122 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 198.00/sqm
Add 3% Area Weightage = Rs 5.94/sqm
Total = Rs 203.94/sqm
Err:511

Item no. 23
KSRB 15-3.6 : Providing 15mm thick cement plaster in single coat with cement mortar 1:6, to brick masonry including
rounding off corners wherever required smooth rendering, : providing and removing scaffolding, including cost of
materials, labuor, curing complete as per specifications.

(SR Item No.15.14, page 109 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 147.00/sqm
Add 3% Area Weightage = Rs 4.41/sqm
Total = Rs 151.41/sqm
Err:511

Item no. 24
KSRB 15-3-13 : Providing 12mm thick cement plaster in single coat with cement mortar 1:3, to ceiling including rounding
off corners wherever required smooth rendering, : providing and removing scaffolding, including cost of materials,
labuor, curing complete as per specifications.

(SR Item No.15.21, page 110 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 174.00/sqm
Add 3% Area Weightage = Rs 5.22/sqm
Total = Rs 179.22/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 25
KSRB 15-7 : Providing lime rendering for plastering to wall and ceiling , including cost of materials, labour, curing
complete as per specifications.
(SR Item No.15.33, page 111 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 20.00/sqm
Add 3% Area Weightage = Rs 0.60/sqm
Total = Rs 20.60/sqm
Err:511

Item no. 26
KSRB 14.10-1 : Flooring with 25 mm to 40mm thick polished tandur blue stone slabs using cement mortar 1:6 , 25 mm
thick over existing cement concrete bed or top of roof laid to line and level and jointed with cement slurry mixed with
pigment to match the shade of the slab, including cost of all materials ,labour,curing ,polishing complete as per
specifications

(SR Item No.14.15, page 100 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 1067.00/sqm
Add 3% Area Weightage = Rs 32.01/sqm
Total = Rs 1099.01/sqm
Err:511

Item no. 27
KSRB 14-17.2 : Providing skirting, dado, rises of steps with colour glazed tiles 15x15 cms 6mm thick cement mortar 1:3
and jointed with white cement slurry over rough plaster surface using glazed tiles of approved make and size including
cost of materials, labuor, complete as per specifications.

(SR Item No.14.41.1, page103 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 999.00/sqm
Add 3% Area Weightage = Rs 29.97/sqm
Total = Rs 1028.97/sqm
Err:511

Item no. 28
KSRB 15-16.1 : Providing and finishing external walls in two coats with water proof cement paint of approved brand and
shade to give an even shade after throughly brooming the surface to remove all dirt and loose powdered material, free
from mortar drops and other foreign matter cost of materials, labour, complete as per specifications.

(SR Item No.15.53.1 page 114 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 55.00/sqm
Add 3% Area Weightage = Rs 1.65/sqm
Total = Rs 56.65/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 29
KSRB 15-15.1 : Providing and applying painting in two coats plastic emulsion with primer paint of approved brand on
wall surface to give an even approved shade after throughly brushing the surface, free from mortar drops and other
foreign matter including preparing the surface even and sand paper smooh, cost of materials, labuor, complete as per
specifications.

(SR Item No.15.51.2, page 113 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 80.00/sqm
Add 3% Area Weightage = Rs 2.40/sqm
Total = Rs 82.40/sqm
Err:511

Item no. 30
KSRB 15-17.4 : Applying priming coat over new wood surface and / or wood based surface after brushing with ready
mix Enamel priming paint including preparing the surface after throughly cleaning oil, grease, dirt and foreign matter,
sand papering and knotting ready mix paint including cost of materials, labour, complete as per specifications.

(SR Item No.15.58, page 115 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 28.00/sqm
Add 3% Area Weightage = Rs 0.84/sqm
Total = Rs 28.84/sqm
Err:511

Item no. 31
KSRB 15-17.6 : Providing and applying painting two coats ( excluding priming coat ) on new wood surface and / or wood
based surface with enamel paint to give an even shade, cleaning the surface of all dirt, dust and foreign matter, sand
papering including cost of materials, labour, complete as per specifications.

(SR Item No.15.60.1, page 115 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 81.00/sqm
Add 3% Area Weightage = Rs 2.43/sqm
Total = Rs 83.43/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 32
KSRB 10.4 : Providing and laying four courses water proofing treatment with bitumin felt over roof consisting of first and
third courses of blown and / or residual bitumin applied hot at 1.45 kg / sqm of area for each course second course of
roofing feltType - 3 grade-I ( hessian based self finish bitumin felt ) and forth and final course of stone grit 6mm and
down size or pea sized gravel spread at 0.06cum. / sqm including preparation of surface but excluding grading complete
with bitumin felt ( hessian based ) Type - 3 grade-l blown or / and residual bitumen applied hot 1.4 kg / sqm including
cost of materials, labour complete as per specifications. KBS 10.4.3

(SR Item No.10.3, page 64 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 374.00/sqm
Add 3% Area Weightage = Rs 11.22/sqm
Total = Rs 385.22/sqm
Err:511

Item no. 33
KSRB 8.6-8 : Providing and fixing on wall surface 4.0 kg / sq.cm H.D.P.E rain down water pipes 110mm outer dia.
Approved make and brand with necessary specials like shoes, bends and offets fixed with iron clamps, wall plugs,
screws, including cost of materials, labuor, complete as per specifications.

(SR Item No.8.19, page 47 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 601.00/ m
Add 3% Area Weightage = Rs 18.03/ m
Total = Rs 619.03/ m
Err:511

Item no. 34
KSRB 4.9.2 : Providing T.M.T steel reinforcement for RCC works including straightening, cutting, bending, hooking,
placing in position, lapping and/ or welding wherevere requried, tying with binding wire and anchoring to the adjoining
members wherever necessary complete as per design(laps,hooks and wastage shall not be measuered and paid), cost
of materials, labours, HOM of machinery complete as per spcifications No. KBS 4.6.3

(SR Item No.4.46.2, page 17 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 70.29/ Kg
Add 3% Area Weightage = Rs 2.11/ Kg
Total = Rs 72.39/ Kg
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 35
KSRB 12-8.3 : Constructing brick masonary inspection chamber 600x850mm and 450mm depth, ( clear inside
dimension) for pipeline with three or more inlets, using table moulded non-modular bricks of class designation 50 in
cement mortar 1:5, C.I cover withframe (light duty) 455x610mm interal dimensions, total weight of cover with frame to be
not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) R.C.C top slab with cement concrete M 15 with
20mm and downsize granite metal, fundatin concrete M 5 with 40mm and downsize granite matall, inside plastering
12mm thick with cement mortar 1:3, finish smooth with a floating coat of cement on walls and bed concrete complete as
per standard design including cost of materials, labuor charges, curing complete as per specifications.

(SR Item No.11.54, page 71 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 8170.00/ Each
Add 3% Area Weightage = Rs 245.10/ Each
Total = Rs 8415.10/ Each
Err:511

Item no. 36
KSRB 13-11.1 : Providing and placing on terrace, polyethylene water storage tanks as per IS 12701 : 1996 with manhole
lid and suitable locking arrangements, making holes of suitable diameter for inlet, outlet and over flow pipes, including
cost of all materials, labour, transport charges, HOM of equipments and testing complete as per specifications.(For 1000
litre capacity) Specification No.KBS 13.22

(SR Item No.13.78, page 91 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 8350.00/ Nos
Add 3% Area Weightage = Rs 250.50/ Nos
Total = Rs 8600.50/ Nos
Err:511

Item no. 37
Providing and laying platform using prepolished, water cut / gang saw 40mm thick telephonic Black Granite. Laid on
existing vertical supports and fixing in CM 1:3 proportion, including cutting to required shape, patttern with paper joints,
including full rounding for nosing, finished with cement mortar, pointed with colour pigments to match the colour of slab
making through jointing with sealant, making holes 25mm x 12mm grooves joints including curing.

(SR Item No.14.52, page 105 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 3412.00/sqm
Add 3% Area Weightage = Rs 102.36/sqm
Total = Rs 3514.36/sqm
Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 38
Providing and fixing polished granite sink of size 60cmsx 75 cms of 23cm thick, the sink portion shall be 15cm in depth
of shapes oval / round / square over brick masonry in cement mortar 1:6 incuding cost and conveyance of all materials,
labuor for all items of work, HOM of equipment with all lead and lift, loading and unloading, transportation charges and
all other incidental charges etc., complete as per specification and directions of the Engineer-in-Charge of the work.

(SR Item No 13.89, page 94 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 5902.00/ Each
Add 3% Area Weightage = Rs 177.06/ Each
Total = Rs 6079.06/ Each
Err:511

Item no. 39
KSRB 13-10.2 : Providing and fixing to wall, ceiling and floor unplasticised PVC pipes 10.00 kgs/sq.cm working pressure
20mm outside diameter chemp plast / wavin or eqivalent make with pipe fittings, wall clips, making good the wall, ceiling
and floor, including cost of all materials, labour charges, HOM of equipments and testing complete a per specifications.
No. KBS 13.2.15.4 / 13.9

(SR Item No 13.75, page 91 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 94.00/m
Add 3% Area Weightage = Rs 2.82/m
Total = Rs 96.82/m
Err:511

Item no. 40
KSRB 11-18-1.1 : Providing and fixing sand cast iron soil waste and vent pipes 100mm dia withn spun yard soaked in
cement slurry and cement mortar 1:2 including cost of materials, labour, testing complete a per specifications. KBS 11-
1.10

(SR Item No 12.47, page 80 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 743.00/m
Add 3% Area Weightage = Rs 22.29/m
Total = Rs 765.29/m
Err:511

Item no. 41
KSRB 11-18-3.1 : Providing and fixing sand cast iron soil waste plain bend, 100mm dia withn spun yard soaked in
cement slurry and cement mortar 1:2 including cost of materials, labour, testing complete a per specifications. KBS 11-
1.10

(SR Item No 12.53, page 80 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 398.00/ Each
Add 3% Area Weightage = Rs 11.94/ Each
Total = Rs 409.94/ Each

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Err:511

Item no. 42
Providing stone ware gully trap of approved quality and make fixing in M-15 and plastering with 1:3 CM wherver
necessary (Rate includes cost of all materials, fixture ad lead)
(SR Item No 12.112.1, page 85 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 185.00/ Each
Add 3% Area Weightage = Rs 5.55/ Each
Total = Rs 190.55/ Each
Err:511

Item no. 43
KSRB 13-6.1-1 : Providing and fixing in position brass bib cock of approved quality of 15mm nominal bore including cost
of all materials, labour and HOM of equipmants with all lead complete as per specifications. No. KBS 13.2.2 / 13.3

(SR Item No.13.23, page 88 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 233.00/ Each
Add 3% Area Weightage = Rs 6.99/ Each
Total = Rs 239.99/ Each
Err:511

Item no. 44
KSRB 11-1 : Providing and fixing white vitreous china clay, water closet Indian type ( Squatting pan ) of size 580mm with
footrests, 100mm S or P trap, 10 litre low level, P.V.C flushing cistern ( all are approved make ) with fittings, C.I / M.S
brackets, 32mm diameter flush pipe fittings and clamps, overflow arrangements with specials and 25mm mosquito proof
coupling of approved design, painting of fittings and brackets, cutting and making good the wall and floor wherever
required, including cost of all materials, labour complete as per specifications. No. KBS 11

(SR Item No.12.1, page 74 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3564.00/ Pan
Add 3% Area Weightage = Rs 106.92/ Pan
Total = Rs 3670.92/ Pan
Err:511

Item no. 45
KSRB 11-11.6 : Providing and fixing white vitreous china clay, angle back wash basin 600x480mm with a single 15mm
C.P brass pillar tap with C.I / M.S brackets, 32 mm C.P brass waste of standard pattern, painting, of fittings and
brackets, cutting and making good the wall and floor wherever required, including cost of all materials, labuor complete
as per specifications.

(SR Item No.12.28, page 78 of PWD SR,Dharwad Circle for 2014-15)


Basic Rate = Rs 3120.00/ Unit

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Add 3% Area Weightage = Rs 93.60/ Unit


Total = Rs 3213.60/ Unit
Err:511

Item no. 46
Providing and fixing M.S ladder between landing 45 cms. Wide using iron of following size and 20 mm M.S bars at 25
cms. Centre to centre with necessary supports of same angle iron as directed including hand railing on both sides with
25 mm dia G.I pipes with angle iron props at 2 mtrs, interval and 0.5 mtr, height including fixing in ground with C.C 1:2:4
and two coats of non-poisonous anticorrosive bituminous paint with all lead and lift etc., complete. Note: only exposed
ladder portion above G.L to be paid for.

(PRE Dharwad Circle for 2012-13, Page No.37 4.6a)


Basic Rate = Rs 1864.30/m
Total = Rs 1864.30/m
Err:511

Item no. 47
KSRRBM800-9 : Printing New Letter and Figures of any Shade with synthetic enamel paint black or any other approved
colour to give an even shade complete as per specifications.("i) Hindi ( Matras commas and the like not to be measured
and paid for half letter shall be counted as half) MORTH Spec No. 803

(SR Item No.24.9, page 178 of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 0.65/ cm
Add 3% Area Weightage = Rs 0.02/ cm
Total = Rs 0.67/ cm
Err:511

Item no. 48
Providing & fixing M.S.Oxidized Hinges of length 150mm of approved make & quality including cost & conveyance of all
materials and as per the directions of Engineer - in charge of work etc., complete as per directions of the Engineer-in-
charge

(SR Item No.395, page XIV of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 40.00/ Each
Add 3% Area Weightage = Rs 1.20/ Each
Total = Rs 41.20/ Each
Err:511

Item no. 49
Providing & fixing DOOR LOCK of approved make & quality including cost & conveyance of all materials and as per the
directions of Engineer - in charge of work etc., complete as per directions of the Engineer-in-charge
(SR Item No.391, page XIV of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 429.00/ Each
Add 3% Area Weightage = Rs 12.87/ Each

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Total = Rs 441.87/ Each


Err:511

E I Technologies Pvt Ltd Rate analysis


Karnataka Neeravari Nigam Limited Singatalur Lift Irrigation Scheme

Item no. 50
Providing & fixing Alu.tower bolt of size 200x12mm of approved make & quality including cost & conveyance of all
materials and as per the directions of Engineer - in charge of work
(SR Item No.412, page XIV of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 124.00/ Each
Add 3% Area Weightage = Rs 3.72/ Each
Total = Rs 127.72/ Each
Err:511

Item no. 51
Providing & fixing Alu.handle of size 150mm of approved make & quality including cost & conveyance of all materials
and as per the directions of Engineer - in charge of work
(SR Item No.404, page XIV of PWD SR,Dharwad Circle for 2014-15)
Basic Rate = Rs 67.00/ Each
Add 3% Area Weightage = Rs 2.01/ Each
Total = Rs 69.01/ Each
Err:511

Consultant Assistant Executive Engineer Executive Engineer


E I Technologies Pvt. Ltd., R&R Sub- Division SLIS KNNL SLIS Division No.1
Bangalore Mundaragi Mundaragi

Superintending Engineer
WRD, TBP Circle
Munirabad

E I Technologies Pvt Ltd Rate analysis