Project Brief
Labour Report
Variation statement
Cash Flow
HSE Report
Project Management Consultant : Across & Beyond Development Consultancy Pvt. Ltd.
SALE BUILDING:
1) Raft pour-3 reinforcement completed - (41.50MT)
2) Raft concreting pour-3 completed - (384Cum)
3) Brickwork from Raft top work in progress - (304 Sq.m Completed/368 Sqm).
4) Plaster work from Raft top work in progress - (206.4 Sq m Completed /375 Sqm)
5) Column Reinforcement work completed.
6) Column shuttering work in progress.
7) Column and retaining wall concreting work in progress – (146.9 cum completed)
REHAB -2 BUILDING:
1) Brickwork completed – (219.2 Sqm)
2) Plaster work completed – (130.9 Sqm)
3) Waterproofing work up to raft completed – (545 Sqm)
4) Raft reinforcement work completed - (75.50 MT)
5) Raft shuttering work completed – (53.68 Sqm)
6) Raft concreting work completed – (387.50 Cum)
7) UG tank bottom reinforcement work completed – (2.4MT Completed)
8) UG tank Bottom concreting work completed.
9) Waterproofing work Above raft in progress – (129.3 Sqm Completed)
10) Column and retaining wall reinforcement work in progress – (16.9 MT completed )
11) Column Concreting work in progress – (36 Cum completed )
REHAB -1 BUILDING:
1) Brickwork from raft top to pile cap top completed – (115 Sqm)
2) Plaster work from raft top to pile cap top completed –( 115 Sqm)
3) Column, r/w reinforcement work completed - (19.75 MT)
4) Column & Retaining wall concreting work in progress – ( 146.9 Cum completed)
5) Waterproofing work completed – (120 Sqm Completed)
6) Retaining wall, Column & Slab shuttering work in progress – (609.7 Sqm Completed)
7) Service Basement level 1st Pour Slab Casted on 26-Feb-2016 - (21 Cum Completed)
EXECUTION DEPARTMENT
01 Mr. Sameer Mestry Sr. Manager (Project-In charge) 8879643769
02 Mr. Manoj Kumar Manager – Construction 7045778892
03 Mr. Sahadev Jadhav Supervisor- Civil 7208138400
QA/QC DEPARTMENT
01 Mr. Sushil Rai Manager – QA /QC 8286514113
02 Mr. Sukhen Pal Asst Engineer – QA/QC 7679999580
03 Mr. Vijay Behra Lab Technician 9762464396
SURVEY DEPARTMENT
01 Mr. Raju Melgiri Surveyor 9819016701
02 Mr. Deepak Gupta Surveyor Helper 9768127295
477 M/C
375
9% 12%
Pump Operator/Helper
5 Vibrator 5 3/10/2015
CONCRETE PUMP
10% 1%
1 18-09-2015 Excavation & Basement Layout (Rehab -1) Structural 18-09-2015 MCPL_REHAB1_S_PL_1.2 1
2 09-10-2015 Layout of U. G tank Bottom Slab Structural 09-10-2015 MCPL_REHAB1_S_PL_1.4 2
3 09-10-2015 Layout of U. G tank Top Slab Structural 09-10-2015 MCPL_REHAB1_S_PL_1.5 2
4 09-10-2015 Stilt Floor Plan Structural 09-10-2015 MCPL_REHAB1_S_PL_1.6 2
5 09-10-2015 Section Of ret. wall Part-1 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.1 2
6 09-10-2015 Section Of ret. wall Part-2 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.2 2
7 09-10-2015 Section Of ret. wall Part-3 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.3 2
8 09-10-2015 Column Bar placing Details For Stilt Floor Structural 09-10-2015 MCPL_REHAB1_S_DT_1.3 2
9 09-10-2015 Layout Of raft Detail-1 Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_01 2
10 09-10-2015 Layout Of raft Detail-2 Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_02 2
11 09-10-2015 Layout of Raft Showing Chairs. Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_03 2
12 09-10-2015 Column Schedule Structural 09-10-2015 MCPL_Rehab1_S_PL_1.1 2
GN-1 Std Details Of Bending & Assembling of
13 09-10-2015 Reinforcement For RCC Menmbers General Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_1 2
Drawing
14 09-10-2015 GN-2 Typical Frame Beam Details Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_2 2
GN-3 Drawing Of Reinforcement For RCC
15 09-10-2015 Member (Ductile Detailing OF Column & Beam Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_4 2
Junction)
16 26-11-2015 LAYOUT OF TYPICAL 8,10,12,14TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.10 4
17 26-11-2015 LAYOUT OF TYPICAL 16,18,20TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.12 4
LAYOUT & SCHEDULE OF REFUGE FLOOR
18 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.11 4
(15TH , 17TH, 19TH)
LAYOUT & SCHEDULE OF REFUGE FLOOR
19 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.14 4
(22ND FLOOR)
LAYOUT & SCHEDULE OF TYPICAL FLOOR
20 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.13 4
(21ST & 23RD)
21 26-11-2015 SECTION OF TYPICAL REFUGE FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.5 4
LAYOUT & SCHEDULE OF REFUGE FLOOR
22 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.9 4
(7,9,11 & 13THFLOOR)
23 26-11-2015 LAYOUT & SCHEDULE OF 1ST FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.7 4
24 26-11-2015 LAYOUT OF TYPICAL 2ND TO 6TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.8 4
MCPL_SALEBLDG_S_PL_1.
1 10-11-2015 EXCAVATION PLAN Structural R3 2
2
COLUMN BAR PLACING MCPL_SALEBLDG_S_DT_1.
2 10-11-2015 Structural R3 3
DETAILS 1
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
3 10-11-2015 Structural R3 3
PART 7 9
LAYOUT OF PARKING FLOOR MCPL_SALEBLDG_S_PL_1.
4 10-11-2015 Structural R3 3
1ST LEVEL 9
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
5 10-11-2015 Structural R3 3
PART 3 5
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
6 10-11-2015 Structural R3 3
PART 2 3
SCHEDULE OF BEAM & SLAB MCPL_SALEBLDG_S_SH_1.
7 10-11-2015 Structural R3 3
1ST LEVEL PARKING 5
SCHEDULE OF BEAM & SLAB MCPL_SALEBLDG_S_SH_1.
8 10-11-2015 Structural R3 3
MEZZANINE FLOOR 4
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
9 10-11-2015 Structural R3 3
PART 6 8
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
10 10-11-2015 Structural R3 3
PART 1 2
LAYOUT AT MEZANINE MCPL_SALEBLDG_S_PL_1.
11 10-11-2015 Structural R3 3
FLOOR 7
MCPL_SALEBLDG_S_PL_1.
12 10-11-2015 LAYOUT OF STILT FLOOR Structural R3 3
6
LAYOUT OF STILT FLOOR/ UG MCPL_SALEBLDG_S_PL_1.
13 10-11-2015 Structural R3 3
TANK TOP 5
LAYOUT OF STILT FLOOR MCPL_SALEBLDG_S_PL_1.
14 10-11-2015 Structural R3 3
(SERVICE BASEMENT-1) 4
LAYOUT OF RAFT SHOWING MCPL_SALEBLDG_S_PL_1.
15 10-11-2015 Structural R3 3
CHAIR 8
MCPL_SALEBLDG_S_SH_1.
16 10-11-2015 COLUMN SCHEDULE Structural R3 3
1
SCHEDULE OF BEAMS & SLAB MCPL_SALEBLDG_S_SH_1.
17 10-11-2015 Structural R3 3
FOR UG TANK TOP SLAB 2
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
18 10-11-2015 Structural R3 3
PART 4 6
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
19 10-11-2015 Structural R3 3
PART 5 7
MCPL_SALEBLDG_S_PL_1.
20 10-11-2015 LAYOUT OF RAFT DETAIL Structural R3 3
3
MCPL_SALEBLDG_S_PL_1.
21 10-11-2015 LAYOUT OF RAFT DETAIL Structural R3 3
3
SCHEDULE OF BEAMS & SLAB MCPL_SALEBLDG_S_SH_1.
22 10-11-2015 Structural R3 3
FOR STILT FLOOR 3
ADCS_ST_A_1.10_L
6 10-11-2015 LOWER BASEMENT LEVEL ARCH 10-11-2015 2
B
ADCS_ST_A_1.10_U
7 10-11-2015 UPPER BASEMENT LEVEL ARCH 10-11-2015 2
B
Note: All GFC drawings to be given 30 days in advance for Studying, Material Procurement & Planning the activities.
Reinforcement Steel
NAHAR PROJECT(MAHALAXMI)
DATE-29.02.2016
1 Ply 8' x 4' x 12mm Thk. Sqm 50 550 400 505 527.5 75 775 470 360 567.5 75 1115 560 1050 1082.5 8162.5 1301 6861.5
2 Ply 8' x 4' x 12mm Thk. (for Gabadi) Sqm 200 200 205 200 205 240 240 1490 0 1490
3 Timber 2" x 3" x 8' Cuft 110 210 110 110 110 250 155 125 210 500 312.5 2202.5 657.67 1544.83
4 Timber 2" x 4" x 8' Cuft 100 100 0 100 300 0 300
5 Timber 3" x 4" x 8' Cuft 50 165 150 520 342.5 60 165 160 640 402.5 60 250 150 2200 1225 6540 1055 5485
6 Guy Rope dia 10 Mtrs 300 330 264 894 645 249
7 U clamp for Guy Rope Nos 110 154 200 464 319 145
8 Tie rod (dia 15 x 3.0M lg.) Nos 159 142 190 174 190 392 1247 922 325
9 Anchor Nut Nos 1150 660 1270 760 1500 550 5890 1810 4080
10 Lean - Forged Pin Dia 16 x 110mm with Spring Cotter Nos 440 490 520 1450 1450 0
11 Lean - Wedge & Pin (100mm Lg.) Nos 1600 2000 2100 5700 4950 750
12 Water barrier Nos 700 850 850 2400 1618 782
13 Hex Bolt M16 x 150 Lg. with nut & double washer Nos 400 0 400 423 -23
14 ISMC 100 x 50 MT 2 6 5 2 4 7 2 6 7 41 18.42 22.58
15 Sq. Tube 50 x 50 x 2.9Thk. MT 7 5 6 18 0 18
16 Lean - Panel 300 x 2700 Nos 10 14 14 38 24 14
17 Lean - Panel 450 x 2700 Nos 10 24 30 64 40 24
18 Lean - Panel 600 x 2700 Nos 20 46 60 126 81 45
19 Lean - Panel 750 x 2700 Nos 12 68 86 166 92 74
20 Lean - Panel 900 x 2700 Nos 66 44 30 140 109 31
21 Lean - Inner Corner 2700 Nos 22 20 24 66 24 42
22 Lean - Waler 1.5M Lg. Nos 57 54 54 165 111 54
23 Lean - Waler 1.75M Lg. Nos 54 45 45 144 99 45
24 Lean - Waler 2.0M Lg. Nos 69 75 90 234 183 51
25 Lean - Waler 3.0M Lg. Nos 51 51 60 162 111 51
26 Lean - Push Pull Prop (Type - 1) Nos 110 120 130 360 360 0
27 Lean - Push Pull Prop (Type - 2) Nos 110 120 130 360 360 0
28 Lean - Prop Top Connector Nos 220 240 260 720 480 240
29 Lean - Prop Bottom Connector Nos 110 120 130 360 360 0
30 Lean - Stop end Bolt with Anchor nut Nos 72 72 72 216 216 0
31 Lean - GTX connector Push pull with double nut & washer Nos 72 72 72 216 216 0
32 Lean - Outer Corner Angle 2700 Nos 6 8 8 22 22 0
33 Stop end waler 1.0 (G. I Plated) Nos 42 54 54 150 150 0
34 RMD GTX (65 x 150) 2700mm Nos 36 36 36 108 36 72
35 RMD Rapid ply Panel system Sqm 250 300 485 1035 0 1035
36 CT Prop (2.0+2.0) Nos 415 165 470 165 590 284 2089 584 1505
37 Fixed U Head Nos 330 374 470 1174 330 844
38 Cuplock vertical 1.0M Nos 333 264 144 138 879 56 823
39 Cuplock vertical 1.5M Nos 220 242 576 1038 1038 0
40 Cuplock vertical 2.0M Nos 168 264 365 242 913 1952 1185 767
41 Cuplock vertical 2.5M Nos 168 365 576 154 1263 1263 0
42 Cuplock ledger 0.9M Nos 248 374 264 642 792 1884 4204 2756 1448
43 Cuplock ledger 1.2M Nos 823 264 1650 374 1768 1281 6160 5447 713
44 Cuplock ledger 1.5M Nos 343 264 949 110 1430 1315 4411 0 4411
45 Stirrup head 450 Lg. Nos 168 440 365 464 576 913 2926 2926 0
46 Base jack 450 Lg. Nos 168 242 365 242 576 913 2506 2648 -142
47 40 NB B Class pipe MT 1 3 1 3.5 1.5 3 13 12.32 0.68
48 Tripod Nos 246 176 264 264 320 276 1546 100 1446
49 Swivel coupler Nos 150 330 110 374 100 352 1416 1416 0
50 Cuplock working platform bracket Nos 156 176 176 508 0 508
51 Internal beam bottom bracket Nos 176 232 166 574 150 424
52 Shikanja 750mm Lg. Nos 550 565 752 1867 950 917
53 Beam side bracket Nos 352 464 332 1148 150 998
54 ISA 40 x 40 x 5Thk. MT 9 11 15 35 0 35
55 CT Prop (1.5+1.5) Outer with plate & Inner without plate Nos 176 232 166 574 176 398
56 CT Prop (2.0+2.0) Outer with plate & Inner without plate Nos 166 166 0 166
TOTAL… 5700 250 4599 2573 5064 1180 6220 300 6806 2954 5453.5 1330 6682 485 9661.5 3061 13321 2860 78500 39430.41 39069.59
19366 23063.5 36070.5
350.95 5,380
350.00 5,266
5,166
5,000.00
4,815
307.83 305.92
297.16 4,564
300.00 290.24 4,429
4,242
268.02
258.87 3,989 4,000.00
AMOUNT IN LACS
3,433
209.54 211.58 3,238
- - 156
- 0 -
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Monthly plan Invoicing - 155.87 268.02 209.54 211.58 115.71 137.12 135.64 190.95 307.83 163.27 253.23 144.03 194.91 290.24 154.65 305.92 194.93 297.16 258.87 252.74 186.33 135.77 251.05 350.95 99.94 113.68
monthly actual invoicing - 194.00 154.08 101.24
Cumm. Plan Invoicing - 155.87 423.89 633.43 845.00 960.71 1,097.83 1,233.47 1,424.41 1,732.24 1,895.51 2,148.74 2,292.77 2,487.68 2,777.92 2,932.57 3,238.49 3,433.42 3,730.58 3,989.45 4,242.19 4,428.51 4,564.29 4,815.33 5,166.29 5,266.22 5,379.90
cumm. Actual invoicing - 194.00 348.08 449.32
QA/QC REPORT
QAQC-MTC REPORT
SAFETY IN
MPR
CHARGE FEB-2016 PROJECT INCHARGE Page 28
MEDICAL
ZERO INJURY FIRST AID CASE TREATMENT CASE LTI
(MTC)
1 2 3
4 5 6
7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26
27 28 29
1) Work delay due to BMC road work near sale main gate from 06-Jan-2016 to
15-JAN-2016.
2) Reinforcement work because steel supplier not ready to supply 32mm steel
JAN-2016)
4) Brickwork at sale and rehab 1 building delay due to approval of using crush
Brickwork in Progress