Monthly Progres Report - Feb-2016

The monthly progress report summarizes work completed in February 2016 on the Nahar Excalibur Mahalaxmi project. Key achievements included completing raft concrete pours, brickwork, plastering and waterproofing on Rehab-2. Column and slab work progressed on Rehab-1. Project staffing, equipment deployed, and labor details are provided along with 3-week look ahead, photos and other enclosures.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
197 views

Monthly Progres Report - Feb-2016

The monthly progress report summarizes work completed in February 2016 on the Nahar Excalibur Mahalaxmi project. Key achievements included completing raft concrete pours, brickwork, plastering and waterproofing on Rehab-2. Column and slab work progressed on Rehab-1. Project staffing, equipment deployed, and labor details are provided along with 3-week look ahead, photos and other enclosures.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 40

MONTHLY PROGRESS REPORT

For the Project

NAHAR MAHALAXMI
By

CAPACIT'E INFRAPROJECTS LTD

For the Month of

FEB’16

MPR FEB-2016 Page 1


Enclosure
 General Layout

 Project Brief

 Key Achievement for the month

 Project Team & Organisation Chart

 Labour Report

 Equipment Deployed at site

 Variation statement

 Drawings Log & Drawing Requirement

 Material Quantity Received at Site for the Month

 Cash Flow

 HSE Report

 Site Logistic Plan

 3 Week look ahead

 Work Progress photos

MPR FEB-2016 Page 2


GENERAL LAYOUT

MPR FEB-2016 Page 3


PROJECT BRIEF

Project Name : Nahar Excalibur Mahalaxmi Project.

Project Details : Shuttering, concrete, Reinforcement, Block Work,

Plastering & Misc. works. Excavation (Coordination)

& Waterproofing (Coordination),

Main Sales - 1 No's Buildings


(Lower Basement+ Ground Floor+ 5 Parking Level + 1 Service Floor+ 1 Fire
Check Floor + 20 Upper Floors.)

Rehab 1 & Rehab 2 - 2 No's Buildings:


(Lower Basement+ Ground Floor+ 3 Refuge Floor+ 20 Upper Floor .)

Project Cost: Rs. 59, 50, 16, 926.08 Incl. taxes


(As per LOI Dated: 16th Oct 2015, Contract Ref no NAHAR/LOA/CON/2015-16/01)

Project Duration : 25 Months

Contractual Agreement Date : 7th Oct 2015.

Start Date of Work : 22nd Oct 2015.

MPR FEB-2016 Page 4


PROJECT TEAM

Client : M/s Nahar Excalibur Project Pvt. Ltd

Architect : M/s Atul Desai Consultants

Structural Consultant : M/s Mahimtura Consultants Pvt. Ltd.

Service Consultant : Across & Beyond Development Consultancy Pvt. Ltd.

Project Management Consultant : Across & Beyond Development Consultancy Pvt. Ltd.

MPR FEB-2016 Page 5


KEY ACHIEVEMENTS FOR THE MONTH OF FEB - 2016

SALE BUILDING:
1) Raft pour-3 reinforcement completed - (41.50MT)
2) Raft concreting pour-3 completed - (384Cum)
3) Brickwork from Raft top work in progress - (304 Sq.m Completed/368 Sqm).
4) Plaster work from Raft top work in progress - (206.4 Sq m Completed /375 Sqm)
5) Column Reinforcement work completed.
6) Column shuttering work in progress.
7) Column and retaining wall concreting work in progress – (146.9 cum completed)

REHAB -2 BUILDING:
1) Brickwork completed – (219.2 Sqm)
2) Plaster work completed – (130.9 Sqm)
3) Waterproofing work up to raft completed – (545 Sqm)
4) Raft reinforcement work completed - (75.50 MT)
5) Raft shuttering work completed – (53.68 Sqm)
6) Raft concreting work completed – (387.50 Cum)
7) UG tank bottom reinforcement work completed – (2.4MT Completed)
8) UG tank Bottom concreting work completed.
9) Waterproofing work Above raft in progress – (129.3 Sqm Completed)
10) Column and retaining wall reinforcement work in progress – (16.9 MT completed )
11) Column Concreting work in progress – (36 Cum completed )

REHAB -1 BUILDING:
1) Brickwork from raft top to pile cap top completed – (115 Sqm)
2) Plaster work from raft top to pile cap top completed –( 115 Sqm)
3) Column, r/w reinforcement work completed - (19.75 MT)
4) Column & Retaining wall concreting work in progress – ( 146.9 Cum completed)
5) Waterproofing work completed – (120 Sqm Completed)
6) Retaining wall, Column & Slab shuttering work in progress – (609.7 Sqm Completed)
7) Service Basement level 1st Pour Slab Casted on 26-Feb-2016 - (21 Cum Completed)

MPR FEB-2016 Page 6


MPR FEB-2016 Page 7
STAFF DETAILS (NAHAR PROJECT)
S.N Name DESIGNATION Contact Number

EXECUTION DEPARTMENT
01 Mr. Sameer Mestry Sr. Manager (Project-In charge) 8879643769
02 Mr. Manoj Kumar Manager – Construction 7045778892
03 Mr. Sahadev Jadhav Supervisor- Civil 7208138400

04 Mr. Nitin Pawar Jr. Engineer 8454067907

05 Mr. Sanket Jare GET-Execution 8097844474

06 Mr. Bhairavnath Mote Foreman –Rebar 8652874352

07 Mr. Ranjan Kumar GET-Civil 7039938516


08 Mr. Ranjt Gajbe Foremen- Civil 8087942334
09 Mr. Sahadev Jadhav Supervisor- Civil 7208138400

10 Mr. Ranjan Kumar GET-Civil 7039938516


11 Mr. Yogesh Gund Foreman- Shuttring 8460474687
PLANNING & BILLING DEPARTMENT
01 Mr. Premkumar Bagalkot Manager- Planning 7045778890
02 Mr. Amol Patil Billing Engineer 7045778870
03 Archana Ghodekar Jr. Engineer – Billing 7506650625

QA/QC DEPARTMENT
01 Mr. Sushil Rai Manager – QA /QC 8286514113
02 Mr. Sukhen Pal Asst Engineer – QA/QC 7679999580
03 Mr. Vijay Behra Lab Technician 9762464396
SURVEY DEPARTMENT
01 Mr. Raju Melgiri Surveyor 9819016701
02 Mr. Deepak Gupta Surveyor Helper 9768127295

MPR FEB-2016 Page 8


ADMIN DEPARTMENT
01 Mr. Ramesh Chavan Officer – Administration 7506403348
02 Mr. Ajay Mishra Camp Boss 9967573112
03 Mr. Agyaram Varma Office Boy 7039513049
04 Mr. Premlal Cook 8462052790
SAFETY DEPARTMENT
01 Mr.Bimlesh Kumar Deputy Manager –HSE & Safety 7045900516
02 Mr. Sagar Budhakar Asst. Engineer – Safety /HSE 7045778891
STORE DEPARTMENT
01 Mr. Satish Lagare Officer- Store 8879643770
02 Mr. Sandeep Bhalekar Asst. Store 7506650673
P & M DEPARTMENT
01 Mr. Bharat Kumar GET- P & M 7045778871
02 Mr. Sonelal Gupta Electrician 7709270738

03 Mr. Mukim Alam Electrician 9867959454


8108848182
04 Mr. Ajay Kumar Mechanic

05 Mr.Bashishth Yadav Tower Crane Oprator 9923904608


06 Mr.Vushnu Chauhan Signal Man 8898663838
07 Mr. Shamim Azad Mechanic 9930902762

08 Mr. Abhimanyu Gupta Signal Man 9837396693


09 Mr. Sanjay Yadav Tower Crane Oprator 8879403039

10 Mr.Vijay Kumar Signal Man 902282563


11 Mr. Padan Malik Plumber 7666292085

MPR FEB-2016 Page 9


LABOUR REPORT FEB-16

MPR FEB-2016 Page 10


Percentage labour Strength

201 30 139 Supervisor or Foreman


102
76 2% 5% 1% 3% 440
Carpenter
195 2% 11%
5% Carp. Helper
144
4% Fitter
594
15% Fitt. Helper
Mason
Helper
Rigger
895 Helper2
22%
362 Breaker/ Chipper
9% Welder
Welder Helper

477 M/C
375
9% 12%
Pump Operator/Helper

MPR FEB-2016 Page 11


EQUIPMENT DEPLOYMENT STATUS

SR NO DESCRIPTION OF PLANT NOS DEPLOYMENT DATE

1 Concrete Pump 1 08/10/2015

2 Submersible pump 4 6/10/2015

3 Auto Level 1 23/09/2015

4 Total Station 1 23/09/2015

5 Vibrator 5 3/10/2015

6 Bar Cutting Machine 2 14/10/2015

7 Bar Bending Machine 2 14/10/2015

8 Mud Pump 10HP 1 14/10/2015

9 Compression Testing Machine 1 18/10/2015

MPR FEB-2016 Page 12


EQUIPMENT UTILISATION
TOTAL
CONCRETE TOTAL NO. DOWNTIME
DIESEL WORKING NON
SR. QUANTITY OF HRS IN HRS DUE TO
NAME OF THE EQUIPMENT CONSUMED HRS AT SITE UTILISATION REMARKS
NO. POURED ACTUAL BREAKDOWN/
(LTR) DURING THE HRS
(CUM) OPERATION MAINTENANCE
MONTH
CONCRETE PUMP SH 1800
1 411 258 300 30 4 266
SCHEWING STETTER

PRODUCTIVITY PER HR 13.7 CUM/HR

DIESEL CONSUMPTION PER HR 8.6 LTR/HR

CONCRETE PUMP

10% 1%

TOTAL NO. OF HRS IN ACTUAL OPERATION

DOWNTIME HRS DUE TO BREAKDOWN/ MAINTENANCE


89%
NON UTILISATION HRS

MPR FEB-2016 Page 13


DRAWING LOG As on 29th Feb 2016
REHAB 1 (STRUCTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
REHAB -1 STR. DRAWING
Revision Issued Copies
No. Of
Sr. No. Date Drawing Title Drawing Type Drawing No.s Billing / Executi Fitter/ Remark
R0 R1 R2 R3 R4 Copies
Planning on Carp.

1 18-09-2015 Excavation & Basement Layout (Rehab -1) Structural 18-09-2015 MCPL_REHAB1_S_PL_1.2 1
2 09-10-2015 Layout of U. G tank Bottom Slab Structural 09-10-2015 MCPL_REHAB1_S_PL_1.4 2
3 09-10-2015 Layout of U. G tank Top Slab Structural 09-10-2015 MCPL_REHAB1_S_PL_1.5 2
4 09-10-2015 Stilt Floor Plan Structural 09-10-2015 MCPL_REHAB1_S_PL_1.6 2
5 09-10-2015 Section Of ret. wall Part-1 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.1 2
6 09-10-2015 Section Of ret. wall Part-2 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.2 2
7 09-10-2015 Section Of ret. wall Part-3 Structural 09-10-2015 MCPL_REHAB1_S_DT_1.3 2
8 09-10-2015 Column Bar placing Details For Stilt Floor Structural 09-10-2015 MCPL_REHAB1_S_DT_1.3 2
9 09-10-2015 Layout Of raft Detail-1 Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_01 2
10 09-10-2015 Layout Of raft Detail-2 Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_02 2
11 09-10-2015 Layout of Raft Showing Chairs. Structural 09-10-2015 MCPL_Rehab1_S_PL_1.3_03 2
12 09-10-2015 Column Schedule Structural 09-10-2015 MCPL_Rehab1_S_PL_1.1 2
GN-1 Std Details Of Bending & Assembling of
13 09-10-2015 Reinforcement For RCC Menmbers General Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_1 2
Drawing
14 09-10-2015 GN-2 Typical Frame Beam Details Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_2 2
GN-3 Drawing Of Reinforcement For RCC
15 09-10-2015 Member (Ductile Detailing OF Column & Beam Structural 09-10-2015 MCPL_Rehab1_S_DT_GN_4 2
Junction)
16 26-11-2015 LAYOUT OF TYPICAL 8,10,12,14TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.10 4
17 26-11-2015 LAYOUT OF TYPICAL 16,18,20TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.12 4
LAYOUT & SCHEDULE OF REFUGE FLOOR
18 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.11 4
(15TH , 17TH, 19TH)
LAYOUT & SCHEDULE OF REFUGE FLOOR
19 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.14 4
(22ND FLOOR)
LAYOUT & SCHEDULE OF TYPICAL FLOOR
20 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.13 4
(21ST & 23RD)
21 26-11-2015 SECTION OF TYPICAL REFUGE FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.5 4
LAYOUT & SCHEDULE OF REFUGE FLOOR
22 26-11-2015 Structural 26-11-2015 MCPL_REHAB1_S_PL_1.9 4
(7,9,11 & 13THFLOOR)
23 26-11-2015 LAYOUT & SCHEDULE OF 1ST FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.7 4
24 26-11-2015 LAYOUT OF TYPICAL 2ND TO 6TH FLOOR Structural 26-11-2015 MCPL_REHAB1_S_PL_1.8 4

MPR FEB-2016 Page 14


REHAB 1 (ARCHITECTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Billing
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s / Executi Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies
Planni on Carp.
ng
1 09-10-2015 Rehab Building -1 Centre Line Plan ARCH 09-10-2015 ADCS_R1_A_1.00 2
2 09-10-2015 Rehab Building -1 Section A-A ARCH 09-10-2015 ADCS_R1_A_2.10 2
26-11-2015 Section A-A ARCH 26-11-2015 ADCS_R1_A_2.10 5
3 09-10-2015 Rehab Building -1 Section B-B ARCH 09-10-2015 ADCS_R1_A_2.11 2
4 09-10-2015 Rehab Building -1 Stilt Level Plan ARCH 09-10-2015 ADCS_R1_A_1.11 2
29-10-2015 Stilt Level Plan ARCH 29-10-2015 ADCS_R1_A_1.11 2
26-11-2015 Stilt Level Plan ARCH 26-11-2015 ADCS_R1_A_1.11 5
Rehab Building 1 & 2 Settting out
5 09-10-2015 ARCH R6 ADCS_LAY_A_1.01A.RB 2
basement Plan
Rehab 1 & 2 Setting Out Ground
6 09-10-2015 ARCH R5 ADCS_LAY_A_1.01A.RG 2
floor
7 29-10-2015 Lower Basement UGT level Plan ARCH R0 ADCS_R1_A_1.10_A 2
8 29-10-2015 Upper Basement UGT level Plan ARCH R0 ADCS_R1_A_1.10_B
9 26-11-2015 SectionC-C,D-D,E-E ARCH R0 ADCS_R1_A_2.12 5
10 26-11-2015 North east Elevation ARCH R1 ADCS_R1_A_3 5
11 26-11-2015 South East Elevation ARCH R0 ADCS_R1_A_3.10 5
12 26-11-2015 Door and Window Schedule ARCH R0 ADCS_R1_A_4.14 5
26-11-2015 Door Window Schedule ARCH 26-11-2015 ADCS_R1_A_4.14 5
13 26-11-2015 Staircase Details ARCH R0 ADCS_R1_A_4.10 5
14 26-11-2015 First Floor Plan ARCH 26-11-2015 ADCS_R1_A_1.12 5
Typical floor 2nd to 6th,
15 26-11-2015 8th,10th,12th,14th,16th,18th,and ARCH 26-11-2015 ADCS_R1_A_1.13 5
20th floor
16 26-11-2015 Typical floor plan 22nd floor ARCH 26-11-2015 ADCS_R1_A_1.15 5
Refuge floor plan 21st and 23rd
17 26-11-2015 ARCH 26-11-2015 ADCS_R1_A_1.16 5
floor
Refuge floor
18 26-11-2015 7th,9th,11th,13th,15th,17th,and ARCH 26-11-2015 ADCS_R1_A_1.14 5
19th floor

MPR FEB-2016 Page 15


REHAB 1 (MEP DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Executi Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies
Planning on Carp.

Rehab Building - 1 Under Ground


1 09-10-2015 MEP 09-10-2015 ABDC_REH1_MEP_1 B1 2
water Tank Sleeves Details & cutout
Rehab Building - 1 Under Ground
2 09-10-2015 MEP 09-10-2015 ABDC_REH1_MEP_1 B1 2
water Tank Sleeves Details & cutout
Rehab Building -1 Ground Floor
3 09-10-2015 MEP 14-10-2015 ABDC_REH1_MEP_100 2
Cutout Details
4 14-10-2015 Pump Room Ventilation MEP 14-10-2015 ABDC_REH1_HVAC_B1 2
Electrical Concealed Conduit layout
5 14-10-2015 MEP 14-10-2015 ABDC_REH1_MEP_1 B1_CONDUIT 2
@ -1.69 MTR Level
Electrical Concealed Conduit layout
6 14-10-2015 MEP 14-10-2015 ABDC_REH1_MEP_1 B2_CONDUIT 2
@ stilt Level
REFUGE FLOOR MEP CUTOUT
7 26-11-2015 DETAILS MEP 26-11-2015 ABDC_REH1_MEP_104 1
(7,9,11,13,15,17,19,21,23RD)
TYPICAL FLOOR MEP CUTOUT
8 26-11-2015 DETAILS (2 TO 6, MEP 26-11-2015 ABDC_REH1_MEP_102 1
8,10,12,14,16,18,20 & 22ND)
9 26-11-2015 1ST FLOOR MEP CUTOUT DETAILS MEP 26-11-2015 ABDC_REH1_MEP_101 1
CONCEALED CONDUIT LAYOUT @
10 26-11-2015 MEP 26-11-2015 ABDC_REH1_EL_103_CONDUIT 1
REFUGE (10,12,14,16,18 & 20TH)
CONCEALED CONDUIT LAYOUT @
11 26-11-2015 TYPICAL FLOOR(3 TO 9 & MEP 26-11-2015 ABDC_REH1_EL_102_CONDUIT 1
11,13,15,17,19, & 21ST)
CONCEALED CONDUIT LAYOUT @
12 26-11-2015 MEP 26-11-2015 ABDC_REH1_EL_101_CONDUIT 1
2ND FLOOR LEVEL

MPR FEB-2016 Page 16


REHAB 2 (STRUCTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
REHAB -2 STR. DRAWING
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.
Excavation & Basement Layout
1 18-09-2015 Structural 18-09-2015 MCPL_REHAB2_S_PL_1.2 1
(Rehab -2)
2 14-10-2015 Column Schedule Structural 14-10-2015 MCPL_REHAB1_S_SH_1.1 2
Column Bar placing Details For
3 14-10-2015 Structural 14-10-2015 MCPL_REHAB1_S_DT_1.4 2
Stilt Floor
MCPL_REHAB_2S_PL_1.3_0
4 14-10-2015 Layout of Raft Showing Chairs. Structural 14-10-2015 _
3
MCPL_REHAB_2S_PL_1.3_0
5 14-10-2015 Layout Of raft Detail-1 Structural 14-10-2015 2
1
MCPL_REHAB_2S_PL_1.3_0
6 14-10-2015 Layout Of raft Detail-2 Structural 14-10-2015 2
2
7 14-10-2015 Layout of U. G tank Bottom Slab Structural 14-10-2015 MCPL_REHAB1_S_PL_1.4 2
8 14-10-2015 Retaining Wall Details Part-1 Structural 14-10-2015 MCPL_REHAB2_S_DT_1.1 2
9 14-10-2015 Retaining Wall Details Part-2 Structural 14-10-2015 MCPL_REHAB2_S_DT_1.2 2
10 14-10-2015 Retaining Wall Details Part-3 Structural 14-10-2015 MCPL_REHAB2_S_DT_1.3 2
11 14-10-2015 Layout of U. G tank Top Slab Structural 14-10-2015 MCPL_REHAB2_S_PL_1.5 2
12 14-10-2015 Layout of Stilt Floor Structural 14-10-2015 MCPL_Rehab2_S_PL_1.6 2
TYPICAL FLOOR PLAN 9TH TO
13 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.11 4
14TH
REFUGE FLOOR PLAN 8TH & 15
14 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.8 4
TH
15 26-11-2015 TYPICAL FLOOR PLAN 22ND Structural 26-11-2015 MCPL_REHAB2_S_PL_1.9 4
16 26-11-2015 TYPICAL 1ST FLOOR PLAN Structural 26-11-2015 MCPL_REHAB2_S_PL_1.7 4
TYPICAL FLOOR PLAN 16TH TO
17 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.12 4
21ST & 23RD
TYPICAL FLOOR PLAN 2ND TO
18 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.13 4
7TH
LAYOUT OF TYPICAL
19 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.10 4
8,10,12,14TH FLOOR
LAYOUT OF TYPICAL 16,18,20TH
20 26-11-2015 Structural 26-11-2015 MCPL_REHAB2_S_PL_1.12 4
FLOOR

MPR FEB-2016 Page 17


REHAB 2 (ARCHITECTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.
1 09-10-2015 Rehab Building -2 Centre Line Plan ARCH 09-10-2015 ADCS_R2_A_1.00 2
2 09-10-2015 Rehab Building -2 Stilt Level Plan ARCH 09-10-2015 ADCS_R2_A_1.00 2
3 09-10-2015 Rehab Building -2 Section B-B ARCH 09-10-2015 ADCS_R2_A_2.00 2
Rehab Building -2 Lower basement
4 14-10-2015 ARCH 14-10-2015 ADCS_R2_A_1.10_A 2
level Plan
Rehab Building -2 upper basement
5 14-10-2015 ARCH 14-10-2015 ADCS_R2_A_1.10_B 2
level Plan
6 14-10-2015 Rehab Building -2 Stilt Level Plan ARCH 14-10-2015 ADCS_R2_A_1.11 2
26-11-2015 Stilt Level Plan ARCH 26-11-2015 ADCS_R2_A_1.11 5
7 29-10-2015 Reahab 2 Section A-A ARCH 29-10-2015 ADCS_R2_A_2.00 2
Typical floor plan 1st ,7th, 9th,14th to
8 26-11-2015 ARCH 26-11-2015 ADCS_HGM_A_1.12 5
14th, 16th to 21st and 23rd
9 26-11-2015 Refuge Floor Plan 8th and 15th floor ARCH 26-11-2015 ADCS_HGM_A_1.13 5
10 26-11-2015 Refuge floor plan 22nd floor ARCH 26-11-2015 ADCS_HGM_A_1.14 5
11 26-11-2015 Section A-A ARCH 26-11-2015 ADCS_HGM_A_2.10 5
12 26-11-2015 Section C-C, D-D, and E-E ARCH 26-11-2015 ADCS_R2_A_2.12
13 26-11-2015 Staircase Details ARCH ADCS_R2_A_4.10
14 26-11-2015 North Elevation ARCH 26-11-2015 ADCS_R2_A_3.00
26-11-2015 West Elevation ARCH 26-11-2015 ADCS_R2_A_3.00
15 26-11-2015 South Elevation ARCH 26-11-2015 ADCS_R2_A_3.01
26-11-2015 East Elevation ARCH 26-11-2015 ADCS_R2_A_3.01

MPR FEB-2016 Page 18


REHAB 2 (MEP DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.
Rehab Building - 2 Under Ground water
1 09-10-2015 MEP 09-10-2015 ABDC_REH2_MEP_1 B1 2
Tank Sleeves Details & cutout
Rehab Building - 2 Under Ground water
2 09-10-2015 MEP 09-10-2015 ABDC_REH2_MEP_1 B1 2
Tank Sleeves Details & cutout
Rehab Building -2 Ground Floor Cutout
3 09-10-2015 MEP 14-10-2015 ABDC_REH2_MEP_100 2
Details
4 14-10-2015 Pump Room Ventilation Layout MEP 14-10-2015 ABDC_REH2_HVAC_B1 2
Electrical Concealed Conduit layout @ - ABDC_REH2_MEP_1
5 14-10-2015 MEP 14-10-2015 2
1.69 MTR Level B1_CONDUIT
Electrical Concealed Conduit layout @ ABDC_REH2_MEP_1
6 14-10-2015 MEP 14-10-2015 2
stilt Level B2_CONDUIT
Electrical Concealed Conduit layout @ ABDC_REH2_EL_104_CONDUI
7 26-11-2015 MEP 26-11-2015 1
REFUGE FLOOR 22ND T
Electrical Concealed Conduit layout @ ABDC_REH2_EL_103_CONDUI
8 26-11-2015 MEP 26-11-2015 1
REFUGE FLOOR T
Electrical Concealed Conduit layout @
ABDC_REH2_EL_102_CONDUI
9 26-11-2015 TYPICAL FLOOR (1ST TO 7TH, 9TH TO MEP 26-11-2015 1
T
14TH, 16TH TO 21ST & 23RD)
Refuge floor MEP cutout details 22nd
10 26-11-2015 MEP 26-11-2015 ABDC_REH2_MEP_103 1
floor
Refuge floor MEP cutout details 8th to
11 26-11-2015 MEP 26-11-2015 ABDC_REH2_MEP_102 1
15th floor
Typical floor_MEP_cutout
12 26-11-2015 details(1st,7th,9th to 14th, 16th to 21st MEP 26-11-2015 ABDC_REH2_MEP_101 1
and 23rd )

MPR FEB-2016 Page 19


NAHAR EXCALIBUR (STRUCTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.

MCPL_SALEBLDG_S_PL_1.
1 10-11-2015 EXCAVATION PLAN Structural R3 2
2
COLUMN BAR PLACING MCPL_SALEBLDG_S_DT_1.
2 10-11-2015 Structural R3 3
DETAILS 1
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
3 10-11-2015 Structural R3 3
PART 7 9
LAYOUT OF PARKING FLOOR MCPL_SALEBLDG_S_PL_1.
4 10-11-2015 Structural R3 3
1ST LEVEL 9
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
5 10-11-2015 Structural R3 3
PART 3 5
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
6 10-11-2015 Structural R3 3
PART 2 3
SCHEDULE OF BEAM & SLAB MCPL_SALEBLDG_S_SH_1.
7 10-11-2015 Structural R3 3
1ST LEVEL PARKING 5
SCHEDULE OF BEAM & SLAB MCPL_SALEBLDG_S_SH_1.
8 10-11-2015 Structural R3 3
MEZZANINE FLOOR 4
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
9 10-11-2015 Structural R3 3
PART 6 8
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
10 10-11-2015 Structural R3 3
PART 1 2
LAYOUT AT MEZANINE MCPL_SALEBLDG_S_PL_1.
11 10-11-2015 Structural R3 3
FLOOR 7
MCPL_SALEBLDG_S_PL_1.
12 10-11-2015 LAYOUT OF STILT FLOOR Structural R3 3
6
LAYOUT OF STILT FLOOR/ UG MCPL_SALEBLDG_S_PL_1.
13 10-11-2015 Structural R3 3
TANK TOP 5
LAYOUT OF STILT FLOOR MCPL_SALEBLDG_S_PL_1.
14 10-11-2015 Structural R3 3
(SERVICE BASEMENT-1) 4
LAYOUT OF RAFT SHOWING MCPL_SALEBLDG_S_PL_1.
15 10-11-2015 Structural R3 3
CHAIR 8
MCPL_SALEBLDG_S_SH_1.
16 10-11-2015 COLUMN SCHEDULE Structural R3 3
1
SCHEDULE OF BEAMS & SLAB MCPL_SALEBLDG_S_SH_1.
17 10-11-2015 Structural R3 3
FOR UG TANK TOP SLAB 2
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
18 10-11-2015 Structural R3 3
PART 4 6
RETAINING WALL DETAIL MCPL_SALEBLDG_S_DT_1.
19 10-11-2015 Structural R3 3
PART 5 7
MCPL_SALEBLDG_S_PL_1.
20 10-11-2015 LAYOUT OF RAFT DETAIL Structural R3 3
3
MCPL_SALEBLDG_S_PL_1.
21 10-11-2015 LAYOUT OF RAFT DETAIL Structural R3 3
3
SCHEDULE OF BEAMS & SLAB MCPL_SALEBLDG_S_SH_1.
22 10-11-2015 Structural R3 3
FOR STILT FLOOR 3

MPR FEB-2016 Page 20


NAHAR EXCALIBUR (ARCHITECTURAL DRAWING)
CAPACIT'E INFRAPROJECTS LTD.
Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.
Excalibur Sale Setting out ADCS_LAY_A1.01_S
1 09-10-2015 ARCH R6 2
Plan Basement Level B

Excalibur Sale Setting out ADCS_LAY_A1.01_S


2 09-10-2015 ARCH R6 2
Plan Ground Level G

Nahar Excalibur Centre Line


3 09-10-2015 ARCH 09-10-2015 10-11-2015 ADCS_ST_A_1.01 2
Plan

4 09-10-2015 Nahar Excalibur Section A-A ARCH 09-10-2015 10-11-2015 ADCS_ST_A_2.00 2

5 09-10-2015 Nahar Excalibur Section B-B ARCH 09-10-2015 10-11-2015 ADCS_ST_A_2.01 2

ADCS_ST_A_1.10_L
6 10-11-2015 LOWER BASEMENT LEVEL ARCH 10-11-2015 2
B

ADCS_ST_A_1.10_U
7 10-11-2015 UPPER BASEMENT LEVEL ARCH 10-11-2015 2
B

8 10-11-2015 STILT LEVEL PLAN ARCH 10-11-2015 ADCS_ST_A_1.11 2

MPR FEB-2016 Page 21


NAHAR EXCALIBUR (MEP DRAWING)

CAPACIT'E INFRAPROJECTS LTD.


Project Name - NAHAR EXCALIBUR AT MAHALAXMI
IFC Drawing Records
Revision Issued Copies
Drawing No. Of
Sr. No. Date Drawing Title Drawing No.s Billing / Fitter/ Remark
Type R0 R1 R2 R3 R4 Copies Execution
Planning Carp.

UNDERGROUND WATER TANK


1 17-11-2015 MEP 17-11-2015 ABDC_ST_MEP_B1
SLEEVE & CUTOUT DETAIL

UNDERGROUND WATER TANK


2 17-11-2015 MEP 17-11-2015 ABDC_ST_MEP_1.10A
SECTIONAL DETAIL
BASEMENT VENTILATION
3 17-11-2015 MEP 17-11-2015 ABDC_SALE_HVAC_R0
LAYOUT
ELECTRICAL CONCEALED
ABDC_SALE_EL_1B1_C
4 17-11-2015 CONDUIT LAYOUT @ +.3 MTR MEP 17-11-2015
ONDUIT
LEVEL

Note: All GFC drawings to be given 30 days in advance for Studying, Material Procurement & Planning the activities.

MPR FEB-2016 Page 22


MAJOR MATERIAL RECEIVED FOR FEB-2015

Ready Mix Concrete - RMC

Sr no Description of Material Unit This Month Qty Cum Qty

1 Ready Mix Concrete M5 Cum - -

2 Ready Mix Concrete M10 Cum - -

3 Ready Mix Concrete M15 Cum - 480

4 Ready Mix Concrete M25 Cum - -

5 Ready Mix Concrete M30 Cum 16 773

6 Ready Mix Concrete M40 Cum 103 1301

7 Ready Mix Concrete M50 Cum 81 122

Total Steel Received MT 200 2676

Reinforcement Steel

Sr no Description of Material Unit This Month Qty Cum Qty

1 TMT BAR FE500 08 MM DIA MT - 29.514

2 TMT BAR FE500 10 MM DIA MT - 57.680

3 TMT BAR FE500 12 MM DIA MT - 56.231

4 TMT BAR FE500 16 MM DIA MT - 92.764

5 TMT BAR FE500 20 MM DIA MT - 65.040

6 TMT BAR FE500 25MM DIA MT - 99.215

7 TMT BAR FE500 32 MM DIA MT 189.231

Total Steel Received MT 589.675

MPR FEB-2016 Page 23


FROMWORK MATERIAL DETAIL
CAPACITE INFRAPROJECTS LTD.

NAHAR PROJECT(MAHALAXMI)

FORMWORK MATERIAL DETAILS

DATE-29.02.2016

REHAB-1 REHAB-2 SALE TOWER

Sr. no. Description / Item Unit ADDITIONAL ADDITIONAL TOTAL


Typical & Typical & TYPICAL TYPICAL TYPICAL ADDITIONAL
VERTICAL Typical & MATERIAL FOR RAFT / VERTICAL TYPICAL TYPICAL /BASEMENT MATERIAL FOR RAFT / VERTICAL TYPICAL
RAFT/RETAING WALL Basement Beam Basement Beam /BASEMENT /BASEMENT /BASEMENT MATERIAL FOR
SYSTEM Basement Slab TYPICAL FLOOR RETAING WALL SYSTEM /BASEMENT SLAB BEEAM BOTTOM TYPICAL FLOOR RETAING WALL SYSTEM /BASEMENT SLAB
Side bottom BEEAM SIDE BEEAM SIDE BEEAM BOTTOM TYPICAL FLOOR SLAB
SLAB SLAB

REQUIRED QTY RECEIVED QTY BALANCE QTY

1 Ply 8' x 4' x 12mm Thk. Sqm 50 550 400 505 527.5 75 775 470 360 567.5 75 1115 560 1050 1082.5 8162.5 1301 6861.5
2 Ply 8' x 4' x 12mm Thk. (for Gabadi) Sqm 200 200 205 200 205 240 240 1490 0 1490
3 Timber 2" x 3" x 8' Cuft 110 210 110 110 110 250 155 125 210 500 312.5 2202.5 657.67 1544.83
4 Timber 2" x 4" x 8' Cuft 100 100 0 100 300 0 300
5 Timber 3" x 4" x 8' Cuft 50 165 150 520 342.5 60 165 160 640 402.5 60 250 150 2200 1225 6540 1055 5485
6 Guy Rope dia 10 Mtrs 300 330 264 894 645 249
7 U clamp for Guy Rope Nos 110 154 200 464 319 145
8 Tie rod (dia 15 x 3.0M lg.) Nos 159 142 190 174 190 392 1247 922 325
9 Anchor Nut Nos 1150 660 1270 760 1500 550 5890 1810 4080
10 Lean - Forged Pin Dia 16 x 110mm with Spring Cotter Nos 440 490 520 1450 1450 0
11 Lean - Wedge & Pin (100mm Lg.) Nos 1600 2000 2100 5700 4950 750
12 Water barrier Nos 700 850 850 2400 1618 782
13 Hex Bolt M16 x 150 Lg. with nut & double washer Nos 400 0 400 423 -23
14 ISMC 100 x 50 MT 2 6 5 2 4 7 2 6 7 41 18.42 22.58
15 Sq. Tube 50 x 50 x 2.9Thk. MT 7 5 6 18 0 18
16 Lean - Panel 300 x 2700 Nos 10 14 14 38 24 14
17 Lean - Panel 450 x 2700 Nos 10 24 30 64 40 24
18 Lean - Panel 600 x 2700 Nos 20 46 60 126 81 45
19 Lean - Panel 750 x 2700 Nos 12 68 86 166 92 74
20 Lean - Panel 900 x 2700 Nos 66 44 30 140 109 31
21 Lean - Inner Corner 2700 Nos 22 20 24 66 24 42
22 Lean - Waler 1.5M Lg. Nos 57 54 54 165 111 54
23 Lean - Waler 1.75M Lg. Nos 54 45 45 144 99 45
24 Lean - Waler 2.0M Lg. Nos 69 75 90 234 183 51
25 Lean - Waler 3.0M Lg. Nos 51 51 60 162 111 51
26 Lean - Push Pull Prop (Type - 1) Nos 110 120 130 360 360 0
27 Lean - Push Pull Prop (Type - 2) Nos 110 120 130 360 360 0
28 Lean - Prop Top Connector Nos 220 240 260 720 480 240
29 Lean - Prop Bottom Connector Nos 110 120 130 360 360 0
30 Lean - Stop end Bolt with Anchor nut Nos 72 72 72 216 216 0
31 Lean - GTX connector Push pull with double nut & washer Nos 72 72 72 216 216 0
32 Lean - Outer Corner Angle 2700 Nos 6 8 8 22 22 0
33 Stop end waler 1.0 (G. I Plated) Nos 42 54 54 150 150 0
34 RMD GTX (65 x 150) 2700mm Nos 36 36 36 108 36 72
35 RMD Rapid ply Panel system Sqm 250 300 485 1035 0 1035
36 CT Prop (2.0+2.0) Nos 415 165 470 165 590 284 2089 584 1505
37 Fixed U Head Nos 330 374 470 1174 330 844
38 Cuplock vertical 1.0M Nos 333 264 144 138 879 56 823
39 Cuplock vertical 1.5M Nos 220 242 576 1038 1038 0
40 Cuplock vertical 2.0M Nos 168 264 365 242 913 1952 1185 767
41 Cuplock vertical 2.5M Nos 168 365 576 154 1263 1263 0
42 Cuplock ledger 0.9M Nos 248 374 264 642 792 1884 4204 2756 1448
43 Cuplock ledger 1.2M Nos 823 264 1650 374 1768 1281 6160 5447 713
44 Cuplock ledger 1.5M Nos 343 264 949 110 1430 1315 4411 0 4411
45 Stirrup head 450 Lg. Nos 168 440 365 464 576 913 2926 2926 0
46 Base jack 450 Lg. Nos 168 242 365 242 576 913 2506 2648 -142
47 40 NB B Class pipe MT 1 3 1 3.5 1.5 3 13 12.32 0.68
48 Tripod Nos 246 176 264 264 320 276 1546 100 1446
49 Swivel coupler Nos 150 330 110 374 100 352 1416 1416 0
50 Cuplock working platform bracket Nos 156 176 176 508 0 508
51 Internal beam bottom bracket Nos 176 232 166 574 150 424
52 Shikanja 750mm Lg. Nos 550 565 752 1867 950 917
53 Beam side bracket Nos 352 464 332 1148 150 998
54 ISA 40 x 40 x 5Thk. MT 9 11 15 35 0 35
55 CT Prop (1.5+1.5) Outer with plate & Inner without plate Nos 176 232 166 574 176 398
56 CT Prop (2.0+2.0) Outer with plate & Inner without plate Nos 166 166 0 166
TOTAL… 5700 250 4599 2573 5064 1180 6220 300 6806 2954 5453.5 1330 6682 485 9661.5 3061 13321 2860 78500 39430.41 39069.59
19366 23063.5 36070.5

MPR FEB-2016 Page 24


CASH FLOW
S- CURVE (INVOICING RA BILL AGAINST WORKDONE) PLANNED VS ACTUAL
CASHFLOW
400.00 6,000.00
NAHAR ESCALIBUR- S CURVE

350.95 5,380
350.00 5,266
5,166
5,000.00
4,815
307.83 305.92
297.16 4,564
300.00 290.24 4,429
4,242
268.02
258.87 3,989 4,000.00
AMOUNT IN LACS

253.23 252.74 251.05


250.00 3,731

3,433
209.54 211.58 3,238

200.00 194.00 194.91 194.93 3,000.00


190.95 2,933 186.33
2,778
163.27
155.87 154.08 2,488 154.65
150.00 144.03 2,293
137.12 135.64 2,149 135.77
2,000.00
115.71 1,896
113.68
1,732
101.24 99.94
100.00
1,424
1,233
1,098
961 1,000.00
845
50.00
633
424

- - 156
- 0 -
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Monthly plan Invoicing - 155.87 268.02 209.54 211.58 115.71 137.12 135.64 190.95 307.83 163.27 253.23 144.03 194.91 290.24 154.65 305.92 194.93 297.16 258.87 252.74 186.33 135.77 251.05 350.95 99.94 113.68
monthly actual invoicing - 194.00 154.08 101.24
Cumm. Plan Invoicing - 155.87 423.89 633.43 845.00 960.71 1,097.83 1,233.47 1,424.41 1,732.24 1,895.51 2,148.74 2,292.77 2,487.68 2,777.92 2,932.57 3,238.49 3,433.42 3,730.58 3,989.45 4,242.19 4,428.51 4,564.29 4,815.33 5,166.29 5,266.22 5,379.90
cumm. Actual invoicing - 194.00 348.08 449.32

MPR FEB-2016 Page 25


Look Ahead Micro Schedule for the Month of March-16.
Schedule up to Plinth Level_ R2_Excallibur.pdf

QA/QC REPORT
QAQC-MTC REPORT

MPR FEB-2016 Page 26


SAFETY

MPR FEB-2016 Page 27


MONTHLY HSE PERFORMANCE REPORT
MONTH Feb-16 DATE 29.02.16
PROJECT NAHAR EXCALIBUR, MAHALAXMI CLIENT NAHAR

Sr. No. Particulars Calculation Current Cumulative Remark

A Total Man Hours


Total Man-Days worked(TMDW) 4763 15942

Total Man-hours Worked(TMHW) TMDW*09 hrs 42867 143478


Total safe man hours worked (TSMHW) TMHW - TMHL 42867 143478

B Monthly Incident/Accident Record

Near Miss Report 1 4


First-aid cases 4 30
Medical Treatment Cases (Visited Hospital.) 0 1
LTI Cases (Hospitalised and duty resumed after 48
hrs.) 0 0
Fatal Cases (1 Fatal Case = 6000 MDL) 0

C Total Mandays Lost (MDL) 0


Total Man-Hrs. lost (TMHL) MDL*9 0 0

D Frequency Rate (For LTI) FR= No. of LTI*10^6)/TMHW 0 0

E Severity Rate SR= (MDL)*10^6)/ TMHW 0 0

F HSE Inspection Reports

Fire Extinguisher Inspection 0 4


Labour camp Inspection 2 11
Electrical Inspection 1 5
Housekeeping Inspection 2 8
Mechanical Equipments Inspection 2 5
PPE Inspection 1 9
Store Inspection 1 4

G HSE Related Deficiencies


Observation Reports:
Closed 97 301
Open 6 42
Internal NCR 0 4
Violation Notice 7 23
Safety Violation Debit (In Rs.)

H SAFETY MEETINGS AND TRAININGS


Safety Committee Meeting helds 1 3
No. of Weekly Safety Walk Conducted 3 15

No. of Person safety Inducted(NOSPI) 144 602


Total Safety Induction Training hrs.(TITH) TSITH= NOSPI*1 Hrs. 144 602
Total nos Tool Box Talk 9 41
Total No. of Person attended TBT 243 640
Total TBT Training Hrs.(TTBTTH) TTBTTH= TBT*0.25 60.75 160
Special Training arranged/Job Specific Training given 2 5
Total No. of Training Attendees (TNOTA)
43
TTH=TSITH+TTBTTH +
(TNOTA*X), X- Avrg. Training
Total No. of Training Hours hrs. of special training. 204.75 977

SAFETY IN
MPR
CHARGE FEB-2016 PROJECT INCHARGE Page 28
MEDICAL
ZERO INJURY FIRST AID CASE TREATMENT CASE LTI
(MTC)

1 2 3

4 5 6

7 8 9

10 11 12 13 14 15 16

17 18 19 20 21 22 23

24 25 26

27 28 29

MPR FEB-2016 Page 29


Site Logistic Plan

MPR FEB-2016 Page 30


General Hindrances

1) Work delay due to BMC road work near sale main gate from 06-Jan-2016 to

15-JAN-2016.

2) Reinforcement work because steel supplier not ready to supply 32mm steel

due to payment issue. (Expected delivery on 28-DEC-2015 , Received on 07-

JAN-2016)

3) Waterproofing work at rehab-1 and sale building is affected due to

approval of waterproofing Bituthene-300 membrane for Vertical member is

pending with Nahar team.

4) Brickwork at sale and rehab 1 building delay due to approval of using crush

sand instant of river sand pending with Nahar team.

MPR FEB-2016 Page 31


PROGRESS PHOTOGRAPHS

MPR FEB-2016 Page 32


Sale Building

Brickwork Work in Progress

Brickwork Work in Progress

MPR FEB-2016 Page 33


Plaster Work in Progress

Waterproofing Work in Progress

MPR FEB-2016 Page 34


UG Tank Reinforcement work in Progress

Retaining wall Reinforcement & Shuttering work in Progress

MPR FEB-2016 Page 35


Rehab -1

Flushing Tank 1st Pour Slab Shuttering work in Progress

Flushing Tank 1st Pour Slab Shuttering work in Progress

MPR FEB-2016 Page 36


1st Pour Slab at Service Basement level Slab casted on 26th Feb 2016

Curing of Casted Element

MPR FEB-2016 Page 37


Column Reinforcement work in Progress

Service Basement 2nd Pour Slab Reinforcement work in Progress

MPR FEB-2016 Page 38


Rehab -2

Brickwork in Progress

Plastering work in Progress

MPR FEB-2016 Page 39


Plastering work in Progress

Waterproofing work in Progress

MPR FEB-2016 Page 40