AESS
AESS
MAXIMUM
Exposure
WHEN THE WORD “STEEL” is mentioned, its flexibility, Exposed or Architecturally Exposed?
durability and strength typically come to mind. The AISC Code defines structural steel as elements that
But what about its beauty? More and more designers are required to support the design loads of a building and
are choosing to expose steel in their projects—not just out fit within the components of a structural frame. For clar-
of a sense of practicality or functionality, but also for its ity, the AESS category system is typically only applied to
aesthetic attributes. They do so because they realize that fabricated structural steel as referenced in Section 2.1 of
steel can do more than simply support a design; it can also the Code: anchor rods, base plates, beams, bracing, canopy
become an integral part of it. framing, columns, connection materials, crane stops, girders,
And in doing so, they often hold steel to as high a standard lintels, posts, shear stud connectors, trusses, etc. Unfinished,
as any other fixture or finish. They aren’t just going for an reused, galvanized or weathering steel members may all be
industrial look. They’re elevating the material to a new level: fabricated with AESS requirements.
architecturally exposed structural steel (AESS). So where to AESS goes a step beyond standard fabrication and erec-
begin when considering AESS for your next project? Start tion. During fabrication, shipment and erection, extra care is
with the Code. taken to avoid blemishes and unwanted surface appearance
The 2016 AISC Code of Standard Practice (ANSI/AISC when handling the steel and removing temporary braces or
303-16) implements a defined approach to specifying AESS fixtures. For some categories, all backing and runoff tabs are
in the contract documents by using five categories—AESS removed, and welds are to be ground smooth for those areas.
1, 2, 3, 4 and C—which differentiate levels of steel fabrica- Basic unpainted steel must also be cleaned of oil, grease, dirt
tion and erection. As the numbers in this tiered system rise, and loose mill.
the cost and time for fabrication and erection typically also There are “other steel, iron or metal items” that are not
increase. (A similar approach was adopted in the Canadian typically specified as AESS, though there may be exceptions
Code of Standard Practice in 2009 via the Canadian Institute depending on project requirements. Cables, castings, catwalks,
of Steel Construction—CISC—Code of Standard Practice for chutes, cold-formed steel products, corner guards, flagpole
Structural Steel, Seventh Edition.) Previous versions of the supports, grating, handrails, ladders, ornamental metal, stacks,
codes did not define the terms of AESS as distinctly, leav- stairs, steel deck, open-web steel joists, joist girders and trench-
ing room for interpretation and cost escalation, and this lat- es are examples of components that do not typically receive
est version of the AISC Code helps clear things up. The new AESS identification (reference Section 2.2 of the AISC Code
guidelines establish the same level of expectations between for the full list).
designers, fabricators and erectors for the visual appearance Everyone in the building industry is familiar with the phrase
of AESS. The category system provides architects with a “location, location, location.” When architecturally exposing the
method of articulating AESS in their projects with a much structure as an integral part of the design intent, the following
clearer understanding of deliverables. phrase comes into play: “coordination, coordination, coordina-
tion.” While the architect chooses the locations of AESS in a
project, the structural engineer should document it. According
Striking structural steel, exposed not only architecturally but to Bill Andrews, SE, a principal at structural engineering firm
also to the elements, lets Chicago’s newest transit station, the Walter P Moore, fabricators and detailers will typically look to
Washington/Wabash “L” station, take on its own unique look the structural drawings in the contract documents as the pri-
and feel. (See page 36 for more on this project, which opened
this past summer.) mary source of information for structural steel, including AESS.
NOVEMBER 2017
This methodology saves time and cost during construction,
with the intent of consolidating references to AESS as much
as possible. It is of utmost importance that successful coor-
dination between these disciplines takes place to ensure the
contract documents are bid per the design intent.
Equally imperative is selecting the correct category for all
AESS components in a project. Per the AISC Code, it is re-
quired that all AESS is identified as Categories 1, 2, 3, 4 or C.
“This is a dramatic improvement over the previous code edi-
tion [2010],” says Andrews, “in terms of better clarity, articu-
lating expression... and giving everyone a better understand-
ing of relative costs when choosing AESS and at what level.”
Sufficient coordination and understanding of best practices
are essential to keeping a project within budget and schedule.
AESS Categories
There are five categories under which AESS can fall:
➤ AESS 1: Basic Elements
➤ AESS 2: Feature Elements not in Close View
➤ AESS 3: Feature Elements in Close View
➤ AESS 4: Showcase Elements
➤ AESS C: Custom Elements
More requirements, and therefore typically greater costs, are inherent as the
AESS category number increases. AESS C is Custom and could require fewer
levels of finish than Basic Elements in AESS 1, or go even further beyond what
is included in Showcase Elements of AESS 4. When choosing AESS C, more
The Queen Richmond Centre West
information should be included in the drawings and specifications to clarify the
in Toronto (above) and San Francis-
intent. It is required that one or more of these five AESS categories be anno-
co’s Transbay Transit Center (below)
tated in the contract documents when the AISC Code is referenced as a standard.
are two projects featuring massive
“Section 10 of the AISC Code provides specifiers with a much clearer roadmap
cast elements designated as AESS.
to convey what they are looking for,” acknowledges Babette Freund with AISC
Selection of the appropriate AESS
member fabricator Universal Steel of North Carolina. Freund serves as chair
Category should consider not only
of the Code of Standard Practice Committee to recognize and document stan-
viewing distance but also the coating
dards within the U.S. structural steel industry to help meet design expectations
system to be implemented. In the
between fabricators and designers. Larry Kloiber, who serves on the commit-
case of the Queen Richmond Centre
tee with Freund, encourages architects to consider the appearance they want to
West, an intumescent coating has
achieve for the design intent prior to selecting an AESS category.
been applied to the steel. The Trans-
AESS 1: BASIC ELEMENTS. By default, AESS 1 is the minimum treatment
bay Transit Center’s signature Light
of exposed steel beyond standard fabrication of structural steel. This category
Column feature is comprised of steel
typically incurs the lowest cost of all the AESS categories and also serves as a
castings and API pipe. AESS require-
prerequisite for AESS categories 2, 3 and 4. There are aspects of AESS 1 that
ments for this assembly range from
meet the same requirements of standard fabrication. For example, the toler-
AESS 2 to AESS 4 based on viewing
ances required for standard structural steel are the same for AESS 1 and can be
distance. The Transbay Transit Cen-
referenced in the AISC Code.
ter is scheduled to open next year;
Surface preparation in AESS 1 is different from standard fabrication, as the
the Queen Richmond Centre West is
exposed steel must receive commercial blast cleaning to meet the provisions
already open.
of SSPC SP-6: Commercial Blast Cleaning. The Society for Protective Coatings
(SSPC) sets the standards for coatings and protection on structural steel. The
Adamson Associates
SP-6 standard requires steel to be cleaned of oil, grease, dust, oxides, rust, etc.
In order to complete this surface preparation, weld spatter and similar surface
discontinuities must be removed and sharp edges ground smooth. Specifications
for paint and coatings should be thoroughly reviewed for use with the required
surface preparation of AESS members.
Consistency of appearance between components is also a key strategy when
specifying AESS. The AESS 1 category requires that bolt heads be consistently
located on the same side of a member as well as on adjacent steel members. The
goal is to provide a uniform appearance beyond the standard requirements of
structural steel.
When steel components are welded together, there may not always be a need
for a continuous weld per the structural design. Visually, however, the appear-
ance of a continuous weld is more desirable than intermittent welds. AESS 1
requires that all welds are to appear continuous and can be caulked, filled or ad-
ditionally welded to achieve this look. The projection of welds can be no higher
than 1⁄ 16 in. above the surface.
Questions to Consider
MIG Steel Fabrication (an AISC member) shares some
questions and suggestions based on its first experience
with a complex AESS project: the decorative
Technology Tower on North Carolina State University’s
campus in Raleigh, N.C.:
➤ Are the project specifications for AESS in
alignment with Section 10 of the AISC Code?
Do they clearly address requirements for special
fabrication, handling and erection of AESS?
➤ What are the requirements for preinstallation
conferences, mock-up procedures and testing?
If these are not addressed in the specs, the
fabricator should have recourse to include them
in order to facilitate communication and address
quality issues prior to installation.
➤ Will outside vendors be required to complete
the AESS project? If so, are there clear protocols
in place to reconcile quality issues if and when
Robert Benson Photography
they arise?
➤ Include a budget for contingencies. Unforeseen
challenges happen on every project, but AESS
may require implementing completely unique
solutions.
➤ Learn to be flexible. Thinking outside the box
and meeting the challenges of a complex AESS
project can reap great knowledge and experience
dividends applicable to future projects.
NOVEMBER 2017
CannonDesign/Scott Frances
An addition to Dickinson College’s Kline Center in Carlisle, Pa., features exposed steel throughout the building, but only select
exposed structural members close to view were designated as AESS.
Making an (Exposed) Connection down to meet the primary plate, whose purpose is to
Terri Meyer Boake, an architecture professor at the Uni- transfer loads to the mast. It widens to provide ade-
versity of Waterloo in Waterloo, Ontario, has an eye for quate transfer via its fillet welds. There is just enough
interesting and attractive exposed steel. Below are two room between the many plates to do the welding. On
exposed connections that she’s come across in her trav- the right, the detailing of the large arched trusses that
els, highlighting impressive AESS detailing. span the departures hall of this airport is playful.
The connection on the left showcases a high level The members have been chosen to highlight their
of thought in accommodating the transition from the tensile versus compressive function. Pin connections
small diameter of the cable to the attachment of about are extensively used to attach the tension mem-
20 plates to a mast. The thickness of the plate at bers, while plates inserted into the round tubes that
the pin connection has been increased to resist comprise the compression members create a visual
pull-through forces. The thickened element tapers contrast.
NOVEMBER 2017
Different Viewing Levels, Different AESS Levels
Spaces like multilevel concourses provide the possibility for multiple AESS categories all in a single space and all
visible at once. Kansas City’s Sprint Center was built before the current AESS categories were implemented, but in
looking at the below photo of the space, you can see where various categories could have been implemented. With
any area employing multiple categories, the architect should provide clear notes as to where each category should
be used and coordinate this documentation with the structural engineer’s drawings and specifications.
AESS 1
AESS 2
Copyright Bill Cobb/kcphoto.com
AESS 3
manner across all members is another solution. There are mul- plates over them, a detail that should be clearly expressed in
tiple methods of fulfilling this requirement, some of which are the contract documents.
less costly than others. AESS 4: SHOWCASE ELEMENTS. The sculptural nature
When two cross sections of steel come together, such as a of steel is meant to be the main focus when specifying AESS 4.
column splice with connection plates, it is critical the sections This category draws inspiration from the expression of form as
align when in close viewing range. Lighting showcasing an AESS the featured aesthetic in a project. Making material connections
component can expose misaligned surfaces in an obvious and appear seamless in a project can sometimes be the most chal-
undesirable manner. AESS 3 specifically addresses components lenging ones to design and construct. The latter is also true of
within range of touch or within closer viewing distances up to structure, especially when AESS is to have a very smooth and
20 ft away. Misalignments are not acceptable and require greater sleek finished appearance. It is generally understood that AESS
care in fabrication and erection to avoid these issues at cross- 4 components may entail the highest premium over the previ-
sectional surfaces that abut one another. ous categories, not only per the desired “glove-smooth” finish,
The tolerance for straightness must be tighter than the but more often due to the complexity of structural geometry.
standard level, as noted under AESS 2. Tolerance require- The design approach should be discussed between the archi-
ments in AESS 3 go further to minimize the gaps between tect and structural engineer in advance of selecting the AESS
the components that have bolted connections. Greater preci- category.
sion during fabrication and erection is required so that these The characteristics of the previous categories, AESS 1, 2
gaps are no greater than 1⁄8 in. and are uniform among all and 3, are all included with the selection of AESS 4. In AESS
adjacent components. 3, it is acceptable to reduce the visibility of weld seams. The
Determining the style of aesthetic is a prerequisite for glove- smooth finish desired for showcase elements in AESS
choosing the appropriate AESS category. Oftentimes, design- 4 necessitates that weld seams are no longer visible. Certain
ers wish to expose their bolts for a more tectonic aesthetic. structural steel shapes and sections, such as pipe or some
In cases where visible bolted connections aren’t desired or types of HSS, lend themselves to having few or no seams. If
are challenging to access and tighten—e.g., when trying to at all possible, turn the seam away from view for the most
achieve a seamless, plastic look—AESS 3 includes an option cost-effective strategy.
to use all-welded connections or reduce bolt usage. This can The smooth and contoured appearance of welds enhances
be achieved by coordinating the design intent with the struc- the style of the more plastic look of AESS 4 components. The
tural engineer to use only welds for a particular connection. majority of steel designs in this category focus less on bolted
An alternate solution may be to hide the bolts by placing cover connections and implement more welded connections for
a seamless aesthetic. There are cases where welds may show architects to coordinate or customize AESS requirements with
through the back face of an exposed steel element. Locations structural engineers. The matrix should be used to specify spe-
where welds show through to the other side of the AESS com- cial requirements for AESS C in the contract documents.
ponent must be addressed to reduce their undesirable appear-
ance. Open holes placed in the steel members, often for the The Last Piece
welding process, are to be closed off and smoothed out for a The last portion of the AESS process is just as critical as
clean, finished surface. a well-coordinated design phase. The AISC Code addresses re-
More labor and time are often necessary during fabrication quirements for erection of AESS in Section 10. The higher-
and erection to achieve the quality of AESS 4 compared to the quality finish and treatment of AESS necessitates extra care and
previous categories. Surfaces that are in view range are to be handling during transit and placement. The timeline for erec-
free of imperfections. Filling any deviations with a body filler tion may be slightly longer when AESS is specified on a project.
as well as sanding textured surfaces are methods of fabrication Erectors are tasked with assembling the steel with careful plan-
used in this category. This higher level of care and detail allows ning and methods to avoid damage to the finished product.
for glossy coats on steel to be a truly successful aesthetic in The decision to architecturally expose structural steel can
close view range. add significant value to a building. Improvements in 2016 AISC
AESS C: CUSTOM ELEMENTS. Any deviation from the Code satisfy the desire to create efficient and cost-effective mea-
requirements of AESS 1, 2, 3 and 4 falls under the Custom cat- sures when implementing AESS on a project. The five categories
egory, AESS C. Occasionally, there are situations when sharp (AESS 1, 2, 3, 4 and C) that distinguish AESS require sufficient
edges do not need to be ground smooth or erection and painted evaluation and coordination in order to meet project expecta-
marks are not required to be removed from view. Allowing this tions within budget and schedule. Establishing the same level of
flexibility in choosing characteristics provides designers with expectations between owners, architects, engineers, general con-
greater freedom but also notifies steel fabricators and erectors tractors, fabricators, detailers and erectors is critical to achieving
that there is a noteworthy difference from the typical category the best end results for a project.
requirements. Custom elements should be clearly defined in
the contract documents with AESS C located as needed. See the following pages for more on AESS, including the aforemen-
The AISC Code recommends using Table 10.1 (on the fol- tioned AESS Category Matrix and Table 10.1, a sample AESS speci-
lowing page), similar to the more comprehensive AESS Cat- fication and a list of helpful resources.
egory Matrix (see last spread of this PDF), as a checklist for
NOVEMBER 2017
TABLE 10.1: AESS Category Matrix
CATEGORY AESS C AESS 4 AESS 3 AESS 2 AESS 1 SSS
FEATURE FEATURE STANDARD
CUSTOM SHOWCASE BASIC
I.D. CHARACTERISTICS ELEMENTS IN ELEMENTS NOT STRUCTURAL
ELEMENTS ELEMENTS ELEMENTS
CLOSE VIEW IN CLOSE VIEW STEEL
1.1 Surface preparation to SSPC-SP 6 × × × ×
1.2 Sharp edges ground smooth × × × ×
1.3 Continuous weld appearance × × × ×
1.4 Standard structural bolts × × × ×
1.5 Weld spatters removed × × × ×
2.1 Visual Samples × × optional
One-half standard fabrication
2.2
tolerances × × ×
2.3 Fabrication marks not apparent × × ×
2.4 Welds uniform and smooth × × ×
3.1 Mill marks removed × ×
Butt and plug welds ground
3.2
smooth and filled × × A matrix is provided in Section 10
of the AISC Code, outlining which
HSS weld seam oriented for
3.3
reduced visibility × × fabrication processes are present within
each category. And for exposed steel
Cross-sectional abutting surface goals that don’t fit into categories
3.4
aligned × ×
AESS 1 through 4, a Custom category
3.5 Joint gap tolerances minimized × × (C) and blank matrix space are available
for teams to discuss and create their
3.6 All welded connections optional optional
own unique guidelines.
4.1 HSS seam not apparent × Note: Descriptions of the I.D.
characteristics can be found on the
4.2 Welds contoured and blended × last page of this PDF, to the right
4.3 Surfaces filled and sanded × of the AESS Category Matrix.
4.4 Weld show-through minimized ×
C.1
Paul Warchol Photogaphy, Inc.
Details tend to disappear from the naked eye the further away they are located. When an object is beyond 20 ft, the
distinction between components is not as clearly seen as when it is within reach. For example, the residential project
on the left allows people touch every element of the exposed structure, all of which is in close view. The exposed
steel in the office building on the right is so high that only maintenance staff, and the occasional bird, will be able to
see the level of fabrication.
NOVEMBER 2017
From left to right: Standard structural steel (SSS), AESS 1, AESS 2, AESS 3 and AESS 4.
Sample Specification, Section 05 12 13: Editor’s Note: Narratively describe the areas on the drawings that
Architecturally Exposed Structural Steel have been designated as AESS 1, AESS 2, AESS 3, AESS 4 and
AESS C. Delete sentences where the AESS category is not used for
PART 1 – GENERAL
the project. The specifier may consider using AESS C. Refer to the
1.1 RELATED DOCUMENTS Editor’s Note to Section 1.3.
A. Drawings and general provisions of the Contract, B. Related Sections: The following Sections contain
including General and Supplementary Conditions and requirements that relate to this Section:
Division 1 Specification Sections, apply to the Section.
1. Division 1
1.2 SUMMARY
a. Section 01 22 00 “Submittal Procedures”
Editor’s Note: It is critical to define to the bidders what members will for Fabrication Documents, Product Data,
be considered as Architecturally Exposed Structural Steel (AESS) and Samples
and what category of AESS applies to each area. Furthermore,
b. Section 01 43 00”Quality Assurance” for
any variations to the requirements of the American Institute of
fabricator and installer qualifications independent
Steel Construction (AISC) Code of Standard Practice for Steel
testing agency procedures and administrative
Buildings and Bridges ANSI/AISC 303-16 (COSP) must be
requirements.
spelled out. Delete references to AESS categories not required for
the project. c. Section 01 45 00 “Quality Control” for Source and
Field quality control requirements.
A. This Section includes requirements regarding the
appearance and surface preparation of Architecturally 2. Division 5 Sections 05 12 00 “Structural Steel
Exposed Structural Steel (AESS). Refer to Division 5 Framing “Sections 05 20 00 “Steel Joist Framing”
Section “Structural Steel” for all other requirements for metal joist requirements.
regarding steel work not included in this Section.
Editor’s Note: Address alignment and location of bridging where
Requirements of Section 05 12 23 also apply to material
joists are visible in Division 5 Section “Open Web Metal Joists.”
covered under this Section.
This Section applies to any members noted on 3. Division 5 Sections 05 30 00 “Metal Decking” for
Architectural [and Structural] drawings as AESS 1, AESS erection requirements relating to exposed steel
2, AESS 3, AESS 4 and AESS C; and in the areas defined decking and its connections
as AESS below.
Editor’s Note: Address fastener spacing and weld show through in
1. The following structural steel elements and connections areas where decking is visible in the finished structure. Coordinate
are to be supplied and erected per AESS 1: paint system requirements with that of AESS.
2. The following structural steel elements and connections 4. Division 5 Sections 05 50 00 “Metal Fabrications”
are to be supplied and erected per AESS 2: for loose steel bearing plates and miscellaneous
steel framing.
3. The following structural steel elements and connections
are to be supplied and erected per AESS 3: 5. Division 9 Sections 09 97 00 “Special Coatings” for
finish coat requirements and coordination with primer
4. The following structural steel elements and connections
and surface preparation specified in this Section.
are to be supplied and erected per AESS 4:
5. The following structural steel elements and connections
are to be supplied and erected per AESS C:
Modern STEEL CONSTRUCTION
AESS 3: Joint gap tolerances minimized, butt and plug welds AESS 4: Surfaces filed and sanded.
ground smooth and filled.
NOVEMBER 2017
SSS: Weld backing bar in place and non-uniform welds. AESS 1: Welds uniform and smooth and backing bars removed.
6. Clearly indicate which surfaces or edges are exposed a. Approved mockups in an undisturbed condition at
and what class of surface preparation is being used. the time of Substantial Completion may become
part of the completed work.
7. Indicate special tolerances and erection requirements
as noted on the drawings or defined herein. Editor’s Note: The contract documents (architectural drawings)
need to indicate the framing to be submitted as a mock up. The
8. Indicate vent or drainage holes for HSS members.
Architect must define the size and extent of the pieces required
D. Mock Up: Provide mock ups of the nature and extent and what specific finishes must be demonstrated. The typical
indicated on the contract documents. mock up is a standalone item that is not incorporated into the
final work. However, the specifier may designate a larger mock
1. Locate mockups on-site or in the fabricator’s shop as
up that is incorporated into the final work. This intent must be
directed by Architect. Mockups shall be full size unless
clearly indicated on the architectural drawings and the specifier
the Architect approves smaller models. Alternatively,
should consult with the fabricator and contractor regarding the
when a mockup is not practical, the first piece of an
practicality and sequencing of incorporating a mock up into the
element or connection can be used to determine
final work.
acceptability.
Mock ups are only required for AESS 3, AESS 4 and AESS C.
2. Notify the Architect one week in advance of the dates Delete “D” for AESS 1 and 2.
and times when mockups will be available for review.
E. Samples: Provide samples of specific AESS characteristics
3. Demonstrate all applicable AESS characteristics for Samples may be small size samples or components of
the specified category of AESS on the elements and conventional structural steel demonstrating the following
joints in the mock up. specific AESS characteristics.
4. Build mockups using member sizes and materials 1. Continuous weld appearance
indicated for final Work.
2. Sharp edges ground smooth
5. The mock up shall demonstrate weld quality and
3. Surface preparation
contouring of the welds at the aligned walls of the
members. 4. Fabrication mark removal
6. The mock up shall demonstrate the specified surface 5. Weld show through.
preparation and finish coating.
Editor’s Note: Delete samples for AESS 3, 4 and C where a mock
7. HSS members shall extend at least 6 in. from the joint up is used. Section E provides the editor with the option to obtain
in the mock-up. samples for AESS 1 and 2 without requirement for a full mock up.
Delete Section E if samples are not desired. Consider expanding
8. Obtain Architect’s written approval of mockups before
Section E to include AESS 3 and 4 characteristics if a full-scale
starting fabrication
mock up is not used for AESS 3 and 4.
9. Retain and maintain mockups during construction in
an undisturbed condition as a standard for judging the
completed work.
NOVEMBER 2017
SSS: Intermittent/stitch weld between bottom flange and AESS 1: Continuous weld appearance.
cover plate.
H. Finish Coating: Field apply intermediate and top coats B. The permissible tolerances for member depth, width, out
per Section 09 97 00. of square, and camber and sweep shall be as specified in
ASTM A6/A6M-2014 Standard Specification for General
FINISHES
Requirements for Rolled Structural Steel Bars, Plates,
When possible, finish coating should be done in the field after
Shapes, and Sheet Piling (ASTM A6/A6M), ASTM A500/
erection. Finish coats applied in the shop almost always incur
A500M-2013 Standard Specification for Cold-Formed
damage from handling in shipping and erection. This often results
Welded and Seamless Carbon Steel Structural Tubing in
in applying an additional finish coat in the field or completing
Rounds and Shapes (ASTM A500/A500M), and Standard
costly touch up which often does not blend in with the original
Specification for Cold-Formed Welded Carbon Steel Structural
finish. Finish coats for aggressive environments such as swimming
Sections (HSS) (ASTM A1085/A1085M).
pools may require special preparation of the steel, primer and finish
coating. Consult with a manufacturer’s representative for such C. Fabricate and assemble AESS in the shop to the greatest
special conditions. extent possible. Locate field joints in AESS assemblies
at concealed locations or as approved by the Architect.
*Note—If finish painting is to be done prior to delivery of the steel,
Detail AESS assemblies to minimize field handling and
special Sections should be added to ensure proper handling and
expedite erection.
minimize damage.
Common Finish coatings for commercial projects with AESS D. Remove blemishes or unsightly surfaces resulting from
fall into the following categories. temporary braces or fixtures.
Alkyds (Oil-based): Acceptable finish coat for interior E. Remove all backing and run out tabs.
applications and some exterior application. Dries to hard
F. Grind all sharp edges smooth, including all sheared,
durable finish. When applied specified for exterior use, alkyds
punched or flame cut edges
will chalk and fade with UV exposure in a relatively brief
period. Can be brush, roll or spray applied. G. Provide a continuous appearance to all welded joints includ-
ing tack welds. Provide joint filler at intermittent welds.
Acrylics (Waterborne): Acceptable finish coat for both interior
and exterior service. Acrylics provide good color and gloss H. Bolted Connections: Make in accordance with Section 05
retention under UV exposure. Can be easily applied by brush, 12 00. Provide bolt type and finish as noted herein.
roller or spray. Low odor and VOC for interior application.
I. Weld Connections: Comply with AWS D1.1 and Section
Epoxy: Can be applied as a finish for interior use where 05 12 00. Appearance and quality of welds shall be
abrasion resistance is required. The high build nature of film consistent. Assemble and weld built-up Sections by
can help cover imperfections in the steel. It will chalk and fade methods that will maintain alignment of members
with UV exposure. without warp exceeding the tolerance of this Section.
Polyurethane: Provides high performance protection with J. Install all bolts on the same side of the connection.
excellent color and gloss retention. It has a higher film build Oriented uniformly in the direction indicated Consistent
than alkyd or acrylic will help cover imperfections in the steel. from one connection to another.
Should be spray applied for best appearance.
K. Remove all weld spatter, slivers and similar surface
2.3 FABRICATION AESS 1 discontinuities.
A. Use special care in handling and shipping of AESS both L. Grind off projections larger than 1∕16 in. at butt and
before and after shop painting minimize damage to any plug welds.
shop finish. Use Nylon type slings or softeners when
using chains or wire rope slings.
NOVEMBER 2017
AESS 3: A contoured weld. AESS 4: In addition to a contoured and blended appearance,
weld transitions also are contoured and blended.
M.
Continuous Weld Appearance: Where continuous F. Mill marks shall not be exposed to view. If it is not possible
welding is noted on the drawings, provide welds of a to hide mill marks, then the mill marks are to be removed
uniform size and profile by appropriate length cutting of mill material. If this is
not possible, the fabricator shall remove the mill mark,
N. Seal Welds: Seal weld open ends of round and rectangular
grind, and fill the surface to be consistent with the
hollow structural Section with 3∕8 in. closure plates.
approved mock up.
Provide venting as required for galvanized members.
G. The matching of abutting cross Sections is required
Editor’s Note: drainage and venting holes need to be coordinated to
account for the galvanizing process and in-service drainage. 2.6 FABRICATION AESS 4
2.4 FABRICATION AESS 2 A. Fabricate to the requirements of 2.5 and as follows.
A. Fabricate to Requirements of 2.3 and as follows B. Contouring and blending of welds: Where welds are indi-
cated to be ground contoured, or blended, oversize welds
B. The as-fabricated straightness tolerance shall be one-
as required and grind to provide a smooth transition and
half of that specified in ASTM A6/A6M, ASTM A500/
match profile on approved mock-up.
A500M, or ASTM A1085/A1085M.
C. Minimize Weld Show Through: At locations where weld-
C. For curved structural members, whether composed of a
ing on the opposite side of an exposed connection creates
single standard structural shape or built-up, the as-fab-
distortion, weld show through shall be minimized to con-
ricated variation from the theoretical curvature shall be
form to the approved mock up.
equal to or less than the standard camber and sweep tol-
erances permitted for straight members in the applicable D. Open holes shall be filled with weld metal or body filler
ASTM standard. and smoothed by grinding or filling to the standards ap-
plicable to the shop fabrication of the materials.
D. The tolerance on overall profile dimensions of welded built-
up members shall one-half of that specified in AWS D1.1/ 2.7 FABRICATION AESS C
D1.1M: 2015 Structural Welding Code – Steel (AWS D1.1).
Editor’s Note: This Section is for customized projects, hence the lack of
E. Provide hidden part marks or piece marks that may be specific language.
fully removed after erection.
A. X
2.5 FABRICATION AESS 3
B. X
A. Fabricate to Requirements of 2.4 and as follows
C. X
B. Fabricate AESS with exposed surfaces smooth, square and
Editor’s Note: Refer to the Editor’s Note to Paragraph 1.3
of surface quality consistent with the approved mock up.
2.8 SHOP PRIMING
C. Grind projections at butt and plug welds to be smooth
with the adjacent surface. A. Provide surface preparations to SSPC-SP6. Coordinate the
required surface profile with the approved paint submittal
D. Orientation of HSS seams shall be as shown.
prior to beginning surface preparation. Prior to blasting
E. Copes, miters, and cuts in surfaces exposed to view shall remove any grease and oil using solvent cleaning to meet
have a maximum gap of 1∕8 in. in an open joint. If the gap SSPC-SP 1. Weld spatter, slivers and similar surface
is shown to be in contact, the contact shall be uniform discontinuities shall be removed. Sharp corners resulting
within 1∕16 in. from shearing, flame cutting or grinding shall be eased.
B. Place weld tabs for temporary bracing and safety cabling K. Grind off projections larger than 1∕16 in. at field butt and
at points concealed from view in the completed structure plug welds.
or where approved by the Architect during the pre-
L. Continuous Welds: Where continuous welding is noted
installation meeting. Methods of removing temporary
on the drawings, provide continuous welds of a uniform
erection devices and finishing the AESS members shall be
size and profile.
approved by the Architect prior to erection.
M. Do not enlarge holes in members by burning or by using
C. AESS Erection tolerances: Erection tolerances shall meet
drift pins. Ream holes that must be enlarged to admit
the requirements of standard frame tolerances for struc-
bolts. Replace connection plates that are misaligned where
tural steel per Chapter 7 of ANSI/AISC 303-16.
holes cannot be aligned with acceptable final appearance.
Editor’s Note: ANSI/AISC 303-16 specifies that AESS 2 and
N. Splice members only where indicated.
above framing shall be fabricated to one-half the tolerance of typical
structural steel frames. This requirement is intended to improve O. Obtain permission for any torch cutting or field fabri-
fit up when the exposed steel interfaces with other materials such cation from the Architect. Finish Sections thermally cut
as curtain wall masonry, etc. The variations permitted under the during erection to a surface appearance consistent with
standard frame tolerances noted in Chapter 7 will typically be the mock up.
acceptable when viewed by eye (without instruments). Therefore,
3.4 ERECTION AESS 2
standard frame tolerances are allowed for Erection tolerances.
Adjust if tighter tolerances are required. A. Erect to the requirements of 3.3 and as follows.
D. Set AESS accurately in locations and to elevations indi- B. AESS Erection Tolerances: Erect to standard frame
cated and according to AISC specifications referenced in tolerances for structural steel per Chapter 7 of ANSI/
this Section. AISC 303-16.
E. Remove blemishes or unsightly surfaces resulting from 3.5 ERECTION AESS 3
temporary braces or fixtures.
A. Erect to the requirements of 3.4 and as follows.
F. Remove all backing and run out tabs.
B. Field Welding: Weld profile, quality, and finish shall be
G. When temporary braces or fixtures are required to facili- consistent with mock-ups approved prior to fabrication.
tate erection, care shall be taken to avoid any blemishes,
C. Provide a continuous appearance to all welded joints
holes or unsightly surfaces resulting from the use or re-
including tack welds. Provide joint filler at intermittent
moval of such temporary elements.
welds.
H. Bolted Connections: Align bolt heads on the same side of
3.6 ERECTION AESS 4
the connection as indicated on the approved fabrication
or erection documents. A. Erect to the requirements of 3.5 and as follows.
I. Weld Connections: Comply with AWS D1.1 and B. Welds ground smooth: Erector shall grind welds smooth.
Section 05 12 00. Appearance and quality of welds
shall be consistent. Employ methods that will maintain C. Minimize Weld Show Through: At locations where
alignment of members without warp exceeding the welding on the far side of an exposed connection creates
tolerance of this Section. distortion, grind distortion and marking of the steel to a
smooth profile with adjacent material.
J. Remove all weld spatter exposed to view.
NOVEMBER 2017
D. Filling of weld access holes: Where holes must be cut in
the web at the interSection with flanges on W shapes and
Resources
structural tees to permit field welding of the flanges, they
Visit www.aisc.org/AESS to access a variety of
shall be filled with joint filler.
AESS reources:
E. Where welds are indicated to be ground, contoured, or ➤ The 2016 Code of Standard Practice for
blended, oversize welds as required and grind to provide a Steel Buildings and Bridges (ANSI/AISC
smooth transition and match profile on approved mock-up. 303-16) provides a framework for a common
understanding of the acceptable standards
3.7 ERECTION AESS C when contracting for structural steel. Section
Editor’s Note: This Section is for customized projects, hence the lack of 10 deals explicitly with AESS.
specific language. ➤ The AESS sample specification (also on the
preceding pages) is an editable sample spec
A. …. that you can update and insert into your
B. ….. individual project specifications.
➤ The AESS Cost Matrix (also on the following
C. ….. page) is an editable matrix that you can
3.8 FIELD QUALITY CONTROL AND QUALITY update to anticipate cost implications by
ASSURANCE AESS 1 and 2 specifying various levels of AESS on
your project.
C. Structural requirements: ➤ Shop drawings of the five AESS sculptures,
3. Conform to Quality Control requirements per ANSI/ which you can download and use to fabricate
AISC 360-16 Specification for Structural Steel Buildings your own versions. Or reach out to the AISC
Chapter N and ANSI/AISC 303-16, Code of Standard Steel Solutions Center at [email protected]
Practice for Steel Buildings and Bridges, Section 10. Refer if you’d like us to put you in touch with a local
to Section 05 12 00 “Structural Steel” for additional fabricator to purchase your own sculptures!
requirements.
You can also visit www.modernsteel.com to view
4. Owner will engage a Quality Assurance agency per the articles on the photos and projects that appeared
requirements of ANSI/AISC 360-16 Specification for in this section:
Structural Steel Buildings Chapter N and ANSI/AISC 303- ➤ Terri Meyer Boake’s favorite exposed
16, Code of Standard Practice for Steel Buildings and Bridges, connections: “Fun is in the Details,”
Section 10 March 2016
➤ Kline Fitness Center addition at Dickinson
D. AESS acceptance: The Architect shall observe the AESS
College: “Squashing the Competition,”
steel in place and determine acceptability based on the
January 2016
qualification data and submittals. The Quality Assurance ➤ Technology Tower at North Carolina State
Agency shall have no responsibility for enforcing the University’s Talley Center:
requirements of this Section. “Tower of Technology,” June 2015
3.9 FIELD QUALITY CONTROL AESS 3, 4, and C ➤ Anaheim Regional Transportation Intermodal
Center (ARTIC): IDEAS2 Awards article,
A. Conform to 3.7 and as follows. May 2015
➤ Denver Union Station: IDEAS2 Awards article,
B. AESS acceptance: The Architect shall observe the AESS steel
May 2015
in place and determine acceptability based on the approved
➤ Landscape Evolution Observatory (LEO)
mock up. The Quality Assurance Agency shall have no
at the University of Arizona’s Biosphere
responsibility for enforcing the requirements of this Section. 2 research facility: “Under the Dome,”
3.10 ADJUSTING AND CLEANING November 2014
➤ United Therapeutics Pedestrian Connector:
A. Touchup Painting: Cleaning and touchup painting of field IDEAS2 Awards article, May 2014
welds, bolted connections, and abraded areas of shop paint ➤ Queen Richmond Centre West:
shall be completed to blend with the adjacent surfaces of “Jacks of All Trades,” March 2014
AESS. Such touch up work shall be done in accordance with ➤ Solar Canopy: IDEAS2 Awards article,
manufacturer’s instructions and as specified in Division 9, May 2013
Section “Painting.” ➤ National Geospatial-Intelligence Agency:
IDEAS2 Awards article, May 2013
B. Galvanized Surfaces: Clean field welds, bolted connections, ➤ The Tea House, “What’s Cool in Steel,”
and abraded area. Any repairs to galvanized surfaces August 2012
shall comply with ASTM A780/A780M – 2015 Standard ➤ Sprint Center: “Bending Around
Practice for Repair of Damaged and Uncoated Areas of Hot Dip (Sprint Center),” July 2008
Galvanized Coatings.
1.4.D, 1.4.E 10.1.1, 10.1.2 2.1 Visual Samples mock-up required mock-up required
2.4.B 10.4.3(b), 10.4.5 2.2 One-half standard fabrication tolerances × ×
2.4.E 10.4.1 2.3 Fabrication marks not apparent × ×
** ** 2.4 Welds uniform and smooth × ×
1.7.B, 2.3.A,
3.3.A
10.5, 10.6 Special care in fabrication and erection × × ×
Footnote A. Cost premium for SSPC-SP6 is included in values provided for Primer and Finish Coatings, Finish B through Finish D.
Disclaimer: Cost premiums shown here are for informational purposes, and are not intended to be used for cost estimating purposes.
Every project is unique, and budgeting must be performed on a project-by-project basis.
NOVEMBER 2017
AESS 2 AESS 1
FEATURE ADDED COST I.D. CHARACTERISTICS DESCRIPTION
ELEMENTS NOT BASIC RANGE 1.1 Surface preparation to Grease, oil, weld spatter and surface
IN CLOSE VIEW ELEMENTS TO AESS SSPC-SP 6 discontinuities are removed
view distance > 20 ft (Relative to non-AESS) 1.2 Sharp edges Rough surfaces are deburred and ground
ground smooth smooth. Sharp edges resulting from flame
× × footnote A
cutting, grinding and especially shearing
× × 1% – 10% are softened.
× × 1% – 10% 1.3 Continuous weld Intermittent welds are made to appear
× × 1% – 5% appearance continuous, either with additional welding,
caulking or body filler. For corrosive
× × 1% – 5% environments, all joints are seal welded.
Seams of hollow structural sections are
optional 5% – 25% acceptable as produced.
1.4 Standard structural bolts All bolt heads in connections are on the
× 5% – 15%
same side, as specified, and consistent
× 5% – 15% from one connection to another.
× 5% – 15% 1.5 Weld spatters removed Weld spatter, slivers, surface
discontinuities are removed.
Weld projection up to 1⁄16 in. (2 mm)
5% – 15%
is acceptable for butt and plug
5% – 10% welded joints.
1% – 5%
5% – 15% 2.1 Visual Samples Visual samples are either a 3D rendering,
5% – 10% a physical sample, a first-off inspection, a
scaled mock-up or a full-scale mock-up,
15% – 30% as specified in the contract documents.
Mock-ups are optional in AESS 2.
5% – 20% 2.2 One-half standard These tolerances are one-half of those for
fabrication tolerances standard structural steel as specified in
25% – 40%
this Code.
30% – 50%
2.3 Fabrication marks not Members markings during the fabrication
5% – 20% apparent and erection processes are not to be
visible to view.
2.4 Welds uniform Welds are to be uniform and smooth.
and smooth
3.1 Mill marks removed Mill marks are to be removed from view.
3.2 Butt and plug welds Caulking or body filler is acceptable.
ground smooth and filled
3.3 HSS weld seam oriented Seams are oriented away from view or as
per contract documents indicated in the contract documents.
× × XX% to XX%
3.4 Cross sectional abutting The matching of abutting cross sections is
surface aligned required.
3.5 Joint gap tolerances This characteristic is similar to 2.2 above.
low to moderate low minimized A clear distance between abutting
members of 1⁄8 in. (3 mm) is required.
25% – 35% 10% – 20% 3.6 All welded connections Hidden bolts may be considered.
4.1 HSS seam not apparent Seams on HSS members are treated so
they are not apparent.
XX% to XX% XX% to XX% 4.2 Welds contoured In addition to a contoured and blended
and blended appearance, welded transitions between
members also are contoured and blended.
4.3 Surfaces filled Surfaces are to be filled with weld metal
5% – 15% and sanded or body filler, smoothed and sanded to
15% – 30% achieve a smooth surface.
20% – 40% 4.4 Weld show-through Weld show-through on the back side of
minimized a welded element can be minimized by
30% – 50% hand grinding the back side surface. The
20% – 40% degree of weld-through is a function of
weld size and material.
XX% to XX% XX% to XX% C Custom elements Additional characteristics may be added
for custom elements. The AESS matrix
XX% to XX% XX% to XX%
included in Table 10.1 of the 2016
AISC Code of Standard Practice shall
be used to specify the required treatment
of the elements.