A Standard Procedure For Deviation
A Standard Procedure For Deviation
What is a Deviation:
Types of Deviations:
1. Following are some examples of deviations raised from different functional areas of business:
2. Production Deviation - usually raised during the manufacture of a batch production.
3. EHS Deviation - raised due to an environmental, health and safety hazards.
4. Quality Improvement Deviation - may be raised if a potential weakness has been identified and the
implementation will require project approval.
5. Audit Deviation - raised to flag non-conformance identified during internal, external, supplier or
corporate audits.
6. Customer Service Deviation - raised to track implementation measures related to customer
complaints.
7. Technical Deviation - can be raised for validation discrepancies. For example: changes in
Manufacturing Instruction.
8. Material Complaint - raised to document any issues with regards to non-conforming, superseded or
obsolete raw materials/components, packaging or imported finished goods.
9. System Routing Deviation - raised to track changes made to Bill of materials as a result of an
Artwork change.
Reporting deviation is required regardless of final batch disposition. If a batch is rejected a deviation
reporting is still required.
QA has to evaluate the deviation and assess the potential impact to the product quality, validation and
regulatory requirement. All completed deviation investigations are to be approved by QA Manager or
delegate. QA Manger has to justify wither the deviation is a Critical, Serious or Standard in nature. For
a deviation of either critical or serious nature QA delegate has to arrange a Cross Functional
Investigation.
For a standard type deviation a Cross functional Investigation (CFI) is not necessary. Immediate
corrective actions have to be completed before the final disposition of a batch. Final batch disposition
is the responsibility of Quality Assurance Department.
If a critical or serious deviation leads to a CFI, corrective and preventive actions should be determined
and follow up tasks should be assigned to area representatives. Follow up tasks should be completed
within 30 business days of the observation of deviation. If a deviation with CFI can not be completed
within 30 business days, an interim report should be generated detailing the reason for the delay and
the progress so far.
After successful completion of the Follow up tasks Deviation should be completed and attached with
the Batch Report /Audit report/ Product complaint report /Safety investigation report as appropriate.
QA delegate has to conduct a primary Investigation on the deviation reported and evaluate the
following information
1. Scope of the deviation - batch affected (both in-process and previously released)
2. Trends relating to (but limited to) similar products, materials, equipment and testing processes,
product complaints, previous deviations, annual product reviews, and /or returned goods etc where
appropriate.
3. A review of similar causes.
4. Potential quality impact.
5. Regulatory commitment impact.
6. Other batches potentially affected.
7. Market actions ( Home Page. recall etc)