Time Schedule

This document outlines a work schedule for the rehabilitation of irrigation networks at the Sambogunung Reservoir in Dukun District for the 2019 budget year. It details 14 categories of work including preparatory work, earthworks, installations and concrete work, other work, and testing. The work is scheduled over 20 weeks with varying percentages of work planned for each week, and cumulative progress projected to reach 100% completion by week 20. Key milestones include 75% of preparatory work by week 1, 70% of installations and 54% of concrete work by week 10, and all work 50% completed by week 15.

Uploaded by

Mohammad Firdaus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views

Time Schedule

This document outlines a work schedule for the rehabilitation of irrigation networks at the Sambogunung Reservoir in Dukun District for the 2019 budget year. It details 14 categories of work including preparatory work, earthworks, installations and concrete work, other work, and testing. The work is scheduled over 20 weeks with varying percentages of work planned for each week, and cumulative progress projected to reach 100% completion by week 20. Key milestones include 75% of preparatory work by week 1, 70% of installations and 54% of concrete work by week 10, and all work 50% completed by week 15.

Uploaded by

Mohammad Firdaus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

RENCANA JADWAL WAKTU PELAKSANAAN PEKERJAAN

PEKERJAAN : Rehabilitasi Jaringan Irigasi Waduk Sambogunung


LOKASI : Kecamatan Dukun
TAHUN ANGGARAN : 2019

BOBOT MINGGU KE
NO. URAIAN SATUAN KUANTITAS FISIK PROSENTASE
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0

I. PEKERJAAN PERSIAPAN
Uitzet trase Saluran irigasi M 254,50 0,75 0,38 0,38 0,75 100
-
II. PEKERJAAN TANAH - 90
1 Galian tanah biasa pada saluran sedalam M3 97,00 1,02 0,25 0,17 0,17 0,17 0,17 0,08 1,01
lebih kecil sama dengan 1 m -
80
-
III. PEKERJAAN PASANGAN DAN BETON -
1 Pengadaan LPC 800 X 300 X 60 K -350 bh 1018,00 54,27 4,52 4,52 4,52 4,52 4,52 4,52 4,52 4,52 4,52 4,52 4,52 4,52 54,27 70

2 Pemasangan LPC 800 X 300 X 60 K -350 bh 1018,00 8,61 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 0,66 8,61
3 Beton Lantai t = 10 cm K -225 M3 22,91 10,80 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 10,80 60
4 Plat Beton uk. 6 x 30 cm M3 9,16 7,11 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 0,55 7,11
5 Sloof uk 15 x 15 cm M3 11,45 7,46 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 0,57 7,46 50
6 Acian Beton ( Sloof dan sambungan pracetak) M2 285,04 2,19 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 0,17 2,19
7 Pekerjaan gedek guling ruas P.U-9a M2 338,49 1,34 0,13 0,13 0,13 0,13 0,13 0,13 0,13 0,13 0,13 0,13 1,34
40
8 Pekerjaan trucuk bambu ori o 10 cm, P = 2 m BH 148,00 0,29 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,29
9 Pengadaan Box Culvert Top Button 1000/50-1200 K-350 Gandar 10 ton BH 3,00 1,24 0,21 0,21 0,21 0,21 0,21 0,21 1,24
10 Pemasangan Box Culvert Top BH 6,00 0,12 0,12 0,12 30

11 Pekerjaan beton bertuang plat BAWAH Box Culvert t=10 cm (K-225) M3 0,86 0,68 0,68 0,68
12 Pekerjaan beton bertuang plat ATAS Box Culvert t=15 cm (K-225) M3 2,66 2,11 1,05 1,05 2,11 20
13 Pekerjaan trucuk bambu ori o 10 cm, P = 2 m BH 16,00 0,03 0,03 0,03
- 10
IV. PEKERJAAN LAIN - LAIN -
1 Pekerjaan Cat ( 1x Cat dasar , 2x Finishing Warna Biru ) M2 157,9 1,38 0,69 0,69 1,38
0
Test laborotium ls 1 0,59 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,59
JUMLAH 100,00 100,00
RENCANA TIAP MINGGU 0,41 0,79 4,88 5,54 6,37 7,66 7,57 7,70 7,70 7,70 7,70 7,69 8,28 8,41 3,89 2,81 2,15 1,32 0,72 0,72
RENCANA KUMULATIF TIAP MINGGU 0,41 1,20 6,08 11,62 17,99 25,65 33,22 40,92 48,61 56,31 64,01 71,69 79,97 88,38 92,27 95,08 97,23 98,55 99,27 100,00