Construction PDF
Construction PDF
CONSTRUCTION
DIFFERENCE BETWEEN TILE FLOORING & MARBLE FLOORING
TILE FLOORING:
Tiles are precast units of pottery, cement concrete or terrazzo. They are manufactured
in various thickness and shapes like square, polygonal etc. Precast terrazzo tiles are
known as mosaic tiles. Mosaic tiles have to be polished after fixing them in their
position.
White glazed tiles, manufactured from pottery clay are used for flooring, W.C,
bathrooms, swimming pools and other sanitary blocks. These tiles do not require any
polishing. Tiled floorings require hard sub-grade with may be in the form o RCC slab or
cement concrete.
MARBLE FLOORING:
This flooring is very high class and commonly used in places of worship (temples,
churches, mosques etc) and in public buildings having rich specifications. Marbles are
laid in floors just like other tile floors. The surface off the floor is rubbed and polished
with the help of power driven polishing machine. Resulting surface of the floor is very
pleasing and smooth.
The size of marble slabs to be used in flooring depends upon the pattern to be adopted.
The slabs for normal works are square or rectangular in shape and their thickness
varies from 20 mm to 40 mm. The flooring is laid on prepared sub-grade of concrete or
RCC slab. In view of high cost of material, use of marble flooring in residential buildings
is normally restricted to areas like kitchen, bathroom entrance etc.
BRIDGE:
1. The drainage structure which facilitates a communication route for carrying road or
railway traffic across an obstruction or depression with or without water is called a
bridge.
2.. Bridge is a structure which is built over natural obstructions such as rivers, valleys to
connect two locations separated by these obstructions.
3. Bridges are further classified on the basis of their purpose, lifespan, materials, span
etc.
4. Bridges are used for navigating traffic across the obstruction, to navigate pipelines
and other forms of transport.
FLYOVERS:
1. Flyover is an overpass, a high-level road bridge that crosses over a highway
interchange or intersection.
2. It is a structure which joints two or more points which are separated by accessible
routes or a man-made structure to cut the traffic for faster mode of traveling.
3. They are usually made over road junctions, roads, streets, etc.
4. The name itself suggests that you are flying over a traffic zone.
5. They are usually built for road vehicles.
SYSTEM OF PLUMBING:
There are four systems of plumbing of drainage work in a building.
3. TWO-PIPE SYSTEM:
In this plumbing system, two pipes are installed. W.Cs and urinals are connected to
vertical soil pipe baths, kitchens, basins etc are connected to another separate
vertical waste pipe. Soil pipes and waste pipes are provided with separate vent pipes.
This system thus requires four pipes and hence proves very costly. The soil pipe is
connected to the drain directly but waste pipe should be connected through a
trapped gully.
1. DAMP PREVENTION:
Cavity walls eliminate the penetration of moisture from outer leaf to the inner leaf and
thus help keep inside of the building free from dampness.
2. THERMAL INSULATION:
The air in the cavity wall acts as a non-conductor of thermal heat and hence minimizes
the transmission of heat from the external face of the outer leaf to the internal face of
the interior leaf. Thus cavity walls help greatly in the thermal insulation.
3. SOUND INSULATION:
The air in the cavity acts as a cushion for absorbing sound, by adopting cavity walls
buildings may be rendered sound proof as considerable external noise gets absorbed in
the cavity.
4. EFFLORESCENCE PREVENTION:
As dampness is not allowed penetrate by cavity, the inner wall of the cavity which is
always a load bearing wall is kept free efflorescence effects.
5. ECONOMY:
Cavity walls are found to cost about 20% less than the construction of same thickness
solid wall.
CONSTRUCTION DETAILS:
As already stated, the cavity walls have two leaves- inner and outer with hollow space in
between them. The width of the cavity varies from 50 mm to 75 mm. The thickness of
the outer leaf wall which is usually non-load bearing is half brick. The two portions of the
wall are connected by wall ties or bonded bricks. metal wall ties are spaced horizontal
intervals of about 0.90 mm and vertical interval of 450 mm. the wall ties should be
arranged in staggered form. The outer wall is always in stretcher bond, but it can be
constructed in other bonds as well, by using brick bats.
BAMBOO AS REINFORCEMENT:
Bamboo is used as construction material in certain area of different countries. Bamboo
is also used in reinforcement as an alternative to steel. But is it trustworthy using
bamboo in reinforcement? Or is bamboo stronger than steel? Let us discuss below.
Bamboo has great tensile strength (resistance to being pulled apart) than steel and it
can withstand compression better than concrete.
Bamboo has an impermeable protective layer on the outside which protects it from
rotting due to water or moisture.
ADVANTAGES OF GUNITING:
1. High impermeability can be achieved.
2. The repairs can be carried out in any situation in very short time.
3. High compressive strength, say of the order of 500 to 700 kg/cm2 at 28 days can be
obtained.
DISADVANTAGES OF GUNITING:
1 Production cost is very high.
2 Concrete can be wasted in excess amount.
APPLICATION:
1. Thin overhead vertical or horizontal surfaces.
2. Curved or folded structures such as tunnels, canals, reservoirs, swimming pools, pre-
stressed tanks.
3. Stabilized rock slopes.
4. Restoration and repairing of old building and fire-damaged structure.
5. Waterproofing walls etc.
PIER:
The intermediate supports for the superstructure of a multi-span bridge are known as
piers.
A pier essentially consists of two parts i.ee a column shaft and the foundation. It is
sometimes provided with projections, called cut water and easy passage of water.
FUNCTION OF PIER:
The function of a pier is to transmit the load from the bridge to the underneath sub-soil.
TYPES OF PIERS:
Depending upon the type of superstructure, sub-soil conditions and the construction
procedure of the bridge, pier can be classified into the following two types:
1. Solid piers
2. Open piers.
ABUTMENTS:
The end supports of a bridge superstructure are known as abutments.
Abutments are built either with brick masonry, stone masonry, mass concrete, precast
concrete blocks or RCC. The top surface of abutment is made flat for girder bridges or
SAQIB IMRAN 0341-7549889 15
16 | P a g e
semi-circular arch bridges but provided with skewbacks if the bridge arches are
segmental or elliptical.
FUNCTION OF ABUTMENTS:
1. To transmit the load from the bridge superstructure to the underlying sub-soil.
2. To provide final formation level to the bridge superstructure.
3. To retain the earth pressure of embankment of the approaches.
TYPES OF ABUTMENTS:
Depending upon the layout plan abutments are classified into following types:
1. Abutments with wing walls.
2. Abutments without wing walls.
Moisture is the biggest enemy of cement. Cement has great affinity for moisture and
hence it should be stored well shielded from moisture laden current of air.
The exposed cement is attacked by air which further forms lumps. If the lumps are very
hard which cannot be powdered by fingers then it can not be used in any sound
construction.
Cement should be stored in dry, leakproof and moisture proof sheds with minimum
number of windows and close fitting doors. The cement bags should be stacked on
wooden planks placed about 150 to 200 mm above the floor. The space between stacks
and exterior walls should be 450 to 600 mm.
The maximum height of stack should not exceed 15 bags. The width of stacks should
not be more than 4 bags or 3 m. Thus possibilities of lumping under pressure can be
prevented.
In monsoon or in situations when it is necessary to store cement for unusually long
periods, the cement stacks should be completely enclosed by 700 gauge polythene
sheet or some other waterproofing membrane materials.
The stack should be arranged in such a manner that cement bags can be removed on
principle of first come first serve basis. that means oldest cement should be taken out
first.
TYPE OF CAISSONS:
The various types of caissons used in constructing caisson foundations under water are
given below:
1. Box caissons,
2. Open caissons,
3. Pneumatic caissons.
1. BOX CAISSONS:
The caisson in the form of an air tight vessel without top, floated to the site and sunk to
rest on a firm base, is called box caisson. This type of caisson is made of timber, steel
or reinforced concrete.
2. OPEN CAISSON:
The caisson which is without its top and bottom is called open caisson. This type of
caisson is like a well with vertical sides only. It may be square, rectangular, oval or of
any other suitable shape. Open caissons are usually made of RCC or of steel plates,
riveted or welded together.
3. PNEUMATIC CAISSON:
The caisson which is open at the bottom and close at the top and sunk by means of
utilizing compressed air is known as pneumatic caisson.
Pneumatic caisson consists essentially of the working chamber, the shaft, and an air
lock.
This type of caisson is usually made of n inner and outer skin plates with steel trusses
or girders to form a box like structure. It is provided with a cutting steel edge at its
bottom to facilitate sinking in the soil. The working chamber, provided in the caisson, is
about 3 to 4 m deep and is made air tight by providing an air tight roof. It is meant for
working of workmen during sinking process. Access to the working chamber is made
through the shaft and air lock.
SAQIB IMRAN 0341-7549889 21
22 | P a g e
The air pressure to be used in the working chamber depends upon the depth. The
maximum pressure allowed at a depth of 35 m is 3.75 km/cm2. A normal workman can
work for eight hours under a pressure of 1.3 kg/cm2. For greater pressure, the working
hour is to be reduced accordingly.
3. FOUR-LEGGED STIRRUPS:
4. SIX-LEGGED STIRRUPS:
WHAT IS CULVERT:
A small bridge having total length of 6 m or less than 6 m between the faces of
abutments is known as culvert. Culvert is a permanent drainage structure mainly
constructed to carry roadway or railway track over small streams or channels.
TYPES OF CULVERT:
Culverts are classified into the following four types:
1. Arch Culvert.
2. Open or Slab Culvert.
3. pipe Culvert.
4. Box Culvert.
1. ARCH CULVERT:
The culvert having its superstructure consisting of one or two arches constructed of any
suitable masonry is known as arch culvert.
2. SLAB CULVERTS:
The culvert, having its superstructure consisting of RCC slab which carries the bridge
floor, is known as slab culvert.
In this type of culvert, the RCC slab of suitable thickness is provided as simply
supported over abutments and piers which are constructed of any suitable type of
masonry. Slab culverts are suitable where the bed of the canal or stream is sufficiently
firm. These are provided upto maximum span of 3 m.
3. PIPE CULVERT:
The culvert which consists of one or more pipes placed side by side over a concrete
base below the embankment of a roadway or railway track is known as pipe culvert.
In this type of culvert, one or more pipes consisting of cast iron, steel or RCC are held in
position over a concrete base by fixing their both the ends into masonry walls. In pipe
culverts, generally, more than one pipe, of diameter not less than 30 cm is used.
However, their exact number and diameter depending upon the discharge and height of
the bank. As far as possible the gradient of the pipe should not be less than 1 in 1000.
Pipe culverts are suitable where the flow of water in the stream is very small.
4. BOX CULVERT:
The culvert consisting of one or more numbers of rectangular or square openings,
having their floor and top slabs constructed monolithically with abutments and pier, is
known as box culvert.
Box culverts are usually constructed of precast RCC slabs. Small span box culverts
may be constructed of stone slabs, supported on masonry abutments, with brick or
stone flooring. These culverts provide the least interference to traffic during
construction.
Box culverts are mainly constructed where the sol is soft and the load has to be
distributed over a wider foundation area. This type of culvert can be conventionally used
for a single span of 3 m or for double span of 6 m.
2. RAFT FOUNDATION:
This type of foundation is suitable when the bed of the water course consists of soft clay
and silt and the hard soil is not available within reasonable depth (1.5 to 2.5 m) below
the river bed.
It is best suited in situations where the allowable bearing capacity of the soil is low or
when the bridge loads are heavy. Raft foundation is also suitable when the soil bed has
some soft pockets which are compressible and there is possibility of unequal
settlement.
3. GRILLAGE FOUNDATION:
This type of bridge foundation is suitable for heavy and isolated footings of piers where
deep foundations are to be avoided. It is best suited where sub-soil conditions are poor.
5. PILE FOUNDATION:
This type of bridge foundation is suitable when the soil is very soft and the hard strata
are not available at a reasonable depth below the bed level of the river. It is best suited
where heavy scouring of river bed is expected and heavy concentrated loads are
expected to be taken by the foundation. It is also suitable when it is much expensive to
provide raft or grillage foundation.
6. WELL FOUNDATION:
This type of bridge foundation is suitable where good soil is available at about 3 to 4 m
below the bed level of the river and the bed consists of sandy soil. It is best suited to
soft soils or sandy beds, where heavy scouring is liable to occur due to excessive
velocity of approach of the river water.
7. CAISSON FOUNDATION:
Caisson foundation is suitable when a hard strata is available near to the river bed but
the depth of water is excessive and it is not economically possible to exclude water from
a dry bed for sinking the wells to provide well foundation.
CONSTRUCTION PROCEDURE:
1. Construct the perimeter wall, Constructpiles. Place the steel columns or stanchions
where the piles are constructed.
2. Cast the floor slab of first basement level.
3. Proceed to the first stage of excavation.
The cost of building a house differs from plan to plan. It is always essential to provide
economical design to the house owner. Civil engineers and architects use their
professional experience and technical skills to minimize the cost of a project where it is
possible. In this article, I will give you some basic ideas which can be used to reduce
the overall cost of constructing residential building or house. But these are just basic
ideas, never compromise with the quality and strength to reduce the cost.
PLOT AREA:
Plot area commonly known as site area is a piece of land enclosed by definite
boundaries. The mean horizontal distance between the front and rear site boundaries is
known as depth of the plot area.
CARPET AREA:
Carpet area is the area excluding the walls of built-up area. In simple words, it is the
internal space within the walls which you can actually use. Usually, carpet area is
around 70 -90 % of the built-up area.
SETBACK AREA:
The area on all sides of the plot boundaries laid down by the local municipal authority
beyond which nothing can be constructed toward the plot boundary is known as setback
area.
The line usually parallel to the plot area on each side is call setback line. This area
helps a building to get more daylight and fresh air to the street level.
1. STEP:
It is a combination of tread and riser which permits ascent and descent from one floor to
another.
2. TREAD:
The upper horizontal portion of the step over which foot is placed during ascending or
descending a stairway is known as tread.
3. RISER:
The vertical member of the step is known as riser. It is used to support and connect the
successive treads.
4. RISE:
The vertical height between two consecutive treads is known as rise.
5. LANDING:
A horizontal platform between two successive flight of a stair is called landing. Landing
is used as a resting place during use of the stair. It facilitates the change of direction of
the flight. Landing which extends for full width of the staircase is known as half-space
landing. Landing extending for only half the width of staircase is known as quarter space
landing.
6. NOSING:
It is the projecting part of the tread beyond the face of the riser. Nosing is usually
rounded to give good aesthetic effect to the treads and make staircase convenient and
easy to use.
7. GOING:
The horizontal distance between without the faces of two consecutive risers is known as
going of steps.
8. FLIGHT:
A continuous series of steps without any break between landings or landing and flooring
is known as flight.
9. HEAD ROOM:
The vertical height between the tread of one flight and the ceiling of the overhead
construction is known as head room. Head room should be sufficient so as not to cause
any difficulty to the persons using the stair. Head room is also known as head way.
11. BALUSTER:
It is an individual vertical member made of timber, metal, or masonry and fixed between
string and hand rail to provide support to the hand rail.
12. BALUSTRADE:
Framework made from series of balusters and hand rail is known as balustrade. It is
also known as barrister.
14. RUN:
The total length of the stair in horizontal plane including lengths of landings is known as
run of the stair.
15. SOFFIT:
The undersurface of the stair is known as soffit. It is either finished with plaster or
covered with a ceiling.
16. SCOTIA:
It is a sort of additional moulding provided under the nosing or tread to beautify the step
of elevation.
17. NEWEL-POST:
It is a vertical timber or steel post provided at the head, foot or at point where the
balustrade changes its direction. It is also used for supporting the hand rail.
19. WAIST:
The thickness of the RCC slab over which steps of RCC rest, is known as waist.
22. SPANDREL:
It is triangular framing under the outside string of an open string stair.
SAQIB IMRAN 0341-7549889 38
39 | P a g e
Pile Driving
The process of forcing pile into the ground without any excavation is known as pile
driving. The equipment required for pile driving can be classified as follows:
1. Pile frames,
2. Pile hammers,
3. Leads,
4. Winches,
5. Miscellaneous Equipment.
1. DROP HAMMER:
It is made from solid mass of C.I which is lifted and allowed to fall under gravity on the
pile head. It is provided with two lugs so that it may slide on the leads. It also consists of
a hook to tie the rope to it. Drop hammer weighs 1 ton to 4 ton and has a free fall
varying from about 1.5 to 6 m. It can deliver 4 to 8 blows per minute. The energy
imparted to the pile head by the hammer is dependent on fall and weight of the
hammer. Heavy hammer with short fall should be preferred than using light hammer and
large fall.
2. STEAM HAMMER:
B. DOUBLE-ACTING HAMMER:
In this method, the hammer is lifted by steam or compressed air like single-acting
hammer but during fall steam or compressed air also aids the fall of the hammer in
addition to the gravity effect. If compressed air is used for lifting and dropping the
hammer on the pile head, it is known as pneumatic hammer. Double acting hammer
weighs about 1/2 ton but because of added effect of steam pressure, it develops an
effect of about 3 ton on the pile head. It can deliver 100 to 300 blows per minute. This
hammer is generally fully enclosed in a steel case and hence equally useful for driving
piles under water. In this hammer, energy per blow and number of blows per minute can
be regulated by adjusting steam pressure.
3. WATER JET:
In this method, piles are cast with jetting pipe in them. Water under a pressure of 7 to
17.5 kg/cm2 is forced through this jetting pipe at the rate of 20 to 40 liters per second
near the bottom of the pile. This water dislodged the soil at the bottom of the pile and
pile can sink under its own weight or with a very light blow of the hammer. Some water
from the bottom rises along the sides of the pile and helps in reducing the friction
between the pile and surrounding soil. The water jet is stopped about 1 m to 2 m from
the depth to be reached by the pile and this length is driven entirely with hammers.
4. BY BORING:
Piles may be driven by first boring a hole with the help of auger, rotary well drills or by
any other method. Auger is used when the soil is soft and depth is very small. In case of
rock and hard soils boring may be done by well drill or other methods. A precast pile is
lastly put into the bored hole.
ARCH:
Arch is a mechanical arrangement of wedge-shaped blocks of stones or bricks mutually
supporting each other and supported at the end by piers or abutments. In common with
lintels, the function of an arch is to carry the weight of the structure above the opening.
1. ABUTMENT OR PIER:
It is the part of wall or pier on which the arch rests.
2. ARCH RING:
It is a course of stones or bricks having a curve similar to that of the arch.
3. INTRADOS OR SOFFIT:
It is the under-surface of an arch.
SAQIB IMRAN 0341-7549889 42
43 | P a g e
4. EXTRADOS:
It is the outer surface of an arch or the outer curve of the arch ring.
6. SPRINGING STONE:
Springing stone or springer is the first voussoirs at springing level on either side of the
arch.
7. SPRINGING LINE:
Springing line is an imaginary line joining two springing points.
8. CROWN:
Crown is the highest point of the extrados or it is the highest part of the arch.
9. KEY-STONE:
It is the highest central wedge-shaped block of an arch.
10. SKEW-BACK:
It is the surface of the abutment on which the arch rests.
11. SPAN:
Span is the clear horizontal distance between supports.
12. RISE:
Rise is the vertical distance between the springing line and the highest point on the
intrados.
15. HAUNCH:
Haunch of the arch is the portion of the arch situated centrally between the key and
skew backs.
16. SPANDRIL:
Spandril is the triangular walling enclosed by the extrados of the arch, a horizontal line
from the crown of the arch and a perpendicular line from the springing of the outer
curves.
Gypsum plaster, also known as plaster of paris obtained from gypsum, which occurs in
form of natural rocks. Gypsum consists of one part of calcium sulphate and two parts of
chemically combined water of crystallization.
When gypsum is heated at a certain temperature, water of crystallization is driven off
and the powdery product left is called plaster of paris. As soon as water is added to the
plaster of paris, it sets immediately without giving time for mixing and application.
When plaster of paris is to be used for plastering the surfaces, its setting time will have
to be prolonged which can be done by adding certain salts to it. Addition of some burnt
ash and fine sand prolong its setting time. When used for plastering, the setting time of
the mortar of plaster of paris and sand is normally 5 minutes. Hence it has to be used
very briskly so as to enable its application to the surface before it sets.
SAQIB IMRAN 0341-7549889 44
45 | P a g e
Generally dry mix of paris plaster with sand is prepared on an impervious platform.
Small quantity of mix is taken in pans and carried to masons. The mason will add water
to the dry mix only when it is to be used. This plaster is a very good plaster and gives
very smooth finishing. Since it is slightly soluble in water, it cannot be used for externally
exposed surfaces.
When raw gypsum is heated from 160 to 170 about 15 water of crystallization is driven
off and resulting product is known as hemihydrate calcium sulphate. Hemihydrate is
also known as first settle plaster which is actually plaster of paris. The term hemihydrate
gypsum plaster is used to indicate plaster of paris with retarders mixed with it.
On further heating to about 200C entire water content of crystallization is driven off and
the resulting product is known as gypsum anhydrite or hard burnt plaster. The setting
time of gypsum anhydrite is quite large and requires accelerators to be added to shorten
its setting time. Anhydrous gypsum plaster indicates gypsum anhydrite added with
accelerators.
MACHINE FOUNDATION
MACHINE FOUNDATION:
Foundation provided below the superstructure of vibrating and rotating machine for
installation, is known as machine foundation. It essentially consists of a mass of
concrete. Design of machine foundation involves consideration of static load and kinetic
forces.
The load of the machine is the static load which is of minor importance in the design of
a machine foundation. The moving parts of the machine develop inertia forces which
are the major forces to be considered in its design. The kinetic or inertia forces are
periodic and vibratory in nature, the magnitude of which depends on the type of
machine. The general principles of machine design are enumerated as follows:
1. Machine foundations should be isolated from the adjoining parts of the building by
leaving a gap around it to avoid the transmission of vibrations. The gap is filled with
suitable insulator or dampers.
2. The foundation should be stiff and rigid to avoid possibilities of tilt in it.
3. In static state, the resultant of forces acting on machine foundation should pass
through the c.g of the contact area of the base.
4. The weight of the foundation block should be adequate. It should be able to absorb
vibrations and resist resonance between adjoining soil and the machine. The weight of
the foundation block may be assumed roughly 2.5 times the weight of the machine.
5. A vibration absorbing medium is introduced between bottom of the foundation block
and the floor on which it is resting. This medium may be in form of a rubber or leather
gasket, layer of sawdust etc. Sometimes, springs are used below the machine itself to
prevent the development of the vibrations. It is advised that relevant data of machine
should be obtained from the manufacturer before any design of foundation is
undertaken.
3. Wall Type:
4. Framed Type:
3. Decrease the number of plants and reduce the movement of heavy equipment.
4. Avoid confusion and reduce accidents.
5. Have a tidy outlook to facilitate the inspection of the materials.
The layout satisfying maximum of these conditions increases efficiency and thus
productivity. Such a layout is known as optimum layout. The site layout depends very
largely on the following factors.
1. Location of the site.
2. Availability of space.
3. Access to the site.
4. Material bulk.
5. Type of equipment to be used.
6. Ground conditions.
1. The site should have preferably two openings, one for entry and the other for exist. It
promotes flow of traffic. If there is only one gate then it is preferable to provide a cross-
over near the gate.
2. The general office should be located near the main gate. This avoids confusion at
construction site.
3. The godown should be located just behind the general office. It facilitates delivery of
the material to be stored in it. It also permits a closer supervision of the stores.
4. Temporary roads may be constructed around the operation area. It promotes the flow
of material and movement of equipment. In fact, if such roads are required to be
constructed in the project, it is better to construct them first so that these can be used
during the construction proper.
5. The workshops for joiner, fitter, electrician etc should be decided and located by
balancing easy and short access routes.
6. Staff accommodation should be away from noise. It should be concentrated in one
area to promote communication and reduce the cost of facilities and services.
7. The existing services should be used to the maximum extent.
Report:
Bulk density is reported to the closest decimal place.
Safety And Precautions During Test:
1. Wear hand gloves to remove the container of brick after switching off the oven.
2. Check the electric supply carefully.
3. Clean the container thoroughly and dry it for few minutes before testing.
4. Air should not enter from outside while using the balance.
So it is important to check the quality of cement before using. In our previous article, we
have already discussed the different types of cement and their uses in
construction.Today we will discuss how to check the quality of cement at site.
To check the quality of cement we need to pass some easy tests which are described
below.
1. DATE OF PACKING:
The strength of cement decreases with time. First of all, check the manufacturing date
in the bag before using. Generally, cement should be used before 90 days from the
manufacturing date. The percentage of strength loss of cement is given in the below
table.
2. CEMENT COLOR:
The cement should be uniform in color. Good quality cement should have gray color
with greenish shade.
4. RUBBING TEST:
Cement should feel smooth while rubbing in between fingers. If it gives a rough feeling
that means cement is mixed with sand.
5 TEMPERATURE TEST:
Simply insert your hand into the cement bag, it should give cool feeling if its quality is
good. Otherwise, you may feel warm because of hydration reaction.
6. FLOAT TEST:
Take some amount of cement and throw it in water. The cement should float for
sometimes before it sinks in the water.
7. SETTING TEST:
Make a thick cement paste with water and immerse it in water for 24 hours. It should be
set and should not develop cracks.
8. STRENGTH TEST:
Prepare a cement block of 25 mm x 25 mm and 200 mm in length. Now submerge it in
water for 7 days. Now place it on supports 15 cm apart and load it with 34 kg weight.
Block made from good cement will not show any signs of failure.
SUNK SLAB:
Sunk slabs are slabs which are cast at a certain depth (200 or 300 mm or any other
depending on design) below normal floor level. This extra depth is used for placing
pipes and utility ducts. And then space is filled with sand or other light weight materials
until the normal floor level.
1. The concrete of the R.C.C. (floor and sunken slab) should be mixed with a
waterproofing material to get a denser, watertight concrete.
2. Then cement and waterproofing material should be diluted in water and splashed
onto the RCC sunken slab. Over that, a layer of plaster should be provided using a
mortar plasticizer with the cement mortar.
3. Brick laying of walls and plastering (prior to tiling) of the walls and floor should be
done with cement mortar mixed with a mortar plasticizer.
4. Tile fixing for the floor and walls tiles should be done with non-shrink, waterproof tile
adhesives to make the tiled area waterproof.
5. Sanitary pipe joints should be sealed with sealants specially manufactured for sealing
sanitary joints firmly so that no water can leak through.
2. PARTITION WALL:
It is an interior non-load bearing wall. Its height may be one storey or part of one storey.
Its purpose is to divide the larger space into smaller spaces.
3. PANEL WALL:
It is an exterior non-load bearing wall in framed construction. It remains totally
supported at each storey but subjected to lateral loads.
4. CAVITY WALL:
A wall consists of two leaves, each leaf being built of masonry units and separated by a
cavity and tied together with metal ties or bonding units to ensure that the two leaves
act as one structural unit. The space between the leaves in either left as continuous
cavity or filled with non-load bearing insulating and water proofing material.
5. FACED WALL:
It is a wall in which the facing and backing of two different materials are bonded
together to ensure common action under load.
6. VENEERED WALL:
It is a wall in which the facing is attached to the backing but not so bonded as to result
in a common action under load.
COMPRESSION STRENGTH:
The compression strength of 43 grade cement is 43 MPa after 28 days of setting and
the compression strength of 53 grade cement is 53 MPa after 28 days of setting.
INITIAL STRENGTH:
53 graded cement is mostly used in fast forward construction where initial strength
needs to be achieved quickly.
53 grade cement has faster setting compared to 43 grade cement. Compression
strength of 53 grade cement after 7 days is 27 MPa but 43 grade cement gets 23 MPa
after 7 days.
PRICES:
Well, the prices of 43 and 53 grade cement vary from different brand to brand. Normally
53 grade cement is 3-4% costlier than 43 grade cement.
The strength of brick masonry mainly depends on the strength of bricks that are used in
the construction. The strength of bricks depends on the soil used to make the bricks,
method and making process, burning of bricks. Since the nature of the soil varies from
region to region, the average strength of bricks also varies from region to region.
The permissible compressive stress of brick masonry depend upon several factors such
as,
1. Type of bricks (1st class, 2nd class, 3rd class)
2. Strength of bricks
3. Size and shape of the masonry construction.
4. Mix of mortar.
5. uniformity of bricks
6. Workmanship.
7. The method adopted for laying bricks.
There are some useful checklists which can be applied to increase the strength of brick
masonry.
1 Visual check – The bricks to be used should be good quality, burnt well with uniform
shape, size, and color.
2 A metallic ringing sound should be produced when striking two bricks with each other.
3 A good quality brick will not break if dropped from one meter height.
4 A good brick should not absorb water more than 20% (By its weight) while submerged
in water for 24 hours.
OPC:
OPC or ordinary portland cement is the basic type of cement which is used in all type of
construction work. Basic properties of this cement are listed below:
1. This type of cement has adhesive and cohesive properties, therefore it forms a good
bond with other materials.
2. This cement is comparatively finer and particles are very small.
3. It has low resistance to sulfate reaction.
4. This cement produces greater heat of hydration, therefore more concentrated curing
is required.
5. The rate of gaining strength, drying shrinkage, and resistance to cracking of opc is
moderate.
6. Mainly used in RCC buildings, pavements, culverts, tanks and all other structures
where the heat of hydration will not cause any defect.
PPC:
PPC means portland pozzolana cement. This cement is produced either by uniformly
blending portland cement and fine pozzolana or by grinding portland cement clinker and
pozzolana, The basic properties of this cement are given below:
1. This cement has lower heat of hydration and requires normal curing.
2. Initial strength is low but final strength is similar to opc33.
3. This cement has good resistance to chemical agencies.
4. It can also resist attack by sea water better than opc.
5. The rate of strength development is lower than opc.
6 This cement has same 7 days compressive value as opc.
SAQIB IMRAN 0341-7549889 65
66 | P a g e
7. This cement is suitable for hydraulic works, construction in sea water and for mass
concrete works.
Additional notes such as lap length for column steel of different diameter etc will be
given in the sheet of structural drawing.
3. COLUMN FORMWORK:
The floor height is normally kept at 10 feet. If the slab contains beam, then concrete has
to be poured upto the beam bottom level. For example, if the beam height is given in the
drawing is 1′-6″, the casting height of column and formwork will be 8′-6″. But as we know
that dropping concrete more than 5 feet height is not allowed because it will cause
segregation, we should create formwork within 5 feet height. When the first part will be
cast completely, the rest part should be started.
TYPES OF POINTING
TYPES OF POINTING:
The choice of particular type of pointing depends upon the type of masonry, nature of
the structure and the nature of the finish desired. The various types of pointing
commonly used are described below:
1. Flush Pointing.
2. Cut Or Weathered Or Struck Pointing.
3. Keyed Or Grooved Pointing.
4. V-grooved Pointing.
5. Tuck Pointing.
6. Beaded Pointing.
1. FLUSH POINTING:
In this type of pointing, the mortar is pressed into the raked joints and finished off flush
with the edges of the bricks or stones, so as to give a smooth appearance. The edges
are then nearly trimmed with a trowel and straight edge. This is the simplest type of
pointing and is extensively used in work and stone masonry face work.
4. V-GROOVED POINTING:
This type of pointing is made similar to keyed or grooved pointing by suitably shaping
the end of the steel rod to be used for forming the groove.
5. TUCK POINTING:
In this type of pointing, the mortar is first pressed in the raked joints and after it is
finished flush with the face of the wall. While the pressed mortar is still green, the top
and bottom edges of the joints are cut parallel so as to have a uniformly raised band
about 6 mm high and 10 mm in width.
6. BEADED POINTING:
In this type of pointing, the mortar is pressed in the raked joints and finished off flush
with the face of the wall. While the pressed mortar is still green, a steel rod having its
end suitable shaped is run straight along the center line of the joints to form the
beading.
6. After plastering the defects of masonry are not visible, but the defects of masonry can
be seen in case of pointing.
7. Plastering can be done in all types of brick surface. Pointing is only suitable for first
class bricks.
Plastering
Pointing
Note:
For rapid hardening cement 3/7th of the periods given in the above table will be
sufficient in all cases except vertical sides of slabs, beams, and columns which should
be retained for at least one day.
All formwork should be eased gradually and carefully in order to prevent the load being
suddenly transferred to concrete. The forms can be easily stripped by loosening the
double edges. Sometimes the swelling of timber may result in shuttering getting jammed
at places. In such situation, a small crowbar can be used to strike off the shuttering. In
Case of cantilever slabs and beams, the centering should be removed only after
necessary construction to provide proper counterweight has been carried out and the
same has attained sufficient strength.
Foundation is one of the most important parts of a structure because it transfers loads
of the structure to the underneath soil. That means the whole structure stands on the
foundation. So we need to build a strong foundation to support the structural loads
adequately. Here are some useful construction tips which should be followed in order to
build a strong foundation.
1.The soil on which the structure is to be constructed should be strong and the
foundation should be continuous.
2. A dry base ( soil under the foundation) should be provided to avoid liquefaction and
sinking of structure during earthquake.
3. There are different factors which can affect the depth of the foundation such as,
ground water table, bearing capacity of soil, excavation allowance, shrinkage and
swelling due to seasonal changes, depth of frost penetration etc. So considering these
factors the minimum depth of foundation should be 1.5 m.
4. Only broken stones should be used in the construction of foundation, round and
unbroken stones should be avoided.
5. To join the stones properly, sufficient mortar should be used and if required,
reinforcement can also be used to increase the overall strength of the structure.
6. The width of footings for one and half brick wall should be 1 m and for one brick wall
75 cm.
DEWATERING
WHAT IS DEWATERING?
Dewatering
The process of removing water from an excavation is known as dewatering. In this
process, the water is drained outside by pumping from the location.
The main purpose of dewatering is to provide a dry base for the foundation by lowering
the ground water table of a given location. Dewatering is an useful method for dealing
with running sand, construction as well as repairing of dams, sewers, basement,
building, tunnel etc.
METHODS OF DEWATERING:
There are generally four methods of dewatering which are listed below:
1 Well point method.
2. Eductor wells.
3. Open sump pumping and.
3. Deep Wellpoint method.
Let,
R = Ultimate resistance offered by the soil.
h = Height from the trench bottom, from where weight is dropped
d = Depth of impression made by the falling weight.
A = Cross-sectional area of the falling weight coming in contact with the soil.
W = Weight of the falling weight.
Energy lost in penetration is equal to the potential energy of the falling weight.
Wh = R x d
R = Wh/d
Ultimate resistance of the soil/Unit area = R/A
If f is the factor of safety, the safe bearing capacity of the soil per unit area is equal to R
/Axf
This method of evaluating the safe bearing capacity of the soil is an approximate
method, and hence should be used in case of minor structures only or where the
method of slowly applying load is impracticable.
CONSTRUCTION OF FORMWORK
CONSTRUCTION OF FORMWORK:
The construction of formwork normally involves the followings operations.
1. Propping and Centering.
2. Shuttering.
3. Provision of camber.
4. Cleaning and surface treatment.
2. SHUTTERING:
As described earlier the shuttering can be made up of timber planks, or it may be in the
form panel units made either by fixing plywood to timber frames or by welding steel
plates to angle framing. In any case, the shuttering should be constructed in such a
manner that the joints should be tight against leakage of cement grout.
Sometimes the architect specifies provision of molding in slab or columns or provision of
chamfers at corners of beams and columns. All such moldings, beveled edges,
chamfers etc required to be formed in the concrete work should be made in the
shuttering itself. Similarly, opening for fan clamps or other fittings should be provided in
the shuttering as per details in the drawing.
3. PROVISION OF CAMBER:
Certain amount of deflection in structure is unavoidable. It is therefore desirable to give
an upward camber in the horizontal members of the concrete structure (especially in
members having long spans) to counteract the effect of deflection. The provision of
desired camber should be made in the formwork itself during erection. Camber for slabs
and beams may be ADOPTEED @ 4 mm per meter span. In case of cantilevers, the
camber at free end should normally be taken @1/50th of the projected length of the
cantilever.
4. SURFACE TREATMENT:
Before laying concrete the formwork should be cleaned of all rubbish particularly the
sawdust shavings and chippings etc. All surfaces of timber shuttering that are to come
in contact with concrete should be well wetted with water. This is necessary to prevent
the chances or dry shuttering absorbing water from the concrete which may cause
warping, swelling and distortion of timber besides resulting in defect of honeycombing in
concrete.
Similarly, steel forms that have been exposed to hot weather should be cooled by
watering before laying concrete.
In addition, all surfaces of shuttering which are to come in contact with concrete should
be given a good coating of raw linseed oil or soft soap solution or any other material so
as to prevent the concrete getting stuck to the formwork and thus facilitate easy
removal. It is, however, important to note that the coating should not come in contact
with reinforcement. The selected coating should be impermeable and should neither get
flaky on exposure to weather nor stain the surface of concrete.
Cantilever beam can be defined as a beam which is supported on only one end. That
means one end is fixed and the other end is exposed beyond the support. The beam
transfers the load to the support where it can manage the moment of force and shear
stress. Moment of force is the tendency of a force to twist or rotate an object. Shear
stress is defined as a stress which is applied parallel to the face of a material.
In other words, the beam carries a specific weight on its open end as a result of the
support on its enclosed end, in addition to prevent breaking down as a result of the
shear stress, the weight would generate on the beam structure. Cantilever construction
allows for overhanging structures without external bracing/support pillars. Cantilever
beams can also be constructed with trusses or slabs.
The most common causes of defects in brick masonry are described below:
1. SULPHATE ATTACK:
Sulphate salts present in brickwork react with alumina content of cement and with
hydraulic lime in the lime mortar causing considerable increase in the volume of mortar.
This, in turn results in chipping and spalling of bricks and formation of cracks in joints
and rendering.
This defect occurs in situations where the brickwork is exposed like boundary walls,
parapets etc. or where it is likely to be in contact with moisture like manholes, retaining
walls etc.
This defect can be remedied by adopting suitable construction details and choosing
materials in such a way that entry of moisture into the body of brickwork can be
checked.
4. SHRINKAGE ON DRYING:
Brickwork normally swells with the absorption of water and subsequently shrinks when
the water evaporates. In the process of shrinkage, it develops cracks in the masonry
joints. If the mortar used in the masonry is lean, the cracks are distributed over a large
number of joints and in case of rich mortar, the cracks are few but wider. Such cracks
do not affect the structural strength of the brickwork and can be easily rectified.
This defect can be prevented by using good quality bricks and by protecting masonry
from moisture penetration.
WHAT IS T-BEAM?
It’s simply a rectangular beam cast monolithically with the slab shaped as T.
The various advantages and disadvantages of T-beam are as following:
ADVANTAGES:
1. Since the beam is cast monolithically with the slab, the flange also takes up the
compressive stresses which mean, it will be more effective in resisting the sagging
moment acting on the beam.
2. Better head room, this is direct outcome of the first point since the depth of the beam
can be considerably reduced.
3. For larger spans, t beams are usually preferred rather than rectangular beam as the
deflection is reduced to a good extent.
DISADVANTAGES:
1. There is a considerable increase in the shear stress at the junction of the flange and
the web of the beam due to the change in cross section. So casting should be done
very carefully to ensure both are bonded well.
2. Since the beam slab is monolithic (rigid), it becomes very weak in resisting lateral
shear forces. (cracks develops quickly). Hence usually in earthquake prone zones using
t beams for high rise building is reinforced with mechanical stiffeners in the junction.
3. There will be small savings in steel too (not a significant amount though).
1. Cleats:
Cleats are fixed to the sides of the beams. The size of the cleat is 100 mm x 20 mm or
100 mm x 30 mm.
2. Side forms of the sheathing of the beams are generally 30 mm thick.
3. Joists Or Battens:
Joists support the decking. The size of the joists depends upon the c/c spacing of the
joists and span of the joists. Joists are also known as battens.
4. Ledgers:
Ledgers are horizontal wooden pieces nailed to the cleats. They form the bearing for
joists.
5. Bottom Sheathing:
It should be made 50 mm to 70 mm thick as load is quite heavy over it.
6. Head Tree:
The whole of the beam is supported on a head tree. It is a horizontal beam connected at
top of the vertical post or shore, through inclined cleats or beams.
At the bottom of the vertical posts or shores, a pair or wedges are fixed over sole
pieces. Wedges help in tightening or slightly raising the formwork to develop initial
camber in the formwork. Wedges are withdrawn while stripping the formwork. Formwork
should not be stripped at once, but should be loosened slowly by withdrawing the
wedges slightly in stages.
All the construction joints in beams and floors should be made in the middle third of the
beam.
TYPES OF FOOTINGS:
The different types of footings used for building construction are described below:
1. STRIP FOOTING:
It is a component of shallow foundation which distributes the weight of a load bearing
wall across the area of the ground. It is also known as wall footing.
2. SPREAD FOOTING:
As the name suggests, a spread is given under the base of the foundation so that the
load of the structure is distributed on wide area of the soil in such a way that the safe
bearing capacity of the soil is not exceeded.
3. ISOLATED FOOTINGS:
It is square, circular or individually rectangular slab of uniform thickness, provided under
each column.
4. STEPPED FOOTINGS:
The main purpose of using stepped footing is to keep the metal columns away from
direct contact with soil to save them from corrosive effect. They are used to carry the
load of metal columns and transmit this load to the below ground.
5. COMBINED FOOTINGS:
When two or more columns are supported by a footing it is called combined footing.
This footing may be of rectangular or trapezoidal in plan. Combined footing is provided
under following situations.
When columns are close to each other and their individual footings overlap.
Soil having low bearing capacity and requires more area under individual footing.
The column end is situated near the property line and the footing can not be
extended.
6. STRAP FOOTING:
In such footing, the outer and inner column is connected by a strap beam, does not
transfer any load to the soil. The individual footing areas of the columns are so arranged
that the C.G of the combined loads of the two columns pass through the C.G of the two
footing areas. Once this criterion is achieved, the pressure distribution below each
individual footing will be uniform.
7. MAT FOUNDATION:
This foundation covers the entire area under the structure. This foundation has only
RCC slab covering the whole area or slab and beam together. Mat foundation is
adopted when heavy structures are to be constructed on soft made-up ground or
marshy sites with uncertain behavior. Mat foundation is also known as raft foundation.
8. SLOPED FOOTING:
The footings having sloping top or side faces are known as sloped footings. This type of
footing is useful in the construction of formwork.
SPECIFICATION OF PLASTERING
SPECIFICATION OF PLASTERING:
The general specification of plastering are as following:
1. Plastering is the finishing coat which protects the masonry and gives a decent look. It
also enhances the hygienic conditions in the building.
2. The reference marks (BUNDAS) should be made on the wall in 2″ to 3″ diameter
before starting the plastering work.
3. Cement and sand mortar is used in plastering which comprises of different thickness
according to the requirement of site..
4. Plastering should be done with cement mortar ratio of 1:3, 1:4, 1:6 etc. as per the
requirements of the work.
5. The plaster should be in straight line, leveled, plumbed and the joint must be in right
angle.
6. Before starting the plaster, the surface should be raked and properly cleaned by wire
brush and it should be wet for 24 hours.
7. Door and window frames, water supply lines, electric fittings should be fitted
appropriately before starting the plastering work. They should be laid as per the
drawings.
8. All unnecessary cement mortar should be removed from the frames and electric
fittings instantly after finishing the plaster.
9. Curing of the plastered surface should be done properly. It should be cured at least
for 7 days to get desired strength.
FILLING:
Local sand shall be used to fill the foundation trenches and plinth.
DPC:
2.5 cm thick cement concrete shall be used in the damp proof course and 5 % pudlo or
other good waterproofing materials shall be used at DPC.
SUPER STRUCTURE:
Superstructure shall be made of first class brick work in cement mortar. Lintels over
doors and windows shall be of R.C.C.
ROOFING:
The roof shall be of 10 cm R.C.C. slab with an insulation layer and lime concrete
terracing above, supported over R.S.Joist or R.C.C. beam as required. The height of
rooms shall not be less than 3.7m (12 feet).
FLOORING:
Drawing room and dining room floors shall be mosaic (terrazzo). Bathroom and W.C.
floor and dado shall be of mosaic (terrazzo). Floors of bedroom shall be colored and
polished of 2.5cm (1”) cement concrete over 7.5cm (3”) lime concrete. Floors of other
shall be of 2.5cm (1”) cement concrete over 7.5cm (3”) lime concrete polished.
MISCELLANEOUS:
Rainwater pipes of cast iron or of asbestos cement shall be provided and finished with
painting. The building shall be provided with 1st class Sanitary and Water Fittings and
Electrical installations. 1 meter wide 7.5cm thick C.C. 1:3:3 apron shall be provided all
around the building.
4. The bricks should be laid on their proper bond. The frog of the bricks should be kept
upward.
5. Brick bats should be avoided.
6. The thickness of the joints should not exceed 13 mm.
7. The masonry walls should be always truly vertical and verticality should be checked
continuously using a plumb bob.
8. Brickwork should be raised uniformly. Any part of the masonry should not be raised
more than 90 cm to the rest of the masonry work.
9. The work should be raked back in successive courses if it is to be constructed later.
10. In masonry work, large voids should not be filled with mortar only. It is
uneconomical.
11. Cement mortar should be used to enclose all the iron fixtures of doors and windows.
12. To achieve easy and adequate bond for plastering and pointing, the facing mortar
joints should be raked for a depth of 13-19 mm when the mortar in the joint is green.
13. The finished brick masonry should be cured at least for 7 days.
14. Any brick masonry wall should not be constructed more than 1.5 meters in a day.
15. In brick masonry piers, buttresses, counterforts etc should be constructed along with
the main walls, maintaining a proper bond between them.
16. Suitable scaffolding should be used to carry out masonry work at higher levels.
The scaffolding should be made by giving one end of horizontal bullies into the new
masonry work and secured to it properly.
1 ARCHITECTURAL DRAWING:
This type of drawing provides complete view of a building. It demonstrates the location
of building and all building parts where they will be placed. There are different types of
architectural drawings with different names such as plan, elevation, section etc.
SAQIB IMRAN 0341-7549889 95
96 | P a g e
2 STRUCTURAL DRAWING:
As the name suggests, this type of drawing provides information about structure, like
strength of different structural elements, structural materials, grade, size and placement
of reinforcement etc.
3 ELECTRICAL DRAWING:
This type of drawings provide the details and location of electrical wiring, fixtures, sub-
station etc. The electrical load calculation is also given in the drawing.
5 FINISHING DRAWING:
This types of drawings contain the details of finishing and appearance of the building
such as marbles, tiles, etc.
1. Standards should be created to rest on hard and rigid ground. If hard and farm
ground is not available, standards may be created on ordinary timber sole plate.
2. Loadings on the scaffolding should not be heavy.
3. The scaffoldings should be tied at appropriate levels of the buildings. To tie the
scaffoldings, horizontal or vertical bullies can be used inside the building and secure
scaffolding to it by tying putlogs through door or window openings. To give lateral
support to the scaffoldings rakers should be used.
4. To enable working at heights, working platforms should be lifted by lengthening the
standards and providing extra ledgers and putlogs.
5. Holes left in the walls should be filled immediately after withdrawing of putlogs.
6. The spacing between standards should be made according to the load to be carried
and section of the standards.
7. Special patented scaffoldings should be used for constructing structures like towers,
domes, chimneys etc.
TYPES OF BUILDINGS
TYPES OF BUILDINGS:
Depending upon the character of occupancy or the type of use, building can be
classified into different categories as follows:
10
SAQIB IMRAN 0341-7549889
0
101 | P a g e
1. RESIDENTIAL BUILDINGS:
These buildings include one or two private dwellings, apartment houses (flats), hotels,
dormitories etc.
2. EDUCATIONAL BUILDINGS:
These buildings include any building used for school, college or day care purposes
involving assembly for instruction, education or recreation.
3. INSTITUTIONAL BUILDINGS:
These buildings include any building or part which is used for medical treatment etc.
Such as Hospitals, nursing homes, orphanages, sanatoria, jails, prisons, mental
hospitals etc.
4. ASSEMBLY BUILDINGS:
These buildings may include any building or part of a building where a group of people
gathers for recreation, amusement, social, religious or such types of purposes such as
theaters, assembly halls, exhibition halls, restaurants, museum, club rooms, auditoria
etc.
5. BUSINESS BUILDINGS:
These shall include any building or part of a building which is used for business
transactions, keeping records of accounts, town halls, city halls, court houses etc.
6. MERCANTILE BUILDINGS:
These shall include those buildings which are used for soap, market, stores, wholesale
or retail.
7. INDUSTRIAL BUILDINGS:
This types of building mainly used for manufacturing purposes. Here products or
materials of all kinds and properties are fabricated, assembled or processed, for
example, gas plants, refineries, mills, dairies etc.
8. STORAGE BUILDINGS:
These buildings are generally used for the storage or sheltering of goods, wares, or
merchandise like warehouses, cold storages, garages, stables, transit sheds etc.
10
SAQIB IMRAN 0341-7549889
1
102 | P a g e
9. HAZARDOUS BUILDINGS:
These buildings include any building which is used for storage, handling, manufacture
or processing of highly combustible explosive materials or products which are liable to
burn with extreme rapidly which may produce poisonous fumes, building which is used
for storage, handling or manufacturing highly corrosive, toxic, acid or other liquids or
chemicals producing flame, fumes explosive etc.
SHUTTERING/FORMWORK:
Formwork is a temporary structure used as a mold in which fresh concrete are poured
to cast the members of the structure at the site. It is also known as falsework or
10
SAQIB IMRAN 0341-7549889
2
103 | P a g e
shuttering. In the context of concrete construction, the falsework supports the shuttering
molds for example column sides, beam sides, slab side, wall side etc.
So, By their definitions, scaffolds are for supporting labor and materials and act as
working platforms. Formwork (Shuttering) acts as molds for pouring concrete.
CENTERING:
Part of the formwork which supports the horizontal surface is called centering for
example slab bottom, beam bottom etc.
STAGING:
That portion which supports centering & shuttering is called Staging. This can be:
1. Wooden Ballies
10
SAQIB IMRAN 0341-7549889
3
104 | P a g e
2. Pipes/Props/Jacks
3. H frames
4. Space frames using Coupler / Cup-Lock system
1. PLASTER OF PARIS:
It is also known as calcium sulfate plaster and obtained by heating gypsum. When water
is added to the plaster of paris it forms a plastic mass, which sets quickly.
Plaster of paris adheres well to gypsum, wood, metal lath, masonry or other plastering
surfaces. The setting time of the plaster of Paris can be controlled by the addition of
certain salts. It is mostly used in combination with ordinary lime for making good small
defects in plastered surfaces. Since gypsum is slightly soluble in water, plaster of paris
is not used for external works.
10
SAQIB IMRAN 0341-7549889
4
105 | P a g e
2. KEENE’S CEMENT:
This is hardest and densest form of gypsum plaster. It is obtained by a calcining
selected form of gypsum. It is pure white in color and takes a high glass-like polish. It is
used for highly decorative plastering work and ornamental work. It is used alone for an
extra hard finish or it is mixed with lime putty for a medium hard finish.
3. BARIUM PLASTER:
This is essentially made from barium sulfate and is applied in the form of final coat to
serve as a protection around X-ray rooms.
4. ACOUSTICAL PLASTER:
This is gypsum mixture, which is employed as a final coat to serve the purpose of a
sound-repellent finish. The minute passages in the form of tiny openings in the plaster
coat, absorb sound. The plaster is usually applied in two coats, each 6 mm in thickness.
The surface must be finished uniformly in a manner that promotes porosity. Wooden
floats preferred to a steel trowel in finishing.
Other Plastering Materials:
1. Waterproof plaster.
2. Stucco plaster.
3. Martin’s cement.
4. Parian cement.
5. Sirapite.
6. Scagliola.
7. Asbestos marble plaster.
8. Snowcrete and colorcrete cement.
WATERPROOF CEMENT
10
SAQIB IMRAN 0341-7549889
5
106 | P a g e
WATERPROOF CEMENT:
1. To decide suitable arrangement of beams, columns, foundations etc. for the structure
on the layout plan.
2. To determine all types of loads and forces to which the structure is likely to be
subjected to.
3. To analyze the structure and to calculate, stresses, moments and shears etc. in the
members.
10
SAQIB IMRAN 0341-7549889
6
107 | P a g e
4. To work out safe section and area of steel for different members.
5. To provide the calculated area for tensile, compressive, shear or temperature
reinforcement in right positions so as to ensure that the stresses remain within
permissible limits.
6. To provide sufficient anchorage for all reinforcement, so that the anchorage and bond
requirements are fully met.
1. HEADER:
It is a full brick or stone which is laid with its length perpendicular to the face of the wall.
2. STRETCHER:
It is a full brick or stone in which is laid its length parallel to the face of the wall.
3. BOND:
It is a term applied to the overlapping of bricks or stones in a wall in alternate courses,
to bind the whole wall together.
4. COURSE:
A horizontal layer of bricks or stones is termed as course.
5. HEADER COURSE:
It is a course of brickwork entirely composed of headers.
6. STRETCHER COURSE:
It is a course of brickwork in which all the bricks are laid as stretchers.
7. BED:
It is a term used to indicate the lower surface of bricks or stones in each course. It may
also be termed as surface of the bricks on which it rests.
8. FACE:
The surface of a wall exposed to weather is termed as face.
9. FACING:
The material used in the face of the wall is known as facing.
10
SAQIB IMRAN 0341-7549889
7
108 | P a g e
10. BACK:
The inner surface of the wall which is not exposed to the weather is termed as back.
11. BACKING:
The material used in forming the back of the wall is known as backing.
12. HEARTING:
The portion of a wall between facing and backing is termed as hearting.
13. JOINT:
The junction of two or more bricks or stones is called joint.
15. BAT:
It is a portion of a brick cut across the width or a brick cut by some fraction of its length.
16. CLOSER:
It is a portion of a brick cut in such a manner that its one long face remains uncut.
10
SAQIB IMRAN 0341-7549889
8
109 | P a g e
21. PERPEND:
It is a vertical joint on the face of a wall directly over vertical joints in an alternate
course.
22. FROG:
It is a depression on the top face of a brick. Frog provides a recess for the mortar which
on setting forms a key and prevents the displacement of the brick above.
23. PLINTH:
The horizontal projecting or flush course of stone or brick provided at the base of the
wall above ground level is known as plinth.
24. SILL:
It is a horizontal member of brick, stone, concrete or wood provided to give support for
the vertical members of a window.
25. JAMBS:
The vertical sides of a finished opening for door, window or fire place etc. are termed as
jambs.
26. REVEALS:
Reveals are the exposed vertical surfaces left on the sides of an opening after the door
or window frame has been fitted in position.
27. LINTEL:
A horizontal member of stone, brick, steel or RCC, used to support the masonry or load
above an opening.
28. ARCH:
A mechanical arrangement of wedge-shaped blocks of stone or brick arranged in the
form of a curve supporting the masonry or load above an opening.
29. CORNICE:
It is a horizontal moulded projection provided near the top of a building or at the junction
of a wall and ceiling.
30. PARAPET:
It is a term applied to a low wall built around a flat roof to act as a protective solid
balustrade for the users of the terrace.
10
SAQIB IMRAN 0341-7549889
9
110 | P a g e
31. WEATHERING:
Weathering is the term applied to the bevelled top surface of a stone.
32. GABLE:
It is a triangular shaped portion of masonry at the end of a sloped roof.
33. SPALLS:
Chips or small pieces of stone broken off a large block are termed as spalls.
34. COLUMNS:
It is an isolated vertical load bearing member whose width does not exceed four times
its thickness.
35. PIER:
It is a vertical member of stone or brick masonry constructed to support an arch, beam
or lintel etc.
36. BUTTRESS:
It is similar to pier built on the exterior of a wall properly bonded to it.
37. CORBEL:
It is the extension of one or more course of brick or stone from the face of a wall.
38. THRESHOLDS:
The arrangement of steps provided from ground level to reach plinth level on external
doors and verandah is termed as thresholds.
DEFECTS IN PLASTERING
The common defects in plaster works are listed below
11
SAQIB IMRAN 0341-7549889
0
111 | P a g e
1. CRACKING:
2. BLOWING OR BLISTERING:
This consists in formation of small patches of plaster swelling out beyond the plastered
surface.
11
SAQIB IMRAN 0341-7549889
1
112 | P a g e
4. EFFLORESCENCE:
A deposit of soluble salts in the form of whitish crystalline substance appears on the
surface or background of the plaster.
11
SAQIB IMRAN 0341-7549889
2
113 | P a g e
5. CRAZING:
6. GRINNING:
In this formation, a pattern of joints or similar breaks in the continuity of the surface is
found.
COMPONENTS OF A BUILDING
COMPONENTS OF A BUILDING:
A building can be divided into two general categories
1. SUB-STRUCTURE:
It is the portion of a building situated underneath the surrounding ground.
11
SAQIB IMRAN 0341-7549889
3
114 | P a g e
2. SUPERSTRUCTURE:
The portion which is situated above the ground level is called superstructure.
The components of a building can be further classified as under:
1. FOUNDATION:
Foundation is the lowest part of a structure below the ground level which transfers all
the loads (dead load, live load etc) to the soil.
2. PLINTH:
The Portion of a building between the ground surrounding the building and the top floor
just above the ground is termed as plinth. Plinth is provided to prevent the surface water
from entering the building.
3. DPC:
DPC or damp proof course is a layer of waterproofing materials like asphalt, bitumen,
waterproof cement etc on which the walls are constructed.
4. WALLS:
Walls are the vertical members on which the roof finally rests. Walls are provided to
divide the floor space in the desired pattern. Walls provide privacy, security, and
protects from the sun, rain wind, cold etc.
5. COLUMN:
Columns are the isolated load bearing member which carry the axial compressive load
of a structure.
6. FLOORS:
Floors can be defined as flat supporting elements dividing a building into different levels
( e.g first floor, second floor etc) to create more accommodation on a given land. They
provide a firm and dry platform for people and other items like furniture, equipment,
stores etc.
11
SAQIB IMRAN 0341-7549889
4
115 | P a g e
8. STAIRS:
Stairs can be defined as a structure comprising a number of steps arranged in a series
connecting one floor to another. Stairs are used to access various floors of the building.
9. ROOF:
A roof is the topmost part of a building which covers the space below and protects from
rain, direct sunlight, snow, the wind etc.
11
SAQIB IMRAN 0341-7549889
5
116 | P a g e
dead and live loads. The types of formwork totally depend on the material of formwork
and the structural elements.
Formworks are generally three types:
1. Beam Formwork: Used in beams.
2. Slab Formwork: Used in slabs.
3. Column Formwork: Used in columns.
The checklists for before and after shuttering are as following:
1. The material of shuttering is new/old?
2. Are repairs Ok?
3. Cleanness of shuttering is Ok?
4. Oiling of shuttering?
FIXED SHUTTERING:
5. The design of shuttering is Ok?
6. Rigidity, levelling, and allignment Ok?
7. Check the props. Ok?
8. Check the acrow span. Ok?
9. Check the braces. Ok?
10. Check the holes, sealing joints. Ok?
11. Check for any changes or rework.
11
SAQIB IMRAN 0341-7549889
7
118 | P a g e
6. The site should not be located near kilns, quarries, industrial plants emitting smoke,
steam, fumes and obnoxious odour, noise or other polluting agents. The site should be
far away from them.
7. Natural light and air should be sufficient in the site and the building should not get
overshadowed by the adjacent buildings.
8. The site should not be very much undulating.
TYPES OF FLOORING
11
SAQIB IMRAN 0341-7549889
8
119 | P a g e
TYPES OF FLOORING:
There are several types of floors which are mostly adopted by the public as well as
residential buildings nowadays. But there is not a single type of floor that could be used
under all circumstances because each floor has its own merits in specific
circumstances. The various types of floors which are most commonly adopted for
construction of ground floor are listed below.
1. Terrazzo flooring.
2. Mud flooring.
3. Brick flooring.
4. Cement concrete flooring.
5. Tiled flooring.
6. Mosaic flooring.
7. Marble flooring.
8. Asphalt flooring.
9. Flagstone flooring.
10. Rubber flooring.
11. Timber flooring.
12. Acidproof flooring.
13. Granolithic flooring.
14. Muram flooring.
15. Linoleum flooring.
Due to their different advantages in different conditions, it becomes very hard to select
the type of floor and as such the following points should be kept in view while selecting
the type of floor.
1. The floor should be strong and durable,
2. It should be easy to clean.
3. It should possess pleasing appearance.
4. It should be free from dampness.
5. It should be noiseless as far as possible.
11
SAQIB IMRAN 0341-7549889
9
120 | P a g e
12
SAQIB IMRAN 0341-7549889
0
121 | P a g e
9. In modern sky scraper construction always framed structures are adopted, for such
structures R.C.C stairs are the one and only stairs which can be used.
Due to the lower compressive strength of bricks (For 1:2:4 cement concrete works), the
width of load bearing walls for the building having more than four story becomes
extremely thick and for such cases, RCC framed structures are suitably adopted.
Framed structures are generally of two types.
1. Steel Frame
2. RCC Frame.
In this article, we will discuss various advantages of RCC framed structure which are as
following:
1. In RCC framed structure building the floor area is normally 10% to 12 % greater
compared to a load bearing walled building. hence, this type of building is preferably
economical where the value of land is very high.
2. It is very easy to alternate the interior plan of a room, bathroom, W.C etc by changing
the actual position of the partition walls which ultimately gives more freedom in
planning.
12
SAQIB IMRAN 0341-7549889
1
122 | P a g e
3. Monolithic construction can be adopted for resisting shocks and vibrations more
effectively than load bearing walled buildings.
4. Normal earthquake effects can also be resisted by providing required further design.
5. Faster construction work saves time, early finishing.
6. No matter the soil is soft or hard, RCC framed buildings can be established
anywhere.
7. Maintenance cost is also minimum which can be ignored.
12
SAQIB IMRAN 0341-7549889
2
123 | P a g e
12
SAQIB IMRAN 0341-7549889
3
124 | P a g e
Manufactured Sand
Manufactured sand or M-Sand is a replacement of natural river sand made artificially
from hard granite stone by crushing. M-sand is cubical in shape and edges are rounded.
After crushing, the sand is clearly washed and graded properly for using as construction
material. Generally, the size of M-sand is less than 4.75 mm.
M-sand is gaining its popularity and uses over vast construction works due to several
advantages which are described below.
ADVANTAGES OF M-SAND:
1. Manufactured sand is graded very well at their right proportion.
2. Organic and soluble compounds are eliminated which can affect the properties and
setting time.
3. In this sand no impurities are available such ads dust, clay, silt coatings etc requires
more water as on account of river sand which makes weaker the cement-aggregate
bond. Therefore the quality and durability of concrete are increased.
4. M-Sand is produced from granite using latest techniques which ensure their required
properties. Here high carbon steel hit rock and then Rock On Rock technology is used
which is also similar to the natural process of river sand formation.
5. Modern and imported machines are used to manufacture M-Sand which gives cubical
shape and confirms their proper gradings.
12
SAQIB IMRAN 0341-7549889
4
125 | P a g e
WEIR:
BARRAGE:
When adjustable gates are installed in a weir to keep up the surface the water at a
diverse level at various time, is called barrage.
In this system, the water level is balanced by operating the shutters or gates. The gates
are provided at different levels and operated by cables from a cabin. These gates are
supported on piers at both ends. The pier to pier distance is called bay.
4. The concrete should be prepared in the quantitive ratio of 1:2:4 (Cement: Sand:
Stone chips 12 mm).
5. The concrete used in the DPC should be workable.
6. The concrete should be placed and tempered roughly to make a thick mass.
7. After laying the concrete of 24 hours, it should be cured minimum for 7 days.
8. After completing the curing properly, the surface should be left to dry out to get the
cover of hot bitumen.
9. After drying the concrete surface, it should be cleaned with brushes and with a
kerosine soaked cloth piece.
10. Finally, the treated concrete surface should be filled uniformly with hot bitumen in
specified quantity.
1. FINISHING:
Just in case of ordinary and low-cost construction the rooftop surface should be finished
by cement mortar ideally in the quantitive proportion of 1:4. To face up to the shrinkage
12
SAQIB IMRAN 0341-7549889
6
127 | P a g e
and extensive impacts of cement concrete or mortar, lime cream may be included in the
finishing layer of concrete or mortar.
2. ASPHALT LAYER:
In this process, a mastic layer of asphalt is provided on the roof floor earlier than the
mud or lime concrete is being placed. Sometimes, asphalt layer is additionally laid on
highly finished roof surface that is later sanded and properly finished.
12
SAQIB IMRAN 0341-7549889
7
128 | P a g e
Construction Equipment
Every construction project involves different work process such as earth cutting, earth
moving, hauling, concreting equipment, equipment for compaction and different
construction materials etc. In case of small projects, manual labor with ordinary
instruments are used. But when it is a large project we must need heavy construction
equipment to finish the work comfortably. Here in this article equipment commonly used
for heavy construction are given.
1. Tractor.
2. Bulldozer.
3. Grader.
12
SAQIB IMRAN 0341-7549889
8
129 | P a g e
4. Scraper.
5. Basic shovel.
6. Drag Line.
7. Clam Shell.
8. Power Shovel.
9. Back Hoe.
10. Dumper Trucks.
11. Road roller.
12. Sheep’s Root Roller.
13. Electric Over Head Crane.
14. Whirler Crane.
15. Single Cable Rope Way.
16. Belt Conveyor.
17. Concrete Mixer.
18. Pumpcrete.
19. Concrete Vibrator.
20. Crusher Machine.
21. Paver.
22. Excavator.
23. Reach Truck etc.
12
SAQIB IMRAN 0341-7549889
9
130 | P a g e
13
SAQIB IMRAN 0341-7549889
0
131 | P a g e
13
SAQIB IMRAN 0341-7549889
2
133 | P a g e
2. STEEL PIPES:
Steel pipes are utilized in water mains circumstances where the pipes are going through
very high pressure ( More than 7 kg/cm2) and required large diameter pipes. These
pipes have greater strength and less weight than CI pipes. Satisfactory treatments
should be given to maintain antagonistic climatic conditions.
4. COPPER PIPES:
Copper pipes are most commonly utilized in hot water supply establishment. Some
features of this pipes are as following:
1. They possess high tensile strength.
2. They can be bent easily.
3. Copper pipes can be used in thin wall.
Copper pipes are sometimes chromium plated to enhance their appearance and to
match with the chromium plated water supply fittings.
5. POLYTHENE PIPES:
Polythene and PVC pipes are being utilized progressively nowadays for cold water
supply inside and outside works. These pipes are lightweight, cheaper, corrosion
resistant, and require no threading for making any connections.
Besides these, there are other pipes commonly used for water distribution such as
asbestos cement (AC) pipes, reinforced concrete (RCC) pipes, prestressed reinforced
concrete (PSC) pipes etc. The selection of the types of pipe for utilizing any purposes is
adopted according to the design criteria, material availability, cost, and other
comparative variables.
13
SAQIB IMRAN 0341-7549889
3
134 | P a g e
Precast Piles
The various advantages and disadvantages of precast piles are described below:
PIER FOUNDATION
13
SAQIB IMRAN 0341-7549889
4
135 | P a g e
PIER FOUNDATION:
When a heavy structure or building is to be constructed in soft or sandy soil and hard
bed stratum for the foundation is situated at the reasonable depth pier foundation is
suitably provided for transmitting the load into strong stratum.
In this method, vertical shafts are made upto hard bed and then filled with freshly mixed
concrete. Thus concrete piers rest on the hard stratum and transfer the load of the
structure into it,
The diameter and center to center to spacing of shafts mainly depends upon the
character of soil, depth at which the hard stratum is located, condition of loading etc,
The diameter of the shaft (In case of square or rectangular pier) should be less than
1/12 th of its height. Sometimes the shaft may be lined with timber to prevent thee side
earth sliding. The timber lining is eliminated after filling the shaft with concrete.
Generally, reinforce concrete, or grillage cap or concrete arch is used to connect the
shafts with each other. The arrangement of pier foundation is shown in the following
figure.
13
SAQIB IMRAN 0341-7549889
5
136 | P a g e
BRICK TESTS:
Bricks are the most common and useful building materials used for masonry
construction works. To build a long lasting structure we should always use good quality
bricks and other building materials. In our previous article, we have already discussed
the types of bricks used in construction. Today we will discuss some important brick
tests to determine the quality of bricks. The common brick tests performed on the field
as well as in the laboratory are described below.
13
SAQIB IMRAN 0341-7549889
6
137 | P a g e
condition is considered as the water absorbed by the bricks. Then the amount of water
absorption is determined in percentage.
Water absorption (%) = [(W2-W1)/W1] * 100
The less water consumption by the bricks indicates their greater quality. A brick will be
considered as good quality if it does not consume more than 20% water of its own
weight.
3. EFFLORESCENCE TEST:
This test is carried out to obtain the presence of alkaline substances in bricks. First,
bricks are fully submerged in fresh water for 24 hours. After 24 hours they are collected
from water and left them to dry. After completely dried the bricks are closely observed to
find the presence of alkali. If a white or gray layer is formed on the brick surface, it
means alkali is present in the brick.
Observation Efflorescence
No Deposition Nil
13
SAQIB IMRAN 0341-7549889
7
138 | P a g e
4. IMPACT TEST:
In this test few bricks are dropped from 1-meter height. If bricks are broken it indicates
low impact value and not acceptable for construction work. Good quality bricks do not
break at all.
6. SOUNDNESS TEST:
In this test, two randomly selected bricks are hardly punched with each other. If they
produce a clear metallic sound and remain unbroken then they are good quality bricks.
7. HARDNESS TEST:
This test is done to know the hardness of bricks. In this test, scratches are made on the
surface of the brick by a hard thing. If it does not leave any impression on the brick
surface then it will be considered as good quality bricks.
13
SAQIB IMRAN 0341-7549889
8
139 | P a g e
8. STRUCTURE TEST:
In this test, a brick is fractured and firmly investigated. If any flaws, holes or cracks are
seen inside the broken brick, then it is considered as poor quality brick.
ENGLISH BOND:
13
SAQIB IMRAN 0341-7549889
9
140 | P a g e
9. The quantity of joint in header course is about twice than that in stretcher course. So,
header joints ought to be kept as thin as possible to maintain appropriate lapping over
joints. (immediately below the course)
FLEMISH BOND:
Primary elements of flemish bond are as following:
14
SAQIB IMRAN 0341-7549889
0
141 | P a g e
It is a combination of english bond and flemish bond. Facing of the wall is developed by
using flemish bond and backing is developed by using english bond. This type of bond
can not be used in walls less than one and a half brick thickness. However, this bond
gives better and attractive looks.
In this brick bond, each course demonstrates the same appearance both in the front as
well as back elevations (headers and stretchers are laid in every course alternatively).
Alternate headers and stretchers are used in every course. This bond enables one brick
wall to have flush and uniform faces on the both sides. It gives better appearance but
comparatively weaker than english bond.
STRETCHER BOND:
Stretcher bond is the simplest form of brick bond utilized for construction works.
Sometimes it is also known as running bond. In the arrangement of stretcher bond, all
the bricks are laid as stretchers (as shown in fig). No header is present in this bond,
14
SAQIB IMRAN 0341-7549889
1
142 | P a g e
HEADER BOND:
In this pattern of bonding all the bricks are placed as header on the faces (as shown in
fig). This bond is also known as heading bond.The overlap is half the width of the brick
and can be achieved by providing a three-quarter bat in each alternate course at
quoins. Header bond can be used in the construction of curved structure, brick
foundation etc.
Other Brick Bonds:
1. Facing Bond.
2. Garden Wall Bond.
3. Raking Bond.
4. Dutch Bond.
5. English Cross Bond.
6. Zig-zag bond.
7. Silverlock’s Bond.
14
SAQIB IMRAN 0341-7549889
2
143 | P a g e
14
SAQIB IMRAN 0341-7549889
3
144 | P a g e
4. Make sure that one carpenter and one helper is always present under the shuttering
slab to confirm that it is supported well and will stay constant during and after
concreting.
5. Assure the presence of a bar bender to avoid displacement of steel reinforcement.
6. Never permit extremely smooth finishing for the concrete slabs.
7. Try not to permit sprinkling of dry cement during finishing, It will help to prevent micro
shrinkage cracks in the concrete.
8. Put the chairs appropriately to avoid disturbance at the top reinforcement bars during
concreting.
9. Try to prevent cold joints in the casting slab.
10. In case of concreting in hot weather, protect the concrete surface by covering with
wet gunny bags at least for 4 – 5 hours.
11. In case of concreting in rainy, windy, or extremely hot weather, put a cover of
tarpaulin over the slab. It will protect the slab from getting damaged.
12. To prevent plastic shrinkage cracks in the concrete slab, avoid drastic drying of
green concrete.
13. Ensure full compaction and complete finishing of the concrete.
14
SAQIB IMRAN 0341-7549889
4
145 | P a g e
TYPES OF BRICKS
14
SAQIB IMRAN 0341-7549889
5
146 | P a g e
TYPES OF BRICKS:
types of bricks
Bricks are one of the most useful building materials used in construction works. It is
important to know the types of bricks for understanding the masonry work properly. The
types of bricks depend on their quality, strength, making process, motivation behind
their utilizing etc. In this article, we will discuss types of bricks used for different criteria.
Bricks are mainly classified into two general categories.
1. Unburnt Bricks & 2. Burnt Bricks.
UNBURNT BRICKS:
Unburnt bricks are also known as sun-dried bricks because they are dried by the heat
coming from the sun. Nowadays these bricks are not used in construction due to their
lower strength but if required they can be used for constructing temporary structures.
BURNT BRICKS:
This types of bricks are made by burning in the kilns. Depending upon the quality burnt
bricks can further be classified into 3 categories which are as following:
1. Type 1. Class 1
14
SAQIB IMRAN 0341-7549889
6
147 | P a g e
1. Type 1. Class 2
14
SAQIB IMRAN 0341-7549889
7
148 | P a g e
1. Type 1. Class 3
14
SAQIB IMRAN 0341-7549889
8
149 | P a g e
14
SAQIB IMRAN 0341-7549889
9
150 | P a g e
RAFT FOUNDATION:
Raft foundation is a type of shallow foundation that is made with dense reinforced
concrete slab covering the total area of the bottom of a structure. Sometimes the slabs
are used at the bottom and the beams at the top. This foundation is mostly suitable for
constructing heavy structures on soft made ground or marshy sites having a low bearing
capacity.
Raft foundation is also provided in the mining area where the structure is liable to fail
due to uncertain behaviour. It gives an economical solution to difficult site conditions
when pile foundation can not be used. This foundation sometimes is also known as mat
foundation because the RCC slab covers the whole area of a structure like a mat.
METHOD OF CONSTRUCTION:
The raft slab is projected at a distance of 30 cm to 40 cm on every side of the outer
walls of a structure. Thus the area of excavation becomes slightly greater than the area
15
SAQIB IMRAN 0341-7549889
0
151 | P a g e
of the structure. The entire area is then excavated to its required depth and
consolidated. When the surface becomes dry it gives a strong base on which the raft
slab is established.
All the necessary precautions should be taken during the construction of RCC
structures. Further construction should be started after the curing of the raft.
1. Raft foundation can be suitably used in difficult site conditions. It is mostly preferred
for the erratic, soft and marshy sites. It bridges the erratic deposits and reduces the
differential settlement.
2. The intensity of pressure on the foundation soil is considerably decreased due to
the distribution of total load over a large area.
3. The load is uniformly distributed on the entire foundation area.
15
SAQIB IMRAN 0341-7549889
1
152 | P a g e
Formwork is a temporary but rigid structure in which the cast in situ concrete is laid for
casting the members to required shape. It is also known as centering or shuttering.
Formwork is placed at its right position before pouring the fresh concrete in it. Poured
concrete is then compacted and permitted to solidify to gain strength. The formwork is
permitted to stay in position till the concrete achieve enough strength to resist the
stresses coming on it without the assistance of the formwork. After this, the formwork is
removed.
The formwork is permitted to stay in position till the concrete achieve enough strength to
resist the stresses coming on it without the assistance of the formwork. After this, the
formwork is removed.
A good formwork should satisfy the following requirements:
1. It should be adequately strong to withstand an extensive variety of dead and live
loads. For instance, self-weight, weight of reinforcement, weight of wet concrete, loads
of workers, and any other loads during and after casting of concrete.
2. It should be inflexibly built and efficiently propped and supported to hold its shape
without undue deflection.
3. The joints in the formwork should be tight enough to prevent leakage of cement grout.
4. The formwork should be created in such a way that it may allow the evacuation of
different parts in the desired sequence without shaking or damaging the concrete.
5. The material of the formwork should be inexpensive, easily accessible and can be
reused for several times.
6. The surface of the formwork should be plain and smooth, and set properly to the
desired line and level.
7. The material of the formwork should not bend or get perverted in presence of sun,
rain or water at the time of concreting.
15
SAQIB IMRAN 0341-7549889
2
153 | P a g e
8. It should be lightweight.
9. It should be easy to remove.
Fasteners are the smallest part of a structure. Bolts and screws are the most commonly
used as fasteners for joining of materials. In this article, we will discuss the differences
between bolt vs screw.
In this article, we will discuss the differences between bolt vs screw.
Bolt Screw
1. Bolt has an external thread at the 1. Screw has no external thread except
lower end. one head.
2. Bolts are always assembled with 2. Screws are always used by itself.
nuts.
15
SAQIB IMRAN 0341-7549889
3
154 | P a g e
5. The threads are spiral in shape. 5. The threads are helical in shape.
6. Holes are required for inserting the 6. Usually, screws are inserted without
bolts. any holes.
7. Bolts are always fixed at a single 7. It requires being turned every time
position and do not need to be to be joined or to be removed.
turned.
10. The structure that is joined with 10. It gives less strength than the bolt.
bolts possesses a greater strength.
15
SAQIB IMRAN 0341-7549889
4
155 | P a g e
As the name suggest, precast concrete is prepared by casting and curing the concrete
in a mold under specific circumstances. The concrete is totally manufactured in a
factory by adopting special construction techniques. When the concrete is fully
hardened and prepared, it is sent to the final construction site. Precast concrete
construction has become very popular in some countries like the USA, UK etc. The
advantages and disadvantages of this type of concrete are given below:
15
SAQIB IMRAN 0341-7549889
5
156 | P a g e
15
SAQIB IMRAN 0341-7549889
6
157 | P a g e
During the time of concreting the tremie is continuously lifted keeping the lower end of
the tube in the concrete that is already poured. To reduce the extra loss of cement
under water, rich concrete mix should be always used. Thus concrete laid underwater
should never be compacted or consolidated.
TYPES OF SCAFFOLDING
TYPES OF SCAFFOLDING IN BUILDING CONSTRUCTION:
Scaffolding is a temporary rigid structure having still, bamboo or timber platforms raised
up with increasing the building height. It enables the mason work at different stages of a
15
SAQIB IMRAN 0341-7549889
7
158 | P a g e
building and takes up the materials for the immediate use at various heights. Different
types of scaffolding are used depending upon the types of construction.
TYPES OF SCAFFOLDING:
Different types of scaffolding are described below:
1. Brick layer’s scaffolding,
2. Mason’s scaffolding,
15
SAQIB IMRAN 0341-7549889
8
159 | P a g e
2. MASON’S SCAFFOLDING:
Since it is difficult to leave holes in the stone masonry to provide a bearing for the
putlogs, in mason’s scaffolding two frames of standards, at a distance of 1.5 m from the
first one. Thus the mason’s scaffolding is entirely independent of the stone wall.
Close mason’s scaffolding: They are supposed to carry loads of heavy blocks of
stones and the stresses produced on account of the lifting device and hence they are
made stronger by placing the standards at a fairly close distance apart.
3. STEEL SCAFFOLDING:
The construction of steel scaffolding is essentially similar to that of timber scaffolding. In
this case, the wooden members are replaced by 38 mm to 64 mm diameter steel tubes
and instead of rope-lashings, special types of steel couplets or fittings are used for
connecting different members.
The steel tubes used for scaffolding for normal building construction work are heavy
class and of diameter varying from 40 to 60 mm.
In this type of scaffolding, the vertical tubes called uprights or standards are spaced 2.5
to 3 m apart. Each standard is welded to a base plate, square or circular in plan. The
base plate has holes so that it can be spiked to a timber or concrete base, thus forming
a rigid foundation for the scaffolding. Ledgers or the longitudinal tubes connecting the
standard and are spaced at 1.8 m vertically apart. Short tubes or put logs are normally
1.2 m to 1.8 m in length. The putlogs have special ends to fit into the joints in the wall
and thus no big holes are required to be left on the wall for their bearing.
Tubular scaffolding has several advantages over the timber scaffolding such as rapid
erection and dismantling, greater strength and durability, higher fire resisting qualities
and salvage value. Although it works out to be costlier initially, but considering its
several advantages and the increased number of reuses, it proves to be economical in
the long run and hence it is being extensively used these days.
15
SAQIB IMRAN 0341-7549889
9
160 | P a g e
Tubular scaffolding mounted on wheels can be used for carrying out the work of
painting the walls, underside roofs etc.
4. NEEDLE SCAFFOLDING:
When scaffolding is to provide for a building on the side of a busy street where the
construction of ordinary scaffolding will obstruct the traffic on road, needle scaffold is
used. The scaffold is erected from window corners of string courses by means of
projecting needles. A needle is a timber beam which cantilevers out through the holes
cut in the wall. From inside the needles are supported on sole pieces and are prevented
from lifting up by vertical struts wedged between the needles and the headpieces. The
projected end of the needle is supported by an inclined strut which rests on the window
sill. The joint between the raking or inclined strut and the needle is clamped by mean of
dogs. The arrangement provides the staging for the erection of ordinary type of
scaffolding.
English bond is considered as the strongest and most widely used brick bond in
construction work. It consists of alternate course of headers and stretchers.
In this arrangement, vertical joints in the header and stretcher courses come over each
other. To break the vertical joints in the consecutive courses queen closer should be
placed after the first header in every header course.
FLEMISH BOND:
In this brick bond, each course consists of alternate headers and stretchers. Every
header is centrally supported over the stretchers below it. To break the vertical joints in
the successive courses queen closers are placed in alternate courses next to the queen
header. Bats are essentially required for the walls having their thickness equal to odd
numbers of half bricks. Flemish bond gives better appearance than english bond.
16
SAQIB IMRAN 0341-7549889
0
161 | P a g e
Flemish Bonds
1. English bond is much stronger than flemish bond for the walls thicker more than 1½
brick.
2. Flemish bond shows more attractive and pleasing appearance of masonry work.
3. Flemish bond is economical as it uses broken brick bats, although it requires some
extra mortar for additional joints.
4. Uses of flemish bond is a bit difficult than english bond. Flemish bond requires more
skilled labour and supervision.
CLASSIFICATION OF STAIRS
TYPES OF STAIRS:
Depending upon the various arrangement of steps, stairs can be classified under
following categories:
16
SAQIB IMRAN 0341-7549889
1
162 | P a g e
1. STRAIGHT STAIR:
In this stair, all the steps are arranged continuously along in one direction. One flight
may be split into one or more than one flight by interposing a landing. This stair can be
used where narrow and long space is available for a staircase such as entrance, porch
etc.
2. DOGGED-LEGGED STAIR:
This stair consists of two straight flights of steps with direct turns between them. This
stair is very useful where the total width of the stair is just twice the width of the steps.
16
SAQIB IMRAN 0341-7549889
2
163 | P a g e
This type of stair consists of two or more flights arranging a well or opening between the
backward and forward flights. When all the steps are difficult to arrange in two flights, a
short third flight of 3 to 6 steps may be provided along the direction perpendicular to the
hall. Open newel stair is mostly adopted in the lift.
4. GEOMETRICAL STAIR:
This is another type of open newel stair where the open well between the forward and
the backward flight is curved. This stair may contain different geometrical shape. Here
the change in direction is achieved by using winders.
16
SAQIB IMRAN 0341-7549889
3
164 | P a g e
5. CIRCULAR STAIR:
In this type of stair, all the steps radiate from a newel or well hole, in the form of
winders. The circular stair is adopted at the back side of a building to access its various
floors.
6. SPIRAL STAIR:
Spiral stair is very similar to a circular stair. It consists of individual steps or treads,
connecting to a centre column. The overall diameter of the stair may range from 1 to 2.5
m.
16
SAQIB IMRAN 0341-7549889
4
165 | P a g e
7. QUARTER-TURN STAIR:
The quarter-turn stair can be defined as the stairs that are turned at 90 degrees with the
help of level landing.
8. BIFURCATED STAIR:
This type of stair is provided in modern public buildings as well as residential buildings.
In this stair, the flight is so arranged that there is a wide flight at the start which is sub-
divided into narrow flights at the mid-landing. The narrow flights start from either side of
the mid landing.
16
SAQIB IMRAN 0341-7549889
5
166 | P a g e
ADMIXTURES:
Admixtures are the special ingredients added during concrete mixing to enhance the
properties and performance of fresh concrete. Various types of admixtures are available
in the market which is used in construction work.
FUNCTION OF ADMIXTURES:
1. To accelerate or retard the setting time of fresh concrete.
2. To improve the workability or flowability of concrete.
3. To increase the strength and durability of concrete.
4. To reduce the heat of hydration.
5. To reduce the segregation and bleeding.
6. To decrease the permeability.
7. To achieve other desired properties.
TYPES OF ADMIXTURES:
1. ACCELERATING ADMIXTURES:
This admixture is added in concrete or mortar for increasing the rate of hydration of
hydraulic cement and for shortening the setting time. Calcium chloride (CaCl2) is the
most widely used accelerating admixture.
2. RETARDING ADMIXTURES:
Retarding admixtures delay the initial rate of hydration of cement and extend the setting
time of cement paste. This admixture can be used in high temperature and where the
concrete has to be transported to a long distance. It is also suitable for using in grouting
oil wells.
3. AIR-ENTRAINING ADMIXTURES:
Air entraining admixtures help to produce a certain amount of air bubbles in the
concrete mixture. The main goal of this admixture is to increase the resistance against
freeze-thaw degradation and cohesion. It also improves the workability of fresh concrete
without changing the setting or the rate of hardening.
16
SAQIB IMRAN 0341-7549889
6
167 | P a g e
SPECIAL ADMIXTURES:
1. Superplasticizing admixtures.
2. Corrosion-inhibiting admixtures.
3. Grouting admixtures.
4. Coloring admixtures etc.
TYPES OF FOUNDATION
FOUNDATION:
Foundation is the lowest portion of a structure which transmits the load into the
supporting soil. The main purpose of the foundation is to distribute the total weight of
the superstructure over a large area of soil. Various types of foundation are described
below which are used in construction.
TYPES OF FOUNDATION:
Foundation can be classified into two general categories:
1. Shallow Foundation.
2. Deep Foundation.
16
SAQIB IMRAN 0341-7549889
7
168 | P a g e
1. SHALLOW FOUNDATION:
A Shallow foundation is a type of foundation in which the foundation is situated instantly
below the lowest part of a structure. The depth of foundation is equal or less than its
width.
In this foundation, the total loads of the structure are distributed over a horizontal area
at shallow depth below the ground level.
SPREAD FOOTINGS:
Generally, spread footing consists of a wide base of foundation for transmitting the load
to the soil over a wider area.
COMBINED FOOTINGS:
Combined footing consists of a common footing provided to two columns which may be
either rectangular or trapezoidal.
Strap Footing.
Strip Footing.
RAFT FOUNDATION:
Raft foundation consists of dense reinforced concrete slab which covers the total bottom
area of the structure. It is provided in the soil with low bearing capacity where structural
loads are heavy.
16
SAQIB IMRAN 0341-7549889
8
169 | P a g e
2. DEEP FOUNDATION:
A deep foundation is a type of foundation in which the foundation is placed at a deeper
depth below the ground level. The depth of foundation is much greater than its width.
1. Pile Foundation.
2. Cofferdams.
3. Caisson Foundation.
PILE FOUNDATION:
Pile foundation is a type of foundation where a slender member of wood or concrete or
steel is inserted into the ground for transferring the load of a structure. The load is
transferred to a stronger stratum by friction or by bearing.
Classification Of Pile Foundation:
Classification Based On function:
1. Bearing Piles.
2. Friction Piles.
3. Sheet piles.
4. Anchor Piles.
5. Batter Piles.
6. Fender Piles.
7. Compaction Piles.
1. Timber piles.
2. Concrete Piles.
3. Steel Piles.
16
SAQIB IMRAN 0341-7549889
9
170 | P a g e
COFFERDAMS:
A Cofferdam is a temporary structure which excludes the water from a given site to
enable the construction on a dry surface.
Classification Of Cofferdams Based On Material:
1. Earthen Cofferdam.
2. Rock-fill Cofferdam.
3. Single-walled cofferdam.
4. Double-walled cofferdam.
5. Crib Cofferdam.
6. Cellular Cofferdam.
CAISSON FOUNDATION:
1. Open Caisson.
2. Box Caisson.
3. Pneumatic Caisson.
AIR CIRCULATION:
The doors should be provided on the opposite walls, facing each other to ensure
adequate air circulation in a room.
17
SAQIB IMRAN 0341-7549889
0
171 | P a g e
NUMBER OF DOORS:
Excellent utilization of space can be achieved by lowering the number of doors in a
room, because a large number of doors occupy more area, creates an obstruction in
circulation.
UTILIZATION OF LIGHT:
The door should be so located that no dark corner is left in the room and light and
ventilation are evenly distributed.
FUNCTIONAL REQUIREMENTS:
The location of doors must fulfill all the functional requirements of the room.
Stairs are the steps arranged in a series to access the various floors of a building. A
well-established staircase should have an easy, quick and safe mode of communication
between the different floors of that building. The following points should be kept in view
to design and build a good stair.
17
SAQIB IMRAN 0341-7549889
1
172 | P a g e
1. LOCATION OF STAIR:
The staircase should be located at the right place in a building with adequate light and
ventilation. In a residential house, the stairs may be provided near the main entrance. In
case of a public building, it should be located at the central position for a quick
accessibility.
2. WIDTH OF STAIR:
The width of stairs depends on the traffic flow and may vary from building to building. In
public building, the width of stairs should be at least 6 feet and in a residential building,
it should be 3 feet.
3. LENGTH OF STAIR:
The flight should provide a maximum of 12 and a minimum number of 3 steps.
4. PITCH OF STAIR:
The maximum pitch for a domestic building should not exceed 42° and for a public
building, it should not exceed 33°.
5. HEADROOM:
The minimum headroom in a staircase should not be less than 6 feet 8 inches.
6. LANDING:
The width of landing should be always greater than the width of a stair.
7. MATERIALS:
Fire resisting materials should be used to construct the staircase for better safety.
8. BALUSTRADE:
Balustrade should be provided in all open well stairs to minimize the accidents. Handrail
must be used on both sides of wide stairs (When stair is wider than 44 cm).
9. WINDERS:
To build a safe and easy staircase, winders should be avoided, but if necessary it may
be provided at lower end of the flight.
17
SAQIB IMRAN 0341-7549889
2
173 | P a g e
1. Painting the top of roof slab uniformly with a layer of hot bitumen spread at the rate of
1.70 of bitumen per sq.m of the roof surface.
2. Spreading immediately coarse sand at the rate of 0.6 cu.m of sand per 100 sq.m of
roof surface when the bitumen is still hot.
3. Laying cinder concrete 1:15 (1 cement:15 cinders of 13 mm and down gauge) in an
average thickness of 15 cm, the slope for the proper drainage of the roof being given to
this layer.
4. Laying 7.6 cm thick layer of lime concrete over the consolidated layer of cinder
concrete, the lime concrete being prepared bu mixing 50% of mortar consisting of lime
and sand mixed in the ratio of 1:2 with brick ballast 25 mm, and down gauge.
5. Spreading 13 mm. a thick layer of cement mortar 1:3 and laying tile brick flat and
open jointed over the mortar. Finally grouting the joints in the bricks with cement mortar
1:3.
17
SAQIB IMRAN 0341-7549889
3