NEA Engineering Company: Kathmandu District: - . F.Y: - .. Rate of Labours S.N. Labour Type Unit Rate Remarks
NEA Engineering Company: Kathmandu District: - . F.Y: - .. Rate of Labours S.N. Labour Type Unit Rate Remarks
Kathmandu
District:- …………….
F.Y:- …………………..
Rate of Labours
Construction Materials
S.N. Material Name Unit Rate Market Location
1 OPC Nepali Cement 50kg Bag 888.00
Sand m3 1000.00
Aggregate (5-10) mm. m3 2361.40
Aggregate (10-20) mm. m3 2156.06
Aggregate (20-40) mm. m3 2053.39
Boulder m3 2657.14
GI Wire Heavy Coated (8/10
2 Kg 91.00
gauge)
GI Wire Medium Coated (12
3 Kg 86.00
gauge)
4 GI Wire Commercial (8/10 gauge) Kg 80.00
5 Binding Wire Kg 100.00
6 Steel Bars 10-25 mm. Kg 80.05
8 Nails Kg 130.00
9 Wood, Local cft 3500.00
12 Geo-textile (TS-30) Sq-m 202.00
16 Rubber seal m 400.00
20 Np2 RCC Humepipe 900 mmø RM 4410.00
21 Np3 RCC Humepipe 450 mmø RM 3290.00
22 Np3 RCC Humepipe 600 mmø RM 4480.00
23 Np3 RCC Humepipe 900 mmø RM 7460.00
Fuels
S.N. Material Name Unit Rate Market Location
1 HSD Litre 100.00
2 Mobil Litre 800.00
3 Gear oil Litre 800.00
4 Grease Kg 800.00
5 Brake Oil Litre 700.00
1) Ownership Cost/Hr
a) Depreciation Cost = CoT/LS NRs/ Hr
b) Insurance Cost = 0.02 x CoT/T NRs/ Hr
c) Interest Cost = 0.01xCoT/T NRs/ Hr
Sub-Total of (1) NRs/ Hr
2) Operation Cost
2.1
Maintainance Cost
)
a) Overhauling Cost = 0.55 x CoT/LS NRs/ Hr
b) Operation & Maintenance
= 0.23 x CoT / LS NRs/ Hr
Cost
Sub-Total NRs/ Hr
2.2
Cost of Consumables
)
A) Oil & Lubrication Cost / Hr
HSD 5.50 Litre @ 100.00 NRs/ Hr
Mobil 0.10 Litre @ 800.00 NRs/ Hr
Gear Oil 0.03 Litre @ 700.00 NRs/ Hr
Grease 0.015 Kg @ 550.00 NRs/ Hr
Sub-Total NRs/ Hr
B) Spare Parts
Tyre Life Span Hr
Cost of One Tyre NRs
Cost per Hour ( 6 Tyres) = 6 x tyre cost / Tyre life NRs/ Hr
Misc. (Lump Sum) NRs/ Hr
Extra (Lump Sum) NRs/ Hr
Sub-Total NRs/ Hr
C) Salaries
Driver @ NRs 1000.00 md NRs/ Hr
Helper @ NRs 600.00 md NRs/ Hr
Loading & Unloading
L.S. NRs/ Hr
Expenses
Sub-Total NRs/ Hr
250.00
20.00
10.00
280.00
137.50
57.50
195.00
550.00
80.00
21.00
8.25
659.25
2000.00
18000.00
54.00
2.00
1.00
57.00
125.00
75.00
4.00
204.00
300.00
1220.25
1415.25
100.00
100.00
1795.25
1795.25
775.00
NEA Engineering Company
Kathmandu
F.Y = ……………….
Collection of materials.
Resources
S.N Ref. Labor
Description of Works Unit Cost Remarks
. no. Quantit Rate
Class Unit (NRs)
y (NRs)
1 Collection, screening &
providing of sand
(haulage distance 10 m)
3.1.b Source Capacity 31-50% m3 unskl m-day 3.45 800.00
2 Collection, screening
and providing of gravel
(haulage distance 10 m)
3.2.a 5 mm-70 mm & above m3 unskl m-day 2.50 800.00
3.2.b 5 mm-40mm (Up to) m3 unskl m-day 4.00 800.00
3.2.c 5 mm-20mm (Up to) m3 unskl m-day 5.88 800.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Remarks
21
Remarks
21
Basic
S. Basic Price Fuel
Machinery Price
N. Consumption
US$ (NRs)
1 Bulldozer 11 ton 118,200 12,411,000 11.5 Ltr/hr
2 Bulldozer 15 ton 160,000 16,800,000 16.5 Ltr/hr
3 Backhoe shovel 0.35m3 85,700 8,998,500 6.0 Ltr/hr
4 Backhoe shovel 0.70m3 183,600 19,278,000 11.0 Ltr/hr
3) Basis of the Hire Charge Rate of Heavy Equipments : Backhoe shovel 0.35m2
5) Basis of the Hire Charge Rate of Heavy Equipments: Tractor shovel 0.80 m 3 ( whee
type ) :
1 Estimated Ownership period ( YEARS ) 10
Where, H = Estimated life in hrs 10,000
h = Estimated annual operating hrs 1,000
7) Basis of the Hire Charge Rate of Heavy Equipments : Dump Truck 8 ton
11) Basis of the Hire Charge Rate of Heavy Equipments : Truck 8 ton
13) Basis of the Hire Charge Rate of Heavy Equipments : Vibration 28mm
Hire
Charge
per hour
4575.04
6067.00
3195.72
5777.43
2208.88
1911.68
2935.45
2826.65
1921.33
934.54
2,579.95
1078.30
1089.97
1. Labour
Unskilled m/d 0.03 800.00 24.00
Sub-total 24.00
Overhead cost 15.00% 3.60
Grand -total (NRs): 27.60
1. Equipment
Backhoe 0.35 m3 hr. 4.17 3,195.72 13,326.16
Dump truck 4 ton hr. 2.00 1,911.68 3,823.36
2. Labour
Foreman m/d 0.52 800.00 416.00
Unskilled m/d 0.52 800.00 416.00
3 Tools and plants @ 3% of labour cost 24.96
Sub-total 18,006.48
Overhead cost 15.00% 2,700.97
Grand -total (NRs): 20,707.46
207.07
1. Equipment
Bulldozer 11 ton hr. 0.70 4,575.04 3,202.52
Backhoe 0.70 m3 hr. 0.80 5,777.43 4,621.94
Dump truck 8 ton hr. 3.00 2,935.45 8,806.35
Tyre roller 8 ton hr. 1.60 2,826.65 4,522.64
2. Labour
Foreman m/d 0.20 800.00 160.00
Unskilled m/d 0.20 800.00 160.00
For watering & trimming -
Foreman m/d 0.50 800.00 400.00
Unskilled m/d 3.00 800.00 2,400.00
3 Tools and plants @ 3% of labour cost 93.60
Sub-total 24,367.05
4 Overhead cost 15.00% 3,655.06
1. Labour
Unskilled m/d 7.00 800.00 5,600.00
Mason m/d 0.80 1,000.00 800.00
2. Material
Sand cu.m 0.425 2,099.18 892.15
Cement ton 0.40 18,762.73 7,505.09
Aggregate (5-20 mm) cu.m 0.86 3,438.87 2,957.42
Sub-total 17,754.66
Overhead cost 15.00% 2,663.19
Grand -total (NRs): 20,417.85
2. Material -
Sand cu.m 0.47 2,099.18 986.61
Cement ton 0.22 18,762.73 4,127.80
Aggregate (5-40 mm) cu.m 0.89 3,644.21 3,243.34
Sub-total 12,557.75
Overhead cost 15.00% 1,883.66
Grand -total (NRs): 14,441.41
2. Material
Nails kg 2.5000 131.00 327.50
Timber cu.m 0.5260 15,435.00 8,118.81
Sub-total 11,566.31
Overhead cost 15.00% 1,734.95
Grand -total (NRs): 13,301.26
1,330.12
1. Labour
Unskilled m/d 12.00 800.00 9,600.00
Steel worker m/d 12.00 1,000.00 12,000.00
2. Material
Steel bar 10-25 mm ø ton 1.05 81,050.00 85,102.50
Binding wire kg 10.00 101.00 1,010.00
Sub-total 107,712.50
Overhead cost 15.00% 16,156.88
Grand -total (NRs): 123,869.38
123.86
25 Geo-textile Fabric(TS-30).
1. Labour
Skilled m/d 1/8 1,000.00 125.00
2. Material
Geo-textile Fabric for laying sq.m 30.00 202.00 6,060.00
0.5 m lap in width = 3m for lap sq.m 0.75 202.00 151.50
Sub-total 6,336.50
Overhead cost 15.00% 950.48
Grand -total (NRs): 7,286.98
242.89
27 Making gabion boxes (3*1*1m) with hexagonal mesh including wire cutting, nett
all complete
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-7 SWG
1. Labour
Skilled m/d 0.63 1,000.00 630.00
Unskilled m/d 0.28 800.00 224.00
2. Material
G.I. wire (Including salvedge wire) Kg 39.200 92.00 3,606.40
Sub-total 4,460.40
Overhead cost 15.00% 669.06
Grand -total (NRs): 5,129.46
366.39
28 Making gabion boxes (3*1.0*50m) with hexagonal mesh including wire cutting, n
etc all complete
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-7 SWG
1. Labour
Skilled m/d 0.45 1,000.00 450.00
Unskilled m/d 0.2 800.00 160.00
2. Material
G.I. wire (Including salvedge wire) Kg 27.450 92.00 2,525.40
Sub-total 3,135.40
Overhead cost 15.00% 470.31
Grand -total (NRs): 3,605.71
360.57
29 Making gabion boxes (3*1.0*30m) with hexagonal mesh including wire cutting, n
etc all complete.
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-7 SWG
1. Labour
Skilled m/d 0.37 1,000.00 370.00
Unskilled m/d 0.17 800.00 136.00
2. Material
G.I. wire (Including salvedge wire) Kg 22.750 92.00 2,093.00
Sub-total 2,599.00
Overhead cost 15.00% 389.85
Grand -total (NRs): 2,988.85
355.81
37 Supply of Boulder & filling in gabion boxes including placing in position, tighting
complete.
Per m3 Norm.Ref.-16.11,16.7.b,d,f
1. Labour
Skilled m/d 0.5 1,000.00 500.00
Unskilled (0.60+0.30+0 m/d 0.36 800.00 288.00
2. Material
Boulder cum 1 2,657.14 2,657.14
Sub-total 3,445.14
Overhead cost 15.00% 516.77
Grand -total (NRs): 3,961.91
40 Laying 15cm thick sub-grade of gravel of required size and binding material clay
incl. loading & transporting materials, surface levelling compacting using roller i
const. site (Norms 15-10 b)
S.No. Particular Description Unit Qty Unit Rate Amount
1 Gravel rever singel m3 0.2025 3334.97 675.33
Aggregate screened
m3 0.063 3644.21 229.58
river singel
Binding material Clay and silt m3 0.015 813.28 12.19
Roller hr 0.042 2,826.65 118.71
Total of Material and equipment 1035.81
Labour
Unskilled m/d 0.21 800.00 168.00
T & P 3% of labour charge 5.04
Sub-total 173.04
1,208.85
Overhead cost 15.00% 181.33
Total 1,390.17
1. Labour
Skilled m/d 0.71 1,000.00 710.00
Unskilled m/d 2.12 800.00 1,696.00
2. Material
Boulder cum 1 2,657.14 2,657.14
Sub-total 5,063.14
Overhead cost 15.00% 759.47
Grand -total (NRs): 5,822.61
42 Gravel Filter.
Per m3 Norm.Ref.-23.1
1. Labour
Skilled m/d 0.35 1,000.00 350.00
Unskilled m/d 0.53 800.00 424.00
2. Material
Gravel cum 1.00 3,334.97 3,334.97
Sub-total 4,108.97
Overhead cost 15.00% 616.34
Grand -total (NRs): 4,725.31
1. Labour
Skilled m/d 11 1,000.00 11,000.00
Unskilled m/d 50 800.00 40,000.00
2. Material
60 dia. NP3 Hume Pipe m 32.00 7,460.00 238,720.00
[0.04+.0015
Transportation( Distance=30 *distance in
Km) KM] 20,291.20
Sub-total 310,011.20
Overhead cost 15.00% 46,501.68
Grand -total (NRs): 356,512.88
11,141.02
49 Stripping works.
Per M2 (Thickness 15-20 cm ) Norm.Ref. 1.8
1. Labour
Unskilled m/d 0.160 800.00 128.00
2 Tools and plants @ 3% of Labour cost 3.84
Sub-total 131.84
Overhead cost 15.00% 19.78
Grand -total (NRs): 151.61
50 Supply,fitting and fixing of Steel gate for inlet and outlet all complete set.( mild s
Spindle rod ,6mm th. Skin plate,gear box complete set , stiffener , bracing and ru
seal as per require)
Per M2
1. Material
Mild steel Gate as per required m2 1.00 27,500.00 27,500.00
2 Transportation and fitting ,fixing etc all omplete LS 3,000.00
Sub-total 30,500.00
Overhead cost 15.00% 4,575.00
Grand -total (NRs): 35,075.00
any
Remarks
Per m2
Remarks
Per 100m3
Per m3
Remarks
Per 100m3
Per m3
Remarks
Per 100m2
Per m2
Remarks
Per m3
Remarks
Per m3
Remarks
Per m3
Remarks
Per 10m2
Per m2
Remarks
Per MT
Per Kg
Remarks
Per 30 m2
Per m2
Remarks
Box
m2
Remarks
Box
m2
Remarks
Box
m2
Remarks
m3
per m2
Remarks
m3
Remarks
m3
Remarks
For 32M
M
Remarks
Per m2
Remarks
Per m2
9 Construction of earthen
Embankment for approach road 2 10.00 5.00 1.00 100.00
above pipe 1 5.00 5.00 0.60 15.00
115.00 m3
10 Turfing work
approach road sides 4 10.00 1.00 40.00 m2
11 Site clearance L.S. 1 job
8 Dowel bars 14
Slab bottom 10
Total
9 0.30 m dry stone pitching on
0.15 m gravel backing
u/s bed 1 1 4.6 0.3 1.38
slope 2 1 1.34 0.3 0.80
d/s bed 1 2 4.6 0.3 2.76
slopes 2 2 1.34 0.3 1.61
Total 6.55 m2
10 0.15 m gravel filter under 0.30
m boulder pitching
u/s bed 1 1 4.6 0.15 0.69
slope 2 1 1.34 0.15 0.40
d/s bed 1 2 4.6 0.15 1.38
slopes 2 2 1.34 0.15 0.80
Total 3.27 m2
11 E/W in embankment filling
Approach road 2 20 6 1.50 360.00 m3
The weir shall be designed as glacis weir hence floor length & thickness shall be calculated from surface &
subsurface flow conditions
Case II:Design for max flow with o.5m retrogression & 20 % flow concentration
Case III:Design for pond level flow with sluice gate opened
Case IVI:Design for pond level flow with o.5m retrogression & 20 % flow concentration
Case II
Velocity of approach Va= q/R 1.08 1.11 0.56 0.60 0.94 1.00
Head over the crest (q/1.70)2/3 1.49 1.58 0.40 0.45 1.13 1.27
d/s total energy level 154.76 154.26 153.62 153.12 154.74 154.24
u/s total energy level 155.44 155.48 154.32 154.35 155.42 155.57
head loss HL 0.68 1.22 0.70 1.24 0.68 1.33
D/s conju y2(assume for trial) m 1.80 2.09 0.62 0.77 1.43 1.78
Critical depth Yc= (q2/g)1/3 m 0.99 1.05 0.27 0.31 0.75 0.85
Jump formation level =d/s TEL-EF2 152.81 152.04 152.97 152.32 153.21 152.37
Length of concrete floor Lc = 6(Y2-y1) for hydraulic 6.64 8.24 2.66 3.43 5.48 7.28
Ge=(h/d)/(pÖl)
Overflow weir
d= 1.50 m d= 2.00 m
fC1 correction
fD correction
for interfarance
for interfarance
of d/s sheetofpile
d/s line
sheet pile line
d= 1.20 m d= 1.00
D= 2.60 m D= 0.00
b= 17.90 m b= 17.90
C=19ÖD/b'((d+D)/b 1.58% +ve C=19ÖD/b'((d+D)/b 0.00% -ve
fC1 corrected 81.07% fE1 corrected 25.01%
No flow maximum stati 152.40 154.30 1.90 1.90 1.56 1.54 0.48 0.39 0.00
high flood head 154.20 155.38 1.18 1.18 0.97 0.79 0.20 0.04 0.00
Floor thickness
II d/s protection
Anticipated scour = 2R 5.71 m 4.33 m
d/s scour level=d/ HFL 148.49 m 149.87 m
D= 3.51 2.53
Block size 1*1*.75
provide 3 rows of blocks with 10cm gab between the rows
No of blocks in a row = 21.00 Numbers Numbers
Total blocks = 63.00
Total width of block pr 3.20 m
b. d/s Launching apron
Quantity of launching appron=2.25D
Let thickness = 0.75m
Length required = 2.25 10.53 m 7.59 m
Provide 3*1.5*0.75m gabion launching
Length = 9.00 m 9.00 m
Abutment & wing walls
u' sluice weir
u/s wing wall level = u/s HFL+.4 155.80 155.80
d/s wingwall level = d/s HFL(before retrogr 154.45 154.45
u/s wall height h1= 2.50 2.50
d/s wall height h2= 2.45 2.05
width of u/s wing wall to accomate 2:1 ban 5.20 5.20
width of d/s wing wall to accomate 2:1 ban 5.1 4.30
provide top width of wing wall 0.30m and base as designed 4:10 outer slope
provide top width of abutment & divide wall 0.40m and base as resulted from 3:10 outer slope
depth of base = 0.5m
outer width of base = 0.5m
inner =o.5
cutoff depth as designed in u/s & d/s weir
Reinforcement detail as given in drawing
Design of Intake
CCA 350 ha
Canal bed level 153.15
Full supply of canal 154.00
Width W= 2.50 m
Intake discharge Qi= 1.10 m3/s
Head over the crest H=(Qi/(1.71W))^.67 0.40 m
Crest Level 153.90
if flow is in submersed stage
Actual Qi = 2/3*0.577*((2g)(h+ha)^3/2-ha^3/2)^0.5+0.8Ld(2g(h+ha))^0.5
here, h= 0.30
d= 0.10
Qi= Ok 2.51
HFL flow
Qi=CA(2gh)^.5
Let get oprning be X
Qi=0.62*Wx(2gh)^.5
X=Qi/(.62*W*(2gh)^.5) 0.14 m
Velocity through opening v=Q/A 3.22 m/s
loss of head at entry =0.5v2/2g 0.26 m
TEL u/s of gate= 155.44 m
TEL d/s of gate= 155.17
headloss during HFL = 1.17 m
HFL Pond level
Particulars
Discharge intensity q q = Q/L 0.44 0.440
D/s water level 154.00 154.00
u/s water level 155.38 154.30
d/s total energy level 154.00 154.00
u/s total energy level 155.17 154.30
head loss HL 1.17 0.30
D/s conju y2(assume for trial) m 0.69 0.54
y =-y
u/s conjug 1 2 /2+SQRT(2q 2
/gym2
+y22/4) 0.07 0.11
D/s energyEf1=y1+q /2gy2
2 2
m 1.84 0.88
Energy u/sEf2=y2+q /2gy2
2 2
m 0.71 0.57
Headloss HL=Ef1-Ef2 m 1.12 0.31
D/s conjugy2=-y1/2+SQRT(2q /gym +y1 /4)
2 2
1 0.69 0.54
Critical de Yc= (q /g)
2 1/3
m 0.27 0.27
Jump formation level =d/s TEL-EF2 154.46 153.73
provided at 153.70
d/s floor length 5*(y2-y1) 3.076 2.106
Required length 3.00
Top level of u/s wing wall & abutment = 155.78 m
Height of u/s wing wall & abutment = 2.50 m
Top level of d/s canal wall= 154.25 m
Height of d/s = 0.55 m
Length of u/s wing wall of weir/sluice to accomadate 1:2 slope of bank = 5.20 m
Bank width 3.00 m
Min length of floor & glacis = 8.20 m
Length of glacis = 2:1 0.40 m
crest width = 0.50 m
d/s floor length = 7.30 m
page 77 of Siuriya estimate
Weiring layer
U'sluice
Crest 1 1.00 2.50 0.15 0.38
d/s glacis 1 3.91 2.50 0.15 1.47
Weir 0
Crest 1 1.00 18.10 0.15 2.72
d/s glacis 1 3.91 18.10 0.15 10.62
d/s floor 1 8.70 18.10 0.15 23.62
intke cutoff 1.00 8.90 0.40 1.00 17.80
Total 56.61 m3
Walls sluice channel
U'sluice
u/s wing wall 1 2.00 10.7 0.5 10.70
Weir parameters
Parameters u/sluice Weir intake
Existing GL 154 154 155.3
d/s EGL 153.7 153.7 155.3
crestlevel 153.90 154.30 153.90
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
0 0.00 0.00 0.00
12 8.84 28.60 28.60
50 32.71 105.85 105.85
100 48.21 156.01 156.01
150 47.68 154.29 154.29
200 45.97 148.77 148.77
216 14.58 47.17 47.17
250 31.17 100.86 100.86
300 46.25 149.68 149.68
341 34.98 113.18 113.18
394 39.48 127.77 127.77
400 4.28 13.84 13.84
435 25.18 81.49 81.49
450 10.81 34.97 34.97
450 0.00 0.00 0.00
455 5.98 22.61 13.66
500 83.77 428.93 328.51
550 102.29 591.92 535.50
556 11.64 62.40 52.12
600 82.05 413.83 319.60
650 93.43 472.75 366.80
651 1.99 11.12 9.69
651 0.00 0.00 0.00
700 51.45 51.45 0.00
428841703.xlsxEarthwork page 113 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
750 55.84 79.54 0.00
800 68.29 194.60 0.00
850 80.58 318.48 132.59
890 71.29 336.07 230.07
890 0.00 0.00 0.00
900 18.85 96.71 76.50
950 98.21 536.68 457.61
1000 127.07 708.16 680.12
1050 153.42 880.39 880.39
1100 157.22 1015.61 1015.61
1140 121.24 848.60 848.60
1150 28.77 206.49 206.49
1200 145.17 1076.30 1076.30
1250 144.92 1068.06 1068.06
1300 142.41 985.18 985.18
1333 97.80 780.36 780.36
1400 197.03 1535.48 1535.48
1450 140.68 929.36 929.36
1500 141.84 966.66 966.66
1500 0.00 0.00 0.00
1550 141.50 955.58 955.58
1575 73.38 565.98 565.98
1590 45.53 390.26 390.26
1591 3.03 25.91 25.91
428841703.xlsxEarthwork page 114 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
1591 0.00 0.00 0.00
1597 10.59 48.98 38.31
1610 22.81 104.33 80.59
1650 62.88 240.50 132.96
1700 77.08 282.52 141.47
1750 91.66 453.57 377.07
1800 117.97 677.24 654.04
1850 142.39 987.80 987.80
1900 148.26 1179.83 1179.83
1950 146.64 1125.70 1125.70
1994 138.17 1322.08 1322.08
1994 0.00 0.00 0.00
2000 12.88 106.29 84.00
2050 56.04 81.19 0.00
2100 59.51 109.35 0.00
2150 55.97 80.66 0.00
2200 105.31 249.32 104.00
2200 0.00 0.00 0.00
2250 99.71 209.87 176.27
2300 97.03 199.84 156.91
2350 95.17 192.95 143.25
2400 93.07 185.27 127.70
2450 91.20 178.51 113.79
2500 89.50 172.38 100.92
428841703.xlsxEarthwork page 115 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
2550 87.55 165.47 86.15
2600 85.72 158.99 72.06
2650 84.09 153.31 59.47
2650 0.00 0.00 0.00
2656 9.96 41.39 31.11
2660 5.40 15.74 0.00
2700 42.00 42.00 0.00
2725 26.25 26.25 0.00
2750 316.10 121.12
2750 0.00 0.00
4841.45
Total to New alignment 25662.92 22849.57
2800 345.39 324.97
2850 231.87 209.00
2950 438.16 377.48
3000 210.57 175.36
3050 219.65 189.84
3100 225.81 199.56
3150 230.79 207.31
3200 239.87 221.30
3250 253.14 241.41
3300 267.91 263.34
3350 287.06 286.52
3400 304.97 304.97
3450 253.54 253.54
428841703.xlsxEarthwork page 116 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
3500 195.31 195.31
3550 195.00 195.00
3650 416.72 416.72
3750 446.05 446.05
3800 250.38 250.38
4150 1949.82 1949.82
4250 592.51 592.51
4300 311.57 311.57
4350 304.45 304.45
4400 301.51 301.51
4450 309.31 309.31
4500 326.45 326.45
4550 346.20 346.20
4600 352.78 352.78
4700 719.41 719.41
4750 367.78 367.78
4750 0.00 0.00
4850 713.26 713.26
4950 702.70 702.70
5100 850.15 850.15
5150 222.02 222.02
5200 220.75 220.75
5250 216.85 216.85
5350 449.22 449.22
428841703.xlsxEarthwork page 117 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
5450 499.68 499.68
5500 262.91 262.91
5500 0.00 0.00
5650 687.11 687.11
5750 446.78 446.78
5800 223.96 223.96
5950 575.09 575.09
6000 186.40 186.40
6010 37.65 37.65
6010 0.00 0.00
6050 0.00 0.00
6050 0.00 0.00
6250 706.93 706.93
6300 193.47 193.47
6450 676.61 676.61
6750 1655.30 1655.30
6800 287.85 287.85
6850 292.81 292.81
6950 606.01 606.01
7050 592.61 592.61
7200 889.58 889.58
7350 869.11 869.11
7350 0.00 0.00
7400 289.04 289.04
428841703.xlsxEarthwork page 118 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
7450 360.34 360.34
7550 794.77 794.77
7650 728.48 728.48
7750 825.80 825.80
7800 442.40 442.40
7825 195.60 195.60
7850 182.74 182.74
7850 0.00 0.00
7900 336.58 336.58
7950 342.48 342.48
7950 0.00 0.00
7990 261.26 261.26
7990 0.00 0.00
8000 59.14 59.14
8000 0.00 0.00
8050 320.72 320.72
8080 146.34 144.68
8080 0.00 0.00
8100 88.08 85.37
8150 354.53 354.53
8200 379.31 379.31
8250 361.25 361.25
8270 126.20 126.20
8270 0.00 0.00
428841703.xlsxEarthwork page 119 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
8300 184.28 184.28
8350 357.37 357.37
8400 354.09 354.09
8450 384.04 384.04
8500 409.33 409.33
8550 376.13 376.13
8600 328.63 328.63
8610 60.20 60.20
8610 0.00 0.00
8650 72.41 42.86
8700 153.20 150.23
8750 158.41 157.09
8800 156.34 155.02
8850 160.24 160.01
8950 307.04 302.78
8990 146.31 144.79
8990 0.00 0.00
9000 41.44 41.44
9050 178.21 176.61
9100 151.46 148.79
9140 124.59 123.44
9140 0.00 0.00
9150 30.03 29.25
9200 187.85 187.32
428841703.xlsxEarthwork page 120 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
9210 43.74 43.74
9210 0.00 0.00
9250 163.15 163.15
9250 0.00 0.00
9300 127.74 122.04
9350 145.69 142.38
9400 167.88 167.03
9450 167.29 166.38
9500 142.58 138.75
9550 199.56 196.40
9600 227.15 227.04
9640 142.15 141.90
9640 0.00 0.00
9650 38.51 38.40
9700 215.30 215.30
9750 193.88 193.74
9775 94.72 94.66
9775 0.00 0.00
9800 65.83 64.19
9850 91.24 83.71
9875 47.25 43.82
9875 0.00 0.00
9900 56.71 54.88
9950 108.72 104.66
428841703.xlsxEarthwork page 121 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
10000 116.89 114.55
10050 127.34 125.66
10100 151.32 151.30
10150 164.37 164.37
10200 192.77 192.77
10250 213.73 213.73
10300 219.89 219.89
10350 230.83 230.83
10400 256.31 256.31
10450 262.59 262.59
10500 231.41 231.41
10550 214.06 214.06
10550 0.00 0.00
10575 63.24 57.54
10575 0.00 0.00
10600 51.52 42.29
10650 187.67 187.67
10690 151.77 151.77
10690 0.00 0.00
10700 30.27 30.27
10750 146.95 146.95
10800 151.32 151.32
10850 160.19 160.19
10900 170.55 170.55
428841703.xlsxEarthwork page 122 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
10910 31.05 31.05
10910 0.00 0.00
10930 51.82 51.72
10930 0.00 0.00
10950 0.00 0.00
10990 0.00 0.00
10990 0.00 0.00
11000 0.00 0.00
11050 0.00 0.00
11050 0.00 0.00
11100 0.00 0.00
11150 0.00 0.00
11200 0.00 0.00
11250 0.00 0.00
11300 0.00 0.00
11350 0.00 0.00
11400 0.00 0.00
11450 0.00 0.00
11500 0.00 0.00
11550 0.00 0.00
11600 0.00 0.00
11650 0.00 0.00
11700 0.00 0.00
11750 0.00 0.00
428841703.xlsxEarthwork page 123 of 162
filling to filling
Chainage stripped Total filling from
area Borrowpit
m m3 m3 m3
11800 0.00 0.00
11850 0.00 0.00
11900 0.00 0.00
11950 0.00 0.00
12000 0.00 0.00
12050 0.00 0.00
0.00 40892.43 40530.09
4841.45 66555.35 63379.66
HIS MAJESTY'S GOVERNMENT
DEPARTMENT OF IRRIGATION
BABAI IRRIGATION PROJECT
BARDIYA
158.976
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
0+050 2.270 156.706
1.565 2.090 158.451 156.886
0+100 1.765 156.686
0+200 1.700 156.751
0+250 1.752 156.699
1.250 2.200 157.501 156.251
0+300 0.850 156.651
0+350 0.880 156.621
1.560 1.650 157.411 155.851
0+400 0.830 156.581
0+450 0.890 156.521
1.300 1.710 157.001 155.701
0+500 0.550 156.451
0+550 0.620 156.381
1.480 1.650 156.830 155.350
0+600 0.550 156.280
0+650 4.230 0.610 161.670 157.440
0.248 1.110 159.588 159.340
0+700 3.42 156.168
0+750 3.43 156.158
R bank 0.51 159.078
L bank 0.26 159.328
0+800 3.45 156.138
1.402 0.482 160.508 159.106
0+900 4.54 155.968
L bank 1.350 1.700 160.158 158.808
1+000 4.24 155.918
L bank 1.32 158.838
1.30 158.858
1.140 1.552 159.746 158.606
1+050 4.10 155.646
1.360 1.620 159.486 158.126
1.470 1.680 159.276 157.806
1+400 3.77 155.506
L bank 1.33 157.946
R/S bank road 1.35 157.926
1.19 158.086 On TBM on bamboo.
1.160 158.116
0.743 158.859 158.116
1+500 3.53 155.329
1.12 157.739
1.14 157.719
2.41 156.449
1.265 1.152 158.972 157.707
1+550 3.66 155.312
1+600 3.61 155.362
1.22 157.752
Page 124file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
1.36 157.612
1.083 1.430 158.625 157.542
1+650 3.319 155.306
0.456 158.169 TBM on piller bed
0.487 158.656 158.169
1+700 3.40 155.256
1.18 157.476
1.20 157.456
1+750 3.54 155.116
1.120 1.252 158.524 157.404
1+800 3.48 155.044
1+850 3.50 155.024
1.23 157.294
1.36 157.164
1.410 1.541 158.393 156.983
1+950 3.46 155.41 154.933
1.13 157.279 157.263 Baidi Kulo on wall
2+000 3.49 154.903
1.57 156.823
0.82 157.573
1.03 157.363
1.025 1.369 158.049 157.024
2+100 3.205 154.844
0.620 1.085 157.584 156.964
2+200 2.76 154.824
0.75 156.834
1.02 156.564
0.76 156.824
1.50 156.084
1.82 155.764
1.121 1.401 157.304 156.183
2+350 2.73 154.574
2+400 2.81 154.494
0.825 156.479
1.30 156.004
0.78 156.524
1.45 155.854
1.90 155.404
2+450 2.785 154.519
1.140 1.381 157.063 155.923
2+500 2.60 154.463
VRB crossing at
2+600 2.715 154.348 ch.2+750
TBM of wooden bridge
1.191 1.430 156.824 155.633 center beam
0.14 156.684
2+700 2.51 154.314
2+750 2.49 154.334
1.06 155.764
0.80 156.024
1.20 155.624
1.129 1.542 156.411 155.282
2+900 2.34 154.071
Page 125file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
0.75 155.661
0.87 155.541
0.74 155.671
1.23 155.181
1.253 0.839 156.825 155.572
3+000 3.04 153.785 Both kulo different
1.30 155.525
1.49 155.525
1.32 155.335
156.825
156.825
3+050 2.86 153.965
TBM on wooden bridge
0.835 1.312 156.348 155.513 at ch, 3+100
3+200 2.36 153.988
0.649 155.699
3+250 2.46 153.888
L/S off take from cha.
3+260 2.42 153.928 3+260
2.60 153.748
1.387 1.660 156.075 154.688
3.32 152.755
1.60 154.475
3+300 3.43 152.645
0.87 155.205
1.41 154.665
0.99 155.085
1.46 154.615
1.57 154.505
1.125 1.531 155.669 154.544
3+500 3.25 152.419
3+550 3.30 152.369
2.930 1.500 157.099 154.169
On BM east coner of
south parapet of VRB
0.757 156.342 at 3+600
1.501 2.530 156.070 154.569
0+300 2.47 153.600
0+350 2.50 153.600
3+700 4.05 152.020
0.907 1.720 155.257 154.350
4+000 3.555 151.702
1.17 154.087
1.58 153.677
1.52 153.737 VRB at 4+150
1.67 153.587
4+050 3.49 151.767 VRB at 4+400
4+100 3.64 151.617
1.031 1.760 154.528 153.497
4+200 2.915 151.613
4+300 2.93 151.598
1.591 1.578 154.541 152.950
Page 126file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
TBM on wooden bridge
at ch.4+400 weast
0.85 153.691 side.
4+450 3.03 151.511
4+600 3.00 151.541
1.670 1.982 154.229 152.559
4+600 2.69 151.539
1.05 153.179
1.78 152.449
1.29 152.939
1.60 152.629 Road parallet to drain.
1.77 152.459
4+650 2.79 151.439
1.038 1.302 153.965 152.927
4+700 2.41 151.555
4+800 2.68 151.285
BM on brick mesonary
1.434 152.531 wall.
4+900 2.66 151.305
near hand piller at
1.05 152.915 ch.4+900.
2.08 151.885
1.04 152.925
1.72 152.245 road parapet to drain.
1.650 1.620 153.995 152.345
5+000 3.16 150.835
1.37 152.625
1.95 152.045
1.47 152.525
2.05 151.945
R/S kulo off take from
2.18 151.815 ch.5+075.
5+050 2.98 151.015 U/S of culvert
2.54 151.455 from 5+100
5+100 2.79 151.205 Two kulo off take.
2.56 151.435
2.64 151.355 Near the side pillar.
On east side of
parapet wall of culvert
0.313 0.371 153.937 153.624 at cha.5+075.
5+150 2.85 151.087
5+200 2.82 151.117
1.215 1.380 153.772 152.557
Left side off take at
2.045 151.727 5+200
2.55 151.222
Earth daown at
5+250 2.67 151.102 ch.5+240
1.051 152.721 On PCC old BM pillar
5+300 2.78 150.992
2.05 151.722
Page 127file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
R/S off take from
5+350 2.87 150.902 ch.5+330
2.50 151.272
2.78 150.992
2.81 150.962
1.010 1.165 153.617 152.607
5+400 3.093 150.524
2.11 151.507
1.985 151.632 Irrigation store point
5+450 2.98 150.637
2.205 151.412
Page 128file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
2.285 150.249
6+400 2.455 150.079
6+450 2.63 149.904 VRB at ch 6+460
1.940 1.946 152.528 150.588
R/S off take from ch.
6+500 2.725 149.803 6+500
2.484 150.044
6+550 2.76 149.768
1.310 1.464 152.374 151.064
6+600 2.765 149.609
6+650 2.835 149.539
6+700 2.80 149.574
1.53 150.844
2.33 150.040
1.53 150.844
2.31 150.064
1.066 1.430 152.010 150.944
6+750 2.30 149.710
6+800 2.935 149.075
6+850 2.575 149.435 VRB at 6+890
6+900 2.815 149.195
0.735 1.125 151.620 150.885
L/S Kulo off take from
6+950 2.397 149.223 ch. 7+025
7+000 2.29 149.330
7+050 2.24 149.380
1.484 1.150 151.954 150.470
2.725 149.229
BM on porpet east side
0.23 151.724 south corner
7+100 2.52 149.434
7+150 2.66 149.294 VRB at 7+125
7+200 2.82 149.134
1.190 2.207 150.937 149.747
7+250 1.80 149.137
7+300 2.02 148.917
0.81 150.127
1.45 149.487
1.27 149.667
1.60 149.337
7+350 2.12 148.817
7+400 2.22 148.717
0.915 1.267 150.585 149.670
7+450 2.115 148.470
7+500 2.14 148.445
7+550 2.24 148.345
7+600 2.31 148.275
0.350 0.886 150.049 149.699
7+650 2.004 148.045
7+700 2.07 147.979
7+750 1.942 148.107
7+800 1.96 148.089
Page 129file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
0.98 149.069
7+850 2.032 148.017
0.79 149.259
Near foot bridge at ch.
1.71 148.339 7+800
1.473 1.762 149.760 148.287
7+900 1.79 147.970
1.76 148.000 L/S of take at 7+825
7+950 1.71 148.050
L/S off take from
8+000 1.77 147.990 7+940
8+050 1.81 147.950
8+100 1.92 147.840 L/S off take at 8+160
1.285 1.571 149.474 148.189
8+150 1.69 147.784 L/S off take at 8+180
8+200 1.83 147.644
8+160 1.49 147.984
8+180 1.57 147.904
8+250 2.05 147.424
1.485 1.390 149.569 148.084 L/S of take 8+240
2.29 147.279
8+300 2.13 147.439
On head of tubwel
1.350 0.965 149.954 148.604 near cha.8+300
8+350 2.565 149.954
8+400 2.635 147.389
1.365 1.30 150.019 148.654
8+450 2.730 147.289
8+500 2.80 147.219
1.200 1.65 149.569 148.369 BM on tree root
8+550 2.40 147.169
8+600 2.42 147.149 -0.020
1.010 1.46 149.119 148.109
8+650 2.02 147.099
8+700 2.06 147.059
0.555 1.555 148.119 147.564
8+750 1.110 147.009
8+800 1.140 146.979
0.680 0.52 148.279 147.599
8+850 1.360 146.919
8+900 1.420 146.859
0.820 0.65 148.449 147.629
8+950 1.640 146.809
9+000 1.700 146.749
1.170 0.58 149.039 147.869
9+050 2.340 146.699
9+100 2.390 146.649
2.620 1.80 149.859 147.239 BM On R/S piller
9+150 3.240 146.619
9+200 3.280 146.579
2.220 2.100 149.979 147.759
9+250 2.440 147.539
Page 130file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
9+300 2.490 147.489
Page 131file:///conversion/tmp/scratch/428841703.xlsx
158.976
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
0 156.686
50 2.270 156.706
100 1.765 156.686
200 1.700 156.751
250 1.752 156.699
300 0.850 156.650
350 0.880 156.620
400 0.830 156.580
450 0.890 156.520
500 0.550 156.450
550 0.620 156.380
600 0.550 156.280
650 4.230 0.610 160.540 156.220
700 3.42 156.168
750 3.43 156.158
800 3.45 156.138
900 4.54 155.968
1000 4.24 155.918
1050 4.10 155.646
1400 3.77 155.506
1500 3.53 155.329
1550 3.66 155.312
1600 3.61 155.362
1650 3.319 155.306
1700 3.40 155.256
1750 3.54 155.116
1800 3.48 155.044
1850 3.50 155.024
1950 3.46 154.933
2000 3.49 154.903
2100 3.205 154.844
2200 2.76 154.824
2350 2.73 154.574
2400 2.81 154.494
2450 2.785 154.519
2500 2.60 154.463
VRB crossing at
2600 2.715 154.348 ch.2+750
2700 2.51 154.314
2750 2.49 154.334
2900 2.34 154.071
3000 3.04 153.785 Both kulo different
3050 2.86 153.965
3200 2.36 153.988
3250 2.46 153.888
L/S off take from cha.
3260 2.42 153.928 3+260
Page 132file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
3300 3.43 152.645
3500 3.25 152.419
3550 3.30 152.369
3700 4.05 152.020
4000 3.555 151.702
4050 3.49 151.767 VRB at 4+400
4100 3.64 151.617
4200 2.915 151.613
4300 2.93 151.598
4450 3.03 151.511
4600 3.00 151.541
4600 2.69 151.539
4650 2.79 151.439
4700 2.41 151.555
4800 2.68 151.285
4900 2.66 151.305
5000 3.16 150.835
5050 2.98 151.015 U/S of culvert
5100 2.79 151.205 Two kulo off take.
5150 2.85 151.087
5200 2.82 151.117
5300 2.78 150.992
R/S off take from
5350 2.87 150.902 ch.5+330
5400 3.093 150.524
5450 2.98 150.637
Page 133file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
6700 2.80 149.574
6750 2.30 149.710
6800 2.935 149.075
6850 2.575 149.435 VRB at 6+890
6900 2.815 149.195
L/S Kulo off take from
6950 2.397 149.223 ch. 7+025
7000 2.29 149.330
7050 2.24 149.380
7100 2.52 149.434
7150 2.66 149.294 VRB at 7+125
7200 2.86 149.094
7250 1.80 149.137
7300 2.02 148.917
7350 2.12 148.817
7400 2.22 148.717
7450 2.115 148.470
7500 2.14 148.445
7550 2.24 148.345
7600 2.31 148.275
7650 2.004 148.045
7700 2.07 147.979
7750 1.942 148.107
7800 1.96 148.089
7850 2.032 148.017
7900 1.79 147.970
7950 1.71 148.050
L/S off take from
8000 1.77 147.990 7+940
8050 1.81 147.950
8100 1.92 147.840 L/S off take at 8+160
8150 1.69 147.784 L/S off take at 8+180
8200 1.83 147.644
8250 2.05 147.424
8300 2.13 147.439
8350 2.565 147.439
8400 2.635 147.289
8450 2.73 147.389
8500 2.80 147.219
8550 2.40 147.169
8600 2.420 147.149 -0.02
8650 2.020 147.099
8700 2.060 147.059
8750 1.110 147.009
8800 1.140 146.979
8850 1.360 146.919
8900 1.420 146.859
8950 1.640 146.809
9000 1.7 146.749
9050 2.34 146.699
9100 2.39 147.239
9150 3.24 146.619
Page 134file:///conversion/tmp/scratch/428841703.xlsx
Readings Height of
Chainge Bearing Rise Fall R.L Remarks
Back Inter Fore Instrument
9200 3.28 146.579
9250 2.44 147.539
9300 2.49 147.489
Page 135file:///conversion/tmp/scratch/428841703.xlsx
Canal Design Sheet : S5 Canal
Chainage DistancBed slopExisting Bed WidtDepth TriArea PerimeteQd Qact Velocit FSL BL BTL
m m 1/S m m m m2 m m3/s m3/s m/s m m
Main Canal at 12+570 ###
0 ### 165.85 3.000 0.790 ### 5.848 ### ### 0.705 ### ### ###
12 12 ### 165.7 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
50 38 ### 165.42 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
100 50 ### 165.33 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
150 50 ### 165.39 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
200 50 ### 165.37 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
216 PUP existing 16 ### 165.37 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
250 34 ### 165.32 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
300 50 ### 165.29 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
341 Existing CUP 41 ### 165.47 3.000 0.766 ### 5.762 ### ### 0.693 ### ### ###
394 53 ### 164.95 3.000 0.700 ### 5.524 ### ### 0.809 ### ### ###
400 6 ### 164.93 3.000 0.700 ### 5.524 ### ### 0.809 ### ### ###
435 35 ### 164.89 3.000 0.700 ### 5.524 ### ### 0.809 ### ### ###
450 Existing VRB 15 ### 164.87 3.000 0.700 ### 5.524 ### ### 0.809 ### ### ###
450 & overflow 0 ### 164.87 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
455 5 ### 164.87 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
500 45 ### 164.41 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
550 50 ### ### 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
556 IP1, 1640 51' 6 ### ### 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
600 44 ### ### 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
650 50 ### 164.5 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
Both side
Outlet to
651 local 1 ### 164.3 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
Outlet to
651 locaKulo 0 ### 164.3 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
700 49 ### 163.99 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
750 50 ### 163.6 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
800 50 ### 163.22 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
850 50 ### 163.07 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
890 40 ### 162.84 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
890 0 ### 162.84 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
900 10 ### 162.84 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
950 IP2, 1640 05' 50 ### 162.65 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1000 50 ### 162.37 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1050 50 ### 162.23 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1100 Drain PUP 50 ### 162.05 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1140 FB 40 ### 162.05 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1150 10 ### 162.03 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1200 50 ### 161.92 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
IP3, 2140 46'
1250 05" 50 ### 161.98 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1300 50 ### 162.03 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1333 33 ### 161.54 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1400 67 ### 162.03 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1450 50 ### 161.89 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1500 50 ### 161.89 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1500 0 ### 161.89 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
1550 50 ### 161.85 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
Outlet to
1575 locaKulo 25 ### 161.49 3.000 0.760 ### 5.740 ### ### 0.690 ### ### ###
10575 LS offtake DB 25 ### ### 1.300 0.510 ### 3.139 ### ### 0.430 ### ### ###
10575 DB HL 0.15m 0 ### ### 1.300 0.460 ### 2.959 ### ### 0.408 ### ### ###
10600 25 ### ### 1.300 0.460 ### 2.959 ### ### 0.408 ### ### ###
10650 50 ### ### 1.300 0.460 ### 2.959 ### ### 0.408 ### ### ###
10690 RS offtake 40 ### ### 1.300 0.480 ### 3.031 ### ### 0.417 ### ### ###
10690 DB HL 0.15m 0 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10700 10 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10750 50 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10800 50 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10850 50 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10900 50 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10910 LS offtake 10 ### ### 1.200 0.460 ### 2.859 ### ### 0.403 ### ### ###
10910 DB HL 0.15m 0 ### ### 1.200 0.530 ### 3.111 ### ### 0.434 ### ### ###
10930 LS offtake 20 ### ### 1.200 0.530 ### 3.111 ### ### 0.434 ### ### ###
10930 DB HL 0.15m 0 ### ### 1.200 0.390 ### 2.606 ### ### 0.369 ### ### ###
10950 20 ### ### 1.200 0.390 ### 2.606 ### ### 0.369 ### ### ###
10990 LS offtake 40 ### ### 1.200 0.390 ### 2.606 ### ### 0.369 ### ### ###
10990 DB HL 0.15m 0 ### ### 1.000 0.310 ### 2.118 ### ### 0.451 ### ### ###
16 8
16 6
16 4
16 2
16 0
RL,m
15 8
15 6
15 4
15 2
15 0
EGL
BL
FSL
BTL
14 8
14 6
B2 Branch
20 0
40 0
60 0
80 0
0
1 ,0 0 0
1 ,2 0 0
1 ,4 0 0
1 ,6 0 0
1 ,8 0 0
2 ,0 0 0
2 ,2 0 0
2,4 0 0
2,6 0 0
2 ,8 0 0
3 ,0 0 0
EGL
BL
FSL
BTL
3 ,0 0 0
6,0 0 0
Ch a in a g e m
2 ,8 0 0
5 ,8 0 0
2,6 0 0
5 ,6 0 0
2,4 0 0
5 ,4 0 0
2 ,2 0 0
5 ,2 0 0
L-Section of S5 Secondary Canal
2 ,0 0 0
5 ,0 0 0
1 ,8 0 0
4 ,8 0 0
1 ,6 0 0
4 ,6 0 0
1 ,4 0 0
4 ,4 0 0
1 ,2 0 0
4 ,2 0 0
1 ,0 0 0
4 ,0 0 0
80 0
3 ,8 0 0
EGL
FSL
BTL
BL
60 0
3 ,6 0 0
40 0
3 ,4 0 0
20 0
3 ,2 0 0
0
16 8
16 6
16 4
16 2
16 0
15 8
15 6
15 4
15 2
15 0
14 8
14 6
EGL
RL,m
FSL
BTL
3 ,0 0 0
BL
9 ,2 0 0
3 ,0 0 0
9 ,0 0 0
2 ,8 0 0
8 ,8 0 0
2,6 0 0
8 ,6 0 0
2,4 0 0
8 ,4 0 0
2 ,2 0 0
8 ,2 0 0
L-Section of S5 Secondary Canal
2 ,0 0 0
8 ,0 0 0
1 ,8 0 0
7 ,8 0 0
1 ,6 0 0
7 ,6 0 0
1 ,4 0 0
7 ,4 0 0
1 ,2 0 0
7 ,2 0 0
1 ,0 0 0
7 ,0 0 0
80 0
6 ,8 0 0
EGL
FSL
BTL
BL
60 0
6 ,6 0 0
40 0
6 ,4 0 0
20 0
6 ,2 0 0
0
16 8
16 6
16 4
16 2
16 0
15 8
15 6
15 4
15 2
15 0
14 8
14 6
EGL
RL,m
FSL
BTL
BL
6,0 0 0
3 ,0 0 0
1 2 ,0 0 0
2 ,8 0 0
1 ,8 0 0
2,6 0 0
1 ,6 0 0
2,4 0 0
1 ,4 0 0
2 ,2 0 0
1 ,2 0 0
L-Section of S5 Secondary Canal
2 ,0 0 0
1 ,0 0 0
1 ,8 0 0
1 0 ,8 0 0
1 ,6 0 0
1 0 ,6 0 0
1 ,4 0 0
1 0 ,4 0 0
1 ,2 0 0
1 0 ,2 0 0
1 ,0 0 0
1 0 ,0 0 0
80 0
EGL
FSL
BTL
BL
9 ,8 0 0
60 0
9 ,6 0 0
40 0
9 ,4 0 0
20 0
9 ,2 0 0
0
16 8
16 6
16 4
16 2
16 0
15 8
15 6
15 4
15 2
15 0
14 8
14 6
EGL
RL,m
FSL
BTL
BL
Detailed Quantity Estimate 145 of 162
Component: Weir
Location : Rajkulo(S1), Gulara Bandh
Component: Weir
Location : Rajkulo(S1), Gulara Bandh
Component: Weir
Location : Rajkulo(S1), Gulara Bandh
10
Boulder filling in gabion boxes
U/s guide wall protection both sides 10 9.00 3.00 0.75 202.50
u/s launching 1 30.00 3.00 0.75 67.50
D/s guide wall protection both sides 10 12.00 3.00 0.75 270.00
d/s launching 1 30.00 4.50 0.75 101.25
Total 641.25 m3
11 Making gabion boxes 190 15.75 m2 2993.00 m2
D/s guide wall protection both sides 2 12.00 3.00 0.20 14.40
d/s launching 1 30.00 4.50 0.20 27.00
88.20 m3
13 Structural backfilling work 30% of item no 1 & 2 340.00 m3
14 Construction of earthen
Embankment u/s 2 50.00 4.00 1.50 600.00
d/s 2 25.00 4.00 1.50 300.00
900.00 m3
15 Turfing work
u/s 2 50.00 4.68 468.00
d/s 2 25.00 4.68 234.00
702.00 m2
17
Dewatering & diversion work 1 job
18 Site clearance L.S. 1 job
Component: Weir
Location : Rajkulo(S1), Jabdahawa Bandh
Component: Weir
Location : Rajkulo(S1), Jabdahawa Bandh
Component: Weir
Location : Rajkulo(S1), Jabdahawa Bandh
10
Boulder filling in gabion boxes
U/s guide wall protection both sides 10 12.00 3.00 0.75 270.00
u/s launching 1 15.00 3.00 0.75 33.75
D/s guide wall protection both sides 10 12.00 3.00 0.75 270.00
d/s launching 1 15.00 4.50 0.75 50.63
Total 624.38 m3
11 Making gabion boxes 185 15.75 m2 2914.00 m2
D/s guide wall protection both sides 2 12.00 3.00 0.20 14.40
d/s launching 1 15.00 4.50 0.20 13.50
60.30 m3
13 Structural backfilling work 30% of item no 1 & 2 331.00 m3
14 Construction of earthen
Embankment u/s 2 50.00 4.00 1.50 600.00
d/s 2 25.00 4.00 1.50 300.00
900.00 m3
15 Turfing work
u/s 2 50.00 4.68 468.00
d/s 2 25.00 4.68 234.00
702.00 m2
17
Dewatering & diversion work 1 job
18 Site clearance L.S. 1 job
Component: Weir
Location : Rajkulo(S1), Chor Kulo Bandh
Component: Weir
Location : Rajkulo(S1), Chor Kulo Bandh
Component: Weir
Location : Rajkulo(S1), Chor Kulo Bandh
10
Boulder filling in gabion boxes
U/s guide wall protection both sides 10 9.00 3.00 0.75 202.50
u/s launching 1 16.00 3.00 0.75 36.00
D/s guide wall protection both sides 10 12.00 3.00 0.75 270.00
d/s launching 1 16.00 4.50 0.75 54.00
Total 562.50 m3
11 Making gabion boxes 166.67 15.75 m2 2625.00 m2
D/s guide wall protection both sides 2 12.00 3.00 0.20 14.40
d/s launching 1 16.00 4.50 0.20 14.40
58.80 m3
13 Structural backfilling work 30% of item no 1 & 2 425.00 m3
14 Construction of earthen
Embankment u/s 2 50.00 4.00 1.50 600.00
d/s 2 25.00 4.00 1.50 300.00
900.00 m3
15 Turfing work
u/s 2 50.00 4.68 468.00
d/s 2 25.00 4.68 234.00
702.00 m2
17
Dewatering & diversion work 1 job
18 Site clearance L.S. 1 job
Component: Weir
Location : Rajkulo(S1), magaragadi
Component: Weir
Location : Rajkulo(S1), magaragadi
Component: Weir
Location : Rajkulo(S1), magaragadi
10
Boulder filling in gabion boxes
U/s guide wall protection both sides 10 9.00 3.00 0.75 202.50
u/s launching 1 10.00 3.00 0.75 22.50
D/s guide wall protection both sides 10 12.00 3.00 0.75 270.00
d/s launching 1 10.00 4.50 0.75 33.75
Total 528.75 m3
11 Making gabion boxes 156.67 15.75 m2 2468.00 m2
D/s guide wall protection both sides 2 12.00 3.00 0.20 14.40
d/s launching 1 10.00 4.50 0.20 9.00
46.20 m3
13 Structural backfilling work 30% of item no 1 & 2 276.00 m3
14 Construction of earthen
Embankment u/s 2 50.00 4.00 1.50 600.00
d/s 2 25.00 4.00 1.50 300.00
900.00 m3
15 Turfing work
u/s 2 50.00 4.68 468.00
d/s 2 25.00 4.68 234.00
702.00 m2
17
Dewatering & diversion work 1 job
18 Site clearance L.S. 1 job
Component: Weir
Location : Rajkulo(S1), Khuntipur Bandh
Component: Weir
Location : Rajkulo(S1), Khuntipur Bandh
Component: Weir
Location : Rajkulo(S1), Khuntipur Bandh
10
Boulder filling in gabion boxes
U/s guide wall protection both sides 10 6.00 1.50 0.75 67.50
u/s launching 1 10.00 3.00 0.75 22.50
D/s guide wall protection both sides 10 18.00 1.50 0.75 202.50
d/s launching 1 10.00 4.50 0.75 33.75
Total 326.25 m3
11 Making gabion boxes 96.667 15.75 m2 1523.00 m2
D/s guide wall protection both sides 2 18.00 3.00 0.20 21.60
d/s launching 1 10.00 4.50 0.20 9.00
49.80 m3
13 Structural backfilling work 30% of item no 1 & 2 225.00 m3
14 Construction of earthen
Embankment u/s 2 50.00 4.00 1.50 600.00
d/s 2 25.00 4.00 1.50 300.00
900.00 m3
15 Turfing work
u/s 2 50.00 4.68 468.00
d/s 2 25.00 4.68 234.00
702.00 m2
17
Dewatering & diversion work 1 job
18 Site clearance L.S. 1 job
Summary of Rate
Rate
S.No Description of items Unit Without VAT Remarks
(NRs)
1 Clearing and grubbing m2 27.60
2 Fell trees cut up & disposal. (12-30 cm dia.) No 119.60
3 Fell trees cut up & disposal. (31-60 cm dia.) No 358.80
4 Fell trees cut up & disposal. (61-120 cm dia.) No 901.60
5 Fell trees cut up & disposal. (121-180 cm dia.) No 3680.00
6 Uprooting trees & disposal. (12-30 cm dia.) No 368.00
7 Uprooting trees & disposal. (31-60 cm dia.) No 487.60
8 Uprooting trees & disposal. (61- 120 cm dia.) No 2318.40
9 Uprooting trees & disposal. (121-180 cm dia.) No 11040.00
10 Excavation in major canals by using Machine. m3 207.07
11 Excavation in natural rivers by using machine. m 3
267.81
12 Excavation in foundation for structures in soft clay & silty soil initial lead &
lift. m3 758.08
13 Earth Filling with ecavated soil in15 cm th layer hand compaction with
sprinkling water in initial lead. m3 473.80
14 Embankment filling for pond by using Machine. m3 280.22 415.25
15 Backfill for structures with sprinkling water (filling with excavated soil)
including compaction by using Machine. m3 473.80
16 Hauling of excavated materials more than 200 m m 3
135.03
17 Sod facing on embankment slope (Per 100 m2.)inciuding transportation
of sod. m2 64.25
18 Concrete M20. m3 20417.85
19 Concrete M15. m3 18901.13
20 Concrete M10. m3 14441.41
21 Form work m2 1330.12
22 Reinforcement steel. (10-25 mm ø) Kg 123.86
23 20mm dia Dowel bar 1m long. No Err:509
24 10mm thick Joint filler. m2 1147.12
25 Polysulphide Joint sealer. m2 603.75
26 Geo-textile Fabric(TS-30). m2 242.89
Summary of Rate
Rate
S.No Description of items Unit Without VAT Remarks
(NRs)
27 Making gabion boxes (3*1*1m) with hexagonal mesh including wire
cutting, netting etc all complete
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-
7 SWG
m2 366.39
28 Making gabion boxes (3*1.0*50m) with hexagonal mesh including wire
cutting, netting etc all complete
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-
7 SWG
m2 360.57 360.92
29 Making gabion boxes (3*1.0*30m) with hexagonal mesh including wire
cutting, netting etc all complete.
A) Mesh size 10cm X 12cm, mesh wire -10 SWG heavy coated. Selvege-
7 SWG
m2 355.81
30 Making gabion boxes (3*1*1m) with hexagonal mesh including wire
cutting, netting etc all complete
A) Mesh size 8cm X10cm, mesh wire -10 SWG heavy coated. Selvege- m2 418.99
8SWG
31 Making gabion boxes (3*1.0*50m) with hexagonal mesh including wire
cutting, netting etc all complete
A) Mesh size 8cm X 10cm, mesh wire -10 SWG heavy coated. Selvege-8
m2 411.28
SWG
32 Making gabion boxes (3*1.0*30m) with hexagonal mesh including wire
cutting, netting etc all complete.
A) Mesh size 8cm X 10cm, mesh wire -10 SWG heavy coated. Selvege- m2 406.74
8SWG
33 Supplying heavy zinc coated gabion wire & making gabion boxes
(3*0.60*0.60)m with rectangular (15x15)cm mesh wire 8 SWG,Selvedge
wire 6SWG including wire cutting, netting etc all complete.
m2 285.78
34 Supplying heavy zinc coated gabion wire & making gabion boxes
(3*1.50*0.45)m with rectangular (15x15)cm mesh wire 8 SWG,Selvedge
wire 6SWG including wire cutting, netting etc all complete.
m2 288.95
35 Supplying heavy medium coated gabion wire & making gabion boxes
(3*1.5*0.30)m with rectangular (10x10)cm mesh wire 10 SWG,Selvedge
wire 7SWG including wire cutting, netting etc all complete.
m2 329.45
36 Supplying heavy medium coated gabion wire & making gabion boxes
(3*1*1)m with rectangular (10x10)cm mesh wire 10 SWG,Selvedge wire
7SWG including wire cutting, netting etc all complete.
m2 327.54
37 Supply of Boulder & filling in gabion boxes including placing in position,
tighting it all complete. m3 3961.91
Estimated by Checked by Approved by
Page 162 of 162
Summary of Rate
Rate
S.No Description of items Unit Without VAT Remarks
(NRs)
38 PVC water stop seal, 230 mm wide RM Err:509
39 Making trash rack of steel plate as per direction kg 132.25
40 Laying 15cm thick sub-grade of gravel of required size and binding
material clay and silt incl. loading & transporting materials, surface
levelling compacting using roller in the const. site (Norms 15-10 b) m2 1390.17
41 Dry boulder pitching. m3 5822.61
42 Gravel Filter. m3 4725.31
43 Supply & Laying of NP2 Hume pipe 30 cm dia. Rm Err:509
44 Supply & Laying of NP2 Hume pipe 60 cm dia. Rm Err:509
45 Supply & Laying of NP2 Hume pipe 90 cm dia. Rm 7335.39
46 Supply & Laying of NP3 Hume pipe 45 cm dia. Rm 5183.22
47 Supply & Laying of NP3 Hume pipe 60 cm dia. Rm 6811.79
48 Supply & Laying of NP3 Hume pipe 90 cm dia. Rm 11141.02
49 Stripping works. m2 151.61
50 Supply,fitting and fixing of Steel gate for inlet and outlet all complete set. m2 35,075.00