DPR
DPR
9706464510
BE,PGDRD,MIE,FIV. Chartered Engineer, Approved Valuer
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Sl. Name of Anchalik No. of GPs under the No.of GPs selected
No. Panchayat Corresponding A.P. against each A.P.
1. Titabar AP 16 2
2. North West AP 18 3
3. Jorhat AP 27 4
4. Central Jorhat A.P. 10 2
5. Kaliapani A.P. 10 1
6. East Jorhat AP 9 1
7. Majuli AP 12 2
8. Ujani Majuli AP 8 1
After it, the Gaon Panchayats are selected on the basis of population and availability
of land in each Gaon panchayat area for construction of the Community Hall. The selected
Gaon Panchayats, in the first phase,are------------
Sl
No AP Location (GP)
1 Kaliapani No.5 Pub Teok
2 East Jorhat No.16 NE Nakachari
3 Central Jorhat No.25 Pub Hollongapar
4 No.27 Madhya Chowkhat Hatigarh
5 NW Jorhat No.41 Madhya Parbotia
6 No.40 Uttar Parbatia Janajati
7 No.46 Charingia
8 Jorhat No. 51 Baghchung Charaibahi
Er. B. Bordoloi Ph. 9706464510
BE,PGDRD,MIE,FIV. Chartered Engineer, Approved Valuer
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
9 No.49 Madhya Namani Charaibahi GP
10 No.73 Madhya Thengal Khangia
11 No. 64 Pub Thengal
12 Titabar No.75 Kakadonga Bekajan
13 No. 89 Borholla
14 Ujani Majuli No.95 Luitporia
15 Majuli No. 106 Dakhin Kamalabari
16 No. 111 Sri Luit
4.Availability of land:-The sufficient land is available for all the sites selected for construction of
Community Hall. The sites are so selected that sufficient open space is available around the building.
6.The Building Provision:- Due to varying Communication and geographical condition, two types
of plan & estimates for the Community Hall are prepared for Jorhat District. One is for Majuli and
other is for Titabar & Jorhat Sub-division. The building has the provision of a hall and a stage. In the
hall, the wall will be constructed upto W.S.L, and in the stage, it will be upto PPL. A Urinal with a
soakpit is also provided.
7. Rate:- The estimates are prepared as per APWD Schedule of rates of 2010-11 by deducting 10%
Contractor’s Profit. Additional premium of 20% is added for Majuli Sub-Division as per provision of
APWD SOR. Further, surcharge is also added for Rod and Cement as per notification of
APWD(BUILDING).
9. Drawing:- All the drawings required for this purpose are supplied with the estimate.
10.Execution:- The works will be executed by a construction Committees constituted for this
purpose with one technical expert as the Secretary of the Committee. The works will be executed by
observing all the guideline of the Assam PWD Schedule.
Prepared by:
ER. B.BORDOLI
BE, PGDRD, FIV,MIE
Charterd Engineer, Approved Valuer.
ESTIMATE
REPORT
This estimate amounting to Rs. 800,000.00 ( Rupees Eight Lkhs ) only has been framed to
to show the Probable cost of Construction of community hall cum stage at G.P office campus under general
perfomance grant, 13 F.C in Jorhat District.
The estimate has been prepared as per APWD Schedule of Rates (Building) for the year 2010-2011
and all works will be carried out in accordance with the general guidelines and specification of APWD, Assam
current in the state.
Item No. 2: Providing soling in foundation under floor at all levels with stone best quality jhama bricks,
SOR sand packed and laid to level and in panel after preparing the sub-grade as directed including
4.1.1 (a) all labour and materials and if necessary dewatering complete.(a) Brick on Flat Soling
Item No. 3: Plain cement concrete works with coarse aggregate of size 13mm to 32mm in foundation
SOR steps, footing of column & plinth beam as directed & specified including curing complete
2.1.1 (c) (shuttering where necessary shall be measured & paid separately) in proportion 1 cement: 5
sand: 10 coarse aggregate by volume.
Qnty. : 1 x 14 x 1.20 x 1.20 x 0.10 = 2.016 cum.
Qnty. : 1 x 2 x 1.00 x 1.00 x 0.10 = 0.200 cum.
TOTAL = 2.016 cum.
@ Rs. 3130.44 / cum. - - - - - - - - - - - - - - - Rs. 6,311.00
Cement Required = 2.016 x 4.25 bags = 8.57 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - - - Rs. 556.92
Item No. 4: Supplying, fitting & fixing in position reinforcement bars conforming to IS relevant code for
SOR 18.1.1 RCC work/RB walling including straightening, cleaning, citing & bending to proper shape &
(b) (ii) length as per binding to 20 G annealed black wire & placing in position with cover blocks
support, chairs, spacer etc. complete (upto 1st floor level)
Footing 10ø @100c/c : 16 x 22 x 1.000 x 0.62 = 218.240 Kg.
Column 16ø, 4 Nos. : 10 x 4 x 6.000 x 1.58 = 379.200 Kg.
Column 16ø, 4 Nos. : 4 x 4 x 7.500 x 1.58 = 189.600 Kg.
Column 16ø, 4 Nos. : 2 x 4 x 2.750 x 1.58 = 34.760 Kg.
Tie Beam 16ø, 4 Nos. : 5 x 4 x 9.500 x 1.58 = 300.200 Kg.
Tie Beam 16ø, 4 Nos. : 2 x 4 x 14.900 x 1.58 = 188.336 Kg.
Column 12ø, 2 Nos. : 10 x 2 x 6.000 x 0.89 = 106.800 Kg.
Column 12ø, 2 Nos. : 4 x 2 x 7.500 x 0.89 = 53.400 Kg.
Tie Beam 12ø, 2 Nos. : 4 x 4 x 7.670 x 0.89 = 109.221 Kg.
Tie Beam 12ø, 2 Nos. : 2 x 4 x 14.900 x 0.89 = 106.088 Kg.
Qnty. C/O = 1685.845 Kg.
Item No. 5: Providing formwork of ordinary timber planking so as to give rough finish including centering
SOR shuttering & propping etc. Height of propping & centering below supporting floor to ceiling &
3.1.1.1(ii) removal of same for cast-in-situ reinforced concrete & plain concrete works. (Using 25mm
thick planks)SUB-STRUCTURE
Qnty. Footing 14 x 4 x 0.15 x 1.200 = 10.080 sq.m
Colm. 14 x 4 x 0.25 x 6.000 = 84.000 sq.m
Colm. 2 x 4 x 0.25 x 2.500 = 5.000 sq.m
T.Beam 2 x 5 x 0.30 x 9.000 = 27.000 sq.m
T.Beam 2 x 2 x 0.30 x 14.400 = 17.280 sq.m
L.Beam 2 x 4 x 0.15 x 9.000 = 10.800 sq.m
L.Beam 1 x 4 x 0.125 x 9.000 = 4.500 sq.m
L.Beam 2 x 4 x 0.15 x 14.400 = 17.280 sq.m
L.Beam 1 x 4 x 0.125 x 14.400 = 7.200 sq.m
TOTAL = 183.140 sq.m
@ Rs. 213.70 / sq.m. - - - - - - - - - - - - - - - Rs. 39,137.00
Item No. 6: Providing & laying plain/reinforced cement concrete works in proportion 1:2:4 (1 cement : 2
SOR coarse sand : 4 graded stone aggregate 20mm down) including dewatering if necessary &
2.2.1 (I)(A)(a) curing complete but excluding the cost of form work and reinforcement for RCC work. (Form
work & reinforcement will be measured separately)
SUB-STRUCTURE 16 x 1.200 x 1.200 x 0.150 = 3.456 cum.
16 x 0.625 x 0.625 x 0.400 = 2.500 cum.
16 x 0.250 x 0.250 x 1.250 = 1.250 cum.
5 x 0.250 x 0.300 x 9.000 = 3.375 cum.
2 x 0.250 x 0.300 x 14.400 = 2.160 cum.
TOTAL = 12.741 cum.
@ Rs. 4734.15 / cum. - - - - - - - - - - - - - - - Rs. 60,318.00
Cement Required = 12.741 x6.13 bags 78.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - - - Rs. 5,070.00
Item No. 7 Brick work in cement mortar with 1st class brick including racking out joints and dewatering if
SOR 4.1.4 necessary and curing complete as directed in sub-structure upto Plinth Level.(c) In prop. 1:4
2 x 0.25 x 1.35
9.000x = 6.075 Cum.
3 x 0.25 x 0.70
9.000x = 4.725 Cum.
2 x 0.25 x 1.35
3.600x = 2.430 Cum.
6 x 0.25 x 0.70
3.600x = 3.780 Cum.
2x 0.50 x 1.80 x 1.35
1.200x = 2.916 Cum.
5x 0.50 x 0.90 x 1.35
1.200x = 3.645 Cum.
TOTAL = 23.571 Cum.
@ Rs. 4632.29 / cum. - - - - - - - - - - - - - - - Rs. 109,188.00
Cement Required = 23.571 x 2.00 bags 47.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - - - Rs. 3,055.00
Item No. 8: Sand filling in plinth layers not more than 150mm thick including necessary carriage watering,
SOR 1.3 C ramming etc… with silt (predominantly non plastic) by tuck carriage including loading and
unloading.
1 x 10.80 x 9.00 x 0.700 = 68.040 cum.
1 x 3.60 x 9.00 x 1.350 = 43.740 cum.
TOTAL = 111.780 cum.
@ Rs. 322.75 / cum. - - - - - - - - - - - - - - - Rs. 36,077.00
Item No. 9: 112mm thick 1st class Brick nogged wall in cement mortar including raking out joints and
4.1.7(a) curing comnplete as directed in super structure above plinth level upto 1st floor.(Protruding
rod/Tor steel of columns to be embedded in cement mortar & will be measured and paid for
separately.) In cement mortar 1:4
Wall 1 x 1 x 9.00 x 3.300 = 29.700 sq.m
1 x 2 x 3.60 x 3.300 = 23.760 sq.m
1 x 2 x 10.80 x 1.500 = 32.400 sq.m
1 x 1 x 9.00 x 1.500 = 13.500 sq.m
2 x 0.5 x 9.00 x 1.500 = 13.500 sq.m
Door (-) 2 x 1 x 2.10 x 1.000 = -4.200 sq.m
Door (-) 3 x 1 x 0.70 x 1.200 = -2.520 sq.m
Window (-) 2 x 1 x 1.40 x 1.200 = -3.360 sq.m
Ventilator (-) 3 x 1 x 1.40 x 0.600 = -2.520 sq.m
TOTAL = 100.260 sq.m
@ Rs. 518.62 / Sq.m. - - - - - - - - - - - - - - - - Rs. 51,997.00
Cement Required =100.26 x 2.13 bags/ 10 Sqm 21.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - - - Rs. 1,365.00
Item No. 10: 10mm thick cement plaster in single coat on fair side of single or half brick wall for interrior
SOR 6.2.1(a) plastering upto 1st floor level including arises, internal rounded angles not exceeding 80mm
girth, including curing complete as directed. b) In cement mortar 1:4
Wall 1 x 1 x 9.00 x 3.300 = 29.700 sq.m
1 x 2 x 3.60 x 3.300 = 23.760 sq.m
1 x 2 x 10.80 x 1.500 = 32.400 sq.m
1 x 1 x 9.00 x 1.500 = 13.500 sq.m
2 x 0.5 x 9.00 x 1.500 = 13.500 sq.m
Door (-) 2 x 1 x 2.10 x 1.000 = -4.200 sq.m
Door (-) 3 x 1 x 0.70 x 1.200 = -2.520 sq.m
Window (-) 2 x 1 x 1.40 x 1.200 = -3.360 sq.m
Ventilator (-) 4 x 1 x 1.40 x 0.600 = -3.360 sq.m
TOTAL = 99.420 sq.m
TOTAL both = 198.840 sq.m
Plinth 1 x 2 x 19.60 x 0.750 = 29.400 sq.m
1 x 2 x 12.60 x 1.350 = 34.020 sq.m
TOTAL = 262.260 sq.m
@ Rs. 88.60 / Sq.m. - - - - - - - - - - - - - - - Rs. 23,236.00
Cement Required =262.26 x 0.87bags/10sqm. 23.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - - - Rs. 1,495.00
Item No. 11 65mm thick cement concrete topping 1:2:4 (1cement :2 coarse sand : 4 coarse aggregateof
SOR 5.1.2 12mm nominal size ) finished with a floating coat of neat cement finish (base concrete to be
neasured and paid separately) to be laid in panels including curing complete as directed.
Item No. 12: Supplying, fitting and fixing door frame made of M.S equal anghles of size 40mm x 40mm x
SOR 18.7.1 5mm fabricarted, welded, nitres and joinedas per relevant I.S.Codes……complete at all levels
as specified.
Qnty. : Door 1 x 2 x 5.40 = 10.800 Rm.
Window 1 x 2 x 5.20 = 10.400 Rm.
Ventilator 1 x 4 x 4.00 = 16.000 Rm.
TOTAL = 37.200 Rm.
@ Rs. 344.80 / Rm. - - - - - - - - - - - - - - - Rs. 12,827.00
Item No. 13: Providing, fitting and fixing steel door/window of standard rooled steel section as per relevant
SOR 18.5.3 I.S.code, joints mitred……..applying a priming coat of red-lead paint etc..complete as directed
(a) a). Openable.
Item No. 2: Providing soling in foundation and under floor with stone/best quality picked jhama brick, sand
SOR packed and laid to level and in panel after preparing the sub-grade as directed including all labour
4.1.1 (a) and materials and if necessary dewatering complete.
Footing : 4 x 0.600 x 0.600 = 1.440 Sq.m.
Under Floor 1 x 1.200 x 2.400 = 2.880 Sq.m.
Total Qnty. = 4.320 Sq.m.
@ Rs. 286.37 / Sq.m. - - - - - - - - - - Rs. 1,237.12
Item No. 3: Plain cement concrete works with coarse aggregate of size 13mm to 32mm in foundation steps,
SOR footing of column & plinth beam as directed & specified including curing complete (shuttering
2.1.1 (c) where necessary shall be measured & paid separately) in proportion 1 cement: 5 sand: 10 coarse
aggregate by volume.
Footing : 4 x 0.600 x 0.600 x 0.100 = 0.144 Cum.
Total Qnty. = 0.144 Cum.
@ Rs. 3,130.44 / Cum - - - - - - - - - - Rs. 450.78
Cement Required = 0.144 x 4.25 bags = 1.00 Bags
@ Rs. 65 / Bag - - - - - - - - - = Rs. 65.00
Item No. 4: Supplying, fitting and laying in position reinforcement in position in RCC works including cutting,
SOR bending, crancking, binding with two plies 0.91mm (20SWG) black annelead wire, hooking, tying
18.1.1(b)(ii) complete a directed.
Column: 10ø, 4 Nos. 2 x 4 x 3.725 x 0.620 = 18.476 Kg.
Column: 10ø, 4 Nos. 2 x 4 x 3.425 x 0.620 = 16.988 Kg.
Tie Beam: 10ø, 4 Nos. 2 x 4 x 2.400 x 0.620 = 11.904 Kg.
Tie Beam: 10ø, 4 Nos. 2 x 4 x 1.200 x 0.620 = 5.952 Kg.
Lintel Beam: 8ø, 4 Nos. 2 x 4 x 2.400 x 0.390 = 7.488 Kg.
Lintel Beam: 8ø, 4 Nos. 2 x 4 x 1.200 x 0.390 = 3.744 Kg.
Clom. Binder: 6ø @ 150 c/c 2 x 25 x 0.550 x 0.220 = 6.010 Kg.
Clom. Binder: 6ø @ 150 c/c 2 x 23 x 0.550 x 0.220 = 5.526 Kg.
Tie Binder: 6ø @ 150 c/c 2 x 16 x 0.650 x 0.220 = 4.576 Kg.
Tie Binder: 6ø @ 150 c/c 2 x 8 x 0.650 x 0.220 = 2.288 Kg.
Lintel Binder: 6ø @ 150 c/c 2 x 16 x 0.550 x 0.220 = 3.872 Kg.
Lintel Binder: 6ø @ 150 c/c 2 x 8 x 0.550 x 0.220 = 1.936 Kg.
Total Qnty. = 88.760 Kg.
Total Qnty. = 0.888 Qntl.
@ Rs. 4,746.44 / Qntl. - - - - - - - - - - Rs. 4,214.84
Price Difference @ Rs. 1400.00 / Qtl. - - - - - - - - - - - - - Rs. 1,243.20
Item No. 6: R.C.C work in proportion 1:3:6 in foundation, abutment, piers, wing ewalls etc. with hard broken
SOR stone aggregate of size 13mm to 38mm including curing with necessary timber chuttering,
2.2.1 scaffolding where necessary, complete as directed (Shuttering, scaffolding cost will be paid
(I)(A)(a) separately.)
SUB-STRUCTURE
Footing: 4 x 0.60 x 0.60 x 0.200 = 0.288 Cum.
Colm. upto PL 4 x 0.15 x 0.15 x 0.925 = 0.083 Cum.
2 x 2.40 x 0.15 x 0.20 = 0.144 Cum.
2 x 1.20 x 0.15 x 0.20 = 0.072 Cum.
(-) 4 x 0.15 x 0.15 x 0.20 = -0.018 Cum.
Total Qnty. = 0.569 Cum.
@ Rs. 4,734.15 / Cum - - - - - - - - - - Rs. 2,693.73
Cement Required = 0.692 x 6.13 bags = 3.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - Rs. 195.00
SUPER-STRUCTURE
Cloumn 2 x 2.70 x 0.15 x 0.15 = 0.122 Cum.
2 x 2.40 x 0.15 x 0.15 = 0.108 Cum.
2 x 2.40 x 0.15 x 0.13 = 0.094 Cum.
2 x 1.20 x 0.15 x 0.13 = 0.047 Cum.
(-) 4 x 0.20 x 0.20 x 0.15 = -0.024 Cum.
Total Qnty. = 0.347 Cum.
2.2.1 (B)(ii)(a) @ Rs. 4,929.24 / Cum - - - - - - - - - - Rs. 1,710.45
Cement Required = 0.525 x 6.13 bags = 2.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - Rs. 130.00
Item No. 8: Earth/Sand filling in plinth in layers not more than 15cm thick, including necessary carriage,
SOR watering, ramming, etc. complete as directed and specified including payment of land
1.3 (C) compansation, forest royelty, sales tax and other duties and taxes may be necessary.(C) With
riversand or silt by truck carriage including loading and unloading
1 x 2.40 x 1.20 x 0.300 = 0.864 Cum
Total Qnty. = 0.864 Cum
@ Rs. 322.75 / Cum - - - - - - - - - - Rs. 278.86
Item No.10: 10mm thick cement plaster in single coat on fair side of brick/concrete walls for interior
SOR 6.2.1 plastering upto 1st floor level including arises or rounded angles not exceeding 80mm girth and
finished even and smooth including curing complete as directed. (b). In prop. 1:4
Same as item No.9 = 20.565 Sq.m.
/ Sq.m. - - - - - - - - - -
@ Rs. 88.60 Rs. 1,822.06
Cement Required = 41.13 x 0.87 bags/10sqm. = 2.00 Bags
@ Rs. 65 / Bag - - - - - - - - - - - - - Rs. 130.00
Item No.11: 40mm thick CC flooring consisting of 25mm under layer of cement concrete in prop
SOR 5.1.3 1:3:6(1cement:3coarse sand:6coarse aggregate of 12.5mm down…….complete as directed.
1 x 2.400 x 1.200 = 2.880 Sq.m.
Total Qnty. = 2.880 Sq.m.
@ Rs. 345.32 / Sq.m. - - - - - - - - - - Rs. 994.52
Item No.:12 Providing fitting hoisting and fixing of roof trusses including purlins fabricated out of MS black
SOR 18.3.1 tubes conforming to IS code as per approved design and drawing including providing MS cleats,
base plates, bolts and nuts and one coat of red oxide primer as directed.
42.4ø Pipe 3 x 2.100 x 3.150 = 19.845 Kg.
3 x 3.000 x 3.150 = 28.350 Kg.
Total Qnty. = 48.195 Kg.
Total Qnty. = 0.482 Qntl.
@ Rs. 5,875.00 / Qntl. - - - - - - - - - - Rs. 2,831.46
Item No.13: Supplying, fitting and fixing of GCI Sheet roofing (0.45mm thick)
1 x 2.10 x 3.000 = 6.300 Sq.m.
@ Rs. 335.27 / Sq.m. - - - - - - - - - - Rs. 2,112.20
Item No.:15 Providing, fitting and fixzing ful panel doors/windows including oxidised MS butt
SOR 9.9.2 hinges(100mmx75mmx3.55) with necessary screws(other fittings to be measured and paid
(B) separately.)(iii) 30mm thick
Qnty: 2 x 2.100 x 0.750 = 3.150 Sq.m.
Total Qnty. = 3.150 Sq.m.
@ Rs. 1,406.43 / Qntl. - - - - - - - - - - Rs. 4,430.25
Shri Ratul Ch. Duarah, ACS Shri Bikash Bordoloi Shri Lakhi Handiquie
Chief Executive Officer Assistant Engineer Junior Engineer
Jorhat Zila Parishad Jorhat Zila Parishad Jorhat Zila Parishad
2400
1200 1200
A
3000
2700
2400
1200
300
P.L.
G.L.
A'
1200
PLAN of TOILET BLOCK
Section at A-A'
Column (150x150)
Column (150x150) 10ø - 4 Nos.
10ø, 4 Nos.
P.L.
300
G.L.
Tie Beam (150x200)
600
10ø - 4 Nos.
6ø stirrups @ 150 c/c
900
200
100
P.L.
600
G.L.
P.C.C.
75
BRICK SOLING
300
600
ELEVATION Footing Details
ESTIMATE
REPORT
This estimate amounting to Rs. 800,000.00 ( Rupees Eight Lkhs ) only has been framed to
to show the Probable cost of Construction of community hall cum stage at G.P office campus under general
perfomance grant, 13 F.C in Jorhat District.
The estimate has been prepared as per APWD Schedule of Rates (Building) for the year 2010-2011
and all works will be carried out in accordance with the general guidelines and specification of APWD, Assam
current in the state.
1. GROUND FLOOR
ITEM:
Sl. Description Qty. Unit Rate Amount
1/1.1 Earth work in excavation in foundation trenches of
walls, columns, steps etc. including refilling the quantity
after completion of work—in ordinary soil
Post= 2x1.0x1.0x1.0=2.0 Cm
Post= 14x1.2x1.2x1.2 = 24.192cum 26.19 Cum. 64.67 1693.84
2/4.1. Providing soling in foundation and under floor at all
1 levels with jhama bricks—brick flat soling.
Footing-14x1.2x1.2=20.16 sq.m.
2x1.0x1.0= 2.000sq.m.
Floor&T/beam-12.25x7.75=94.94sq.m. 117.10 Sqm 286.37 33533.93
3/2.1. PCC works in 1:4:8 with coarse agg. of size 13mm to
1 32mm in foundation bed of footing, steps,walls etc.
14x1.20x1.20x0.10=2.016cem.
2x1.00x1.00x0.10=0.200 cem. 2.216 Cum. 3,398.10 7530.19
4/18. Supplying, fitting, fixing in position reinf. bars
1.1 including cutting bending to proper shape and length
and binding with 20G black wire --torsteel.
Footing,100mm c/c,
14x26x1.20x0.62 = 270.811kg.
2x22x1.00x0.62=27.28Kg
Column 16mm & 12mm dia
10x4x6.30x1.58=398.16 kg
2x4x3.05x1.58=38.55kg
10x2x6.30x0.89=112.14 kg.
4x2x7.80x0.89=55.53 kg.
Tie beam , 16mm
2x12.00x4x1.58=151.68kg
3x4x7.5x1.58 =142.20 kg
Extrabar 12mm,2x2x10x1.200x0.89=42.72 kg.
3x2x7.50x0.89 =40.05 kg
Lintel 12mm, 2x4x12.00x089=85.44 kg
2x4x7.50x0.89 =53.40 kg
Stirrups 6mm dia.
Column. 10x41x0.83x0.22=74.86
4x51x0.83x0.22 = 37.25 Kg.
2x19x0.83x0.22=6.93
T.beam 2x80x0.83x0.22=29.21
3x50x0.83x0.22=27.39
Lintel. 2x80x0.55x0.22=19.36
2x50x0.55x0.22=12.10
Total = 1822.24 kg, adding 10% for wastage, lapping 106337.24
etc. total = 2004.46 kg , say 20.1 Qtl 20.1 Qtls. 5290.41
5/3.1. Providing form work of ordinary timber shuttering to
1.1 give a rough finish in sub structure--25mm th.
(a) Substructure
Footing = 14x4x0.20x1.00 = 11.20 sqm.
2x4x0.20x0.80 = 1.28 sqm.
Column =10x4x0.25x5.35 = 53.50 sqm.
4x4x0.25x6.85 = 27.40 sqm.
2x4x0.25x2.05 = 4.10 sqm.
T.beam 2x2x0.30x12.00=14.40 sqm.
3x2x0.30x7.50 = 13.50 sqm.
Lintel 2x2x0.20x12.00 = 9.60 sqm.
2x2x0.20x7.50 = 6.00 sqm.
2x1x0.15x12.00=3.60 sqm.
2x1x0.15x7.50 = 2.25 sqm. 146.83 Sqm 213.7 31377.57
6/2.2. Providing and laying RCC works in Prop. 1:2:4
1(a) including curing etc. complete as directed.
(a) Sub-structure
14x1.00x1.00x0.20 = 2.80cm.
2x0.80x0.80x0.20 = 0.25cm.
14x1/2x(1.0x1.0+0.25x0.25)0.35=2.55 cm
2x1/2(0.80x0.8+0.25x0.25)x0.35 = 0.24cm.
16x0.25x0.25x2.05 = 2.05cm.
T.beam. 2x12.00x0.25x0.30 =1.80cm.
3x7.50x0.25x0.30 = 1.68cm. 11.37 cm 4734.15 53827.29
2.2.1 (b) Super-structure
(ii) 10x0.25x0.25x3.30 = 2.06cm.
4x0.25x0.25x4.80 = 1.20cm.
Lintel 2x12.00x0.20x0.15 =0.72cm.
2x7.50x0.20x0.15 = 0.45cm.
4.43 Cum. 4,929.24 21836.53
7/4.1 Brick work in cement mortar in prop 1:4 with first class
5(c) brick including racking out joints and curing complete
upto plinth level
2x9.00x1.20x0.25 = 5.40
1x7.50x1.20x0.25 = 2.25
2x3.00x1.80x0.25 = 2.70
2x7.50x1.80x0.25 =6.75
Steps,6x1.65x0.3(0.15+0.3+0.45+0.6)=4.46cm 21.56 Cum. 4,632.20 99870.23
8/1.3( Sand filling in layers not more than 15cm thick
c) including breaking clods, dressing, ramming etc.
complete by truck carriage.
1x9.00x7.50x1.50=101.25cm
1x3.00x7.50x2.10=47.25cm
total = 148.5 cm. 148.50 Cum. 322.75 47928.38
st
4/4.1. 112mm thick 1 class brick nogged wall in cement
7 mortar 1:4 including racking out joints and curing
complete.
S/wall, 1x7.5x(0.75+0.75) = 11.25sqm
1x7.5x3.30 =24.75sqm
2x1/2x7.5x1.5 =11.25 sqm
2x3.00x3.30 =19.80 sqm
2x9.00x(0.75+0.75)=27.00 sqm
total = 94.05 sqm.
Deduction.
Door. 2x2.10x1.00=4.20 sqm
3x0.75x1.00=2.25 sqm
Window2x1.20x1.00=2.40 sqm
Ventilator2x0.50x1.00=1.00 sqm
Total deduction = 9.85 sqm
Net Area = 84.2 Sqm. 84.20 sqm 518.62 43667.80
10/62 10mm thick cement plastering in single coat in
.1.a proportion 1:4
Plinth. 2x9.00x1.20 = 21.60cm
2x3.00x1.80 = 10.80cm
1x7.50x1.20 = 9.00cm
1x7.50x1.80 = 13.50cm
Wall. 2x2x(0.75+0.75)x9.00=54.00cm
2x2x3.00x3.30=39.60cm
1x2x7.50x(0.75+0.75)=22.50cm
2x2x0.5x7.5x1.5=22.50cm
1x2x7.50x3.30 =49.50 cm.
Deduction for opening.
Door. 2x2x2.10x1.00 =8.40cm
3x2x0.75x1.00 = 4.50cm
Window.2x2x1.20x1.00=4.80cm
Ventilator.2x2x0.50x1.00=2.00cm 223.30 Sqm 88.6 19784.38
13/5. 65 mm thick PCC flooring in prop. 1:2:4 finished with a
1.4 floating coat of neat cement finish including curing.
1x7.50x12.00 = 90.00 SQm 90.00 Sqm 449.48 40453.20
12/18 Supplying,fitting, fixing door frame made of MS angles
.7.1 of size. 40mmx40mmx5mm fabricated, welded…..
Door 2x(2.1+2.1x1.2)=10.80 rm
Window 2x(2x1.2+2x1.00)=8.80rm
Ventilator 4x(2x0.5+2x1.00)=10.00rm 31.60 Rm 344.8 10895.68
14/13. Colour washing with lime on wall surface two coats to 223.30 Sqm. 21.40 4778.62
2.1 give an even shadeincluding priming coat etc.
8/8.1. Providing Pre Painted Galvanized Iron Sheet roofing
32 (Dyna roof) at all levels including fitting and fixing with
self drilling, self tapping screws complete in 0.60mm
thick.
2x13.2x4.5 = 118.8sqm. 118.80 Sqm. 811.15 96364.62
9/8.1. Providing Pre Painted Galvanized Iron Sheet (Dyna
37 roof) at all levels including fitting and fixing with self
drilling, self tapping screws complete in 0.60mm thick.
13.2 R.m 13.20 R.m 484.89 6400.55
10/18 Providing fitting, hoisting and fixing of roof trusses
.3.1 including purlins fabricated out of M.S. black-tubes
conforming to relevant I.S. code as per approved design
and drawings as directed.
post plate= 2(12.0+7.5)=39 RM
Raftar=5x4.5x2 = 45 RM
King post = 5x1.5 = 7.5 RM
Tie = 5x7.5 = 37.5 RM
Purlin = 10x13.2= 132 RM
Member =5x2(1.8+1.2+.9+.6) = 45.0 RM
Runner=2x10.0=20.0 RM
11.30 Qtls. 5,875.00 66387.50
Total = 326x 3.15Kg/rm =1026.9 kg, adding 10% for wastage,
lapping,base plate etc. = 1129.6 kg, say 11.3 qtl
TOTAL CIVIL COST OF THE BUILDING Rs. 692667.54