RDSO SPEC MRVC Phase 3 TCMS
RDSO SPEC MRVC Phase 3 TCMS
0)
Government of India
Ministry of Railways
TECHNICAL SPECIFICATION
FOR
AC EMUs WITH THREE PHASE ELECTRICS
FOR
MRVC/MUTP-III PROJECT
Approved by
ED (PS&EMU)
SSE/PS&EMU DSE/PS&EMU
Prepared by Checked by
Issued in August'2017
POWER SUPPLY AND EMU DIRECTORATE
RESEARCH DESIGN AND STANDARDS ORGANISATION
MANAK NAGAR, LUCKNOW - 226011
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 2 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Table of Contents
ABBREVIATIONS: ............................................................................................................. 5
DEFINITIONS: ................................................................................................................... 7
Chapter 1 : GENERAL DESCRIPTION AND SUPPLIER’S RESPONSIBILITIES .......... 9
1.1 Introduction ........................................................................................................... 9
1.2 Scope of Supply ................................................................................................. 14
1.3 Supplier’s Responsibilities .................................................................................. 14
1.4 Approval of Design ............................................................................................. 16
Chapter 2 : OPERATING AND SERVICE CONDITIONS, DESIGN CONSTRAINTS ... 20
2.1 Leading Particulars: ............................................................................................ 20
2.2 Payload and Weight Particulars : ....................................................................... 20
2.3 Gauge and Moving Dimensions.......................................................................... 21
2.4 Track Geometry .................................................................................................. 22
2.5 Speed, Acceleration and Deceleration ............................................................... 22
2.6 Traction Power Supply System........................................................................... 23
2.7 Overhead Equipment .......................................................................................... 23
2.8 Power Factor ...................................................................................................... 24
2.9 Fire Safety .......................................................................................................... 24
2.10 Ingress Protection ........................................................................................... 24
2.11 Climatic and Environmental Conditions ........................................................... 24
2.12 Signal and Telecommunication Installations: .................................................. 26
2.13 Reliability, Availability, Maintainability and Safety (RAMS) .............................. 26
2.14 Adhesion Limits: .............................................................................................. 28
Chapter 3 : PERFORMANCE REQUIREMENTS ........................................................ 29
3.1 Performance Requirements ................................................................................ 29
3.2 Power Supply and Environmental Conditions ..................................................... 33
3.3 Neutral Section ................................................................................................... 33
3.4 Interference to Signal and Telecommunication Installations ............................... 33
3.5 Train Resistance: ................................................................................................ 33
3.6 Equipment Layout ............................................................................................... 34
3.7 Minimum Clearance from Rail Level ................................................................... 34
Chapter 4 : SCOPE OF SUPPLY & TECHNICAL SPECIFICATIONS .......................... 35
4.1 A) Scope of Supply ............................................................................................. 35
4.2 B) Technical Specification for 3-Phase Propulsion System with System and
Associated Equipment ................................................................................................. 36
4.3 Traction Transformer .......................................................................................... 36
4.4 Lightning Arrestor ............................................................................................... 37
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 3 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 4 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 5 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
ABBREVIATIONS:
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 6 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 7 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
DEFINITIONS:
Term Definition
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 8 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Rail Level the plane which passes through the top of the cross-
sectional center line of both running rails
RDSO shall mean the Research Designs and Standards
Organization (RDSO), Manak Nagar Lucknow-226011
Reliability shall mean a high degree of probability that an
equipment or system can perform a required function
under specified conditions for a specified period, in
conformity with the operational parameters specified in
this Specification
SDCL ‘SDCL’ means Super Dense Crush Load i.e. Seating
passengers plus standing passengers with density as 16
passengers/m2.
Supplier ‘Supplier’ means the firm or Company or Joint venture
with whom the order for supply of the goods and services
has been placed.
Sub-supplier ‘Sub-supplier’ means any firm or Company from whom
the Supplier may obtain any material, service or fittings
to be used for the goods.
Sub-system shall mean and include all equipment(s) forming part of
such sub-system
TCMS Train Control and Management System (TCMS) is a
modular, scalable, secure, standard control and
communication platform, which manages and controls
the flow of information among various Sub-systems like
Driver’s control, converters, doors, brakes, PIS, lighting,
and air-conditioning etc. TCMS allows for efficient &
reliable Train operation with in-built redundancy. It
generates diagnostic messages useful in Train operation,
troubleshooting, maintenance and communicates with
the wayside control centers
Trailer Car (TC) shall mean Car not fitted with traction motors
Ti shall mean the temperature index of the insulation
system
Transmission and shall mean system comprising traction gears, gear case,
Suspension System primary and secondary suspension springs and dampers
with bogie frame
VDE Verband der Elektrotechnik, Elektronik und
Informationstechnik.
The VDE is the Association for Electrical, Electronic and
Information Technologies and their related sciences,
technologies and applications.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 9 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 10 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
advisable for the Bidder to visit the Mumbai suburban area to assess the
actual site conditions. Some of the salient features of Mumbai suburban
section can be referred in Annexure VII.
1.1.7 This specification establishes requirements for the design, development,
manufacture, supply, testing, delivery, commissioning and integrated testing of
microprocessor controlled 3-phase propulsion and control equipment for broad
gauge AC EMU rolling stock. Leading Car of both the End Basic Unit shall be
provided with driving cab having driver's console duly mounted with the safety
related equipment, instruments and combined master cum brake controller
etc. Each basic unit shall be provided with one pantograph along with
associated high voltage equipment.
1.1.8 Each Middle Basic Unit shall be provided with a shunting panel, which shall
allow to move the single middle basic unit for the shunting purpose. With this
panel, it shall be possible to start the basic unit from de-energized condition,
move the basic unit with a limited speed and de-energize it again. In the End
Basic Units, this operation shall be possible from the regular driver’s desk.
1.1.9 General Design Requirements:-
(i) 3-phase propulsion equipment shall be capable of being mounted in the
underframe and/or roof. Fitment of various equipment will be so
decided that the weight is properly distributed with least possible weight
unbalancing during tare condition. The traction transformer, traction
converter and compressor shall be mounted in the under frame.
(ii) The stock fitted with the supplied equipment shall meet the operating,
service conditions and performance requirements of this specification
and shall be suitable for varying loading conditions occurring in the
Mumbai Suburban.
(iii) Notwithstanding the contents of this specification, the Supplier shall
ensure that the equipment supplied by them is complete in all respect
so as to enable the desired operation & performance of the EMU train
fitted with their equipment.
(iv) The equipment design shall incorporate all essential features necessary
to yield high traffic use, low maintenance requirements, easy
maintainability, high regeneration, high efficiency and high reliability in
train operation.
(v) The entire equipment shall be designed to ensure satisfactory and safe
operation under the running conditions mentioned in this specification
and especially under sudden variations of load and electric pressure as
may arise under working conditions due to faulty operation and short
circuits. The design shall also facilitate erection, inspection,
maintenance and replacement of the various units comprising the
equipment.
(vi) All working parts of the control and auxiliary circuit specifically
electronics and PCBs, shall be suitably covered to keep them free from
moisture, mould growth and dust. The protection level shall be
furnished by the Supplier during design approval.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 11 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(vii) All the electrical equipment shall comply with the latest edition of IEC
specifications unless otherwise specified. The temperature rise shall be
measured according to the procedure stipulated by IEC and shall
comply with the limits specified and the ambient conditions defined in
the Specification. Specified temperature rise of equipment shall be
calculated after taking into account at least 25% choking of air filters
and radiator fins etc. The performance requirements as laid down in
this specification shall be applicable for 12-Car rake considering 4-Car
basic units.
(viii) All equipment shall be adequately earthed, insulated, screened or
enclosed. They shall be provided with essential interlocks & keys as
may be adequate to ensure the protection of the equipment and the
safety of those concerned with its operation and maintenance.
(ix) Supplier shall study the currently available lubricants/cooling oils in
India and employ the same. Full lubrication scheme and schedule for
the equipment shall be submitted. Wherever imported lubricants or
cooling oil are used, Supplier shall study & furnish details of equivalent
Indian lubricants/oil.
(x) The complete system shall be compatible with the Auxiliary Warning
System (AWS) already working in Mumbai area. The AWS Type ZUB –
100 or AAWS as per RDSO specification no. RDSO/SPN/213/2014
Ver. 1.0 shall be made available by the IR. AWS/AAWS shall remain
completely isolated in rear driving cab. TPWS/CBTC may also be
provided by IR in future. Supplier shall ensure the interface of
AWS/AAWS/TPWS/CBTC with TCMS.
(xi) IR may provide Train Protection and Warning System (TPWS),
Automatic Train Protection (ATP) or Communications-Based Train
Control (CBTC) in Mumbai suburban area in future. The complete
system as supplied against this tender shall be fully compatible with the
TPWS/ATP/CBTC and should be fully functional by simple interface
catering the required number of input & output signals. The Supplier
shall furnish the details of the interface arrangement so as to make the
system functional on mutually agreed terms and conditions with the
purchaser during currency of the contract. The traction equipment shall
be suitable for operation with 25 KV AC, 50 Hz supplied by overhead
contact wires.
(xii) The control equipment and TCMS shall be suitable to permit following
configurations of multiple unit operation:
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 12 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(xiii) Same type Cars shall be interchangeable from one basic unit/rake to
another basic unit/rake formation.
(xiv) The equipment shall be designed keeping in view the environmental
conditions specified herein.
(xv) The design shall also facilitate easy erection by means of suitable tools
and equipment, inspection, maintenance and replacement of the
various units comprising the equipment.
(xvi) Software shall be written in a structured manner and fully documented
during all stages of its design and development. This shall meet the
requirements of EN 50126-2: Dependability for Guided Transport
Systems - Part 2 : Safety, EN 50128 : Railway Applications :
Software for Railway Control and Protection Systems, and EN
50129: Safety-related Electronic Railway Control and Protection
Systems. Any deviation from this requirement will need approval of
RDSO in the design stage.
(xvii) Logic of the Software of various sub-systems shall be approved in
consultation with user Railways at the design approval stage. The
Supplier shall submit the values of parameters, list of fault messages,
their environmental data sets, hierarchy of fault display, fault
categorization, trouble shooting of each fault by way of graphical
representation on HMI etc. for the approval. Changes in parameters
shall be demonstrated with their effect on the results.
(xviii) The Supplier shall submit software logic with detailed explanation along
with complete software packages to be loaded in TCMS and Converter
control before commissioning of the prototype rake. Parametric
changes shall be possible in the software in order to meet the future
requirements viz. change in acceleration & deceleration, bogie & coach
suspension, train configurations, OHE voltage, frequency etc. While
listing out the values of various parameters, the Supplier must provide a
range within which any change can be made without jeopardizing the
functionality of the system.
(xix) Software shall be fine tuned through simulations & real life working
conditions based on the extensive trials, associating user Railways
before putting the rake in commercial services. As it requires,
instrumentation and expertise of Software Design Professionals,
software expert(s) of Supplier shall be based at the work place along
with commissioning engineers so that all the software related issues
are resolved before putting the rake into commercial service.
(xx) Quality and efficacy of trouble shooting manual, software tools and
software documentation shall be validated during extensive field trials.
Final version of these documents shall include the changes required
based on the service trials, commercial service operation, experience of
operating Railways and shall be submitted after the expiry of the
warranty period of the prototype rakes.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 13 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 14 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 15 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
1.3.8 The software required for trouble shooting and software tools for maintenance
of equipment shall be supplied to the sheds and workshops. Supplier shall
demonstrate the procedure of trouble shooting through the software tools.
1.3.9 Complete information on equipment testing and commissioning at site/on train,
their interface and complete system testing shall also be provided. The
relevant customized hardware, if any, required for the purpose as above shall
also be supplied to RDSO and Central & Western Railways.
1.3.10 Supply of drawings, operating manuals, maintenance manuals,
troubleshooting manuals and software manuals of the supplied equipment and
systems shall be ensured.
1.3.11 In addition to the equipment and services specified in this Specification, the
Supplier shall supply handling tackle, special tools and appliances which may
be necessary for the installation, testing and commissioning of the supplied
equipment on the new manufacture EMUs, even though such material or work
may not be specifically mentioned in this Specification.
1.3.12 The two prototype EMU rakes (12 car), fitted with the supplied equipment after
the successful completion of all tests and trials and RDSO clearance shall
undergo service trials for six months or one lakh km whichever is later. The
supply of equipment for the “work in progress” for the period of service trials
can commence as agreed by the supplier and purchaser so that the continuity
of the production is not affected. During the prototype tests/service trials, if any
problems arise or feedback information is obtained, which warrants a re-check
of the design/manufacture/quality of the equipment and components, action
will be taken as may be necessary by the Supplier to carry out the required
investigations and to incorporate the modification considered most appropriate
to reach compliance with the specification without any extra costs to the
Purchaser and in a manner approved by the RDSO on equipment/components
already supplied as well as those to be supplied later.
1.3.13 Before carrying out any modification, as found necessary on the basis of tests
and trials, the drawings and execution plan shall be got approved from the
RDSO.
1.3.14 Clause by Clause Compliance
The Bidder shall furnish clause by clause compliance of each clause of the
technical specification. Supplier shall submit the detailed information desired
vide various clauses of the specification at the time of design stage. The
comments like ‘noted’ against the respective clauses shall be considered as
‘not complied’ for the specific clause. Therefore, the Bidder shall clearly
indicate the compliance or otherwise by writing ‘Complied’ or ‘Not Complied’.
Clause by clause compliance to the specification shall only be considered for
evaluation of offers. Compliance against any clause means compliance of all
of it's sub-clauses. Other details given by Bidder shall not be given cognizance
and shall not amount to the acceptance of the design/equipment/scheme. In
case of any discrepancy, clause by clause compliance to the specification
shall only be considered. It shall be the responsibility of the Supplier to meet
the specification as per the clause by clause compliance.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 16 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 17 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
1.4.8 The Supplier shall be responsible for carrying out improvements and
modifications at his own expense on all the equipment supplied, provided such
modifications/improvements are decided to be necessary jointly between
Supplier and RDSO for meeting the requirements of reliability, performance &
safety etc.
1.4.9 For the purpose of technical decisions on improvements/modifications etc. on
equipment, the final authority from the Purchaser’s side will be RDSO.
1.4.10 Design Document, Manual, Spare Parts Catalogue & Material
Specification
Final design document, prototype, type, routine test plan & reports, vehicle
test report, maintenance, troubleshooting & service manual including drawings
and photographs shall be prepared for the various equipment, system and
train operation. The draft contents of the manuals shall be submitted for
examination of RDSO and user Railways.
1.4.11 Detailed spare parts catalogue listing all components manufactured or
purchased by the supplier along with their rating, source & schematic position
etc. Supplier shall furnish purchase specification of the bought items as well.
1.4.12 The complete documentation shall be provided on compact discs (Blue Ray)
along with relevant software and complete arrangement to read, edit and to
take prints in colour. In case the drawing format is not compatible with
AUTOCAD, necessary customized hardware and software shall also be
submitted.
1.4.13 As made drawings
Complete sets of ‘as made’ drawings shall be supplied by the Supplier to the
purchaser/RDSO.
1.4.14 Size of drawings
The drawings of the following parts shall be to the sizes indicated below:
Equipment details - full size or half size
Motor Assemblies - 1: 5
General assemblies - 1 : 10
The dimensions, weight, capacity, etc, shall be in SI units.
1.4.15 Method of filing of drawings
To facilitate filing of drawings, it is essential that each drawing submitted for
approval is marked so that it can be identified. The supplier is, therefore,
required to ensure that all prints are marked legibly at the right hand bottom
corner. The following information is required in respect of each drawing:
(i) Supplier’s drawing number.
(ii) Supplier’s name and date of submission.
(iii) Contract no. given by the purchaser.
(iv) Description of drawings.
(v) Relevant Specifications
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 18 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
1.4.16 Photographs
While the equipment is under manufacturing, photographs of the various
assemblies and sub-assemblies in various stages of production shall be taken.
Photograph size shall not be less than 305 x 203 mm. Photographs shall be
submitted in the form of books suitably bound within a cover of superior quality
durable material with the title block printed on the outside of the cover.
Photographs on digital media shall also be furnished.
1.4.17 Marking of equipment
All main assemblies of the equipment shall bear serial number for
identification and initials of the purchaser. Where the sub-
assemblies/components of the main assemblies are not inter-changeable, the
sub-assemblies shall also be marked with the serial nos. of the main assembly
of which they form a part.
1.4.18 Rating plate
All equipment/cubicles shall contain non-detachable rating plates of anodized
aluminum with embossed letters and fitted in a visible position. The rating
plate will give detailed rating specification and identification of equipment.
1.4.19 References to various standards
The standards applicable and relevant to the complete Train and to the
various Sub-systems and systems shall be:
(i) IEC publications;
(ii) EN ;
(iii) UIC;
(iv) AAR
(v) IEEE;
(vi) BS;
(vii) RDSO specifications
(viii) ICF/RCF specifications
(ix) NF-F
(x) ORE
(xi) VDE
(xii) UL
(xiii) IS; and
(xiv) Any other standards referred to in this Specification.
1.4.20 In the event of any contradiction in the aforesaid standards, the following
standards shall have priority in the order listed:
(i) Standards mentioned in this Specification;
(ii) IEC/EN/UIC/AAR/IEEE/BS/ISO and
(iii) IS.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 19 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
1.4.21 For avoidance of any doubt, in case of any conflict between the requirements
of these standards, the stipulations of this Specification shall have
precedence.
1.4.22 The design of the Train and the Sub-systems and systems thereof shall
comply as per the standards mentioned in Annexure III. The latest version of
the aforesaid codes, standards and specifications which have been published
at least 60 days before the last date of bid submission shall be considered
applicable.
-----------------
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 20 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
centers at the design stage. This shall also include calculation for
unbalance of load under tare load and SDCL conditions on both the
bogies.
(iii) The power equipment viz. traction converter, traction motor &
transformer etc. shall be distributed amongst motor & trailer Cars for
optimized weight distribution and reduced axle load within the unit.
Supplier shall note that actual arrangement shall be of proven layout
which has usually been adopted by the Supplier in other rolling stocks
and shall be in line with the basic guidelines as indicated above. As
such the distribution of weight shall have to be compatible with the
mechanical structure of the coaches which shall be manufactured at
ICF.
(iv) Supplier shall submit the relevant references where the proposed
arrangement has already been supplied and is functioning satisfactorily
for 3-phase drive systems.
(v) Supplier shall ensure that such weight disposition is proven
arrangement for ensuring reduced axle loads. The inter-vehicular
couplers for high-tension connections to traction motors, if used, shall
be proven. Such couplers shall be exposed to vandalism activities
including people riding on the mechanical couplers etc. As such the
coupler shall be designed to cater for all such abnormalities. Details of
the coupling arrangement shall be furnished.
(vi) Each driving Car shall have a Vendor's compartment just behind the
driver's cab i.e. there shall be two such compartments per train. For
passengers with disability (PWD), necessary seats shall be earmarked
in the Car. Layout of individual Cars shall be finalised at the design
stage.
2.2.4 Tare and Pay weight particulars of the existing MRVC Phase II EMU coaches
are as under:
Pay Weight (t)
Tare
Type of Seating Total Weight
Weight Standing
Coach Passenger Vendor Total (t)
(t) Passenger Weight
Weight
MC 52.33 86x60=5.16 349x60=20.94 -- 26.10 78.43
TC 36.34 112x60=6.72 449x60=26.94 -- 33.66 70.0
DTC 38.28 89x60=5.34 433x60=25.98 1.33 32.65 70.93
NDTC 38.0 99x60=5.94 402x60=24.12 1.33 31.39 69.39
It may be noted that the number of passengers will increase in the new
coaches to be manufactured against this project as the onboard HT
compartment and shunting cabs will not be present in this case.
2.3 Gauge and Moving Dimensions
2.3.1 Unless otherwise stated, the EMU coaches shall conform to the Indian
Railways Schedule of Dimension – 1676 mm gauge of 2004 with latest
amendments. Further, maximum moving dimension of coach shall conform to
RDSO Sketch-76180 and Sketch-74176 as per Annexure VIII A & B. However,
the maximum height of the Car in pantograph locked down condition shall not
be more than 4265 mm.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 22 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 23 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
2.5.2 Deceleration
Service braking deceleration
Average from 110 Kmph to 50 Kmph : 0.76 m/s 2
Average from 50 Km/h to standstill : 0.84 m/s 2
2.5.3 Maximum Speed
(i) Maximum service speed : 110 Km/h
(ii) Maximum test speed : 120 Km/h
2.6 Traction Power Supply System
2.6.1 The equipment shall be suitable for operation on the electrical suburban
sections of the Central and Western Railways. The general particulars are:
2.6.2 The operating voltage: 25KV AC power supply:
i) Normal variation : 19 KV to 27.5KV
ii) Occasional maximum ( cut off ) : 30 KV
iii) Occasional minimum : 16.5 KV
iv) Cut off voltage : 16 KV
v) Frequency variation : 48.5 Hz to 51.5 Hz (±3%)
vi) Maximum allowed OHE current : 425A for 45 seconds for 12 Car rake
with 4-Car basic unit
2.6.3 The guaranteed performance shall be available from 22.5 KV to 27.5 KV for
train weight of 948t. Regenerative braking system shall continue to operate
when the supply voltage is in the range from 17kV to 30kV.
2.6.4 The power supply system shall be 25 KV, 50Hz single phase AC, 25 KV being
the nominal voltage of the system. The guaranteed performance shall be
based on voltage of 22.5 KV. However, the run time for all out run for 1.5 km
section on level tangent track and SDCL loaded train shall not deteriorate
more than 5% as compared to that specified at Clause no. 3.1.3 within the
variation of OHE supply in the range 21KV to 28.5 KV and frequency variation
of 48.5Hz to 51.5Hz. Train operation shall be feasible at OHE voltage of
16.5KV, may be with restricted power.
2.7 Overhead Equipment
2.7.1 25KV AC Traction: The overhead equipment is supplied through 3 phase grid
system and step up/down transformers at the traction substations.
Consecutive sections are not supplied from the same phase, therefore neutral
sections are provided in between the traction feed from two adjacent
substations. The length of the neutral section shall be about 9.5 m. The OHE
shall be of regulated and unregulated type.
2.7.2 Limit of Second Harmonic: The second harmonic current of each motor
coach shall not exceed 0.5A and shall be governed by international standard
(IEEE 519-1992). This will supercede the limit of second harmonic stipulated
in the Annexure V. The Supplier shall submit curves of harmonic currents vs
load current per motor coach for EMU rake configurations given in Clause no.
1.1.9 (xii).
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 24 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
2.7.3 The EMU Trains shall collect power when the position of the contact wire
varies laterally (stagger) from the centre line of the track by up to ±200 mm on
straight track and up to ±300 mm on curves, which can go up to 860 mm on
one side on turnout/ crossovers.
2.7.4 The EMU Trains shall collect power when the position of the contact wire
varies between 4.54 m and 5.8 m above rail level. The nominal height of the
contact wire in mid span is 5.5 m above rail level.
2.8 Power Factor
Train shall achieve a minimum power factor of 0.98 as measured at the
pantograph. The power factor shall be governed by EN 50388.
2.9 Fire Safety
2.9.1 The design and manufacturing of equipment shall be in accordance with EN
45545. Please refer to Clause no. 4.16.7 of this Specification.
2.9.2 A reliable Automatic fire detection with alarm system shall be provided, in
accordance with Clause 4.17 hereof. Efficient means of communication
between passenger and Driver / Guard shall a lso be provided in
accordance with section 59 of the Railways Act 1989.
2.10 Ingress Protection
2.10.1 All equipment shall be suitably protected from dust and water. As a minimum,
equipment shall be sealed to the standards stated below.
Under frame mounted equipment : IP65
Equipment mounted inside the Car body : IP54
2.10.2 It may be necessary to protect some equipment to IP 67 in order to meet the
requirements of Clause no. 4.35 of this Specification.
2.11 Climatic and Environmental Conditions
(i) Relative Humidity: upto 100% saturation during monsoon season
which may be as long as five (5) months.
(ii) Ambient temperature max. : 50º C
min. : 0º C
(iii) The temperature of stationary rake in sun may go as high as 70-75º C.
The equipment shall not be adversely affected in any way due to
exposure to such high temperatures. Supplier shall furnish the
precautions taken in equipment/component selection in order to
conform to this requirement. The Supplier will indicate the expected
temperature rise of equipment under the reference site conditions
described above and shall submit the expected MTBF/MDBF at such
temperature.
(iv) The EMU trains shall function in accordance with this Specification
following any period when stationary at the maximum ambient
temperature and in full sunlight as specified in this clause. The EMU
Trains shall not require any pre-cooling of equipment.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 25 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(v) The area along both sides of the track is heavily populated. Bidder may
assess the site conditions by visiting the Mumbai suburban area. The
air discharge from the cubicles, if any, shall be suitably regulated so
that dust blow during the run is bare minimum and does not cause any
inconvenience to passengers.
(vi) Altitude: coastal area
(vii) Rainfall: Very heavy and continuous at any rate between 0 and 100
mm / hour (up to 2500mm during rainy season)
(viii) All under slung equipment shall be designed suitably to ensure its
normal working even in adverse conditions as mentioned in this
Clause.
(ix) Atmosphere during hot weather: Extremely dusty, humid and salty.
The EMU shall be working primarily in coastal area and thus shall be
continuously exposed to highly corrosive, salty atmosphere along with
industrial pollutants.
(x) The EMU trains shall function in accordance with this Specification
when subjected continuously to an atmosphere containing dust in
concentrations up to 1.6 mg / m3.
(xi) The EMU trains shall function in accordance with this Specification
when subjected continuously to a humid and salt laden atmosphere
with maximum pH value of 8.5, sulphate content of 7 mg per litre,
maximum concentration of chlorine 6 mg per litres and maximum
conductivity of 130 micro Siemens / cm.
(xii) The EMU trains shall function in accordance with this Specification
when subjected to high wind speed in certain areas, with wind pressure
reaching 150 kg/m2.
(xiii) EMU Trains shall function in accordance with this Specification when
exposed to solar radiation in the range from 0 kW/m2 to 1 kW/m2.
(xiv) Special care shall be taken to ensure no damage to equipment due to
deposition of atmospheric salts and industrial pollutants. Supplier shall
enclose the details of specific measures adopted to ensure the
satisfactory working of equipment against the deposition of salts &
industrial pollution.
(xv) Vibrations: Because of track irregularities, level of shocks and
vibrations to which traction motors are exposed are far more than
actually given in IEC for fully suspended TM mounting arrangement.
Supplier must carry out instrumented trials on existing stock for
measurement of shocks and vibrations in Mumbai sub-urban area in
consultation with RDSO, at design stage. The suspension system and
the mounting arrangement shall be so designed that the equipment’s
performance is not adversely affected due to such high vibrations and
shocks. Bidders are advised to check and verify the existing track
conditions over the sections of the Railway where the EMU stock shall
run.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 26 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 27 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
2.13.3 The supplier shall develop RAMS targets both for the complete system and for
the major Sub-systems such as transformer, traction converter, auxiliary
converter, electronics, traction motor, Transmission and Suspension System,
high voltage equipment, blowers and other auxiliary machines, such that it will
provide a high level of dependability.
2.13.4 There shall be an efficient means of operation of the EMU after all failures in
accordance with Good Industry Practice.
2.13.5 Components critical for safety shall fall into safe operating mode in case of
malfunctioning. The system safety plan shall identify and list safety critical
components and this list shall be updated periodically.
2.13.6 The Supplier shall establish and operate a detailed reliability, availability,
maintainability and safety (RAMS) Assessment system in support of the
design, manufacture and subsequent testing, commissioning, operation and
maintenance of the Train.
2.13.7 Safety Assessment shall be carried out and shall include the following
principles:
(i) Degraded modes and emergency operations shall be considered as well as
normal operations;
(ii) Safety risk assessment shall utilize more than one methodology to assess
risks; and
(iii) Safety risk assessment shall include the consideration of dependent
failures, in particular the traction power, braking and control systems.
2.13.8 Every complete basic unit, as well as each constituent component, assembly,
subsystem and system element shall be designed in such a manner as to
perform its function reliably in revenue service. To ensure reliability of the
system, redundancy shall be built-in so that:
2.13.8.1 The brake performance i.e. electro-pneumatic (EP) as well as regenerative
brake force of 12-Car EMU train shall not deteriorate in case of failure of one
Brake Electronics Control Unit. However, BP controlled back-up brakes shall
always be available on the Train;
2.13.8.2 The Basic Unit control of each Traction converter shall be independent;
2.13.9 Further, the redundancy shall be built-in so that the performance of the EMU
rake shall not deteriorate in the event of failure of auxiliary supply system
equivalent to that of one Basic Unit.
2.13.10 No single-point of failure shall cause complete failure of the traction system,
auxiliary supply system or inability to control the brakes on Train.
2.13.11 Where the system design of the equipment incorporates component
redundancy as the method of reducing the consequences of a single point
failure, such redundancy shall not allow hidden faults to remain undetected.
2.13.12 Supplier shall submit the basic maintenance schedules of the proposed
equipment. Minimum interval between two maintenance schedules for the
equipment supplied under the specification in the depot shall be 90 days
except for the pantograph strips and 3 years for major works in
workshop/major depot.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 28 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
It may be noted that the periodicity of the present maintenance schedules are
as under:-
I ‘A’ 45 days
I ‘C’ 180 days
POH 18 months
The maintenance programme prepared by Supplier shall have the following
objectives ascertaining the above periodicity of maintenance schedules:
Enhancement of EMU availability
Minimization of maintenance costs
Minimization of coach downtime /MTTS (meantime to restore
serviceability)
2.13.13 Based on the proposed maintenance schedules, the Supplier will submit
average downtime on account of scheduled maintenance for the equipment to
be supplied excluding the time required for transfer of rake to and from the
maintenance depot. Ineffective on this account should not exceed two percent.
Supplier should also submit an estimate for the downtime for unscheduled
maintenance in respect of equipment to be supplied. The Supplier shall
assess and submit the figure for ‘total percentage Ineffective’, in terms of
percentage of rakes expected to be ineffective/unserviceable due to schedule
and unscheduled repairs/maintenance of equipment supplied (excluding the
time taken for transfer of the rakes to and from maintenance depot) against
the total number of rakes fitted with the equipment under his scope of supply.
This ineffective figure shall not exceed FOUR percent in any week (Monday-
Sunday) calculated on 24 hourly basis. If during the test and service trial
period of prototype rakes it is experienced that downtime due to unscheduled
repairs/scheduled maintenance of the equipment supplied is excessive,
supplier shall be required to take suitable remedial measures to bring the
ineffective figure within the limit submitted during the design approval stage.
2.13.14 Modular design principles shall be employed. Requirements for adjustments
after module interchange shall be avoided except as required in the
specification.
2.13.15 All systems, components and structural areas serviced as part of inspection or
periodic preventive maintenance shall be readily accessible for service and
inspection.
2.14 Adhesion Limits:
The equipment shall be so designed that the coefficient of adhesion
requirement does not exceed 20% during powering and 16% during braking
under all requirements of performance as specified in this specification.
-----------------
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 29 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 30 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
braking for a SDCL 12 car rake with an average line voltage of 22.5 KV with
braking rates as specified. The typical run shall be taken as traction cycle with
reference to Claue no. 3.1.7.
3.1.4 A speed of 110kmph shall be achieved in a distance of 1.9km and duration of
90s. With one basic unit isolated condition, a speed of 110kmph shall be
achieved in a distance of 3.1km and duration of 150s. However, the maximum
current drawn from OHE at the average line voltages specified herein shall not
exceed the maximum limit of 425A.
3.1.5 Supplier shall submit the RMS current values of traction motor and
temperature rise of propulsion equipment for a SDCL 12 Car EMU rake
operation under normal and one basic unit isolated condition in all-out mode
for the sections specified in Clause no. 3.1.11. These values shall be
submitted considering the gradient, curves and speed restrictions. Further,
these values shall also be submitted without considering the speed
restrictions. Supplier shall also ensure compliance to Clause no. 2.6. The
R.M.S. (root mean square) loading of the traction motor with regenerative
braking in use for all out running as mentioned herein shall not exceed the
continuous rating of the traction motor.
3.1.6 Ratings of equipment
(i) The continuous rating of the traction converter, traction motor & the
traction transformer shall be based on the criteria specified in Clause
no. 3.1.3. The rating of equipment shall be demonstrated by thermal
simulation and measurement during combined system testing as well
as vehicle testing in the field. The procedure adopted for calculation of
propulsion equipment ratings including the boundary conditions shall be
submitted.
(ii) Supplier shall submit detailed calculations of maximum power loading
of all major components of the traction system including the maximum
r.m.s. currents, tractive effort and motor torque for motoring. Similar
calculations for maximum power loading of all the major components of
traction system including maximum r.m.s. current, braking effort and
motor torque for braking shall be submitted. During traction mode,
maximum auxiliary power shall be taken into account and during
braking mode minimum loading of auxiliary power shall be considered.
While deciding the ratings of the equipment, Supplier shall ensure that
the performance of the EMU shall conform to the conditions laid down
in this specification.
(iii) Efficiency curves of each equipment and tractive effort/braking effort (in
kN) of a basic unit shall be furnished along with overall system
efficiency curves. The total auxiliary power shall be furnished as break
up of power requirement for lights, air-conditioning loads, auxiliary
power required for propulsion system and control electronics.
3.1.7 Calculation/simulation for temperature rise of the propulsion equipment for
repeated all-out cycle as specified above at Clause no. 3.1.3 (without
considering stoppage time) and the specified conditions shall be furnished by
the Supplier. The temperature rise of the propulsion equipment shall not
exceed the permissible value as mentioned in this specification. All the
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 31 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 32 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
3.1.12 The variation of power and TE & BE with the OHE voltage, from starting to
maximum speed, in the range of 16 KV to 22.5 KV AC shall be submitted
during design stage. The effect of the reduced power on run time for
Churchgate–Andheri & Mumbai CST to Thane section and on a representative
section of 1.5 km shall be submitted in graphical and tabulated forms.
3.1.13 The equipment shall be so designed that the coefficient of adhesion does not
exceed the limits defined in Clause no. 2.14 during powering or braking.
Supplier shall furnish the optimized value of coefficient of adhesion and the
reason thereof.
3.1.14 Specified temperature rise of equipment as specified in Clause no. 3.1.7 shall
be calculated after taking into account at least 25 % choking of air filters and
radiator fins.
3.1.15 Regenerated Energy: The regenerated energy for all-out running of 12 Car
rake upto the maximum service speed followed by full service brake shall not
be less than 40% of the energy consumed during powering at the specified
voltage indicated in Clause no. 2.6 . Acceleration and braking rates shall be as
defined in Clause 2.5 and full auxiliary load shall be taken into account except
air-conditioning & emergency load. Duty cycle for the compressor and lights
shall be taken as 100% and for the balance load 100% duty cycle shall be
considered. The net energy consumed or regenerated at the pantograph shall
be used for calculating percentage regeneration energy.
3.1.16 Efficiency
3.1.16.1 The peak efficiency of the propulsion system, consisting of traction
transformer, traction converter and traction motor of an EMU train shall not be
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 33 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
less than 87% in the maximum power zone of the traction characteristics
measured on the combined system test bed.
3.1.16.2 The efficiency of the auxiliary converter shall not be less than 92% at full load.
3.1.16.3 The efficiency of the traction equipment shall be calculated taking into
account energy consumed from auxiliary supplies (e.g. for cooling equipment
– fans, pumps etc.)
3.1.17 Continuous Operating Equipment
3.1.18 The capacity of the traction motors and equipment shall be adequate to permit
continuous and punctual operation of SDCL trains under the operating and
service conditions specified.
3.1.19 Supplier shall submit the residual acceleration for the SDCL loaded 12 Car
train for attaining 110kmph speed on level tangent track. The value shall also
be submitted for one basic unit isolated condition.
3.1.20 Supplier shall submit the balancing speed for the SDCL loaded 12-Car train in
normal and one basic unit isolated condition.
3.2 Power Supply and Environmental Conditions
3.2.1 The details are specified in the Clause no 2.6, 2.7 and 2.11.
3.3 Neutral Section
(i) Neutral section is provided in the AC traction area. Suitable
arrangement shall be provided by the supplier in every motor coach to
ensure that the loss of main power for each basic unit, while traversing
through neutral section, is restricted to bare minimum. The supplier
shall also supply the design details & specification of fixed equipment to
be installed at each neutral section or alternatively shall ensure
compatibility of their equipment with the track side equipment, if already
installed by IR and are already in use at the neutral sections at the time
of design finalization.
(ii) It shall be possible for the system to open or close the circuit breaker
sequentially while approaching and leaving the neutral section
respectively. The system shall have all necessary safety provisions.
3.4 Interference to Signal and Telecommunication Installations
Interference to signal and telecommunication installation shall be as per the
Clause no. 2.12.
3.5 Train Resistance:
Train Resistance of the existing EMU motor and Trailer Coaches is as under:
Motor coach:
R = 2.35 + (0.02922-0.00049xW)xV+(0.03722/W)xVxV Kg/t
Trailer/ Driving trailer Coach:
R = 1.347 + 0.00385xV + 0.000165xVxV Kg/t
where W is the gross wt in tonnes,
R is the resistance in Kg/tonnes, and
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 34 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
--------------
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 35 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 36 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(xvi) Lighting system including coach lighting, headlight and auxiliary head
light & tail light etc. Control switchgear shall also be supplied for these
items.
(xvii) Passenger information system including coach displays, head code,
audio communication system and interface with the existing Train
Monitoring System (TMS) on Central and Western Railway and any
equipment required for interfacing PIS with the Receiver-equipment of
TMS. Receiver Equipment of existing TMS is in the scope of supply of
the Purchaser and may be mounted in the driving cab. The
specification shall be made available to the Supplier at the design
stage, if required.
(xviii) Complete set of MCBs, contactors, relays etc. for propulsion system,
controls, auxiliaries in the assembled form viz. cubicle or cabinet.
(xix) Parking brake equipment complete with controls, associated valves &
wiring etc.
(xx) APC receiver compatible with existing track magnets
(xxi) Brake Control Electronics complete system fulfilling the brake blending
requirements.
(xxii) Weight Sensors with adequate redundancies
(xxiii) CCTV
(xxiv) Cab recording equipment
(xxv) Automatic door closure system
(xxvi) Event Recorder
(xxvii) Fire detection system
(xxviii) Any other equipment for power isolation and interlocking etc. and
required for proper functioning of the traction equipment.
(xxix) Instrumentation required for commissioning and field-testing of the
equipment.
(xxx) Complete air-conditioning system with necessary equipment such as
Roof Mounted Package Unit (RMPU), control panel etc.
4.2 B) Technical Specification for 3-Phase Propulsion System with System
and Associated Equipment
The 3-phase drive equipment shall be based on the technology proven in
successful service applications as per Clause no. 1.1.9 (xxv). The equipment
shall be suitable for regeneration for the full speed range. The broad
specification of the various equipment is furnished below.
4.3 Traction Transformer
4.3.1 A fixed ratio transformer shall be provided with multi traction windings suiting
the requirements of IGBT based traction converter to meet the load of three-
phase propulsion and auxiliary equipment. The kVA rating of the transformer
shall be specified at a line voltage of 22.5kV and shall be designed to deliver
the power at a total current corresponding to the continuous rated traction
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 37 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
motor currents after accounting for the efficiency & power factor of traction
motor, traction converter, auxiliary converter for meeting the auxiliary load as
specified in the specification Clause no. 4.25. The guiding principle for
calculation of rating shall be as per Clause no. 3.1.6. Supplier shall note that
the performance is required to be guaranteed for the range of voltage as per
the Clause no. 2.6. The transformer will be designed with overload capacity to
permit full utilization of the traction motor capacity during starting as well as
running.
4.3.2 The transformer shall be designed with adequate overload capacity, in
accordance with Good Industry Practice, to permit full utilization of the traction
motor capacity during powering as well as full regenerative braking and to
accommodate the maximum loading imposed by the auxiliary supply
system (particularly in the event of failure of auxiliary supply equipment fed
from other transformers).
4.3.3 The transformer will be designed to conform to IEC 60310 and temperature
rise limits of the windings and oil shall correspond to IEC 60310 minus 200C
under all conditions of operations. Winding conductor of transformer shall be
provided with 'H' class enamel and nomex paper insulation.
4.3.4 The secondary windings shall have a very high magnetic de-coupling.
4.3.5 The transformer shall be of modular construction. Means will be provided for
letting out the oil from transformer to the underside of the coach in the event of
any fault/electrical disturbance in the transformer causing oil to rush out. No
part of the transformer shall protrude above floor level. The radiator shall be
so designed so that cleaning interval is in synchronization with the Scheduled
Maintenance but shall not be less than two years.
4.3.6 Adequate care shall be taken in design in view of the high humidity for long
duration (in coastal areas). The silica gel, if used, should not require attention
in between the Schedule examination.
4.3.7 The transformer tank, radiators and associated equipment shall be coated with
pollution/oil resistant and dust repellant epoxy paint. The lower portion of the
tank shall be of adequately strong so as to protect against hitting by
extraneous objects while on run.
4.3.8 The cooling agent for the transformer shall be K-class, biodegradable, arc
resistant and shall have high flash point (> 250 ºC) & high fire point (>300 ºC)
4.3.9 The transformer shall be under slung and the mounting arrangement shall
preferably be the same as of the existing transformer, otherwise it shall clearly
be indicated by the Supplier.
4.3.10 Current transformer, potential transformer and matching overload relay etc.
shall be in the scope of supply of the Supplier.
4.4 Lightning Arrestor
4.4.1 Two metal oxide gapless lightning arrestors shall be provided on the roof of
each Car fitted with a pantograph and/or traction transformer for protection
against the line voltage transients caused by lightning and system switching.
One lightning arrestor shall be connected to the high voltage circuit between
the pantograph & the main circuit breaker and the other shall be connected to
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 38 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
the high voltage circuit between the main circuit breaker and the transformer.
These gapless lighting arrestors shall have minimum line discharge class-3.
4.5 Traction Converter
4.5.1 The four quadrant traction converter shall be of a design service proven in
similar applications, IGBT based with PWM control to ensure regeneration and
the power factor near to unity. The range of variation of power factor shall be
submitted by the Supplier. The traction converter shall be installed underslung
and shall be protected by a housing made of stainless steel SS304 or
anodized sea water proof aluminum. However, the traction converter shall be
protected against ballast hitting as per the relevant international standards.
There shall be no need of painting.
4.5.2 Cooling System
Traction converter offered shall be forced air/water/convection cooled.
4.5.3 The voltage rating of IGBT would be so chosen that at least 25 % margin is
available after taking into consideration the DC link voltage and voltage jump
on account of inductance and capacitors in the circuit. The current rating of
IGBT shall be such that the junction temperature has minimum thermal margin
of 10°C in the worst loading conditions and under the ambient conditions as
specified. Supplier shall submit the maximum junction temperature of the
devices under worst operating conditions.
4.5.4 The wheel slip detection and correction system shall be an integral part of the
control system of the traction converters which shall capture any excessive
acceleration, differential speeds between axles, over speed and any other
parameter considered necessary to maximize adhesion and minimize wheel
slipping / skidding.
4.5.5 The catenary voltage fluctuates widely as indicated in the Clause no. 2.6. The
variation of frequency has also been indicated therein. The converter shall be
provided with necessary control for the guaranteed performance under such
fluctuations without exceeding the rated cut off current of IGBT and keeping
minimum cut off time within limits.
4.5.6 In the vital units of power control circuit like power supplies etc., where any
defect/failure of component would cause complete failure of the motor coach,
suitable means for redundancy will be provided in order to avoid the motor
coach failure or reduction in performance due to such defects. Supplier shall
specifically submit details of the redundancy provided in the system to this
effect. Suitable redundancy in the vital PCBs connected with safety and power
supplies, so that the train failure and degradation in performance is minimized
in the event of their failure.
4.5.7 Suitable margin shall be provided in the equipment rating such that under
emergency condition with isolation of single basic unit, there shall be no
necessity to withdraw the rake from service. The one hour rating/thermal
rating as specified herein of the equipment will not be exceeded under such
operation. For such purpose, short time rating of the major electrical
equipment such as main transformer, traction converter, auxiliary converter
and traction motor etc. will be furnished. Supplier may also refer Clause no.
3.1.5.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 39 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.5.8 The propulsion equipment shall ensure the guaranteed performance for wheel
diameter differences for at least up to 6 mm within any bogie and up to 13 mm
between bogies without any adverse affect on any equipment. If the wheel
diameter tolerances exceed the above limits then no damage shall occur to
any equipment. Supplier shall also furnish the permissible diameter difference
between the wheels of the same bogie and those on different bogies of the
same coach as affected by the control of individual motors, individual bogies
or of complete motor coach.
4.5.9 The protection/alarm/indication circuit will normally have self correcting
features rather than cause tripping of the motor coach for reduction of the
tractive effort. If the driver intervention is needed, sufficient indication will be
given to the driver to enable corrective action to be taken in time. It shall be
possible for the driver to take any protective action, or any other action as
indicated to him through diagnostic display, on any of the motor coaches in the
rake, if so desired, from the driving cab itself.
4.5.10 The protection scheme of the traction converter system shall prevent any
damage to the traction converter system in the event of short circuit current
flowing under fault conditions or earth fault on the DC link, in accordance with
Good Industry Practice. The traction converter system shall also be designed
to withstand extreme disturbances like short-circuit / open circuit /voltage
spikes at all points of input / output interfaces with Train, with minimized
effects/damages. This shall be Type tested according to the relevant
provisions of the IEC 61287.
4.5.11 In the event of any earth fault or phase to phase fault in the traction motor(s),
the protection scheme of the traction converter shall prevent any damage to
the converter. The traction system shall be designed so as to protect itself
(including motor, converter and transformer) from over temperature. This
protection shall operate progressively giving a staged reduction in tractive
effort from the affected equipment rather than immediately disabling part of the
traction system.
4.5.12 Freedom from dust and protection from surges will be ensured. Modular
construction will be adopted wherever considered possible. The traction
converter system and transformer will be capable of withstanding the
maximum short circuit current under fault conditions and these will be
established as well. As such in case of any dead short circuit across the
outgoing terminals of traction converter system, the system shall provide
adequate protection so that no damage is reflected on the traction converter
system.
4.5.13 Motor side and line side converter modules shall preferably be of identical
design in use, as far as possible, with identical components.
4.5.14 The propulsion system shall be suitable for operation on 25 KV AC. Supplier
may adopt DC link voltage suitably and submit the details with justification.
4.5.15 The motor converter output current ripple shall be so maintained that it can
keep the torque pulsations and traction motor heating to a minimum. Software
based technique shall be adopted instead of hardware control for controlling
DC link and torque pulsations of traction motor. Only dry type capacitors
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 40 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 41 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 42 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 43 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
traction motor. The Use of helicals for fastening purpose shall not be
permissible.
4.6.2 Traction Motor Tests: The traction motor shall be subjected to all the
prototype & routine tests in line with IEC 60349-2. Prototype tests shall include
continuous temperature rise test, short time rating tests, characteristics tests,
over speed, power factor, efficiency, dielectric & torque measurement tests.
4.6.3 Special tests on traction motor:
The following special tests on traction motor shall be carried out along with
those specified in IEC 60349-2:-
(i) Flood proofing tests: Traction motor fitted with pinion & gear box
running at 200 r.p.m (without gear & other attachment parts) to be
immersed up to 400mm from rail level for 24 hours. Following test
parameters shall be recorded:
a) Insulation resistance before immersion test
b) Insulation resistance after immersion test
c) Visual inspection regarding seepage of water inside the gear box and
motor
(ii) Tests on speed/temperature sensors - in case of proven items, certified
test reports shall be acceptable.
(iii) Testing of insulation system as per IEEE 429-1994 at the relative
humidity of 95-100% for a period of 48 hours and water immersion test
for 30 minutes along with the voltage tests.
(iv) Measurement of waveforms of the motor converter voltage, motor
converter current, motor torque & space vector flux under different
ranges of operation during heat run & characteristics test on converter
supply.
(v) Vibration test as per IEC 60349-2.
(vi) Traction motor bearing test for adequacy of sealing of lubricants
(vii) The hot spot measurements shall be done during prototype tests on
traction motor by embedding thermocouples in the stator winding.
4.7 Train Control and Management System (TCMS)
4.7.1 The general provisions of this Clause shall be applicable to all electronics
used, including that for traction and auxiliary converters. The electronics used
on the Train shall conform to IEC-60571. All electronic equipment shall be
designed so that, it functions correctly when the Train has been standing
stationary in full sunlight at the maximum ambient air temperature. As a
minimum, electronic equipment shall be designed to operate at an ambient air
temperatures of up to 70°C under these conditions. There shall be no
requirement of pre-cooling of the electronics on the Train standing in Sun for
long duration.
4.7.2 TCMS shall integrate the task of fault diagnostics and display the same in
addition to its control task. It shall be capable of real time monitoring of the
status of all the vital equipment continuously and occurrence of faults. It shall
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 44 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
also take appropriate protective action and shut down the equipment
whenever necessary.
4.7.3 Features of self-check and calibration shall be incorporated in the design.
4.7.4 TCMS shall have a diagnostics computer, with non-volatile memory, to store
all the relevant diagnostic data. On occurrence of each fault, besides the fault
information on equipment parameters, GPS location of Train, background data
with time stamp shall also be captured and stored with a view to enable proper
fault analysis. There shall be a facility to capture post-trigger and pre-trigger
background information. The fault display to Driver shall also accompany the
standard troubleshooting instructions in simple language. The diagnostic
computer shall specify diagnostic of fault up to the card level. Faults shall be
suitably prioritized and filtered so that the Driver and maintenance staff receive
information appropriate to their roles. The diagnostic system shall be able to
identify and log the faults of the Train on account of wrong operation by the
Driver and such data (including energy data) shall be stored in the diagnostic
computer for a period of not less than 100 days. Application software shall be
provided to facilitate the fault diagnosis and the analysis of equipment wise
failures. The steps required for investigation to be done, shall be displayed in
simple language along with the background information. Such software shall
be compatible for working on commercially available operating systems.
4.7.5 It shall be possible to access all the processors of propulsion & control
equipment within a Train using a standard laptop from one point provided in
the Driver’s cab. Such access is needed for uploading of firmware/application
program, visualization of process parameters and also force or record the
same and downloading the diagnostic data. Required interfaces shall be built
in so that standard laptops, with commercially available operating systems can
be directly plugged to the port without any special interface. A suitable
software tool shall also be provided in the laptops. Using this tool, it shall be
possible to reset the diagnostic memory for further recording. This tool shall
also provide detailed off line analysis facility. All configuration parameters shall
be protected against unauthorized modification by means of a password.
4.7.6 The Train shall be provided with remote diagnostic and tracking equipment.
The equipment shall be based on GPS and GSM/GSM-R technologies. This
equipment shall perform the function of tracking of the Train and also
communicate with the Train diagnostic system, and pass on this information
to the central server. It shall be possible to remotely send and obtain the
information stored in the diagnostic memory of the computer system,
depending on availability of communication channel, for control and diagnosis,
with the aim of facilitating and speeding up the maintenance process of the
Train. Exception reports shall be generated by the TCMS and downloaded
remotely in the Maintenance Depot for planning the corrective action.
4.7.7 The electronics shall be sealed so as to ensure that there is no dust ingress.
For its cooling, internal ventilation arrangement along with efficient heat
exchanger for removal of heat shall be provided. The electronics shall be
designed with adequate margin so that there are no failures on thermal
account. Temperature near electronic cards in working condition of Train shall
not be more than 70°C.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 45 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.7.8 The majority of control and monitoring function shall be implemented by the
software so as to reduce hardware and cables. The leading cab will be
controlling the motor coaches in the rake formation. Necessary provision shall
be made for acquisition and transmission of data required for leading cabs and
the controlled equipment on other coaches. Necessary measures shall be
taken to ensure that the control signals are not distorted by any type of
interference.
4.7.9 It shall be possible for the IR to execute any modification by parametric
changes in the software in order to improve the performance of EMU viz.
modifying some of the permissible parameters e.g. line current & voltage
sensor settings, temperature sensor setting, pressure sensor setting,
maximum speed of Train, vigilance control timer settings, supervision times
and maximum tractive effort etc., for adjusting the characteristic within
permissible range, changing preset values, limits, characteristics etc. of
Train in general, and add/alter the protection features, if so required in the
future in order to improve the operation of Train. Software tool for parametric
changes shall be password protected and the changes in parameters shall be
demonstrated with their effect on results for verification during vehicle testing.
Supplier shall supply all necessary software/hardware tools required for the
purpose. The modifications shall be restricted to parametric changes as
permissible within the design constraints, details shall be finalized at design
stage.
4.7.10 The electronic cards and couplers / connectors shall be polarized or suitably
designed to ensure that insertion in wrong position is not possible. The TCMS
system shall be modular in design and shall cater for at least 10% capacity
with necessary input & outputs for expansion & future use.
4.7.11 Capacitors shall be suitably rated, keeping in view the high ambient
temperature specified, vibrations of Train and electrical surges expected
during operation. High failure rates of electrolytic capacitors mounted on PCBs
of electronic cards are expected due to high operating temperature / voltage /
current vis-à-vis designed operating temperature / voltage / current. Dry type
of capacitors shall preferably be used. Expected life of the cards and
electronics in general shall be at least 18 years under actual working
conditions.
4.7.12 Features of TCMS:
(i) The diagnostic computer in the Train shall be able to differentiate
between the fault in rest of the Train & fault in the electronic equipment
and between a fault in the monitoring equipment & the equipment being
monitored;
(ii) should the fault be found on electronic equipment, the diagnostic
computer shall enable fault finding to be carried out at module level;
and
(iii) off-Train test equipment shall be provided by the Supplier for use in the
Maintenance Depot. This equipment shall allow fault finding down to
the smallest replaceable item of the Sub-system.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 46 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 47 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 48 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.7.28 It shall be possible to test the software after uploading the same by means of
simulation facility or by some other means. The downloading of the software,
and detail diagnostics etc. shall be feasible through any motor coach & DTC in
the rake. The configuration of the motor coaches for the purpose of interlacing
etc. shall be automatic and without any manual interference in case of
isolation of motor coaches during the service or change in the formation of the
rake in the Shed so as to ensure compliance to Clause no. 1.1.9. It may be
noted that the control for the complete range of operating speeds for one basic
unit level shall also be preferred though the normal operation of the EMUs
shall be in the formation given in Clause no. 1.1.9 (xii).
4.7.29 Acceleration and speed shall be clamped to a selectable value while opting for
‘shunting’ operation. The shunting operation shall be selectable and shall be
recorded.
4.7.30 The microprocessor control and diagnostic system shall also provide for
measurement and recording of speed of the EMU in the driver’s cab with the
provision of wheel diameter correction, distance travelled and time.
4.7.31 The system shall ensure normal working & without any adverse effect on any
equipment while traversing the neutral section.
4.7.32 It shall be possible to selectively operate the circuit breakers or pantographs, if
so required by the driver. Sequential operation of VCB as desired vide Clause
no. 3.3 shall be ensured.
4.7.33 The Supplier shall submit separate lists of safety signals, control signals and
priority signals etc.
4.7.34 TCMS shall be used for integrating and multiplexing of signals for control
purpose and for monitoring of the complete train, its systems and sub-systems
within the appropriate safety framework as per the extant international
practices so as to minimize the inter-vehicular cables. While designing the
multiplexing, the Supplier shall have to ensure fail safe working of the safety
related signals and also indicate the use of such system elsewhere in the
similar traction applications.
4.7.35 Supplier shall submit details of the arrangement proposed to be adopted, the
standard followed and the reference where similar system is functioning,
maximum number of vehicles which can be connected to the network without
need of gateway or repeater and the extent of multiplexing leading to
reduction of the cables. Necessary information, software & hardware tools as
considered necessary shall be supplied to enable IR to interface compatible
equipment with TCMS, if so required in future.
4.8 Event Recorder
The event recorder shall monitor and record various events so that data is
available for analysis to assist in determining the cause of accident, incident or
operational irregularities. The equipment shall be designed in such a way so
as to provide an intelligence based recording of the following parameters
against the time axis (time interval shall be decided by recorder itself,
whenever there is a change in the respective parameter). The memory shall
be sufficient to store short-term data at 1 second interval for the last 72 hrs.
and long term data for 90 days with resolution of 20 seconds.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 49 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 50 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.9.2 The microphone used shall be common for all voice modes and priority shall
be allocated to various modes. Microphone needs to be vandal proof.
4.9.3 The public address intercom system shall have the Train Driver-Guard and
Train Driver/Guard – Passenger communication. The Train Driver/Guard shall
have the facility of adjusting the volume level from a minimum to maximum
level by suitable mode provided in Driving Cab’s dashboard. Emergency
buttons and talk back phones shall be located near all the doors and
gangways.
4.9.4 The communication between Train Driver-Guard shall be in full duplex mode
and multiplexed with suitable measures to prevent acoustic feedback. The
priorities of different functions of the public address system shall be defined.
4.9.5 The public address system shall be acoustically designed and provided with
active noise control to reduce the unwanted sound. The microphone to be
used for public address/announcement shall have high dynamic noise
cancellation feature. The Supplier shall submit the details of the system at the
design stage. The PA system shall have automatic continuous variable
volume control, based on Car background noise level.
4.9.6 In case of failure of one unit of PA system or a passenger communication unit
in one Car, there shall not be failure of the whole system. All the
communication and control cables shall be conforming to international
standards for fire retardant, fire survival characteristics suitable for the EMU
Train services.
4.9.7 A suitable interface shall be provided to enable the control centre to
Passenger/Guard/Driver communication to be transmitted over the Train
public address system.
4.9.8 An integrated main communication touch screen shall be provided to control
the public address functions, cab-to-cab communication and passenger alarm
communication.
4.9.9 At least 8 speakers shall be provided in each coach. The number, positioning
and output of each loudspeaker and power amplifier shall be designed such
that an even sound coverage in all areas of the passenger Car is achieved.
The loudspeaker should be separated into two groups and each audio line
should be supplied by its own amplifier.
4.9.10 The public address amplifiers shall be protected against short circuit at the
outputs of the amplifier. The through line cable inside the Car shall be suitably
insulated, screened, armoured and overall outer sheathed.
4.9.11 Any failure of component which can adversely affect functionality shall be
logged by the system itself and also be communicated to TCMS for reporting
to the Train operator and data logging.
4.9.12 Voice announcements and text messages for the displays shall be pre-
recorded and configured into the system using the “off line” speech and route
data base editor. Messages, audio or visual or both shall be in the Hindi,
English and regional language. The hardware and dedicated software etc. for
editing and modifying the speech and route database shall be supplied.
4.10 Passenger Information System
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 51 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.10.1 A passenger information system (PIS) shall be provided. This shall use GPS
to determine the Train location and shall provide automatic announcement
and the display of destination information on displays throughout the Train.
The system shall be capable of making pre-recorded announcements (both
audio and visual) by manual triggering from main communication panel in the
event positional information is not available. Under such circumstances,
messages shall operate automatically for the route from the TCMS
information. Messages and announcements shall be triggered based on
distance travelled and door operations.
4.10.2 All elements of the PIS installation shall be designed so as to resist damage
and vandalism. Loudspeakers shall be flush mounted and suitably protected
by grills. Information displays shall be protected by transparent covers so as to
protect against damage. The loudspeaker for voice communication system
and PIS shall be common.
4.10.3 The PIS shall be designed to provide audible announcements and information
displays in Hindi, English and regional language throughout the journey. Full
facilities including any hardware/software tools for programming the displays
and system shall be supplied. Supplier shall arrange training to program, edit
and interface the display panels with the system.
4.10.4 At least eight passenger information TFT LCD displays with backlit LED shall
be provided inside each Car. Approximate size for two displays will be 450mm
x 700mm and for six displays, it will be 930mm x 260mm. Dynamic route map
shall be shown on the display. The screen shall also include display of
destination station, present station, approaching stations, real time clock and
door indications. Simultaneous display of advertisement videos shall be
possible on the sceen. The system shall have the features of route-map of
respective lines in different colours, point of inter-change or any other
important information, flashing of emergency messages, advertisements,
videos, important train messages, scrolling of routes, adding/ expunging of
stations, selectable display of route. The size of the letter and resolution shall
be programmable and have adequate clarity and visibility for all the
passengers of the Car. The station names shall be displayed in Hindi, English
& regional language. Detail specification, mounting arrangement and screen
content shall be finalized during the design stage.
4.10.5 Each Basic unit shall be provided with two destination boards on the outside of
one Car (one on each side) in order to show the originating, destination
station, halts, Car number, Train number etc.
4.10.6 The external displays shall have adequate brightness which shall have auto
adjustment with the outside ambient light.
4.10.7 It shall be possible for someone of normal vision to read the display from a
distance of at least 20 meters under all lighting conditions. The viewing angle
for the internal displays shall be 60 degrees for uniform intensity and 90
degree with slight reduction in intensity.
4.10.8 The display screen shall be designed against vandalism, water and dust
ingress. The encapsulation class shall not be less than IP 54 with the suitable
arrangement to avoid damage to display due to vandalism.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 52 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.10.9 The equipment shall suitably interface with TCMS to ensure detection of
equipment failure. The diagnostic and failure data shall be downloadable in
Driving cab and to wayside as described in Clause no. 4.7.6.
4.10.10 Each Driving Car shall be provided with a destination indicator (Head Code)
on the Driving Car face. The destination indicator shall be mounted inside the
Car behind the windscreen and flushed with the Driving Cab interior. A
modern high resolution LED display board with amber colour shall be
provided, which shall be visible clearly from the platform from the distance of
50 meters minimum (in bright day light) while the EMU Train is approaching
the platform. The destination indicator shall have IP54 protection. The viewing
angle for the destination indicators shall be such that it is visible to the person
standing on platform; as such angle from his eyes to the destination board
shall be 30-degree minimum. Head code display shall include destination,
location of PWD coach, rake formation, Slow/Fast etc. However, the
appropriate class and overall dimensions according to the location shall be
frozen during the design stage. There shall be provision of manual over ride
feature for setting the Head Code display in the event of failure of Passenger
Information System (PIS) electronics.
4.10.11 Passenger Information System shall be interfaced with TCMS.
4.10.12 All the communication and control cables shall be conforming to international
standards for fire retardant, fire survival characteristics suitable for the EMU
services.
4.11 Passenger Car Surveillance System
4.11.1 The Passenger Car Surveillance System (PRSS) shall comprise an IP based
close circuit television (CCTV) network using surveillance cameras, routers
and cables, monitors and other accessories.
4.11.2 Each Car of EMU train shall be provided with minimum four surveillance
camera devices at appropriate location to cover the maximum passenger Car
area. Additionally, at least one camera shall be placed in cab for gathering
front end view, track and OHE conditions etc. The camera shall be suitably
selected in respect of resolution, clarity of images, illumination conditions for
on-train applications and shall be of proven design. Additional camera(s) shall
be placed on outer sides of the each Basic Unit as a minimum for gathering
rear view of the platform. Mounting of camera shall be unobtrusive, flushed
with, or recessed into the interior panel. Selection of type and number of
cameras shall be finalized during design and shall ensure clear view of
passengers on platform to Train Driver/Guard before start at each station till
Train leaves the platform completely. The system shall automatically switch to
rear view when the Train stops and will go back to default mode after the Train
leaves the platform.
4.11.3 An integrated screen shall be provided for the passenger Car surveillance
system in each Driving Cab. It shall be so placed in the cab that normally it
does not cause distraction to the Train operator but it shall be easily viewable
by the Train Driver/Guard, when needed.
4.11.4 Under normal operation, the views gathered from each of the camera located
in the Train shall be sequentially played in the monitor screens of both the
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 53 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 54 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.13.3 The doors shall be vibration free and insulated against heat and sound
transmission.
4.13.4 The doors shall be sealed against draughts and water. Any ingressed water
shall drain rapidly without affecting surrounding equipment or systems.
4.13.5 The doors shall be as light and rigid as possible.
4.13.6 The passenger body side door shall fully open in less than 4.5 (four point five)
seconds and shall close within 6 (six) seconds from the instance the Train
Operator operates the door.
4.13.7 The end of the closing stroke (e.g. approximately 100mm) shall be damped or
cushioned to reduce impact and minimise possible injury to passengers.
4.13.8 Obstacle detection shall be provided by the Supplier.
4.13.9 The door mechanism shall have safety provision whereby the EMU Train shall
not start unless all doors have been closed and locked.
4.13.10 It shall be possible to manually push back each closed door leaf to enable
entrapped objects such as clothing and other articles, to be withdrawn, even
after the mechanical lock has engaged. The force required to push back each
door leaf shall neither be less than 80N nor more than 150N.
4.13.11 The door pitch shall be approximately equally spaced over the length of the
Car.
4.13.12 The doors shall be designed so as to retain the passengers during all service
conditions and shall minimise risk in the event of an accident.
4.13.13 The strength of the sliding doors shall be as per EN 14752 and the doors shall
be able to resist the loads without deformation or damage.
4.13.14 Provision shall be made for passengers to open the doors to permit
evacuation from a stopped EMU Train in an emergency. There shall be an
internal and external manual release mechanism on each door.
4.13.15 A door closing warning shall be provided by audible and flashing light
indication.
4.13.16 A visual door open indication on the exterior of the Car adjacent to each
doorway shall be provided. This shall be visible both from the platform and by
looking down the side of the train (subject to any curvature of the track).
4.13.17 It shall be possible to monitor the status of each door on the TCMS.
4.13.18 An indication confirming that all doors are closed shall be provided in the
Driving Cab.
4.14 Master Cum Brake Controller
4.14.1 A combined master cum brake controller, integrated into a single unit shall be
provided in each driving cab. This shall be of a proven design and shall be of
step less type. Suitable provision shall be made to ensure unhindered
operation in case of failure of master cum brake controller. A separate traction
and brake control (e.g. providing at least three levels) shall also be provided to
allow the Train to be moved in the event of failure of the master cum brake
controller.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 55 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.14.2 The master cum brake controller shall be designed so that the brake is applied
by pulling the handle towards the Driver and traction is given by pulling the
handle away from the Driver.
4.14.3 The master cum brake controller shall be provided with a dead man’s device
which shall have to be remained activated manually and consciously by the
driver. In case of the driver gets incapacitated and the ‘dead man’ device is
released, the emergency brakes shall apply through direct opening to
atmosphere.
4.14.4 The master cum brake controller shall be suitable to ensure controlled speed.
For the purpose of wheel slip and slide control, the 3-phase drive
traction/braking control system shall supervise the following condition and take
corrective action:-
Excessive acceleration
Differential speed between axles
Over-speed control
4.14.5 Suitable key-switch, forward/reverse interlocks and interlocks with braking
system shall be incorporated in the master cum brake controller. The traction
shall be possible only from one cab at a time. Master cum brake controller to
be operational only after operation of cab activation switch. It shall not be
possible for unauthorized persons to operate the Master cum Brake Controller.
The key switch, reverser switch & traction/braking lever shall be inter-locked
and only one cab shall be activated in the Train at a time.
4.14.6 Maximum utilization of the regenerative braking is envisaged in the 3-phase
drive system such that regenerative braking is available over full range of
speed to be blended with the EP brakes.
4.15 Driver’s Cab
4.15.1 Layout of Driver’s Cab
(i) Supplier shall design the complete pre-fabricated driver’s desk in line
with the UIC 651 to the extent possible. The layout of the crew area
and control system shall be ergonomically designed to allow crew to
efficiently operate all controls for safe train operation either sitting or
standing. The modification required to be implemented in the coach
body viz. layout of pneumatic pipelines and adjustment to the cab depth
etc. shall be implemented by the Supplier in association with the
manufacturer to the maximum possible extent. All necessary controls
and instrumentation shall be presented in a manner that shall aid the
correct reflex action from the Driver in both normal and emergency
situations. The driving position shall be on the left side of the Driving
Cab and the brake handles shall be located on the left hand side of the
Driver in the running direction. Their relative positions shall be similar to
those available on IR’s present EMUs.
(ii) The cab shall be ergonomically designed for convenience and to
minimize fatigue of the Driver. Ergonomic and human engineering
aspects of the cab design shall be compatible with the range 5th
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 56 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
percentile Indian adult female to 95th percentile Indian adult male. The
visibility diagram shall be in accordance with UIC 651.
(iii) The cab shall include all the cab equipment e.g. combined master-cum-
brake controller, instrument panel with back-lit instruments, gauges for
pneumatic indications, control panels, driver’s diagnostic display unit &
driver’s “log in” device, driver and guard adjustable seats etc.,
ergonomically designed driver’ desk/console, pre-wired and terminated
on a terminal board and multi-pin plugs/sockets for inter-equipment
connections. Cab-equipment shall also include pneumatic horns (on
both sides of the desk), electric motor driven wind screen wipers (wiper
should have wind screen washer & control as well) with redundancy,
rolling blinds, sun-visors, auxiliary head light with tail light, safety
related equipment like bell code system, flasher light and speedometer-
cum-recorder. Driver’s safety system foot pedal incorporated into the
adjustable footrest will be supplied by IR. This shall also include
suitable ‘bell code exchange’ system between the cabs of the EMU
train. Destination indicator (Head Code) shall be provided behind the
lookout glass & flushed with the driver cab interior. Temperature and
humidity indications shall be provided in both the cabs.
(iv) All crew workstation/driving desk and cab area controls must be robust,
of industrial quality and resist physical abuse and vandalism. Moulded
FRP or better material suitable for such application must be used. The
color scheme of interior shall be frozen at the time of design approval.
(v) The top of the driver’s control workstation must accommodate
documents such as timetable or similar books without interfering with
the operation of the controls. Suitable space for keeping crew
bag/briefcase, fire extinguisher and skids shall be provided in the cab.
(vi) The positioning of crew interface controls must be such that they are
within the range of vision, touch and audibility requirements whilst the
crew is in his/her normal operating positions under all operation
conditions.
(vii) Crew cab, pipes and conduits
Equipment such as air pipes, conduits, ducts, cabling, terminals and
connectors shall be hidden from the view and shall not interfere with
the crew operations. The doors of such enclosures shall have proper
locking arrangements with ease of handling.
(viii) Each functional position and/or range must be clearly marked by
embossed or engraved letters. The labeling used must be by
agreement.
(ix) A circuit breaker listing must be included on the inside of any door or
hatch that covers circuit breakers. The circuit breaker listing must relate
the circuit breaker labeling to its function, and the equipment which it
isolates.
(x) Ergonomically Designed Driver’s Desk
Ergonomically designed driver’s desk/console taking into account
necessary traction controls, safety controls and passenger amenities
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 57 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
items etc. shall be a part of the complete driver’s cab. The design of the
console shall also take into account the positioning of various
pneumatic gauges (MR, BP, BC, PB etc.), brake controller, AWS
equipment and any other equipment installed in the cab. Provision for
placing the time table along with clip arrangement shall also be made.
The complete console shall be supplied pre-wired and terminated on
the terminal board and multi-pin plugs/sockets for inter equipment
connections. Lighting on the driver’s console shall not be less than 60
lux measured at the console. The cab shall be provided with LED lights
designed to provide 100 lux (minimum) at 1 metre above floor level.
Supplier shall be responsible for its proper commissioning. One number
LED based cab emergency light shall also be provided on battery
supply. Major functions control and their indications shall be provided
on the desk.
(xi) All the equipment viz indication and instruments, panels, switches,
ventilation control system, lighting, driver and guard seat, sunscreens
and gauges etc. required to be installed in the cab, shall be supplied by
the Supplier except for AWS/AAWS equipment and Auto Brake
Controller which shall be supplied by the Purchaser. As such the
Supplier shall have the complete responsibility of ergonomic design of
driver’s cab and supply, commissioning and interfacing of the complete
cab equipment.
(xii) The layout of the equipment on driver’s desk shall be finalized during
design approval stage to maintain uniformity with cab arrangement of a
similar project of IR so that the cab layout remains same from driver’s
perspective to the extent possible. Based on the approved layout, a
mock up of the complete driver’s cab shall be made at ICF/nominated
manufacturing works to finalize the finer details and freeze the design.
4.15.2 Display Panel
A suitable touch screen display (back lit) with high resolution, wide viewing
angle, suitably designed against vandalism, high impact, rough handling,
ingress of water & dust and IP 54 protected robust & heavy duty input/output
system as per the available technology, shall be provided on driver’s desk to
display fault status, energy values & status of various important parameters as
selected by driver/ maintenance staff or as required for the satisfactory system
operation. The selection of the display panel shall be liberal and details shall
be worked out during design stage. Supplier shall submit options available.
The display system shall be protected against dust and moisture.
The driver’s desk shall include one driver’s display on driver side to display the
status, fault diagnostic and operate the following systems:
Train overview
Basic unit overview
High voltage system,
Train performance parameters,
Propulsion system,
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 58 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Auxiliary system,
Air supply system,
Door system,
Comfort systems,
Passenger alarm system,
Service brake,
Emergency brake,
PI- & PAS,
CCTV
Graphical display of schematics for fault indication and troubleshooting
shall be included in the display etc.
Additionally, there shall be a guard’s display on the guard side to display the
status and operate the following systems:
Train overview
Door system,
Comfort systems,
Emergency brake,
Passenger alarm system
PA & PIS
CCTV etc.
Further details shall be worked out during the design stage.
4.16 Safety Measures
4.16.1 All equipment will be adequately earthed, insulated, screened or enclosed and
provided with essential interlocks and keys as may be appropriate to ensure
the protection of equipment and safety of those concerned with operation and
maintenance.
4.16.2 Standard protective systems, shall be provided, in accordance with the Good
Industry Practice, for protection of the electrical equipment against abnormal
currents, excessive voltages etc., with indicating facilities, so as to ensure safe
and correct operations.
4.16.3 All exterior components including under slung equipment shall be attached
with use of secondary restraints, redundant fixings or secondary latches as
appropriate to ensure that no single point failure shall cause equipment to
either physically detach or protrude out of gauge.
4.16.4 A sensitive and reliable protection arrangement against earth fault shall be
provided in each circuit group.
4.16.5 All electrical circuits shall be fully insulated from the superstructure on both the
positive and negative sides and the super-structure shall not be used as a part
of any earth return circuit.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 59 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.16.6 Relevant provisions stipulated in Indian Electricity Rule 1956 shall be followed
in the interest of safety of passenger/staff as well as for equipment /
instruments provided in the Cars.
4.16.7 Fire prevention measures for equipment design:
4.16.7.1 The design of equipment shall incorporate all measures to prevent fire and will
be such that should any fire take place the effects shall be minimized and no
spread of fire should take place. Materials which are not fire retardant shall not
be used.
4.16.7.2 Materials used in the manufacture of equipment/system shall be selected to
reduce the heat load, rate of heat release, propensity to ignite, rate of flame
spread, smoke emission, toxicity of combustion gases and shall comply with
EN 45545.
4.16.7.3 A manually operated two position earthing switch shall be provided. The
operation of the switch shall enable earthing of the power circuit of the Train
and allow attention to the high voltage equipment by releasing interlocked
keys from a box fitted to the earthing switch.
4.16.7.4 All safety features in design, construction and materials used shall conform to
the best safety standards and shall in particular prevent fires in Train in
accordance with Good Industry Practice.
4.17 Automatic Fire Detection with Alarm System
4.17.1 Train shall have automatic fire/smoke detection system. This shall be capable
of detecting a fire in any Car. On detection of a possible fire by means of
suitable detection, the system shall have different levels of response to be
finalised at design stage.
4.17.2 In the event of detection of a fire, the air conditioning system shall be
controlled to minimize the spread of fire to promote the escape of passenger.
In the event of detection of smoke outside the Train, an alarm shall be
provided to the Driver/Guard. The Driver/Guard shall then be able to remotely
close the air conditioning system fresh air intake.
4.17.3 System shall provide foolproof safety against unauthorized person driving the
train. The authorized person shall have to `log in’ by means of suitable
electronic device in the driver’s cab and the details of the personnel and
timing, journey details etc. shall be recorded in the memory. This shall be
accessible as and when required. The details shall be worked out during
design stage.
4.17.4 The EMU Train shall be provided with speed indicating-cum-recording
equipment in each driving cab. The speed indicating-cum-recording equipment
with electrical/electronic type of drive shall be used. The equipment shall also
incorporate the feature of indicating and recording kilometers travelled by the
Train. The recording shall be on suitable media and readable in graphic and
tabulated form. The capacity of the memory shall be such that it retains most
recent data of at least 45 days service period.
4.17.5 The speed indication cum recording equipment will have a scale range of 0 –
150 km/h. The equipment shall suitably interface with TCMS to ensure
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 60 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 61 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.18.4 The control equipment, relays and switches, and such other devices shall be
in accordance with the Good Industry Practice.
4.18.5 The working of all relays and contactors shall be in the range –30 % / +25 %
of nominal battery voltage when the operating coils are at their rated
temperature and the contacts are subjected to normal pressure.
4.18.6 Rubber components, such as pistons, ‘O’ rings etc. wherever employed in the
control gear, brake system and their controls shall be suitable for the specified
humid and environmentally severe conditions. The life of rubber components
shall not be less than six years.
4.18.7 Surge suppression circuits shall be incorporated to eliminate surges, wherever
required.
4.18.8 Both mechanical and electrical, shall be in accordance with IEC 60337.
4.19 Power and Control Electronic Equipment
The traction converter shall meet the requirements of IEC-61287 & the control
electronic and PCBs shall conform to IEC-60571 including compliance to the
optional tests. However, due to higher ambient temperature in India, the
temperature for dry heat test shall be 80°C as against 70°C specified in
IEC/EN. LCD display units may be tested into 70°C. The electronic control
equipment should be protected against unavoidable EMI. The equipment shall
be suitably mounted in properly designed cabinets for cooling requirements of
the electronic equipment (with or without doors) and shall remain in the scope
of supply of the Supplier. The vibration and shock tests and endurance tests
shall be done as per IEC 61373 as per the requirements of design.
4.20 Brake Blending
4.20.1 Full utilization of the regenerative braking is envisaged in the 3-phase drive
system such that regenerative braking is available over full range of speed to
be blended/interfaced with the existing EP brakes. The control system shall be
designed that in the EP brake region, for any set braking effort demand, as
decided by the position of the brake handle, maximum possible brake effort is
obtained from the regenerative energy of the motor coaches and the EP
brakes of the trailer coaches are applied mainly to supplement the difference
between the demand and the regenerative braking effort achieved.
4.20.2 Normally, in the EP service braking zone, only regenerative braking is applied
in the motor coaches where as the EP brakes are applied on the trailer
coaches. However, if the regenerative braking becomes ineffective, the EP
brakes shall come on the motor coaches. A suitable protection shall be
included for DC link over voltage protection.
4.20.3 The supplier shall modify at his own cost the brake equipment for proper
functioning of the brake blending scheme, in case the design calls for such a
change. The design change in brake system, if become imperative, shall be
got approved by the supplier before implementation. The details of the brake
system shall be provided during design approval stage.
4.20.4 Supplier shall furnish details of the system adopted for ensuring safe and
smooth changeover to EP brakes when regenerative brakes are rendered
ineffective. This smooth changeover shall be achieved in the event of failure of
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 62 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
overhead line or when passing through the neutral section. The Supplier shall
submit the respective distribution/proportion of electrical & mechanical brakes
throughout the operational range of the EMU for achieving the specified rate of
decelerations at Clause no. 2.5.2.
4.20.5 Adequate redundancy shall be provided to ensure that the EP brakes do not
become non functional in case of failure of power supplies, isolation of motor
coach or failure of control electronics and pressure transducers etc. In case of
isolation of any EP valve due to any defect, the brake electronics shall take
adequate corrective action with least system isolation. System shall provide
enough redundancy in the brake electronics and controls so that the isolation
of motor coach does not lead to non-functioning of EP brakes of the motor
coach.
4.20.6 Separate Brake Electronic Control Units of proven design shall be provided to
ensure redundancies and shall perform the functions as defined in this clause.
Brake system integration test shall be performed through simulation on test
bed at manufacturer’s works.
4.20.7 It shall be possible for the driver to know the malfunctioning of brake system of
a coach. Selective isolation of EP valves (coach wise) shall be possible. The
control scheme shall be submitted by the Supplier. Any other associated
components required to realize the above function shall remain in the scope of
supply of the Supplier. Details shall be worked out during the design stage.
However, IR may decide for their provision and implementation based on the
ease of operation offered in the design by the Supplier.
4.20.8 The friction braking system shall function as the ultimate braking system on
the Car, acting as a backup during normal service braking and as the primary
braking system during emergency stops and while parking.
4.20.9 The Supplier shall provide suitable redundant interface of AWS/AAWS with
the brake system for increased reliability and availability. It shall remain
operative as at present without any need for modification therein.
4.20.10 System shall provide for adequate safety measures against rolling back of
EMU in case the train is to be started on a rising gradient.
4.21 Wheel Slip/Slide Protection & Anti Skid Controls
4.21.1 The Wheel slip/slide protection function & anti skid controls should be
integrated/ interfaced with the Traction Control Wheel Spin and Protection
function unit.
4.21.2 The wheel slip/slide protection system, to be installed on motor coach, shall
make maximum use of the available adhesion between the wheels and rail to
minimize slipping distances (and improve acceleration) in adverse rail
conditions. The wheel slide protection system shall be active in all braking
(and acceleration) modes and shall detect and correct negative (and positive)
wheel slip (slide/spin) that may be occurring randomly or synchronously
between axles on the same bogie. The system shall be fail-safe such that any
failure of the system shall render it ineffective. If a failure occurs in braking, the
system shall not reduce the level of braking below the commanded level for
more than 3 seconds. The wheel slide protection system shall monitor all axle
speeds on the motor coach to determine if a slide (or spin) condition exists. If
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 63 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
such a condition is detected, the system shall control negative (or positive)
Tractive effort of each bogie individually to prevent the wheels on each bogie
from sliding, locking or spinning. Supplier shall explicitly submit the complete
control scheme with explanation to achieve the above requirements in their
design.
4.22 Parking Brake
4.22.1 A parking brake system shall be provided in each basic unit and shall be
capable of holding it under SDCL loaded condition on a 1 in 100 gradient
when there is no electrical power. A test scheme shall be submitted by the
Supplier to test the efficacy of parking brake system during the design stage.
Detailed design calculation justifying the suitability of the offered system shall
be submitted during design stage by the supplier. The system shall be tested
for its satisfactory functioning in a 12-car rake.
4.22.2 Parking brake system working shall have the provision for isolation in case of
mal-operation. System shall immediately detect any mal-operation of the
parking brake system before it causes any damage to wheels and other
connected item and shall take suitable protective action.
4.22.3 The parking brakes shall be applied in the event of loss of the main
compressed air supply. The design shall be such that the parking brakes will
take effect prior to fading off of the service brakes. The parking brakes shall be
capable of release from within the cab when the compressed air supply is
present. With no compressed air supply available, it shall be possible to
release individual parking brake actuators manually from track level.
Application of parking brakes shall also be controllable from the cab.
Unintended parking brake application due to air leakage from parking brake
line will be detected and displayed on TCMS as fault indication. Detailed
software logics for system response in the event of unintended application of
parking brake shall be finalized at the design stage.
4.22.4 Status of train parking brake shall be displayed on the HMI of TCMS. A
suitable pressure gauge shall also be provided and shall be in the scope of
supply of the Supplier.
4.22.5 Jerk Limit
Under all normal operating conditions, the rate of change of coach
acceleration or deceleration shall not exceed 0.7 m/s³. Failure of the jerk
limiting system shall not limit braking effort. Emergency brake applications and
any associated ramp out of propulsion shall not be jerk limited. Reduction of
propulsion effort due to a power interruption (including passing through neutral
sections) need not be jerk limited.
4.23 Load Weighing System
Load weighing system shall be used for measurement of air spring pressure to
limit the adhesion utilization, meet the requirements of acceleration, braking,
air-conditioning adjustments and detection of deflated air spring. The
pneumatic signal for the load weigh system is to be provided by the Supplier
on these EMUs. The load weighing compensation signals to the propulsion
and braking systems shall be a continuous function available for all coach
weights up to and including SDCL. Adequate redundancy shall be provided in
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 64 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
the load weighing system and failure shall be recorded in the diagnostic. If
there is a failure of this system, the coach shall respond as if it was loaded to
an SDCL level. A detailed control scheme shall be submitted by the Supplier
along with the calculations for the achieved levels for the acceleration,
deceleration values and for the air-conditioning control system adjustments.
The proven schemes already in use by the Supplier in other similar rolling
stock applications shall also be given in support of the calculations submitted
by the Supplier. The extent of advantage achieved on this account duly
simulated shall be submitted by the Supplier. The same shall be verified
during the prototype approval by the Purchaser for its effectiveness and
implementation.
Air spring deflation indication shall be provided in the driver’s cab including the
information regarding Car, air spring position in Bogie, status messages etc. In
order to ensure reliability of the scheme, adequate redundancy shall be
considered to take care of the failure conditions.
4.24 High Voltage Protection
4.24.1 Roof mounted single bottle Vacuum Circuit breaker of proven and approved
type shall be provided on 25 KV AC system.
4.24.2 A suitably rated high voltage cable conforming to the external application for
running on the roof under the ambient conditions as per the specification shall
connect the VCB to the main transformer. The cable insulation and sheathing
material shall be halogen free, flame retardant and shall have low smoke
emission. The enclosure and termination of the cable shall be protected
against rain water & wear. In the event of the breakdown of cable insulation or
the termination, there shall not be any risk of electrocution, or other hazards to
the persons inside or close to the outside of the coach. The Supplier shall
submit the cable layout schemes (preferably avoiding the passenger areas)
during the design evaluation stage. All the safety measures must be listed
along with the references of materials used by the Supplier.
4.25 Auxiliary Systems:
4.25.1 The power supply for the auxiliaries will be through IGBT based auxiliary
converter. The system shall be protected and devices shall be selected
suitably to ensure that there is no damage on account of surges. The design
of the snubber circuit shall be carefully done so that the components do not
fail due to surges. This aspect shall be specifically checked during
commissioning by actual measurements of the surges and will be complied
accordingly.
4.25.2 The auxiliary system shall be designed in such a way that in the event of
failure of auxiliary converter(s) equivalent to one basic unit, all the loads
(including air conditioning) shall work normally. In case of next auxiliary
converter failure, the unit with failed auxiliary converter shall work with 50% air
conditioning, 100 % fresh air ventilation and all other loads shall be fully
available. In case the third auxiliary converter fails, air conditioning shall be
switched off and all other loads inclusive fresh air ventilation shall work
normally. The above-mentioned design rules shall be fulfilled with a 12-car
rake with three 4-car basic units or higher. During design state the detailed
auxiliary design concept shall be submitted for approval. The changeover shall
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 65 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 66 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Vacuum pressure impregnation (VPI) of the stator winding must be done using
solvent less varnish having thermal index above 200 0C. Any other method
utilized in place of VPI may be considered provided its advantages are listed
and provenness is ensured, for the environmental conditions existing in India,
by the Supplier at the design approval stage.
4.25.12 In the case of squirrel cage motors, aluminum alloy die cast rotor construction
will be preferred.
4.25.13 L-10 life of bearings will not be generally less than 40,000 working hours when
calculated as per ISO recommendation R-281. For motors higher than 15 KW,
flange bearing housing units will be used. The bearing design will be such that
no greasing or any intermediate attention may be required to be done for at
least one and half year after each greasing/adopting maintenance schedule as
recommended by the manufacturer.
4.25.14 All auxiliary motors separately & combined equipment like motor blower sets
will be subjected to prototype tests as per relevant IEC specification. If the
operating conditions of the auxiliary machines differ from the specified test
conditions in relevant IEC publications, additional tests will be carried out.
4.25.15 Auxiliary Compressor Set: A 110 V DC battery operated auxiliary
compressor set having adequate capacity, will be provided in each unit for
feeding the auxiliary air reservoir for operation of the pantograph and main
circuit breaker during the preparation of the EMU for service. A governor
device will also be included in the scope of supply of the Supplier. Any
modification in the existing pneumatic control circuit shall not normally be
preferred. However, if it becomes inevitable due to any design up-gradation of
the equipment, it shall be the responsibility of the Supplier.
4.25.16 Battery and Battery Charger
(i) An automatic static battery charger fed from three phase auxiliary
supply shall be provided. Its rating and charging characteristics shall be
matched to the battery, by monitoring of charging current and voltage
and shall have a provision for fine adjustment and good stability to
avoid overcharging or undercharging of batteries;
(ii) Low maintenance batteries of adequate capacity shall be provided on
each Basic Unit to feed the equipment for at least 3 hours in the event
OHE supply is not available. Nominal voltage of the battery shall be 110
V; and
(iii) The design and control of the battery shall ensure that the battery gets
disconnected from non-essential loads when the battery gets
discharged, however there shall be sufficient capacity left under all
conditions to raise pantograph and to power voice recorder and flasher
light. When auxiliary load is reconnected, the initial battery load shall
not cause the battery output to oscillate.
4.25.16.1 The batteries shall be maintained at an adequate level of charge to satisfy the
requirements as given below:
System maintained Time
Emergency ventilation in all Cars 1 hour after the loss of OHE power
including Driving Cabs
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 67 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Communication system (PIS and PA 1 hour after the loss of OHE power
system)
Emergency lighting 1 hour after the loss of OHE power
Door release of alternate doors on 1 hour after the loss of OHE power
either side
Train controls (full load) 1 hour after the loss of OHE power
Fire detection system 1 hour after the loss of OHE power
For the purpose of capacity calculations, a total of 30 Close-Open operations
of door shall be considered.
4.26 Lights:
4.26.1 Lights shall be fed by the auxiliary power supply system. The guaranteed life
of the LEDs with their control system and optics/luminary shall not be less
than 50000 burning hours. The specified illumination level shall be met till at
the end of the life of 50,000 hours. After 50000 burning hours, the luminaire
intensity shall be at least 70% with degree of uniformity of at least 1:1:3 as per
UIC 555. The colour of the LEDs shall be cool day white (temperature 6000K-
7000K). LED shall be LM80 certified for white LED along with TM 21
projection for more than 50000 hours. Separately protected lighting circuits
shall be used, such that in the event of tripping
4.26.2 of one circuit, the others should provide evenly distributed lighting throughout
the Car. The Supplier shall submit layout of fittings, control circuit and service
life of LED lamp during the design stage which shall be as per the best
international practices. It shall be possible to replace defective LEDs / block of
LEDs with ease and minimum need for readjustments or otherwise.
4.26.3 With all lights switched on in a Car, the illumination shall not be less than 300
lux at height of 1.5m above floor level along the entire length of the Car. With
the exception of the illumination level, lighting shall be of similar or equivalent
performance to EN 13272 – “Railway Application – Electrical Lighting for
Rolling Stock in Public Transport Systems” as applicable to urban rail
transport systems. Uniformity level of 1:1.3 as per UIC 555 shall be achieved.
4.26.4 Selection of diffuser shall be such that the LEDs are not visible and
appearancelooks like a brightly lighted surface. The diffuser shall be compliant
to fire and smoke standards, conforming to UL94-V0 grade.
4.26.5 The lighting system shall be designed so that it is resistant to vandalism; in
particular it shall not be possible to damage or remove any light source without
the use of special tools to dismantle a protective cover.
4.26.6 At least 50% of lights, evenly distributed over the Car area, shall remain
energized and provide sufficient light for safety of passengers, in the event of
a OHE failure.
4.26.7 Car wise indication of healthiness/working of lights shall be provided in the
Driving Cab. It shall be possible to isolate 50% lights of the Train from either of
the Driving Cabs.
4.26.8 For lighting the interior of the Car, suitable lamps with colour rendering index
Ra of 80 or more shall be used. Ra shall be calculated as specified in the
paper by Nickerson and Jerome in 1965, republished by the CIE in 1995.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 68 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.26.9 Lights shall perform normal when the Train is passing through the neutral
section.
4.26.10 Separately protected lighting circuits shall be used, such that in the event of
one tripping, the others provide evenly distributed lighting throughout the
coach.
4.26.11 At least 50% of lamps, evenly distributed over the coach area, shall remain
energized and provide sufficient light for safety of passengers, in the event of
a main auxiliary power failure even from the adjacent unit.
4.26.12 Coach wise indication of healthiness/working of lights shall be provided in the
driving cab. It shall be possible to isolate 50% lights of the rake from driver cab
when the EMU is stabled in yards or shed.
4.26.13 Emergency lights (at least 8 nos. per coach) shall be provided in each coach
to be fed by battery in case of total failure of auxiliary supplies.
4.26.14 Lighting on the driver’s console shall not be less than 60 lux measured at the
console. The cab shall be provided with ceiling lights designed to provide 100
lux at 1 metre above floor level.
4.26.15 The wirings, switch gears, relays and terminal equipment required for proper
working of lights shall be provided by the Supplier.
4.27 Head, Tail & Flasher Lights
4.27.1 The front end of each Driving Car shall be provided with high intensity, long
distance, dimmable twin beam LED headlight in accordance with Indian
Railway practice.
4.27.2 The headlight units shall be pre-focused, capable of giving minimum 3.2 lux at
a distance of 305 meters. The beam spread shall be symmetrical and angle of
beam shall not be less than 7 degrees.
4.27.3 The design of the headlights shall provide for easy replacement of luminaire.
4.27.4 Arrangements shall be provided for dimming the headlight output when
required.
4.27.5 The headlight shall be provided in suitable waterproof enclosures conforming
to IP 65.
4.28 Tail Light
4.28.1 Two auxiliary head light cum tail light shall also be provided on each Driving
Car. Tail light shall be steady red on one side and flashing amber on the other
side.
4.28.2 The tail light shall be red in colour flashing at a rate of 55-65 flashes per
minute in operation.
4.28.3 The clear visibility of tail light in clear daylight shall not be less than 1.6
kilometres along the longitudinal axis and 100 meters at 6 degree angular
displacement from longitudinal axis.
4.28.4 The tail light shall be provided in suitable waterproof enclosures conforming to
IP 65.
4.29 Flasher Light
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 69 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.29.1 Two flasher lights, one at each end of the Train, shall be provided. It shall be
designed to provide 40 ± 5 flashes per minute. It shall emit sufficiently bright
amber-yellow light with dominant wavelength of 590-595 nanometers to be
visible at a distance of 2Kms in clear daylight and not be affected by sunlight
glare. The lux measured in axial direction shall not be less than 500 lux at 1
meter and 55 lux at 3 meters. The flasher lights shall be provided in suitable
waterproof enclosures conforming to IP 65. These shall work on battery
supply. The flasher light shall work in neutral section also.
4.29.2 Facility for monitoring and positive confirmation whether flasher light is lit or
not shall be provided in the form of audio-visual indication in Driver cabs.
4.29.3 The working of the flasher lights shall be so integrated with the Train brake
system that in the event of Train parting, flasher light shall get automatically
turned on and any tractive effort on the Train shall be disabled until
acknowledged by the Driver.
4.29.4 The crew cab light and its control.
4.29.5 Indicator lights test switches.
4.29.6 These will work on the battery supply. The flashers will be used only in the
emergencies arising from accidents to trains etc. Supplier shall ensure that a
separate switch is provided in the driver’s cab to switch ON/OFF the auxiliary
head light independent of Head light and tail light (normal & blinking operation
respectively).
4.30 Pneumatic System
Proven pneumatic system comprising of air compressor, compatible air dryer
and filters shall be supplied so as to ensure delivery of the compressed air
complying with air quality class specified in ISO-8573. The air compressor
shall be supplied as a complete unit containing all equipment required to
supply all air systems with cool dry and filtered air and shall be sized to fulfill
all air requirements of each car under all operating conditions. The
compressor shall be directly driven by the motor and shall deliver required air
for suspension, brakes and other requirements.
4.31 Main Motor-Compressor Set
4.31.1 Compressor suitable for rolling stock applications in dusty and humid climate,
with motor of adequate capacity shall be provided for each unit so as to meet
the total compressed air requirement under all operating conditions such as
but not limited to brake system, control system, air suspension spring, horns
etc.
4.31.2 The motor shall be 3-phase AC motor suitable for working from the 3-phase
output of the Auxiliary inverter or independent inverter as the case may be.
Motor compressor shall be suitable for under-slung mounting. The compressor
and associated pneumatic equipment shall be well located for easy access for
maintenance. System design shall be such that average duty cycle of any
compressor without electrical braking does not exceed 50%. The run time and
duty cycle of each compressor shall be recorded through TCMS for
maintenance schedule point of view.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 70 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.31.3 The compressor shall preferably be of two-stage type, with necessary inter
and after cooler (to cool the discharge air to within 15°C of ambient air). The
compressor capacity shall be such that with isolation of one compressor in a
12-car rake, the remaining compressors shall adequately meet the
compressed air requirement of the rake during service. During selection of
compressor capacity, consideration shall be given to air leakages from
pneumatic system, which starts taking place in course of time and age.
4.31.4 The compressor shall not require overhaul earlier than the overhaul
requirement of the rolling stock at workshop. The air compressor shall be
supplied as a complete unit containing all equipment required to supply all car
air systems with cool dry air and shall be sized to fulfill all air requirements of
each car under all operating conditions including future requirements. The
compressor shall be directly driven by the motor and shall deliver required air
for all requirements.
4.31.5 Details shall be submitted at the design stage to justify the rating of the
compressor selected along with the time taken to charge a completely empty
12-car rake. Finite Element Analysis (FEA) for compressor mounting
arrangement shall also be submitted at the design stage.
4.31.6 The motor-compressor unit shall be resiliently mounted with a 4-point
suspension for minimizing the level of vibrations transmitted to the car body.
4.31.7 Supplier shall ensure that the noise level of the compressor shall be as low as
possible so as not to cause inconvenience to the commuters. Noise emission
level shall be 68 dBA which shall be measured in accordance with ISO
3095:2001 norms satisfying the emission noise level for EMU as mentioned in
UIC guideline for procurement of new rolling stock.
4.31.8 The capacity of the compressor shall be selected after taking into account the
frequent purging of air by the air dryer (due to high ambient humidity), which
may affect the compressor duty cycle.
4.31.9 Supplier shall offer the compressor of proven design and ensure the
provenness of such compressor in the dusty and humid climate as described
in the Clause no. 2.11.
4.32 Air – Dryer And Air Filter
4.32.1 A heatless regenerative type air-dryer shall be provided at the outlet of the
compressor to ensure that the dry air is available for controls and pneumatic
operations on the train. Due to heavy rainfall and high humidity as prevalent in
most part of India, the air dryer shall be of heavy-duty type suitable for
application in coastal areas and shall not require frequent attention & changing
of the coalescing element and other chemicals. Supplier shall furnish the
details in this regard. The mounting arrangement shall be such that the
checking of the humidity indicator and changing of the chemicals shall not
essentially require the pit.
4.32.2 Air Dryer shall be provided with exhaust silencer so that the noise emanating
out of the purging operation does not cause any discomfort to passengers or
otherwise.
4.32.3 The maximum relative humidity at the output of the air dryer shall be smaller
than 35 %.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 71 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.32.4 Air shall be aspirated by the low-pressure cylinders and cleaned by a dry-type
air-filter. The filter element shall be heavy-duty type and shall be specifically
designed for high level of dust and debris as found in the vicinity of tracks in
Mumbai. In any case, there should not be any need for cleaning the filter
before the Schedule examination in the shed. Supplier shall declare the time
period after which the filter shall require cleaning. Suitable mechanism shall be
provided to indicate the quality of the air.
4.32.5 Under the ambient conditions of Mumbai, no condensation shall take place.
Minimum particle size of 1 micron shall be removed and maximum 0.01mg/m3
oil content shall be permissible as remnant. At least 95% liquid water shall be
removed even at the worst condition/efficiency of the filter.
4.32.6 The dryer shall be proven regenerative type under similar coastal conditions
and shall preferably preceded by an automatic drain valve to collect and
discharge the bulk of moisture in the compressed air before it enters the air
dryer. An intercooler and after cooler of liberal capacity shall be supplied.
4.32.7 The working of the air dryer shall be monitored and displayed in the driver’s
cab. In case of any malfunctioning of the dryer requiring isolation of the dryer,
the system shall take suitable protective action without any interference from
the driver.
4.33 Filters
4.33.1 All the filters as required by the Supplier for satisfactory functioning of the
equipment and complete system shall be supplied. IR has experienced that
the cyclonic filters used in the existing rolling stock gets choked with the debris
lying around the track making the filter arrangement ineffective. Air filters
assemblies of suitable type shall be selected accordingly and should be heavy
industrial duty type.
4.33.2 The filtering capability, flow rate capacity, and overall size shall be appropriate
for the application and the ambient conditions like prevalence of heavy dust
and debris in India. It shall be possible to gain access to the filter element for
replacement purposes. The design of capacity requirements shall take into
account at least 25% choking in air filters & radiator fins.
4.34 Air-Conditioning System
4.34.1 All the Cars shall be air-conditioned with a minimum of two roof mounted
packaged unit (RMPU) type air-conditioning units in each Car. Driver's cab
shall also be air-conditioned. Each packaged unit shall have two independent
refrigerant circuits. The control of air conditioning unit shall be performed by
suitably designed microprocessor controller. The complete air system shall
have EER (Ratio of capacity in BTU/Hour and the total power consumption in
watts) better than 9.0 under the specified conditions. No material shall be used
in construction of air conditioning unit that is liable to be adversely affected by
vibration, damp, rotting or growth of moulds. Fire retardant material only
should be used.
4.34.2 The Cars shall be provided with refrigeration system using R 407C refrigerant
or any other eco-friendly HFC refrigerant having zero ozone depletion
potential and A1 safety category as per ASHRAE standards.
4.34.3 The air conditioning units shall be fed from the auxiliary converter.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 72 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.34.4 The roof mounted package unit shall provide air conditioning to the coach
under the following conditions:
Summer condition Dry bulb Wet bulb % RH
Outside (dry summer) 38°C 30.8°C 60%
Inside (dry and wet) 23-25°C - 40-60%
The capacity of the RMPU shall be based on SDCL condition of EMU Car and
the heat load calculation for the following conditions:
Condition Dry bulb Wet bulb % RH
Hot room 38°C 30.8°C 60%
Cold room 25°C - 40%
4.34.5 The design of RMPU shall be such as to restrict relative humidity inside the air
conditioning compartment under any circumstances to a maximum of 60%.
4.34.6 In the event of failure of one RMPU, the second RMPU shall cater 60% of the
total air-conditioning load of the Car.
4.34.7 The single RMPU shall be able to work even with one condenser fan and the
cooling capacity so obtained shall not be less than 75% of the rated capacity
of the said RMPU.
4.34.8 Supplier shall provide controller with smart automatic temperature settings for
comfort of passengers as per ASHARE or any other international standard.
4.34.9 All the equipment shall be capable of continuous operations without detriment
to the operation of cut-outs and circuit breaker or over load, as per the
environmental conditions mentioned in Clause no. 2.11 of this Specification.
Necessary arrangement shall be provided to restrict the relative humidity
inside the Cars to 60% even with the outside ambient air having relative
humidity as high as 100%.
4.34.10 The minimum fresh air quantities shall not be less than 0.14 m3 / minute /
person for all types of Cars. The air flow parameters shall be as per ASHRAE /
EN14750. Limit of noise level generated by the RMPU and air velocity inside
the Car shall be considered as per EN14750.
4.34.11 The air-conditioning unit shall be able to perform at an ambient of 45oC
without any tripping of the equipment and the same shall be tested on test
bed.
4.34.12 The compressor suitable for traction environment, shall only be used and it
shall have adequate capacity at 50°C condensing temperature & 5°C
evaporating temperature. The compressor shall have automatic capacity
control system to match the refrigeration requirement of the Car heat load.
The refrigerant evaporator unit shall comprise of cooling unit with automatic
thermostatic expansion valve. Suitable arrangement for drainage of
condensate water shall be made so that water does not come inside the Car
and does not fall on couplers, gangways, platforms or any other equipment.
4.34.13 Each air conditioning unit shall be constructed as an integral module to enable
removal from the Car as single complete item without the necessity to break
any refrigerant lines or any part of Car or unit itself. All electrical connections
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 73 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
and condensate outlets shall be fitted with standard quick disconnect fittings.
The connectors should be so positioned to ensure that it is not damaged when
the air conditioning unit is removed from the Car and placed on a flat surface.
4.34.14 All fresh air intake shall be filtered and the air filter elements shall be cleanable
and shall not be of disposable type. The Supplier shall use a filtration system
suitable for Indian conditions requiring minimum
attention/cleaning/maintenance. Suitable device to indicate the pressure drop
shall be installed so that filters can be replaced/cleaned after getting
necessary indication for the same.
4.34.15 Microprocessor based controller shall be used for air conditioning system.
However, in case of failure of microprocessor based controller, it shall be
possible to run the system with full capacity in manual mode with all major
protections intact. The link between the microprocessor and interfaced cards
shall be established by means of serial bus system or any other superior
means to ensure error free high speed data transmission. The control and
monitoring function shall be implemented through software to reduce
hardware and cables. The complete control panel along with microprocessor
controller shall be accessible from inside the Car without any requirement of
going on roof.
4.34.16 The microprocessor shall perform the task of fault diagnosis and display in
addition to control task. It shall be a capable of monitoring the status of the
equipment and continuity of jumper cables continuously and the occurrence of
the faults. It shall also take appropriate action and wherever necessary, it shall
shutdown the equipment. The faults shall be stored in the memory of
microprocessor and it shall be possible to download the same using
commercial available USB pen drive or laptop.
4.34.17 Various important parameters of the equipment as well as environmental data
at the time of occurrence of the fault shall also be recorded.
Application/diagnostic software tools as required for trouble shooting and
analysis of the fault shall be provided. Adequate redundancy shall be built in
the microprocessor.
4.34.18 In the event of failure of air-conditioning unit/units, harmful quantities of the
refrigerant shall not be released inside the compartment.
4.34.19 In the event of the failure of 415V power supply in a Car, an emergency
ventilation shall operate automatically to admit fresh air directly into Car to
maintain the required oxygen level in fully loaded Car, in accordance with
ASHRAE. The fresh air intake shall not be less than 18 m 3 / hour / person with
passenger loading as per SDCL condition. The emergency ventilation fan shall
be fed from 110V DC supply with its dedicated inverter.
4.34.20 Superstructure shall be provided with ducting arrangement for discharge /
exhaust of air. It shall be ensured that water does not enter in such
arrangement during rains or Car washing. Complete duct for the air-
conditioning system shall be provided in the prototype unit only for
measurement of air flow in actual conditions. Special care shall be taken to
ensure that there is no ingress of water at the worst conditions, when there is
heavy rain striking at 45° opposite to the movement of the train running at 110
kmph.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 74 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.34.21 Suitable mechanism to adjust the cooling & air flow/speed of the ventilators,
depending upon rush hours and seasonal requirements, shall be provided.
Load weight signal can be used for Car temperature control in suitable steps.
Alternative provision shall also be provided with the driver, which may be
actuated if so desired during exigencies.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 75 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
De-rating of cables due to bunching effect and cable layout shall be taken into
account during design.
4.37.5 All connections shall be terminated on terminal bars manufactured in
accordance with Good Industry Practice. The terminals and wire cable ends
shall be suitably marked to facilitate correct connections. All the end wall
panels in suitable enclosures as per the coach wiring requirements shall be
the responsibility of the Supplier.
4.37.6 Plugs/couplers and sockets shall be used to connect pre-assembled units to
facilitate maintenance and ensure a better layout.
4.37.7 No cable having a conductor size of less than 2.5 sq. mm shall be used except
for multi core cables where 1.0 sq. mm cable is permitted. Smaller size cables
for internal wiring of panels, control cubicles, consistent with the mechanical
and electrical requirements, may be adopted.
4.37.8 A systematic cable transit management & sealing system shall be provided for
protection of cables against cutting, damage, fire, vibration, pull tension,
temperature variation, dust, water, humidity & rodents as well. Cable
management Transit System must be fire resistant, smoke and gas tight, and
the pressure/vibration shall not damage it or compromise its seal or security.
4.37.9 Sufficient spare Train line cables and input/output contacts (at least 10%) shall
be provided for catering to future needs of the IR. As such multiplexing of
signal shall be adapted to the maximum extant possible in line with the best
international practices.
4.37.10 The cables shall be de-rated to take care of the adverse ambient conditions.
All de-rating factors shall be applied, together with the maximum permissible
conductor temperature for the particular insulation type. In no case the
conductor continuous temperature shall exceed 90oC. The maximum short
circuit temperature shall not exceed 250oC. The cable insulation shall be
capable of withstanding these temperatures.
4.37.11 High voltage 3-phase AC and low voltage DC cables/connections will be
physically separated from each other. Adequate number of standby vital spare
control wires will be provided with adequate indications.
4.37.12 The following operational and environmental factor will be specially kept in
view while selecting the cable:
(i) Excessive vibrations that are experienced because of prevalent track
maintenance conditions in India.
(ii) Prevalence of high temperature and humidity for the most part of the
year.
(iii) Operation of the EMU over a humid and salty terrain in which the
climate varies from high rainfall for 4-5 months and extremely dusty
atmosphere during rest of the year.
(iv) Loading of power cables will not be more than 75% of its capacity.
(v) Cables for terminal connections will have only crimped joints.
(vi) Suitable cable Layout to bring down EMI interference levels within
acceptable limits.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 76 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
4.37.13 Cable harness for the two prototype EMU rakes shall be in the scope of
Supplier and further ICF shall provide the same for all the series rakes.
4.37.14 Train Line Cables, Inter Vehicular Electrical Couplers
(i) The electrical coupler shall be capable of making all necessary
electrical connections between adjacent Cars to permit controls of all
Cars in a rake from the leading cab. On minimum radius curves, the
covers shall not exceed the allowable clearance envelope of the Car.
Sufficient spare contacts (at least 10%) shall be provided for catering to
future needs of the IR. As such multiplexing of signal shall be adapted
to the maximum extant possible in line with the current international
practices.
(ii) The outer cover of the electrical coupler shall be additionally
strengthened to protect the coupler against ballast or external hitting.
(iii) In order to secure the cables from external hitting, the cables connected
with the coupler shall not hang lower than the lowermost face of the
coupler and shall be suitably secured to arrest any dangling.
(iv) Electric couplers shall use a configuration so that same type of Car can
be intechanged from one basic unit/rake to the other basic unit/rake.
Contacts shall preferably be spring loaded, of silver/gold surfaced alloy,
shall have sufficient capacity, shape and positive action to prevent
fouling in coupling, shall maintain positive contact under all specified
operating conditions and shall be capable to work even with the
impacts to which the car coupler may be subjected in service.
(v) The inter-vehicular coupler arrangement for both power and control
system shall be proven and shall conform to international standards.
However, special arrangement shall be made to ensure that it is not
damaged due to external reasons like vandalism, ballast hitting and the
flooding conditions.
(vi) The design shall cater for relative movements between the coaches. It
shall be that there is no disruption and sparking due to vehicle
behaviour under worst conditions of operation.
(vii) All end connection and fittings will be supplied by Supplier. The jumper
cables assemblies i.e. jumper cables along with the inter-vehicular
couplers in assembled condition shall be supplied by the Supplier.
These assemblies shall be tested for endurance test for 20 million
cycles on test rigs simulating the conditions of end of coach at level,
curves & crossings.
(viii) These assemblies shall be supplied by the supplier and be fitted on the
newly manufactured coaches by ICF/manufacturing unit. The electrical
couplers to be used shall be designed for trouble free operation under
all operating conditions.
(ix) Couplers shall allow coupled coaches to negotiate curves of radius
152.4 metres and shall be capable of passage in either direction over
standard 1 in 8 ½ turn outs and shall function satisfactorily with
difference in head stock heights of adjacent coaches up to 75 mm.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 77 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Suplier shall ensure that the jumper cable assemblies do not touch/rub
the couplers under any circumstances.
(x) Coupling shall be capable of being accomplished by one person and
shall be practicable with longitudinal axes misalignment between cars
of eight degrees and 100 mm different in height.
(xi) All train lines and inter vehicular couplers shall be so designed that they
are not susceptible to any damage due to vandalism and external
hitting during the run. Further, adequate safety measures shall be taken
to safeguard against ballast hitting, vandalism, rains and flood water.
The layout shall be such that they are accessible to maintenance staff
only. Adequate measures shall be taken to reduce the number of train
lines to bare minimum. Details of the arrangement shall be furnished
during the design approval stage.
(xii) The supply of cables, termination equipment, couplers or any other
material required for laying the cables in the rake shall be the
responsibility of the supplier. This shall also include switch gears,
relays, fittings and terminal equipment required for proper working of
the equipment under Supplier’s scope.
4.38 Pantograph:
4.38.1 A single pantograph suitable for satisfactory operation up to a minimum speed
of 120 Km/h under 25 KV AC power supply systems as given in Clause no.
2.6 and environmental conditions specified in Clause no. 2.11 shall be pro-
vided.
4.38.2 The design of pantograph shall incorporate the following desired features:
(i) Pantograph shall be suitable for satisfactory working in dusty, humid
and saline atmosphere with heavy rains during monsoon seasons. The
IR has experienced the failure of nylon bushes, bolts, washers and
plungers due to ingress of heavy dust. In view of this, their use shall not
be acceptable.
(ii) The design shall provide for efficient damping arrangement for pan
assembly and articulation assembly.
(iii) The minimization of the pan mass shall be preferred.
(iv) The adoption of proven "Air Raising Springs” for pans and hydraulic
damping for articulation assembly shall be used.
(v) The limiting of aero dynamic effect from 3kgf to 5kgf for maximum
speed by the use of aero foils shall be preferred.
(vi) Efficient current collection at all speed with least sparking while
traversing the OHE shall be ensured. As a design criteria, the maximum
limit of contact loss should be of the order of 0.2% in the regulated
OHE. The current collection tests under the actual field conditions shall
be the responsibility of the supplier. Simulated test results and
performance of pantograph for the similar rolling stock and OHE system
shall be preferred during the design stage.
(vii) The maximum electrical resistance between current collector and
power take-off should be limited to 2 milli ohms.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 78 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(viii) The pantograph shall have the feature to protect itself in case there is
any panto entanglement with OHE.
(ix) Supplier shall conduct on line current collection test with GPS
supported location recording system. The output report in soft copy
shall be supplied for continuous / selective viewing of location having
abnormal behavior and in hard copy with exception report of spark
image, location wise report in excel/ word format for complete section
selected for trial in Western & Central Railway.
(x) It shall be possible for each of these pantographs to be electrically
disconnected from the roof equipment and earthed in case of damage.
(xi) The profile of the pantograph shall generally be in accordance with the
drawing no. SKEL-3871 enclosed as Annex-XIII. Metalised carbon strip
in accordance with RDSO’s specification No:
RDSO/2009/EL/SPEC/0097, Rev. ‘0’ shall be used on the pantograph.
(xii) In static condition, the pantograph shall exert upward force of 7 ± 0.4 kg
on OHE.
(xiii) The pantograph shall have auto drop function to drop the pantograph
automatically when excessive height is detected (ORD). The
pantograph shall also have auto drop function in case of worn current
strip or damaged pan head (ADD).
(xiv) The current drawn by the EMU Train shall be limited such that there
shall be no adverse effect on the pantograph or the OHE whilst the
EMU Train is at standstill.
4.38.3 The insulation system of pantograph shall be suitably designed to ensure
satisfactory operation under 25 KV AC systems without any need for attention
other than the specified scheduled maintenance.
4.38.4 The pantograph shall be capable of sustained operation and satisfactory
current collection from 100mm above the collapsed pantograph level up to the
full range of contact wire height, and at all operating speeds as specified.
4.38.5 Pantograph controls shall be configured in the cab car such that any one
pantograph or all pantographs can be raised or lowered. When all
pantographs are raised, there shall be a time delay function such that the
instantaneous line current demand peak and inrush current characteristic are
reduced to less than the operating limit of the traction power and OHE system
-----------------
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 79 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 80 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 81 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Following tests shall be carried out on the electronics PCBs as per IEC
60571/EN 50155 and IEC 61373 with the modified parameters.
(i) Dry Heat test: Dry Heat test shall be done at 800C. Alongwith the
testing for the satisfactory performance, temperature stickers shall be
put on the critical ICs, Controllers & capacitors etc. for monitoring the
maximum temperature of these components during dry heat tests. It
shall be confirmed that the temperature recorded during dry heat test
as above does not exceed the specified operating/surface temperature
of these components. For the purpose, data sheets of such
components shall be referred and submitted during testing.
(ii) Cyclic Humidity test: The tests shall be done for 2 cycles of 24 hours
each and components shall be examined for the performance tests and
physical damage if any. The humidity cycle shall be as specified in IEC
60571.
(iii) Salt Mist Test: The test duration shall be 48 hours and after the tests
the performance test shall be done. There shall be no physical damage,
rusting or deterioration of the varnish/lacquer coating.
(iv) Dust & Sand Test & Mould growth test: The tests to determine the
performance of the electronics in Sand and Dust ambient shall be
carried out with the dust settlement rate of 6gm/m 2/day. The dust
particle size shall not be larger than 100 m. Further details shall be
worked out at design stage. The reference IEC shall be IEC 68; test
Dust and Sand and IEC721-2-5 test Dust and Sand. The component
shall be protected against mould/fungal growth. The test scheme shall
be finalized during design stage.
5.3.7 Power & Auxiliary converter/Inverter: Tests shall be done as per IEC
61287.
5.3.8 Auxiliary Machine
All auxiliary machines including the motor-compressor set shall be tested in
accordance with the relevant IEC specifications. All auxiliary machines not
covered in IEC shall be subjected to such tests as decided by RDSO during
finalisation stage to ensure that it will meet the working conditions.
5.4 Complete Train:
Complete train shall be type & routine tested as per IEC 61133 and as per the
test programme agreed by RDSO. After erection, the complete equipment
shall satisfactorily withstand the dielectric voltages as specified in the IEC
specification.
5.5 Sequence Test:
Connection shall be made to the 25 KV AC overhead contact system and all
parts of the control and main power circuit shall be tested out to ensure correct
sequence of operation, all interlock cut-out switches shall then be tested, and
the pantograph shall be tested to prove the speed of raising and lowering.
5.6 Interference Test:
Tests to determine the levels of interference with traction power supply, signal
and telecommunication equipment and facilities to prove that these are within
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 82 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 83 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
(iii) The Supplier shall supervise and carry out the above tests both at his
works on combined test bed and also at the site (Mumbai) and shall
provide all equipment required for such tests and such special
consumable stores as oil, grease etc, for the first filling and for trial
runs. Special measuring instruments shall be provided by the Supplier.
(iv) During the tests acceleration, deceleration, speed on straight level track
and the energy consumption for a round trip shall be measured. In all
cases, 12-coach super dense crush loaded train shall be tested.
However, certain tests viz. TCMS, braking, interference etc. shall be
carried out on 15-Car configuration also.
5.11 Energy Consumption
The supplier shall measure the required values of energy saving for a 12-car,
SDCL rake as per Clause no. 3.1.15; round trip operation between
Chruchgate & Andheri (WR), Mumbai CST- Kasara/Karjat for all out running
without coasting and as per the time table based on halting at all stations on
the slow corridors. The following values shall be recorded:
Traction energy consumption without electrical braking.
Regenerated energy through electrical braking.
Energy consumption by auxiliaries
5.11.1 The estimated specific energy consumption figures alongwith the break up as
mentioned in above para of this clause, will be submitted by the Supplier for
each section based on the train resistance formula and track profile &
permanent speed restrictions.
5.11.2 The validation of efficiency and energy consumption shall be done on the
combined system test bed and at field on the vehicle as per the IEC 61377
and 61133.
5.11.3 Acceleration: The acceleration will be calculated from the time taken to reach
a speed of 40 km/h. The time taken shall be from the instant master controller
is switched on to the instant speed of 40 Km/h is touched.
5.11.4 Tests will be conducted to confirm acceleration performance according to
values specified in Clause no. 2.5 and jerk performance as per Clause no.
4.22.5.
5.11.5 Test results shall also be recorded for wet rail condition.
5.11.6 Deceleration: The deceleration test shall be taken after preliminary runs of the
rake in order to bed in the brake blocks. The test shall be taken on dry rail and
the average of three tests will be taken as the final figure for deceleration.
5.12 Pre-Commissioning Tests at ICF/Chennai
Supplier shall list the tests that are to be carried out on the supplied equipment
after it has been mounted on the EMUs at ICF/Chennai or at EMU
maintenance shed/workshop of IR or at any other manufacturer’s premises.
The test procedure, instrumentation and tolerance shall be furnished.
The Supplier shall supervise these tests on two prototypes and all series
production of EMU rakes and also train staff of ICF/EMU maintenance
shed/workshop/any other manufacturer’s works where the electrics supplied
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 84 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
as per this specification shall be equipped in EMU coaches in carrying out the
tests. ICF or EMU maintenance shed/workshop of IR or any other
manufacturer’s works shall provide qualified staff for carrying out these tests.
5.13 Commissioning of EMUs at Mumbai:
Each rake shall be commissioned at Mumbai by the Supplier staff before
putting into commercial service. The Supplier will commission two prototype
rakes and all the series production of EMU rakes. The supplier shall furnish a
Commissioning Schedule for the supplied equipment and the system which
shall also include the following:-
(i) Confirming satisfactory functioning of the all system.
(ii) Test run to confirm specified operating parameters such as
acceleration, deceleration, brake blending and energy consumption etc.
(iii) Rectification / replacement of any malfunctioning equipment.
(iv) Check of all the safety related items.
-------------
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Page 85 of 85 Rev. 0 issued in August'2017 Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0)
LIST OF ANNEXURES
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURES
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Annexure I
2. Vacuum Circuit Breaker: Make and type, rated voltage and current,
the maximum permissible operating voltage, rated short time current,
total fault clearing time, making and breaking capacity, impulse voltage
withstand, control circuit voltage, number and rating of auxiliary
contacts, overall dimensions and weight of the equipment.
8. Smoothing Reactor/ Filters: Make and type, number and rating of the
coils, inductance and ripple characteristics up to 1.7 times the rated
transformer secondary current, details of the conductor and insulation
system, current density, losses, temperature rise limit, details of cooling
system, dielectric test voltages, overall dimensions and weight of the
equipment.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
9. Traction Motor: Make and type, continuous rating, one hour rating and
short time rating, maximum starting current and duration, current
ratings for various operating voltages, gear ratio, traction motor
characteristics under different conditions, details and data of windings,
estimated temperature rise of stator winding, air flow, ventilation to
Watt loss ratio, maximum designed / test / service speed, details of
insulation, details of the bearings, L-10 life calculation of the bearings,
FEM analysis of the rotor shaft, details of banding, data for motorette
test, fits and clearances adopted, Details of lubrications to be used in
gear case and different bearings, overall dimensions and weight of the
traction motor. Motor efficiency (with and without gear drive), Details of
suspension, Class of insulation, Maximum temperature index of
winding insulation, Material of gear and pinion, Roller bearing type and
number, Constructional details viz. Rotor bar and rotor end ring
arrangement, overhang to terminal box connection etc.
10. Gears And Pinions: Make and type, grade of steel used, particulars of
heat treatment, material and type of construction of gear case, make &
type of compound of gear case.
11. Auxiliary Machines & Blowers: Make and type of various auxiliary
machines, nominal voltage, starting current and torque, torque speed
characteristics at various voltages, continuous rating, efficiency,
speed, power factor and slip of the motor, type of enclosure, details of
cooling fan, air gap, details of windings and insulation, conductor size,
current density, type of conductor insulation, details of impregnation,
details of lead wire, terminals and terminals block, material of core
stampings and average flux density, details of rotor end rings and bars
with current density, details of bearing giving sizes, clearances,
tolerances, dimensions, L-10 life calculation of the bearings and weight
of machines, tests conducted to ascertain the reliability of
windings/motors. Make and type of the blower units, power
consumption at rated capacity, dimensions and weight of the blower.
12. Contactors / MCB: Make and type, rated voltage and current, making
and breaking capacity, number of auxiliary contacts with control circuits
voltage, magnet valve and coil details, overall dimensions and weight,
mechanical and electrical endurance test data.
13. Lightning Arrestor: Make and type, rated voltage, dry and wet power
frequency withstand voltage, minimum power frequency spark over
voltage, nominal discharge current, impulse spark over voltage, overall
dimensions and weight.
14. Master and Brake Controller: Make and type, rated current, making
and breaking current, positions of reverser and main handle and
auxiliary interlocks, overall dimensions and weight, details of
redundancy, mechanical and electrical endurance test data.
15. Relays: Make and type of various relays, rated current and voltage,
range of setting, rated control voltage, rating of contacts, details of
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
16. Compressor: Make, type and model, number of stages, rated speed,
maximum pressure, graph showing FAD against 8, 9 and 10 kg/cm²
pressures, maximum permissible temperature at inlet and exhaust
ports, details of drive arrangement and coupling, lubrication
requirements, overall dimensions and weight, Type of motor, KW
rating, Voltage, Rated current, Insulation class, Efficiency, Mounting,
Capacity of compressor in lit / min, Noise level at 4.6 m, air intake /
filter system, type of lubrication.
18. Battery Charger: Make and type of the battery charger, capacity and rating,
ripple content, load regulation, dimensions and weight, charging method and
its characteristics.
17. Isolating and Programme Switches: Make and type, rated voltage
and current, short time current, description and details of interlocking
arrangement, number of auxiliary contacts, overall dimensions and
weight, mechanical and electrical endurance test data
18. Auxiliary Compressor: Make and type, capacity and pressure, speed,
motor rating and working voltage, overall dimensions and weight.
2. Adhesion calculation.
13. Calculations for life of bearings used in Traction Motors and aux.
machines.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
19. Time and distance to achieve maximum service speed with normal and
one basic unit isolation
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
C) Drawings:
1. Layout drawing for roof, underfloor, driving cab, motor and trailer
coaches.
13. Master controller drawing showing driving controls, cam contacts and
pneumatic and mechanical connections.
15. General arrangement for wheel slip detection and correction system.
Note: The items as above are indicative only. Supplier is advised to refer the
relevant clauses of the specifications for submitting the details required.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Annexure II
PERFORMANCE SIMULATIONS TO BE SUBMITTED BY THE SUPPLIER
(Refer Chapter 3)
1. Conditions:-
i) 12 car SDCL rake
ii) Line Voltage 22.5 kV AC
ii) All out run (without stop time)
iii) Maximum possible regeneration
2. Simulations
a) Tabulation:-
Section Run time RMS current of Line current
traction motor peak
1.5 km section on level
tangent track
b) Graphical values
i) Time vs. Speed, Distance, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
ii) Distance vs. Speed, time, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
1. Conditions:-
i) 12 car SDCL rake
ii) Line Voltage 22.5 kV AC
iii) One all-out cycle of 110kmph
2. Simulations
a) Tabulation:-
Section Time Distance Line % Regen
current
Time & distance to
achieve speed of
110kmph (normal rake)
Time & distance to
achieve speed of
110kmph (one basic
unit isolated)
Time & distance to
complete one cycle
(with normal rake)
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
c) Graphical values
i) Time vs. Speed, Distance, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
ii) Distance vs. Speed, time, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
1. Conditions:
2. Simulations:-
i) Time vs. Speed, Distance, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
ii) Distance vs. Speed, time, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
1. Conditions:
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
2. Simulations:-
Section Overall run time RMS current Temperatur
of traction e rise of
motor propulsion
equipment
Churchgate – Andheri –
Churchgate
Churchgate – Virar –
Churchgate
CST Mumbai – Thane – CST
Mumbai
CST Mumbai – Kalyan- Kasara
– CST Mumbai
CST Mumbai – Kalyan- Karjat –
CST Mumbai
Start in 1 in 34 gradient, clear
this section of 1 km (Max. speed
attained)
3. Graphical values
i) Time vs. Speed, Distance, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
ii) Distance vs. Speed, time, Motor current, Line current, TE, BE, TR,
acceleration/deceleration
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
a) Churchgate – Andheri – Churchgate b) CST Mumbai – Thane – CST Mumbai c) CST Mumbai – Kasara – CST Mumbai
b) Churchgate-Virar
Stations All out 10 % Coasting
Run Motoring Regenerative Motor Line Run Motoring Regenerative Motor Line
time energy at energy at rms current time energy at energy at rms current
pantograph pantograph current rms pantograph pantograph current rms
including including aux. including including aux.
aux. Load Load aux. Load Load
(Note 1) (Note ) (Note 1) (Note )
Journey total
Net aux. Consumption
(Note 1)
Energy consumption
for air-conditioning
(Note 2)
Note : 1. For simulating the motoring and regenerative energy, full auxiliary load shall be taken into account except emergency load. Duty cycle for
the compressor & lights shall be taken as 50% & for the balance load 100% duty cycle shall be considered. The net auxiliary consumption
calculated as above shall also be furnished separately.
2. Energy consumption for Air-conditioning system shall be separately furnished.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Speed Vs Tractive effort / Braking effort, Train resistance, Line current, Traction
Motor voltage, Traction motor current, Traction motor power factor, Motor frequency,
slip frequency, Balancing speed.
1. Conditions:
Including following
IMPORTANT: The listed requirements as above are indicative, Supplier is advised to refer
the main clauses of the Specification.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE – III
All the equipment shall be type and routine tested with the relevant specification.
Supplier shall conduct all type and routine tests of all clauses of latest
RDSO/IEC/BS/DIN/JIS/IS or latest equivalent specification whichever is applicable,
including optional tests. Detailed test programme shall be furnished by the Supplier
and approved by RDSO before undertaking the type tests.
1. Electric traction – rolling stock – test methods IEC 61133
for electric and thermal /electric rolling stock on
completion of construction and before entry
into service
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE IV
CENTRAL RAILWAY
SECTION CSTM TO KASARA
( DN LINE)
SR. LOCATION (IN KM) GRADIENT CURVE STN. NAME SPEED
NO. RESTR
FROM TO (KMPH)
1. 0 0.333 0.000 CST 15
2. 0.333 0.733 -0.675 (0.00KM) 15
3. 0.733 1.000 -0.026 15
4. 1.000 1.067 0.000 1458R 15
5. 1.067 1.201 -0.095 590R 15
6. 1.201 1.242 -0.081 590R MASJID 15
7. 1.242 1.800 -0.081 (1.22KM) 15
8. 1.800 2.067 0.181 500L 55
9. 2.067 2.368 1.000 500L SANDHURST 100/80
10 2.368 2.500 0.250 RD.(2.08) 40
11. 2.500 2.904 0.250 100/80
12. 2.904 3.450 -0.250 100/80
13. 3.450 3.667 -0.250 60
14. 3.667 3.800 0.250 100/80
15. 3.800 4.000 -0.030 1300L 100/80
16. 4.000 4.700 -0.030 BYCULLA 100/80
17. 4.700 4.900 -0.030 2500L (4.04KM) 100/80
18. 4.900 5.100 -0.030 1458R 100/80
19. 5.100 5.333 -0.030 CHINCHPOKLI 100/80
20. 5.333 5.990 -0.055 (5.53KM) 100/80
21. 5.990 6.400 0.020 100/80
22. 6.400 7.067 0.020 CURREY RD 100/80
23. 7.067 7.500 0.020 (6.07KM) 100/80
24. 7.500 8.134 0.027 PAREL 100/80
25. 8.134 8.400 0.100 (7.65KM) 100/80
26. 8.400 8.550 0.100 2916L 100/80
27. 8.550 8.886 0.100 DADAR 100/80
28. 8.886 9.200 0.100 (8.85KM) 100/80
29. 9.200 9.300 0.100 590L 100/80
30. 9.300 9.600 0.038 100/80
31. 9.600 10.633 0.083 MATUNGA 100/80
32. 10.633 11.000 0.045 (10.12KM) 100/80
33. 11.000 11.100 0.045 1944I 100/80
34. 11.100 11.350 0.050 100/80
35. 11.350 11.802 0.050 1450R SION 100/80
36. 11.802 12.000 -0.312 (12.71KM) 60
37. 12.000 12.200 -0.312 60
38. 12.200 12.534 -0.312 3500L 60
39. 12.534 12.933 -0.312 100/80
40. 12.933 13.200 0.112 100/80
41. 13.200 13.501 0.112 2500L 100/80
42. 13.501 14.034 -0.112 100/80
43. 14.034 14.131 0.000 100/80
44. 14.131 14.200 0.135 2187R 100/80
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
NOTE: For the UP line section the values of gradient and radius of curve are same
as shown for the DN line.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CENTRAL RAILWAY
______________
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
DN LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
DN LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
DN LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
UP LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
UP LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
UP LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
WESTERN RAILWAY
UP LINE
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE V
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE – VI A
(1) Telecom copper cable to the specification IRS: TC 14/75. TO 22/77 and IRS: TC
30/97 laid along the track. These may carry typically following types of circuits:-
(2) Armoured optic fibre cable as per IRS TC 55-98 laid along with the track to carry
the above telecom circuits 1 (i) to 1 (ix) by converting analogue information into
digital and transmitting the information on optical medium at 2 Mbps. 8 Mbps. 34
Mbps. PDH heirchy and at 155 Mbps STM1=SDH heirchy. Associated optical line
equipments and multiplexing equipments shall also be installed at every station.
B. RADIO COMMUNICATION
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
MISCELLANEOUS
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE – VI B
CHAPTER –1
INTRODUCTION
1.1 One of the solutions to avoid accidents is provision of Auxiliary Warning System. The
ZUB-100 system devised by M/s. Siemens Ltd. has been introduced on suburban of
section of Western Railway, Bombay from 24/02/87.
1.3 Control exercised by the system: - When the train passes green signal, maximum
speed of the train is restricted to preset level of 90 KMPH. In the existing form, double
yellow signal has been equated to green on Western Railway. When train passes
yellow signal, the speed of the train has to be reduced to 38KMPH in 290-meter
distance from foot of the yellow signal. When the train passes permissive red signal or
is moved under signal failure bypass condition, maximum speed is restricted to
15KMPH. If vehicle is moved in reverse direction emergency brakes are applied. (EP
brakes at 2 mtrs. and EB at 5-mtrs. distance) If any of the above speed limits are
exceeded the system acts in manner indicated below:
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
by central processing unit from tachogenerator. The driver communicates with central
processing unit through indication panel.
The central processing unit processes information. The output are fed to indication
panel, hooter, buzzer and brake actuating unit. The brake actuating unit is connected
with brake system on train. The isolation unit meant for connecting power supply to the
system.
The opto coupler card connects signal aspect information with track magnet.
Track magnet has oscillators. Depending on signal aspect, particular oscillator oscillates.
On receipt of energy from engine magnet it starts oscillating, thus communicating signal
aspect to central processing unit in engine.
The engine magnet receives energy from power supply card in central unit. It detects
presence of track magnet, receives and transmits signal aspect information on principles
of resonance coupled oscillating circuit to central processing unit.
The Tacho-generator is axle driven unit and informs speed and direction of vehicle to
central processing unit.
The indication panel consists of push buttons, counters and indication lamps. These
convey signal aspect passed, to driver and permit certain operations by driver.
Brake actuating unit consists of brake control relay, emergency braking reverse relay,
emergency braking normal relay and service braking relay. These relays help actuating
EMU braking system.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
The isolation unit has manually operated isolating switch and set of MCBs. It connects
110V supply to AWS system. Provision also exists for counting No. of isolations.
Hooter / Buzzer – these are used for giving audible warning to drivers.
Central processing unit has various printed circuit board cards each with designations
such as B1, A1, B2, A1 etc. and having specific task. Microprocessor is situated in B11,
A1 card. The unit receives, processes, all information and issues instructions for acting
depending on preset programme.
Depending on pulses received from central processing unit, brakes are actuated and are
applied on EMU. EP brakes are applied by connecting supply to EP relays and emergency
brakes are applied by disconnecting supply to magnet valves provided for the purpose.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CHAPTER – 2
2.1 The Central equipment needs information regarding signal aspect being passed by the
train. The information is processed by microprocessor and control is exercised on
EMUs.
2.2.1. The devices used for the purpose of receiving information are as under: -
(i ) Opto coupler card.
(ii) Track magnet.
(iii) Engine magnet.
2.2.2 The engine magnet is installed on EMU bogie. The track magnet is situated in between
two rails. The distance of the both EM and TM from rail inner edge is 283 +40mm
along center. The vertical clearance of EM is kept as 175 + 0 / -5 mm for 1969 stock.
183.5 + 0 /-5 mm for ICF stock, If 180.5 + 0 / -5 mm 1963 stock from rail level.
2.3 Opto coupler card: ( Ref. fig. No. 2.3 ). Opto coupler card helps selection of particular
Oscillator in track magnet depending on aspect of the signal. The tuned oscillator in
turn generates audible range frequencies.
The signal aspect bulbs are lit by a supply across secondary of signal transformer.
This supply is 12V (9 to 20 V). The same is fed to a rectifier and is taken to an LED.
Light emitted by LED is fed to base of photo transistor, the cathode of photo transistor
is fed from power coil of track magnet through terminal No. 6. The particular LED lights
up, the corresponding photo sensitive transistor, is switched on and supply is fed to
corresponding two oscillators through diodes and oscillator generates frequency
which is modulated on 100 kHz coil. This is picked up by engine magnet 100kHz coil
and sent to central equipment where it is demodulated, filtered, amplified for use by
relevant cards and the microprocessor. The oscillators energized correspond to signal
aspect.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
When engine ma`gnet passes over track magnet, dip is experienced in EM coil current
due to tuned circuit in track magnet.
The third chamber consists of power coil, modulator card and 100kHz coil with tuned
circuit. The 100 kHz frequency is used as a carrier for audible range frequency, which
is modulated over it. The amplitude modulation is done in modulator card. Supply for
the oscillators is received from power coil, in which it is induced from engine magnet
coils and approximately 12V supply is obtainable. This is fed to oscillators through
point No. 6 of the coupler. The oscillator circuit is completed through opto coupler card.
2.4.2 The track and engine magnets are supposed to be water tight to prevent / stop
nonfunctioning or malfunctioning during flooding conditions. They are tested for this
property by feeding 9.5kg/cm2 air pressure for one minute and dipping in water. There
should not be any pressure drop, failing which corrective action has to be taken. The
leakage source is identified and proper sealing is done.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
It acts as follows: -
50 kHz coil is fed across elemex terminal No. 1 and 2 and 100 kHz coil is fed across
elemex terminal No. 3 and 4 ( refer fig. No. 2.2 ) The frequencies are received from
frequency generator card B1 in which crystal oscillator generates 400 kHz. Through
frequency deviders 100 kHz and 50 kHz supply is tapped and fed to engine magnet.
2.5.1 Current drawn by coils is measured during tests. In case of engine magnet, the current
is measured on points provided in B1 card and specified values are given below:
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Socket 1-3 200 + / - 20 milli Amps.
Socket 5-7 350 + / - 25 milli Amps.
The actual measurement is across one ohm Resistance and Voltage drop is
measured.
2.6 Cascading: -
Cascading in signalling language means assuming lower signal aspect by a signal in
case of fusing of bulb of higher aspect. But under this condition the AWS opto coupler
card would have assumed lower aspects. This is prevented by blocking circuit in opto
coupler card. For example, consider fusing of green signal bulbs on three-aspect
signal. Frequencies corresponding to green are F3, F4. Now due to cascading signal
will assume yellow aspect. Frequency corresponding to yellow are F1, F4. As soon as
yellow bulb lights the transistor shorts LED corresponding to green aspect and end
result is achieved. However in case of double yellow signal, fusing of bulb does result
in frequency corresponding to yellow signal aspect.
2.7 Out of 7 frequency two are used at a time to communicate particular signal aspect.
Thus, 21 information’s can be fed. Their utilization is given below. However, all
combinations are not being used presently, Frequencies at sr. No. 6,7 and 11, 12, 14
and 21 are not used.
7
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CHAPTER – 3
AWS PERIPHERALS
3.1.1 The Tachogenerator has a toothed rotor. It is connected to axle of EMU through axle
attachment. The rotation of rotor varies inductance of LC resonant circuit, which is
housed in TG assembly. The inductively working scanning heads detune each time
one oscillator and thus frequency is modulated. This is then converted into voltage
change in discriminator card; subsequently schimil trigger generates square wave
output, depending on voltage changes. See diag. 3-1.
3.1.2 24V supply is fed to Tacho oscillators from elmex terminal No. 13 and 11 and pulses
are received at terminal No. 12 and 14 from channel. 1 & 2. Channel 1 & 2 means
pulses received from oscillator circuit 1 & 2. The oscillator sensors are placed 1.25
pole apart. On receipt of pulses HQ LED on card B4 – A1 extinguishes and W1 LED
starts flickering. Non-receipt of tacho pulses results in emergency brake application
which cannot be reset by reset push button on indication panel. (See diag. 3.2 and
3.2A)
3.1.3 Distance travelled is measured taking into account No. of pulses per unit time and
wheel diameter setting in distance evaluator card.
The indication panel is placed adjacent to brake controller and consist of following:-
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Corresponding terminal Nos. of elemex terminal are also indicated in diag.3.3.
The panel is meant for driver to communicate with central equipment and provides him
with visual indications. ( See diag.3-3)
It acts on braking system of EMU to apply EP or emergency brakes. (See diag. 3-4
and 3-5)
It consist of following:-
(i) Emergency braking reverse relay (EBRR)
(ii) Emergency braking normal relay (EBNR)
(iii) Service braking relay (SBR)
(iv) Brake control relay (BCR)
3.3.1 The first three relays operate on 24V where as BCR operates on 110V DC.
Emergency braking reverse relay and emergency braking normal relay are normally in
picked up condition where AWS equipment is functioning and is in operation. Dropping
of EB(R)R results in emergency brake operation as its normally open interlock is in
series with magnet valve coils, operation of EB(R) also results in operation of EP
brakes as normally open interlock of EB(R)R de-energises BCR. Dropping of BCR
results in closing its normally closed interlock and operation of EP relays. When only
service brakes are to be applied BCR is opened through SBR normally closed interlock
to give EP brake application.
3.3.2 In original design EB(R)R and EB(N)R were mechanically interlocked so that when
control supply is switched off by driver at terminating station, EB(N)R operate first and
dropping of EB(R)R was prevented by mechanical latch. A condenser was used for
providing time lag in operation. This arrangement was however not satisfactory and
now electrical interlocking has been provided i.e.
(i) In parallel with normally open interlock of EB(R)R in BCR circuit normally
closed interlock of EB(N)R is provided.
(iii) Supply of SBR coil is taken through EB (N) R normally open interlock to
prevent EP application when control key is out off.
3.3.3 The relay designated as SBR is used for service brake application. It is normally in de-
energized condition and picks up when AWS applied service brakes. These are
normally applied when speed exceeds set limit by 5 to 10 KMPH.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
There is also an inter-coupler between SAU and ISU. The brake output is controlled
through B8 Al card and service brake application through B6 AI card.
This is meant for isolating AWS and connecting AWS with EMU. It consists of Isolating
switch, isolation counter, LEDs in ISU to show availability of control supply, supply to
magnet valves, supply to master controller and actuation of EP brakes. It also has
MCBs 1,2,3 & 4 which operate simultaneously. (See diag. 3.6)
Availability of 110V DC supply is indicated by Yellow LEDs. The first Green LED
shows availability of supply of master controller. Both Red LEDs are energized during
EP application. The first will indicate supply to wire No. 3601-holding relay and second
to wire No. 3602 the application relay.
The counter indicates isolation No. The isolation switch should normally be kept on
and sealed and should be operated only during emergency to switch off the AWS unit.
The functions of other contacts of the isolation switch have already been discussed in
chapter 5. The diagram attached is self-explanatory. In case of a defect on EMUs like
train not moving the LEDs should be checked to know availability of control supply and
supply to master controller.
10
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CHAPTER – 4
CENTRAL EQUIPMENT
1) Housing
2) Main switch
3) Elmex terminal
4) Flexible coupler
5) Central equipment frame (wired)
6) Various PCB cards each with a distance function.
4.2 Housing:
It houses the central equipment. It is mounted in backside of wall of driving cab. It has
six holes on top to receive various cables. On backside it has a cover so that the
housing is not accessible directly from passenger side. On front side a metallic cover is
provided.
It is terminal bar on which various cables are terminated. Two rows of terminal bars
are provided. Terminal numbers are indicated on each terminal and corresponding
wire number can be traced.
There are three such couplers. These are provided between elmex terminal and
central equipment frame. Wire diagram indicates each pin No. and corresponding wire
No. on each of the coupler.
It houses all PCBs receives couplers, and is wired. The PCBs are housed in two rows.
The lower row from left to right houses PCBs viz. B10 A1, B2 A1, B3 A1, B3 A2, B4
A1, B5 A1, B7 A1, & B8 A1. The provision also exists for providing B14 A1 card for
inspection purpose and B15 A1 card for simulation purpose. The top row houses B7
A2, B44 A1 and B11 A1 card.
11
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
4.7 Various PCB Cards:
The designation and function of various PCBs provided as under
4.7.1 B10 A1 It is switching in card and starts pulses to power supply card
on switching ‘ON’ the driver’s key. Also communicates EMU
data like brake curves number, maximum speed, and type of
vehicle (express/goods/passenger) to central processor.
4.7.2 B7 A2 This is power supply card and is used for converting 110V DC
supply to 24V DC.
It further consist of cards viz.,
B46 – Input filter card,
B47 – Rectifier filter card.
B48 – Switching card.
B49 – Regulator card.
4.7.3 B44 A2 This converts 24V DC supply to 12V and 5V supply
4.7.4 B1 A1 This is known as generator card and generates 400kHz,
which is used for various purposes in system.
4.7.6 B3 A1 This filter amplifier card for frequencies F1, F2, F3.
4.7.7 B3 A2 This filter amplifier card for frequencies F4, F5, F6.
4.7.10 B6 A1 This is known as vigilance card and starts signal aspect code.
Hooter and lamps on indication panel are controlled from this
card.
4.7.11 B7 A1 This card controls penalty brakes. The penalty brakes are
applied either for want of vigilance acknowledgement from
driver or for instruction from central equipment.
4.7.12 B8 A1 This is brake out put card.
4.7.13 B11 A1 This further consists of B12 A1 and B13 A1. Microprocessor is
situated here which processes information received and
issues instructions as per present program.
12
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
The wheel diameter setting is required to be done for purpose of distance evaluation
i.e. distance traveled over a length of time. The operation of different switches in
combination, result in different wheel diameter setting. This switch is situated on front
plate of distance evaluation card. i.e. B4 A1, PCB. The cover of the switch should be
opened with a screwdriver. It is a dual in line (DIL) type switch. Switches are ‘ON’ in
top position. The eight micro switches may be set after verifying wheel dia. from wheel
section and referring chart showing switch numbers and wheel dia..
There is switch along lower edge and is meant for change of direction of travel. The
switch No. 3 here is meant for change of direction since all tacho have been mounted
right hand side axle. Generally this switch is not required to be operated.
4.8.3 Setting the switch “Brake curve No. and Max. speed”
These are set on DIL switches in card B10 A1. These switches are in one row, these
are:-
E – Express / EMU
P – Passenger
G – Goods.
This type of switches are known as dual in line type switches. We have to use E switch
for EMUs. On this switch following setting have been done.
13
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
b. Switch number 5,6,7 & 8 are used for setting maximum permissible speed.
At present maximum speed is set at 90 KMPH. This means that on switch number 3,4
& 5,8 should be ‘ON’. It may be noted that switches are “ON” in top position.
These are provided on front plate of PCBs. Some are permanently lit whereas others
are lit only on pressing red switch on PCB B10 A1. Basically red LEDs are lit if
function is disturbed and shows defect.
14
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CHAPTER –5
INTERFACING OF AWS IN EMUs
ELECTRICAL CONNECTIONS :
5.1 AWS needs 110V DC supply from EMU, for its operations. The supply has been taken
from junction box in driving cab across wire No. 16 and 29. The DC supply from
junction box is however not very smooth and disturbances caused due to various
electrical operations in EMUs, cause malfunctioning of AWS. Supply is now being
given from battery fuse through wires SP8, SP9 in jumper B.
5.4 Supply to Master Controller :( Refer diag.5.3) wherever AWS applies brakes on
EMUs, it is essential to cut off supply to master controller for obvious reasons. The
existing circuit of supply to master controller has therefore been modified as under:
It may be seen that supply to Master Controller is through ISU contact in AWS ‘OFF’
position. In AWS ‘ON’ condition the supply is through BCR interlock which opens out
during service and emergency braking. Green LED in ISU indicates availability of
supply to master controller.
15
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Whenever brakes are applied, Brake pipe charging is prevented by the de-energizing
the feed cut off magnet valve. The other magnet valve is also de-energized when
brakes are applied. It connects brake pipe to exhaust and in turn operates emergency
brake valve. The operation of the valve has a similar effect as blowing of pilot valve in
master controller. Its operation is similar to holding magnet valve in EP unit i.e. when
energized it blocks exhaust of air.
These are needed for implementing emergency braking on EMUs. In rakes fitted with
AWS equipment brake pipe is charged through feed cut off magnet valve which is
normally energized. The valve is similar to application magnet valve.
When AWS applies brakes the valve is de-energized and brake pipe charging is
stopped. In case of AWS isolation, Isolating cock is provided across feed cut off valve
to cater for emergency conditions, so that brake pipe charging is not interrupted.
EP exhaust magnet valve is also normally energized and prevents exhaust of B.P.
pressure. When AWS operates to initiates brake application, the valve is de-energized.
The brake pipe pressure is then connected to exhaust to apply emergency brakes. The
cock provided in exhaust circuit is in series with the valve. In case of defect in the
system, the cock can be closed to prevent exhaust of brake pipe pressure. The
operation of this valve is very similar to operation of pilot valve. Both apply brakes after
initiating operation of emergency valve.
16
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
CHAPTER- 6
AWS OPERATION
The chapter deals with AWS operation from driver’s point of view.
6.1 In order to understand the AWS operation, we have to first study indication panel.
6.2.0 Indication panel consists of followings: -
6.2.1 Signal failure by pass button (SFBB)
This button is used only in case of failure of a signal. This permits train to pass over
defective signal without application of emergency brakes. The button must be operated
in stand – still condition and within 100 mtrs. distance in rear of the signal.
6.2.2 Signal failure by pass counter (SFBC)
No. of operations of SFBB are recorded by this counter.
6.2.3 Reset: This is used for releasing emergency brakes. The push button is effective only
in stand-still condition.
6.2.4 Emergency braking counter (EBC)
It counts number of emergency brake applications.
6.2.5 Vigilance push button:
This is required to be operated by driver when he passes yellow or permissive red
signal. On passing these signals audible warning is heard and within 4 second, the
driver must press vigilance push button, failing which emergency brakes are applied.
If push button is kept pressed earlier than required, its action is not registered.
The driver can also perform functional test by pressing the vigilance push button for
10 seconds in stand – still condition.
6.2.6 Blue indication lamp:
This lamp is lit steady when AWS is `ON`. On passing green signal and double yellow
signal the lamp extinguishes for about 5 seconds and reappears. Flashing of this lamp
means fault in power supply, speed check or speed evaluation equipment.
6.2.7 White indication lamp:
This lamp is normally lit steady. On switching on it flashes and becomes steady.
Continuous flashing of this lamp means fault in control card. The lamp before
becoming steady on switching `ON ` must flash twice, failing which fault in control
card is indicated.
6.2.8 Yellow, indication lamp:
This is a set of LEDs and is normally off. It is lit steady if yellow signal is passed. After
passing 290 mtrs. it starts flashing (1:1) and remains flashing upto 800 mtrs. distance.
Also on passing yellow signal with inter-signal distance more than 700 mtrs. the lamp
flashes slowly (7:1) till it passes additional magnet.
6.2.9 Red indication lamp:
It is also a set of LEDs normally off and is lit steady if permissible red signal is passed
or emergency brakes are applied.
The red lamp flashes if service braking takes place or if signal failure by pass
button is pressed in standstill condition.
17
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
6.3.1 Hooter:
It sounds when vigilance push button is required to be pressed. It also sounds when
emergency brakes are applied or train moves in reverse direction 2mtrs. or more.
It sounds intermittently if speed exceeds by 1 KMPH. than permissible speed at any
stage .
6.3.2 Buzzer :
This has been kept disconnected at present.
6.3.4 Switching off isolation switch should be followed by isolation of AWS cocks and
switching off of AWS MCB.
When the driver comes to driving cab, and switches on the driver’s control switch,
AWS gets switched on. Blue and white lamps are lit on indication panel. White lamp
flashes and become steady. Driver should start the train only when white lamp has
become steady.
Prepared by Checked by
SSE/PS&EMU SSE/PS&EMU DSE/PS&EMU
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
ANNEXURE VII
The suburban section of WR extends from Churchgate to Virar, a distance of 59.82 Kms. There
are a total of 28 stations on this section. The section from Churchgate to Borivali is with
quadruple lines, 2 for Up and Down slow suburban services and 2 for Up and Down fast
suburban services, Mail/Express and freight services. The section from Borivali to Virar has
only 2 lines. Presently, the suburban network has been extended up to Dahanu Road, which is
64km from Virar.
The Harbour Branch Line of the Central Railway joins the Western Railway at Mahim and runs
upto Andheri (21.30 Kms)
The suburban section of CR extends from Chhatrapati Shivaji Terminus to Kalyan where it
bifurcates into two directions-one to Kasara (121 Kms.) and the other to Karjat-Khopoli (114
Kms). The section between Chhatrapati Shivaji Terminus and Kalyan is with quadruple lines, 2
for Up and Down slow suburban services and 2 for Up and Down fast trains, Mail/Express and
freight trains. The section beyond Kalyan is double line.
The Harbour Line Corridor of the Central Railway extends from Chhatrapati Shivaji Terminus to
Wadala where it bifurcates into two directions – one joining the Western Railway at Mahim
(12.47 Kms) and the other going to Kurla and beyond to Navi Mumbai terminating at Panvel (49
Kms).
The station stop time is 30 seconds except at some major stations where stop time is 1 minute.
Details of stations can be seen in working time table available with Western & Central Railways.
The minimum terminal station changeover time at present is 3 minutes which may be reduced
further. The number of services being run by Western Railway & Central Railway are 901 &
1082 respectively.
Figure-1
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Annexure-IX
Existing EMU Rake Layout
12 CAR EMU RAKE LAYOUT
WESTERN RAILWAY
CCG END VR
C B A C B A C B A A B C
H H H H
D L H H D
T GS GS L T GS GS GS L GS T GS GS T L GS
C C C C
C C C C
* ICF (86) (86) (62+50) (86) (86) (62+50) (86) (86) (62+50) (26+26+62) (86) (86)
CENTRAL RAILWAY
BE KE
C B A A B C A B C A B C
H H H H
D H H L D
L T GS GS GS T GS L GS GS T L GS GS T GS
C C C C
C C C C
* ICF (86) (86) 62+13+38 (50+62) (86) (62+26) (38+13+62) (86) (86) (38+13+62) (86) (86)
GS GENERAL II ND CLASS 1 ST CLASS LADIES 07-23 HRS. LADIES VENDOR 04.00-10.00 HRS.
Annexure-X
S. Equipment MTBF/MDBF
No.
1. Traction Transformer
2. Traction Motor
3. Traction Converter
4. IGBT modules
5. Pantograph
6. Compressor, Air Dryer & Filters
7. Vacuum Circuit Breaker
8. Lightning Arrestors
9. Auxiliary Converter
10. Master cum Brake Controller
11. Train Control & Management System
12. Passenger Information & Communication
system
13. Cables
14. Inter Vehicular couplers
15. Brake Electronic Control Unit
16. RMPU
17. CCTV
18. Car light
19. Auto door closure system
20. Sensors
Annexure of Spec no. RDSO/PE/SPEC/D/EMU/0190–2017 (Rev.0) issued in August'2017
Annexure XIII