Presented By: Aditi Manoj Charul
Presented By: Aditi Manoj Charul
Manoj
Charul
The CPM, time is related to cost and the objective
is to develop an optimum time –cost relationship.
LIMIT STATE
METHOD
OPTIMUM DURATION:
the duration which gives the most economic cost
for completing the project.
TIME-COST ESTIMATES:
1) NORMAL ESTIMATE:
emphasis is on cost with time being associated
with minimum cost.
2) CRASH ESTIMATE:
emphasis is on time . It involves the absolute
minimum time required for the job and the cost
necessary to achieve it. LIMIT STATE
METHOD
Cost rises if project is crashed
Minimum cost
COST
5
LIMIT STATE
METHOD
LIMIT STATE
METHOD
Total indirect cost curve
INDIRECT COST
Outage loss
Over heads
TIME
LIMIT STATE
METHOD
These are those expenditures which cannot clearly
allocated to the individual activities of a project,
but are assessed as whole.
LIMIT STATE
METHOD
Cc
COST
Cn
tc tn
Crash duration Normal Duration
TIME
LIMIT STATE
METHOD
NORMAL TIME(tn):
Standard time that an estimator whould usually
allow for an activity.
CRASH TIME(tc):
minimum possible time in which an activity can be
completed, by employing extra resources.
NORMAL COST(Cn):
Direct cost required to complete the acticity in
normal time.
CRASH COST(Cc):
Direct cost corresponding to completion of activity
within crash time. LIMIT STATE
METHOD
COST SLOPE:
It is the slope of the direct cost curve, approximated
as a straight line in order to have a single cross
slope.
CS = Cc-Cn = ∆C
tn-tc ∆t
LIMIT STATE
METHOD
It is the sum of direct and indirect costs.
Minimum cost
LIMIT STATE
METHOD
Normal time of project- sum of the normal durations of
each activity along the critical path.
Minimum time of project – sum of the crashed time
duration of each activity along the critical path.
Non-critical activity need not to be speed up as their
crashing is not going to decrease the project duration
further. Moreover the cost will be high without any
additional advantage.
Some non-critical activities become critical in the process
of crashing the critical activities.
It is always better to start with crashing first that critical
activity that has the lowest cost slope.Then we take
another critical activity which is having next higher slope.
While crashing an activity fully by time “t” ,it should be
examined whether its affecting the non –critical
activity or not.
c
9(2)
A B D
1 2 3 4
5(4) 6(2) 5(3)
STEPS IN TIME COST OPTIMISATION
LIMIT STATE
METHOD
.
( 2) 4(
5 2 )
1 2 4
4(2) 7(5)
STEP 1. TIME SCALED VERSION OF NETWORK
7(5)
4(2) 4(2)
1 2 5(2) 3 4
ACTIVITY ΔC Δt COST
(RUPEES) (WEEKS) SLOPE
RS./WEEK
1-2 8000 2 4000
out of these, the first alternative has the minimum cost slope.
Thus, the extra cost of crashing 2-3 & 2-4 by 1 week
= 2700
therefore, Direct cost of Project for 10 weeks duration
= 18600 + 2700 = 21300
In this step, activity 2-3 has been crashed to its fullest extent.
6(5)
1 2 3 4
4(2) 2(2) 4(2)
The remaining activities to be crashed are 1-2 , 2-4, 3-4.
out of these, activities 2-4 & 3-4 are to be crashed
jointly, with a combined cost slope of 2500 + 1200 =
3700.
The cost slope of activity 1-2 is 4000 which is higher .
Hence period of 6-5 = 1 week left.
Hence only 1 week crashing will be done in this step,
leading to a project duration of 9 weeks.
cost of crashing 2-4 & 3-4 by 1 week.
= 3700 * 1 = 3700
Therefore, cost of project for 9 weeks duration
= 21300 + 3700 = 25000.
The Time scaled version of the network for 9 weeks
duration is shown in fig. we crashed activity 2-4 also
to its fullest extent.
Time- scaled network for 9 weeks Duration.
6(5)
1 2 3 4
4(2) 2(2) 3(2)
Out of remaining critical activities ( i.e. 1-2&3-4)
Activity 3-4 cannot be further crashed to its fullest crash
period of 2 weeks, since it will affect activity 2-4 which has
already been fully crashed.
1 2 3 4
2(2) 2(2) 3(2)
PROJECT 13 11 10 9 7
DURATIO (NORMAL
N )
DIRECT 15600 18600 21200 25000 31000
COST (RS.)
INDIRECT 26000 22000 20000 18000 14000
COST (RS.)
TOTAL 41600 40600 41300 43000 47000
COST (RS.)