Computation of Labor: 1St Floor
Computation of Labor: 1St Floor
1ST FLOOR
Activity No. A
Site Clearing and Grubbing
Manual Clearing
2
Manhour Capability = 0.03 m
2
Total Area = 200 m
No. of Persons = 3
No. of Days = 0.25 day(s)
say = 1 day(s)
Activity No. B
Delivery of materials for Field Office and Construction
No. of Persons = 5
No. of Days = 5 day(s)
Activity No. C
Mobilization
No. of Persons = 3
No. of Days = 2 day(s)
Activity No. D
Delivery of materials
No. of Persons = 3
No. of Days = 3 day(s)
Activity No. E
Layout and batterboard
2
Manhour Capability = 0.02 hr/m
Total Area = 200.00 m2
No. of Persons = 3
No. of Days = 0.17 day(s)
say = 1 day(s)
Activity No. F
Fabrication of Rebars for Column, CF and WF (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 706.97 kg
No. of Persons = 3
No. of Days = 2.95 day(s)
say = 3 day(s)
Activity No. G
Excavating of column footing and wall footing
3
Manhour Capability = 1.35 m /m day
3
Total Volume = 26.64 m
No. of Persons = 4
No. of Days = 4.93 day(s)
say = 5 day(s)
Activity No. H
Fabrication of Forms, scaffolding for columns (1st flr)
2
Manhour Capability = 1.42 MH/m
Total Area = 296.19 m2
No. of Persons = 3
No. of Days = 8.67 day(s)
say = 9 day(s)
Activity No. I
Installation of rebars for column, CF and WF (1st flr)
Manhour Capability = 10.00 MH/kg
Total No. of kg = 706.97 kg
No. of Persons = 8
No. of Days = 1.10 day(s)
say = 2 day(s)
Activity No. J
Fabrication of Forms, scaffolding and staging for stairway
2
Manhour Capability = 1.42 m /hr
Total Area = 102.84 m2
No. of Persons = 3
No. of Days = 3.02 day(s)
say = 4 day(s)
Activity No. K
Soil poisoning and excavating of septic tank and catch basin
Soil poisoning
No. of Persons = 3
No. of Days = 2.00 day(s)
Excavation
3
Manhour Capability = 1.35 m /m day
3
Total Volume = 51.99 m
No. of Persons = 6
No. of Days = 6.42 day(s)
say = 7 day(s)
say = 9 day(s)
Activity No. L
Concreting of CF and WF
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 49.10 m
No. of Persons = 14
No. of Days = 9.41 day(s)
say = 10 day(s)
Activity No. M
Concreting of footing of septic tank
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 1.08 m
No. of Persons = 4
No. of Days = 0.18 day(s)
say = 1 day(s)
Activity No. N
Fabrication of rebars for stairway
Manhour Capability = 10.00 kg/hr
Total No. of kg = 33.19 kg
No. of Persons = 3
No. of Days = 0.14 day(s)
say = 1 day(s)
Activity No. O
Dummy
No. of Days = 0 day(s)
Activity No. P
Installation of Forms, scaffolding for columns (1st flr)
2
Manhour Capability = 0.85 m /hr
2
Total Area = 250.29 m
No. of Persons = 6
No. of Days = 8.86 day(s)
say = 9 day(s)
Activity No. Q
Dummy
No. of Days = 0 day(s)
Activity No. R
Laying of CHB for wall (1st flr)
2
Manhour Capability = 1.25 m /hr
2
Total Area = 444.09 m
No. of Persons = 10
No. of Days = 8.88 day(s)
say = 9 day(s)
Activity No. S
Concreting of column (1st flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 22.46 m
No. of Persons = 8
No. of Days = 3.37 day(s)
say = 4 day(s)
Activity No. T
Fabrication of rebars for slab (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 1203.28 kg
No. of Persons = 4
No. of Days = 3.76 day(s)
say = 4 day(s)
Activity No. U
Laying of CHB for septic tank and catch basin
2
Manhour Capability = 1.25 m /hr
2
Total Area = 27.00 m
No. of Persons = 3
No. of Days = 1.80 day(s)
say = 2 day(s)
Activity No. V
Dummy
No. of Days = 0 day(s)
Activity No. W
Stripping of forms & scaffolding of columns (1st flr)
2
Manhour Capability = 2.35 m /hr
Total Area = 250.29 m2
No. of Persons = 6
No. of Days = 4.44 day(s)
say = 5 day(s)
Activity No. X
Dummy
No. of Days = 0.00 day(s)
say = 0 day(s)
Activity No. Y
Earthfilling for slab
3
Manhour Capability = 1.22 m /m day
3
Total Volume = 146.12 m
No. of Persons = 4
No. of Days = 7.49 day(s)
say = 8 day(s)
Activity No. Z
Installation of rebars for slab (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 2431.32 kg
No. of Persons = 8
No. of Days = 7.60 day(s)
say = 8 day(s)