Report EV Infra
Report EV Infra
Infrastructure
Commissioned by Mr Amitabh Kant ,CEO
Chaired by Shri Anil Srivastava , Adviser (EV) and DG (DMEO)
Team members (AC2SG Software) MrJaakkoAho ,CEO
MrDharmender Singh, Country Head for India
MrAnttiLahnaoja, Software architect
Team members (NITI Aayog) Harkiran K. Sanjeevi
ShikhaJuyal
Shashvat Singh
AalekhSharan
Disclaimer: The views and opinions expressed in this document are those of the authors and
do not necessarily reflect the positions of the institutions or governments.
2
EXECUTIVE SUMMARY
The plan for the corridor includes 55 locations with 135 charging stations of which 46 are DC
quick charging stations and 89 are slower AC charging stations. Theactual deployment will rely
on co-operation with state governments, selected government authorities, Ministry of Power,
gridcompanies as well as some private enterprises (e.g. DIAL at IGI, DLF Mall).
The plan includes a deployment timeline with first installations in November 2017 and
completion in June 2018 (tentative timelines). Additional locations have also beenidentified for
the next phase of adoption.
The proposal includes a large number of stations especially in the South Delhi area where the
likely use is higher and traffic more congested. The scope of planning includes the Gurgaon-IGI-
South Delhi-Noida corridor. The scope can however be expanded via a new project.
Thefollowing issues need to be address to create charging infrastructure:
The planning can assist in the deployment of EV charging stations in India. Further expansion
toother cities in India could be explored based on the experiences from this "Quick pilot"
3
1. Introduction
This proposal describes the results of the work done for planning the EV charginginfrastructure
rollout in the urban corridor of Gurgaon-IGI airport-South Delhi-Noida.Planning for broader
range of users and geographical scope can be undertakenas an extension of this plan at a later
date when needed.
- illustrate the scope and advantages of the planning process and tool for the overall EV
charging infrastructure rollout
- create a basis for a discussion on how to continue the work in India to scale up the
deployment of EV charging infrastructure and thus EV adoption.
While the rollout of the EV charginginfrastructure for the whole of India is a huge task and it is
impossible to predict what that will ultimately entail and how the deployment will happen, this
work has been focusing on the amount and type of infrastructure required to get that process
started within a very specific geographic area.
Based on this information material was prepared for the kickoff meeting and additional
information was collected on major roads, intersections, Delhi geography and outline of the IGI
airport to prepare for the planning exercise.
The wrap-up meeting to complete the project was held on 25th of September 2017 and the
findings were reviewed with the whole team from NITI Aayog and AC2SG Software.
The planning tool supports the methodology by allowing the work to be broken into smaller
parts (so called sub-plans), storing the data in an electronic format and by displaying relevant
background information in the tool's map-based user interface. The tool could also be used to
display information on traffic density and grid capacity to support the choice of the sites into the
plan.
4
2. The Planning Process
Planning of EV charging infrastructure needs to take into account multiple issues that often
appear to be contradictory. Therefore the plan is a compromise that is attempting to find a
balance between the various parameters and issues. Examples of such issues are:
The planning was done for 9-12 months more accurately by identifying potential locations with
an approximate timeline. If the EV adoption happens more quickly than anticipated, then the
timeline for the construction is adjusted and deployment accelerated.
The overall targets for the planning outlined in the kick-off meetingare as follows:
As the targets indicate, the plan and the process are intended to improve the understanding of the
issues and challenges in the implementation process. It should be noted that while the plan is
based on user needs and technical solutions to create the necessary services for the users, the
plan will also create the basis for the following tasks that are fundamentally important for the
charging station deployment:
The proposal was created in a stepwise manner with the support of AC2SG Software's planning
tool. The tool is especially helpful in breaking down the full plan into smaller sub-plans that can
look at a specific area or use case. The overall planning process has five major steps:
5
The first task was performed with NITI Aayog in the kickoff meeting. The creation of a
"masterlist" of charging station locations was performed by AC2SG Software after the kickoff in
some cases via site visits and travel, but most importantly using the planning tool complemented
by other IT tools such as Google Maps and other search engines. AC2SG Software also
performed the import of some Points of Interest (POI) data on Indian Oil LPG station locations
and McDonald's restaurants within the Delhi area.
The streamlining was carried out by AC2SG Software after an interim review of results. The
timelines for the deployment for each charging unit were reviewed and some new locations were
added. In addition to this the geographic scope of the planned first phase rollout was reviewed
and stations deemed unnecessary in the short term were moved to year 2019 for implementation.
3.1. Sub-Plans
In order to manage the full plan it was broken into five separate sub-plans. These sub-plans are
mainly based on the ownership of the sites and ease of access to help with the deployment. The
sub-plans are:
- government locations
- governmental authorities (e.g. Highway Authority)
- government owned companies
- IGI airport
- private locations
These sub-plans are slightly overlapping e.g. the charging units at the IGI airport have been
included in this sub-plan regardless of the ownership of the EV charging station. Each sub-plan
has a set of charging stations for the "first wave" (until June 2018) as well as a set of charging
stations for the "second wave" starting (January 2019).These are tentative timelines. However,
these periods will again depend upon adoption. The gap in the timeline between these two
"waves" is intended to be a stabilization period during which the use of the charging stations can
be measured and analyzed for deciding on further actions.
- Delhi traffic is slow-moving and prone to congestion, therefore the EV charging network
needs to be relatively dense. This was dealt with by using a 3 km coverage radius for the
quick charging stations and a 1 km radius for the slow charging units.
6
- Daily driving distance in the Delhi region is around 100 km. This means that one or two
charging sessions are needed for the car per day (to maintain enough range in the car). In
case residential charging is available, the charging could fully happen overnight.
These assumptions are the basis for the geographical coverage planning and ensuring that
sufficient coverage is available throughout the selected pilot area. These assumptions can be
changed later on in case practical user data is available and the data clearly indicates that these
assumptions are misleading.
Altogether there are 135 charging stations and these are in 55 different locations within the
"Quick pilot" focus area. Most of the locations are such that security and access to the charging
stations can be managed and therefore parking enforcement, availability issues and vandalism
are minor issues at this stage. These will become more important as public charging stations are
built.
7
necessary for two reasons: 1) there are likely to be more users in the south Delhi area and 2) the
traffic is more congested in the central parts of Delhi.
4. Key Findings
Although the "Quick pilot" was done within a limited geographical scope and time, there are
some findings that can be pointed out with regards to the planning process and deployment
issues overall. These are briefly summarized below.
There are some locations in the proposal that are accessible to the general public, these are
especially the locations in the IGI airport area and the locations in commercial shopping malls.
8
Additionally the choice of the organizations was done in such a way that they have an interest in
using or deploying the EV charging stations, ideally both.
In the first wave of the plan there are 10 organizations that are planned to have charging stations
at their premises. These organizations are:
- NITI Aayog
- Indian government (e.g. North and South Block, NirmanBhawan, UdyogBhawan)
- Government companies: GAIL, NTPC, Rural Electrification Corporation, Indian Oil,
India Post
- IGI airport (optional, requires a discussion with DIAL)
- DLF Mall (optional, requires discussion with the property owner)
- National Highway Authority of India , Airports Authority of India
An adequate geographical coverage was possible to be planned with this number for the first
wave of installations. In addition to these organizations, the power utilities need to be involved
in the discussions to ensure that adequate grid capacity exists in the planned locations as the plan
is utilized in the implementation phase.
It should be noted that the plan itself is not dependent on the choice of EV charging station
standards in India and the plan is also manufacturer-neutral. However, the deployment
timescales are going to be affected by the availability (or rather unavailability) of the right types
of charging stations for deployment. This has not been taken into account in the planning.
5. Issues to Be Addressed
While the planning itself has been completed there are a few issues that are relevant to be
considered as implementation proceeds in the near future. While AC2SG Software does not have
detailed information on the timelines for the implementation the underlying assumption for these
comments is that the rollout should start as soon as possible and should expand to other cities
and locations as quickly as possible.
5.1. Standardization
Although the plan is neutral in terms of standardization, the standardization decisions will have
an impact on the implementation timelines. Although EV charging equipment is available in the
market, but investments are difficult when clarity on standards is missing.
Largely the standardization is not a question of technical capabilities or features, but more a
question of market policies and openness. In Europe the EV charging equipment is moving
towards CCS Combo with multiple automakers supporting this. Increasingly US and Korean
automakers are using CCS, while Japan follows CHAdeMOand China follows GB/T standards.
9
5.2. Discussions with Stakeholders and Partners
While this plan does not cover the full geographical area of Delhi, it is possible to approach the
key stakeholders with the plan and ask for feedback. At minimum discussions with the grid
companies in this area are relevant to evaluate whether there are major issues with the planned
implementation.
Discussions with public stakeholders and companies may be easier to conduct, therefore it might
be wise to start with these companies. With regards to the private companies more thought is
needed on the proposed model and possible support of private investments with subsidies. The
private companies should be approached with a win-win scenario, e.g. increase in customer
loyalty, new attraction for EV users or additional sales through investment in EV charging
stations.
The availability of sites is a challenging issue in typical Indian urban environments. Construction
of EV charging station requires space mainly due to the space needed for the cars themselves
while they are being charged. Also a typical problem in Western Europe is non-EVs using the
parking spaces reserved for EV charging. These issues should be considered beforehand and
regulations for this should be developed in order to ensure that officials in the cities and states do
not need to develop these from scratch. The more universal the markings, conventions and
regulations are, the easier it is for people to adopt the use of an EV.
Safety issues appear especially with electrical feeds into the public charging stations as well as
with charging stations that are located near petrol pumps and other flammable materials. The
feeders of electricity into especially DC charging stations (3*100A) are very powerful, therefore
the construction work should be done thoroughly especially for ground-mounted units. While the
risk of a spark is minimal, the regulations for the construction in the vicinity of petrol pumps
should be reviewed prior to EV charging station rollout to these locations.
Electricity sales regulation also complicates things further and limits the amount of companies
that could potentially offer EV charging services.
6. Conclusions
This proposal presents a plan for building an EV charging station network in the Gurgaon-IGI-
South Delhi-Noida corridor.
The deployment timeline for the "first wave" of these charging stations starts in November
2017which is very aggressive but at the same time it reflects the importance of moving forward
with the infrastructure deployment in a speedy manner. In order to proceed with the deployment
a number of issues needs need to be worked out, most importantly the decisions on
standardization of the charging technologies for the Indian market.
10
In terms of getting access to the sites, the deployment plan relies on co-operation with four key
groups of organizations in addition to the central government: 1) State organizations (in Delhi),
2) Government-owned companies 3) Government authorities and 4) Private companies.
Discussions with these groups are needed to ensure a smooth rollout. Policy decisions on the
(possible) governmental financial support for this rollout need to be made for the dialogue with
the stakeholder organizations. Additionally, discussions with the power utilities in the Delhi area
are needed to ensure that sufficient electricity capacity is available in these locations.
This plan has been prepared with as much effort and expertise as possible in this short time, it is
likely that further optimization and modification could be performed with more time. However,
ideally a plan should be constructed for the entirety of Delhi NCR or any other city or region to
have a full plan on the rollout.
It should also be noted that the planned rollout may be affected by unforeseen circumstances and
therefore the ideal rollout and numbers cannot be achieved within the tight timelines. Issues that
may affect the numbers are for example access to sites, building permissions and grid capacity.
11