Transformer Testing and Commissioning
Transformer Testing and Commissioning
1 to 1.25 1 to 2 Dubious
Note: IR values of delta tertiary stabilizing winding should also be taken with earth and
with HV and LV winding.
7-Transformer Oil Testing:-
Prior to the charging of transformer confirm the healthiness of the oil by testing the
dielectric strength of oil. The oil is to be tested at 2.5 mm gap. 6 nos reading have to
Break Down voltage > 170 KV IEC 156 Immediately prior charging > 50 KV Reconditioning
70 - 170 KV > 40 KV
< 70 KV > 30 KV
be taken and an average of these reading is the breakdown voltage of the oil.
8-Special Test:-
Winding resistance should be carried out with 24 V battery. Rheostat with 10 A rating,
along & digital multimeter, two pole switch Circuit as per figure connect the battery to
one winding of the transformer and adjust the current to 2A. Measure the voltage at
bushings. Winding resistance calculated should be compared with factory test results.
Do not disconnect the wires without reducing the current avoid voltage spikes.
A winding resistance test should be done after all the other tests have been completed.
Note: –In transformer testing, if more than one run of cable per phase is used on the
transformer LV side, it should be confirmed that there is no cross-over of phases
between any run. Such a crossover would result in a dead short circuit on the LV side
of the transformer. This can be verified during a no-load magnetizing current test the
magnetizing current on the transformer HV side should be in the order of mA, with the
all the LV side cables connected. Alternatively, thus can be confirmed during the
transformer differential stability test.
Prior to energizing ensure the following in transformer testing:-
I. Cleaning of the transformer, especially the bushing. Ensure that all protections
are operative. Buchholz relay may be tested by using the test screw, or by
pumping in air with a bicycle pump, or by draining oil from the relay after closing
both side valves.
II. Air release from the transformer is to be done from air release plugs on the
main tank, radiators, HV & LV bushing, Buchholz relay and OLTC prior to
charging of transformer. Do not release air from the condenser bushing as they
are hermetically sealed.
III. Check operation of OTI / WTI, ensure oil in the temperature probe pots.
IV. All interconnecting valves are the open position.
V. Check IR value between each winding to earth, and between windings. Neutral
earthing is to be disconnected for this purpose.
VI. Check that HV and LV neutral earthing has been re-connected after megger
test.
VII. Earthing and delta shorting of tertiary stabilizing winding (if provided), to be
checked.
VIII. Proper setting of OTI & WTI to be done.
IX. Perform trip test from all the transformer protections, including Buchholz relay,
PRD, Oil surge relay, OTI, and WTI.
X. All protection relays to be properly set.
XI. Reset the maximum reading pointer (MRP) of OTI & WTI.
XII. Ammeter selector switches should be selected to read some phase current.
XIII. All MCBs, fuses, and switches in Marshalling boxes, Craps, isolator cubicles
and breaker cubicles should be in the circuit.
XIV. If the transformer is provided with an OLTC, energize it at Tap#1; if the
transformer is provided with an off-circuit tap changer, energize it at the nominal
tap.
Testing of Fan control Cubicle:-
Fan control cubicle houses the control and hardware for running of cooling fans with
the fans running the transformer can be loaded to the specified rating on the nameplate
(ONAF).
The fans are started with the operation of WTI contact. Preferably S1 should be
allocated to run the fans. Normally two banks of 4 fans are provided on the radiators.
IN each bank one fan is spare and three fans will run continuously until that contact
from WTI drops out. Prior to starting of fans following thing have to be checked:-
1. Measure IR value of the fan motors.
2. Check for free rotation of fan blades (rotor), ensure that they do not foul with
the radiators.
3. Ensure proper earthing of motors, fixing of fan on the frames
4. Check for proper setting of overload relays.
After the fans have been started the direction of airflow should be checked. The flow
of air should be on towards the radiator fins.
Check operation of the fan circuit in auto and manual mode and also confirm the
changeover of standby fan in case of fan failure.
After Energizing the Transformer:-
1. If OLTC is provided, run the tap changer from Tap #1 up to the nominal tap.
2. Check the phase sequence and magnitude of the transformer secondary
voltage at the incoming line PTs.
3. If the transformer is an extension to an existing system, do the phasing out w.r.t
the existing PTs.
4. Check for any abnormal sound or vibration in the transformer.
5. Keep the transformer energized on no-load for 24 hours; take a reading of OTI,
WTI and current.