Gannt Chart Unit 2

This document outlines 36 tasks involved in the shutdown and relining of a marine pipeline over a period of 91 days. Key tasks include permits and insurance, mobilization and demobilization over 91 days costing $300,000, and the epoxy lining system over 61 days costing $20,500,000. Miscellaneous costs including safety, equipment, and inspections total another $250,000 over the 91 day period. The project aims to complete all planned maintenance and upgrade work during the scheduled shutdown.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Gannt Chart Unit 2

This document outlines 36 tasks involved in the shutdown and relining of a marine pipeline over a period of 91 days. Key tasks include permits and insurance, mobilization and demobilization over 91 days costing $300,000, and the epoxy lining system over 61 days costing $20,500,000. Miscellaneous costs including safety, equipment, and inspections total another $250,000 over the 91 day period. The project aims to complete all planned maintenance and upgrade work during the scheduled shutdown.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Contract Amount Weightages Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14
Mode -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97
1 Start of Shutdown 0 days 30 12

2 Cooldown period 9 days

3 Permits 0 days 150,000.00 0.68% 3 01

4 Bonds and Insurances 0 days 100,000.00 0.46% 3 01

5 Mobilization & 91 days 300,000.00 1.37%


Demobilization

6 Mobilization 5 days 75,000.00 0.34%

7 Erection of 5 days 75,000.00 0.34%


Temporary Facilities

8 House Keeping 5 days 75,000.00 0.34%

9 De-mobilization 4 days 75,000.00 0.34%

10 Other Scope of Works 77 days 250,000.00 1.14%

11 Opening of 2 days 41,666.67 0.19%


Manholes

12 De-Watering 5 days 41,666.67 0.19%


(Alphatec-SCPC)

13 Cleaning & Drying of 21 days 41,666.67 0.19%


Pipeline

14 Removal of 3 days 41,666.67 0.19%


Sacrificial Anode

15 Installation of 3 days 41,666.67 0.19%


Sacrificial Anode

16 Closing of Manhole 2 days 41,666.67 0.19%

17 Epoxy Linining System 61 days 20,500,000.00 93.62%

18 Surface Preparation 46 days 4,725,000.00 21.56%


(Removal of old
lining by Grinding)

19 Sand Blasting 48 days 4,725,000.00 21.56%

20 Application of 48 days 2,210,000.00 10.09%


Alphatec 340 Primer

21 Application of 48 days 2,210,000.00 10.09%


Alphatec 200 Putty

22 Application of 48 days 2,210,000.00 10.09%


Alphatec 561
Basecoat

23 Application of 51 days 2,210,000.00 10.09%


Alphatec 561
Topcoat

24 Application of 53 days 2,210,000.00 10.09%


Alphatec 561 Final
Coat

25 Curing 53 days n/a n/a

26 Miscellaneous 91 days 250,000.00 2.73%

27 Safety Cost 91 days 250,000.00 1.14%

28 Equipment Cost 91 days 200,000.00 0.91%

29 Pull-off Test - 30 2 days 21,428.57 0.01%


Locations - Third
Party (Optional) 1

30 Pull-off Test - 30 2 days 21,428.57 0.01%


Locations - Third
Party (Optional) 2

31 Inspection of SCPC 2 days 21,428.57 0.01%


Performance 1

32 Inspection of SCPC 2 days 21,428.57 0.01%


Performance 2

33 Inspection of SCPC 2 days 21,428.57 0.01%


Performance 3

34 Inspection of SCPC 2 days 21,428.57 0.01%


Performance 4

35 Inspection of SCPC 2 days 21,428.57 0.01%


Performance 5

Sem
Project: Sem Calaca
Calaca Marine
Marine Pip Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Pipeline
Date: Fri 14 12 18 Unit 2 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress