Automation System
Automation System
Table of Contents
PART 1. INTRODUCTION ............................................................................................................................. 5
1.1 INTENT ............................................................................................................................................. 5
1.2 DESIGN STANDARD OVERVIEW ................................................................................................ 9
1.3 INTEGRATION REQUIREMENTS ............................................................................................... 12
1.4 OPTIMUM ENERGY EFFICIENT DESIGN ................................................................................. 16
1.5 THE CAMPUS AS A “SINGLE BUILDING” ............................................................................... 16
1.6 DESCRIPTION OF WORK ............................................................................................................ 17
1.7 QUALITY ASSURANCE ............................................................................................................... 21
1.8 SYSTEM ARCHITECTURE .......................................................................................................... 25
1.9 CODES AND STANDARDS .......................................................................................................... 28
1.10 DEFINITIONS ................................................................................................................................. 29
1.11 SUBMITTALS – DOCUMENTS, SHOP DRAWINGS, SEQUENCE OF OPERATIONS .......... 32
1.12 PROJECT RECORD DOCUMENTS:............................................................................................. 44
1.13 WARRANTY MAINTENANCE .................................................................................................... 47
1.14 DELIVERY, STORAGE, AND HANDLING ................................................................................ 51
PART 2 – PRODUCTS ................................................................................................................................... 52
2.1 MATERIALS AND EQUIPMENT ................................................................................................. 52
2.2 UNIFORMITY ................................................................................................................................ 52
2.3 BAS FIELD DEVICES AND INSTRUMENTATION ................................................................... 52
2.4 INSTRUMENTATION ................................................................................................................... 65
PART 3 - EXECUTION .................................................................................................................................. 87
3.1 INSPECTION .................................................................................................................................. 87
3.2 INSTALLATION OF CONTROL SYSTEM .................................................................................. 88
3.3 CONTROL PANELS, CONTROLLER QUANTITY AND LOCATION...................................... 88
3.4 CONTROLLERS FOR TERMINAL EQUIPMENT....................................................................... 88
3.5 UNINTERRUPTIBLE POWER SUPPLY & SURGE PROTECTION .......................................... 89
3.6 INSTALLATION OF METERS AND RELATED DEVICES ....................................................... 89
3.7 DEMOLITION AND REUSE OF EXISTING MATERIALS AND EQUIPMENT ...................... 91
3.8 SEQUENCE OF WORK FOR PNEUMATIC SYSTEMS CONVERSION................................... 93
3.9 CONTROL POWER SOURCE AND SUPPLY ............................................................................. 94
3.10 COORDINATION ........................................................................................................................... 94
3.11 PASSWORD PROTECTION .......................................................................................................... 95
3.12 PASSWORD SETUP....................................................................................................................... 95
3.13 POINT NOMENCLATURE ............................................................................................................ 96
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 4 of 153
PART 1. INTRODUCTION
1.1 INTENT
1.1.1 The purpose of this standard and design guidelines is to convey the UofT
requirements that apply to the Building Automation Systems (BAS) and/or any other
mechanical control systems, Direct Digital Controls components, process
instrumentation components and the integration with the Energy Management and
Reporting System (EMRS).
It outlines the expectations and the bases of design (BOD) for all products, the
installations and the quality of the workmanship.
It also outlines the expectations by the Project Consultant and the Commissioning
Agent involved in the design phase as the below BAS Standard defines all the
information that shall be included in the Design Specification documents.
The report from the sections 3.18 Figures 6 and 7 and 3.19 shall be fully included as
the attachment to the Design Specification and it shall be directly referenced to the
form part of the Design Specification.
1.1.2 This Standard specifies that all BAS on St. George Campus shall be fully
interoperable following communication standards based on ANSI/ASHRAE Standard
135-2012 (or current version). Non-BTL listed or legacy BAS are not to be extended
or installed. The strategy behind specifying interoperable systems based on BACNET is
to:
1.1.3 It is imperative that the University of Toronto procedures defined in this Standard be
followed. All requested submissions by the University of Toronto Project Team
shall be presented prior to construction for review and sign off. University of
Toronto Project Team expects sufficient time to prepare reviews and requires written
responses to each point raised by the University of Toronto Project Team.
1.1.4 Any references to the obligations of the Contractor in this document shall be
incorporated in the Design Specification documentation set provided by the Project
Consultant.
1.1.5 Throughout this Standard, requirements are specified, some of which indicate a
means, method or configuration acceptable to meet that requirement. Project
Consultant may submit products that utilize alternate means, methods, and
configurations that meet the functional intent. However, these will only be allowed
with prior approval by the University of Toronto Project Team.
1.1.7 Subject to the detailed requirements provided throughout the project specifications,
the BAS and digital control and communications components installed shall be an
integrated distributed processing system utilizing BACNET communication
protocols. System components shall communicate using native BACNET protocols
in accordance with ASHRAE Standard 135 and current addenda and annexes.
1.1.8 The U of T is interested in state of the art solutions for BAS on Campus. It will not
however, allow products or solutions to be tested or beta level equipment to be
installed without specific authorization from U of T.
1.1.9 A centralized Enterprise Management and Reporting System (EMRS) exist on
Campus from which all buildings’ BAS can be controlled/monitored. All BAS will
require integration to this F&S EMRS.
1.1.10 Contractor shall provide all labour, materials, products, equipment and services to
supply and install the materials and services indicated on the Drawings and specified
in the projects specifications.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 7 of 153
The project consultant confirming that all the requirements in the Section 1.1 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 1
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 8 of 153
1.2.4 A campus wide Ethernet physical layer is supplied and maintained by F&S - IT to
which all approved IP based devices and systems will connect via a UofT specified
and provided color coded patch panels and switches. The BAS Project Consultant
shall coordinate with UofT representative for integration and installation of supplied
IT components.
1.2.5 The Project Architect shall coordinate with the BAS Project Consultant for the
location and installation of all IP switches for any given project through the Project
Manager.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 10 of 153
The project consultant confirming that all the requirements in the Section 1.2 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 2
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 11 of 153
1.3.2 F&S Project Team: Consists of UofT staff and non-staff assigned by UofT to
manage the design and implementation of the BAS on any project on Campus. The
project manager shall be the main point of contact and coordinate UofT staff for the
approvals of the BAS design and implementation.
1.3.3 F&S VLAN: A dedicated and secure CAT 6 fiber Ethernet intranet throughout the
Campus connecting buildings at a Main Distribution Switch located inside the
buildings with a common IP network. The UofT is responsible for the specification,
implementation and maintenance of this Campus LAN. All BAS shall connect to this
LAN data link layer forming a single campus backbone. Any expansion of this LAN
is coordinated with the UofT Central IT department in coordination with F&S IT.
1.3.4 Access to the LAN: All access to the Campus LAN (also referred to F&S
VLAN) is coordinated and approved with F&S IT who will also control and
distribute any required IP addresses and their access timelines. The F&S I T will
specify and supply any switches, patch panels a n d r a c k s or connection devices to
the F&S LAN. The Project Consultant shall not design around or install any
gateways, Java Application Control Engine (JACE) type of the devices or equivalent,
routers, bridges or repeaters without prior approval by U of T Project Team.
1.3.5 Building level controls: All BAS control devices will connect to the F&S LAN
with approved sub-networks. The Standard stipulates that any new or replacement
BAS devices will be BACNET Testing Laboratories (BTL) listed with current
Protocol Implementation and Conformance Statements (PICS). These include
BACNET device profiles B-OWS, B-BC, B-AAC, B-ASC, B-SS and B-SA. The
BAS control strategies will reside at the controllers and will communicate with the
F&S LAN using MS/TP or IP data link protocols. Other field level network types
must be approved by UofT Project Team. BAS technologies that require dedicated
servers or gateways in the project will not be allowed without written approval from
the UofT Project Team.
1.3.6 Field level devices: These include actuators, sensors, valves, etc., that interact with
and control the space conditions through the BAS controllers. The specifications for
these devices are found in this Standard. Field level devices typically use the serial
field bus RS485 protocol to communicate to the IP based building controller (BC).
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 13 of 153
1.3.7 BACNET object list: BACNET objects associated with a project building controls
implementation, with a description of its physical representation, and system
association. This document is a critical component of the handover material between
a building controls implementation and integration to the EMRS. During BAS
design process, a list of BACNET objects, all binary, analog, calculated and virtual
points associated with the design and sequences and accessed over the F&S VLAN
(not specifically addressed) are required for review by UofT Project Team prior to
final project approval. This list will include objects required from embedded controls
such as within variable speed drives, chillers, heat pumps and other application
specific controllers.
1.3.8 Unless otherwise stipulated, the line of demarcation for the BAS contractor is at the
patch panel(s) within the building. All control sub network cabling, controllers, end
devices and components specified as a part of the BAS are supplied and installed by
the BAS contractor. F&S- IT shall coordinate the supply and installation of all F&S
Ethernet LAN cabling, switches, racks, patch panels, UPS(s), operator work stations
and portable service terminals as required with the BAS contractor.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 14 of 153
The project consultant confirming that all the requirements in the Section 1.3 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 3
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 15 of 153
1.6.2 The BAS design will be the result of coordination with and approvals from the U of
T Project Team.
1.6.7 Contractor shall furnish and install electronic actuation of dampers and valves to
perform control sequences and functions specified. Pneumatic actuation may remain
if already in place and U of T decides to keep that system operational.
DDC/pneumatic interface will be the responsibility of the BAS contractor.
1.6.8 The distributed DDC and BAS defined in this Standard shall interface with the
University F&S Ethernet VLAN.
1.6.9 All BAS control work, labor, software, and services including sub-networks and
F&S LAN within the building beyond the Main Distribution Switch, shall be
installed by the BAS contractor, unless specified otherwise.
1.6.10 Systems i.e., chillers, boilers, cooling towers, VFD’s and energy recovery units that
are equipped with manufacturer furnished controls shall use controllers that follow
these Standards.
1.6.11 IP enabled control devices are to be provided with static IP addresses supplied by
F&S IT.
1.6.12 Location of switch(s) and patch panel(s) will be determined during project design
with the UofT Project Team. BAS network architecture shall be reviewed by the
UofT Project Team prior to acceptance of the design and submission of shop
drawings and include all required switch locations, cable needs and connection to
the F&S VLAN.
1.6.13 All BAS related cabling including sub-networks within the building and VLAN
between Main Distribution Switch/Router and switches is the responsibility of the
BAS contractor.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 18 of 153
1.6.14 No control devices are to be tied into the F&S VLAN without UofT Project Team
approved request protocol. No Ethernet extenders are allowed.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 19 of 153
The project consultant confirming that all the requirements in the Section 1.6 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 4
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 20 of 153
1.7.1 The product line being proposed for the project must have an installed history of
demonstrated satisfactory operation for a length of (3) years since date of final
completion in at least [8] installations of comparative size and complexity.
1.7.2 No beta level or pilot products with less than 3 years field operation are to be used or
tested on Campus without approvals.
1.7.3 Applies to Operator Software, Service Tool Software, Controller resident software, B-
BCs, B-AACs, B-ASCs, SAs.
1.7.4 Documentation of this requirement with references shall be available upon request.
1.7.5 All new, retrofit or renovated BAS devices shall meet the most recent BACNET-135
standards and be verifiably BTL listed.
1.7.9 Installer's Experience with Proposed Product Line: Firms shall be specialized in
and experienced with the installation of the acceptable manufacturers’ product line
for not less than three years from date of final completion on at least 5 projects of
similar size and complexity. Submittals shall document this experience with
references.
1.7.10 Installer’s Field Coordinator and Sequence Programmer Qualifications:
Individual(s) shall specialize in and be experienced with control system installation
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 22 of 153
for not less than 5 years. Proposed field coordinator shall have experience with the
installation of the proposed product line for not less than two (2) projects of similar
size and complexity. Installer shall submit the names of the proposed individual and
at least one alternate for each duty. Submittals shall document this experience with
references. The proposed individuals must show proof of the following training:
1.7.10.1 Product Line Training: Individuals overseeing the installation and
configuration of the proposed product line must provide evidence of the most
advanced training offered by the Manufacturer on that product line for
installation and configuration.
1.7.10.2 Programming Training: Individuals involved with programming the site-
specific sequences shall provide evidence of the most advanced programming
training offered by the vendor of the programming application offered by the
Manufacturer.
1.7.11 Installer’s Service Qualifications: The installer must be experienced in control
system operation, maintenance and service of the acceptable manufacturers’ products.
Installer must document a minimum five (5) year history of servicing installations of
similar size and complexity. Installer must also document at least a one year history
of servicing the proposed product line.
1.7.12 Installer’s Response Time and Proximity
1.7.12.1 Installer must maintain a fully capable service capacity within a 70 km radius
of the project site. Service facility shall manage the emergency service
dispatches and maintain the inventory of spare parts.
1.7.12.2 Emergency response times are listed below in this section. Installer must
demonstrate the ability to meet the response times.
1.7.13 Installer’s Quality Assurance Plan
1.7.13.1 Installer must provide a description of their quality assurance operations from
contract award through final delivery. The description shall include
organizational responsibilities for each department represented within the
execution of this document from installer’s to engineers, service technicians
and management.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 23 of 153
The project consultant confirming that all the requirements in the Section 1.7 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 5
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 24 of 153
1.8.2 A system architecture document shall be developed in cooperation with the UofT
Project Team that describes graphically the extent of controls installed and their
communication hierarchy, from the physical to application (EMRS) layer. All
control devices shall be indicated on the floor plans or identified by a room number.
F&S network components, including UofT IP switches, shall be shown on the
diagram to indicate which equipment is communicating over the F&S network, and
indicating its designated static IP address. This document shall be updated
throughout the project to track modifications made during design, build out,
commissioning and closeout.
1.8.4 The system architecture consists of a secure F&S maintained CAT 6 Ethernet-based,
Campus local area network (F&S VLAN) connected to all buildings, a single
building level or multi-leveled sub-networks (serial field bus, MS/TP, MODBUS)
that support BCs, AACs, ASCs, Operator Workstations (OWS), Smart Devices (SD),
and portable operator’s stations (POTs) as applicable.
1.8.6 All connections by IP enabled devices shall be to the F&S network through F&S
approved switches. The Project Consultant shall confirm the location and capacity of
all switches and shall become aware of where the switches will be located if they are
not existing in order to design the sub-networks required.
1.8.7 All requests for connections shall be made to Project Consultant at least 3 business
days before the connection is required. Any BACNET/IP device shall be specifically
configured to use only designated static IP addresses. IP addresses will be issued to
contractors for the purposes of BAS installation and commissioning with end dates
that will be extended, if requested, through a formal request to F&S - IT.
1.8.8 The BAS contractor is responsible for supply and installation of all networks from
field devices through controllers to the patch panel(s).
1.8.9 Remote Data Access: Design to include remote access connectivity and coordinated
with F&S - IT. The system shall support the following methods of remote access to
the building data through smart phones & portable devices via one or more of the
current common standards: Apple iOS (IPhone, IPad), Android Open Source Project
(Android devices), Windows Mobile Devices. Request for Access Form shall be
submitted to UofT F&S IT. The form is available here:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 26 of 153
http://www.fs.utoronto.ca/wp-content/uploads/forms/12_BAS_and_EMRS_Access_Process.pdf
1.8.10 Browser-based access: A remote user using a standard browser shall be able access
all control system facilities and graphics with proper password. F&S - IT shall
provide the required internet connection. The following paradigms are acceptable
for browser-based access:
1.8.10.1 Native Internet-based user interfaces (HTML, Java, XML, etc.) that do not
require a plug-in. The user interface must be compatible with the most
current stable version of the supporting software (Java, etc.) without requiring
the user to downgrade to a lesser version.
1.8.11 The communication speed between the controllers, LAN interface devices, and
operator interface devices shall be sufficient to ensure fast system response time
under any loading condition. In no case shall delay times between an event, request,
or command initiation and its completion be greater than those listed herein. The
serial field bus, ASC/AAC layout and BC to switch layout is to be planned as
necessary to accomplish these performance requirements (maximum values):
1.8.11.1 3 seconds between a Level 1 (critical) alarm occurrence and enunciation at
operator workstation.
1.8.11.2 8 seconds between a Level 2 alarm occurrence and enunciation at operator
workstation.
1.8.11.3 10 seconds between and a Level 3-5 alarm occurrence and enunciation at
operator workstation.
1.8.11.4 8 seconds between an operator command via the operator interface to change
a setpoint and the subsequent change in the controller.
1.8.11.5 3 seconds between an operator command via the operator interface to
start/stop a device and the subsequent command to be received at the
controller.
1.8.11.6 8 seconds between a change of value or state of an input and it being updated
on the operator interface.
1.8.11.7 8 seconds between an operator selection of a graphic and it completely
painting the screen and updating at least 10 points.
1.8.12 EMRS Control Systems Server: An existing F&S computer (or computers) that
maintain the enterprise systems configuration and programming database. The
EMRS is at the application layer and provides data sharing, alarm and event
management, scheduling, trending and device and network management to approved
B-OWS locations.
This server operates virtually under the supervision of F&S - IT. It shall hold the
backup and point data files of the information downloaded into the individual
controllers and as such support uploading and downloading that information directly
to/from the controllers. It shall also act as a control information server to non-control
system based programs. It shall allow secure multiple-access to the BAS control
information.
1.8.13 The EMRS Operator Interface, typically an OWS, shall provide the overall
system supervision, graphical user interface, management report generation, alarm
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 27 of 153
annunciation, and remote monitoring. The operator interface is the access point to a
collection of dynamic displays at the EMRS.
1.8.14 EMRS interface type and location to be defined with UofT Project Team. Unless
specifically defined otherwise, F&S - IT will supply the operator interface(s).
1.8.17 The BCs, AACs, ASCs, and SDs shall monitor, control, and provide the field
interface for all points specified. Each BC, AAC, or ASC shall be capable of
performing all specified energy management functions, and all DDC functions,
independent of other BCs, AACs, or ASCs and operator interface devices.
1.8.18 Interruptions or fault at any point on the F&S LAN shall not interrupt
communications between other nodes on the network. If a LAN is severed, two
separate networks shall be formed and communications within each network shall
continue uninterrupted.
1.8.19 No connections shall be made between fire, life safety, access control systems and
the BAS/EMRS unless specifically approved by the UofT Project Team.
1.8.20 All line drivers, signal boosters, and signal conditioners etc. if required, shall be
approved by UofT Project Team and then provided as necessary for proper data
communication. The basis of design does is to not use drivers or boosters but rather
through proper network architecture and layout.
1.8.21 The BAS vendor must supply its own dedicated temporary communication gateway
and/or a modem device for the internet connectivity along with the SMTP service
that is properly and securely configured and functional by the BAS vendor. This is to
ensure that all the alarms notifications for the predefined and approved critical
control objects/points are being sent to the predefined list of the alarm recipients
from the Temporary Operator Interface Workstation (Temporary GUI).
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 28 of 153
1.10 DEFINITIONS
1.10.1 Accuracy: Accuracy shall include combined effects of nonlinearity, non-
repeatability and hysteresis.
1.10.2 Advanced Application Controller (AAC): A device with limited resources relative
to the Building Controller (BC). It may support a level of programming and may
also be intended for application specific applications. Typically serviced on the serial
field bus network.
1.10.3 Application Specific Controller (ASC): A device with limited resources relative to
the Advanced Application Controller (AAC). It may support a level of programming
and may also be intended for application-specific applications. Typically serviced on
the serial field bus network.
1.10.4 Approvals: Where ever the term “approvals” or similar is used it shall mean the
reference issue must be approved by the UofT Project Team in writing before the
issue can be incorporated.
1.10.5 BACNET/BACNET Standard: BACNET communication requirements as defined
by ASHRAE/ANSI 135-2016.
1.10.6 BACNET Interoperability Building Blocks (BIBB): A BIBB defines a small
portion of BACNET functionality that is needed to perform a particular task. BIBBS
are combined to build the BACNET functional requirements for a device in a
specification.
1.10.7 Building Automation System (BAS): The entire integrated management and
control system as applied to a specific project or building.
1.10.8 BACNET Building Controller (B-BC): A fully IP programmable device capable of
carrying out a number of tasks including control and monitoring via direct digital
control (DDC) of specific systems, acting as a communications router between the
F&S LAN and serial field buses, and data storage for trend information, time
schedules, and alarm data. A general-purpose device capable of carrying out a
variety of building automation and control tasks including control and monitoring via
direct digital control (DDC) of specific systems and data storage for trend
information, time schedules, and alarm data. Like the other BTL Listed controller
types (B-AAC, B-ASC etc.) a B-BC device is required to support the server ("B")
side of the ReadProperty and WriteProperty services, but unlike the other controller
types it is also required to support the client ("A") side of these services.
Communication between controllers requires that one of them support the client side
and the other support the server side, so a B-BC is often used when communication
between controllers is needed.
1.10.9 BACNET Advanced Application Controller (B-AAC): A control device which
contains BIBBs in support of scheduling and alarming but otherwise has limited
resources relative to a B-BC. It may be intended for specific applications and
supports some degree of programmability.
1.10.10 BACNET Application Specific Controller (B-ASC): A controller with limited
resources relative to a B-AAC. It is intended for use in a specific application and
supports limited programmability.
1.10.11 Consultant: Person(s) responsible for the design of the BAS and retained by and
reporting to the UofT Project Team. May consist of the BAS Contractor, M/E
consultant, Integrator, UofT Project Team any combination or their assigned
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 30 of 153
representatives. The full scope of the BAS project may be developed by the UofT
Project Team or in cooperation with the Consultant.
1.10.12 Device Object Identifier: BACNET can accommodate up to 4,194,305 devices.
UofT Project Team will assign Device Object Identifier properties.
1.10.13 Direct Digital Control (DDC): Microprocessor-based control including
Analog/Digital conversion and program logic.
1.10.14 Embedded Controllers: Certain equipment contains packaged OEM controllers.
These must follow these Standards. Examples can be found in variable speed drives,
chillers, boilers, pump sets, etc. In all cases the controllers must be accessible and
readable/writable to the BAS and EMRS. Proprietary communication protocols will
not be allowed. The integration of the embedded controllers must comply with the
Section 3.19 (3EMRS INTEGRATION WITH NON-BACNET COMPLIANT
COMPONENTS) of this document.
1.10.15 EMRS: Enterprise Management and Reporting System is a campus wide
administration application level system, provided by and maintained by F&S.
BACNET interoperability areas data sharing, alarm and event management,
scheduling, trending and network management can all be performed at this level. All
BAS shall be able to be integrated with the EMRS.
1.10.16 EMRS Integration Agent: Is responsible for performing integration of building
controls into the EMRS. This agent may be a third party contractor or U of T’s own
forces and is responsible for coordinating the BAS/EMRS functionality integration.
1.10.17 Functional Profile: A collection of variables required to define the key parameters
for a standard application. As this applies to the HVAC industry, this would include
applications like VAV terminal, fan coil units, and the like. ASC’s contain
functional profiles.
1.10.18 Facility Information Technology (Fac IT): Reference to the local Information
Technology department, responsible for providing and maintaining all Operator
Interface hardware and network connections within the facility. Will coordinate with
F&S - IT for all local IT related efforts.
1.10.19 Facilities & Services Project Team (F&S or UofT Project Team): The project
Project Team is made up of all or part of the following groups; assigned consultant,
F&S - IT, Sustainability, Project Manager, Controls Technicians, Area Managers,
integrators and any others as assigned by UofT.
1.10.20 Facility & Services IT (F&S IT, UofT - IT): Reference to the U of T Facilities &
Services Information Technology department responsible for providing and
maintaining all F&S LANs, switches, EMRS, integration, IP addresses and access.
1.10.21 Gateway: A device, which contains two or more dissimilar networks/protocols,
permitting information exchange between them (ASHRAE/ANSI 135-2004).
Gateways are not to be included in the basis for design and must be justified and
approved by UofT Project Team before consideration in a final design.
1.10.22 LAN Interface Device: Device or function used to facilitate communication and
sharing of data throughout the BAS. Includes UofT switches, routers, gateways (if
allowed). Typically located in IT rooms, electrical closets, and mechanical rooms.
Consultant shall verify locations and include in tender documents. Shall be
described, justified and approved by U of T before included in any BAS design.
1.10.23 Legacy Systems: Existing BAS controls systems that are not BTL listed BACNET
devices, are no longer supported by the manufacturer, or no longer fit the
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 31 of 153
1.11.1 During the design phase and prior, the project tender, the Project Consultant shall
provide the complete project documentation, including the sequence of operations
(see section (1.11.13) along with the high level controls architecture diagram for the
UofT Project Team to review.
Within 30 days of award of contract, before start of construction, BAS Project
Consultant submits completely engineered and coordinated shop drawing package.
1.11.2 Electronic Submittals: Four (4) copies of the Control submittals and O&M
information shall be provided in unlocked, editable Adobe PDF or Microsoft Word
format. Documents will be converted from their native electronic format directly to
a preferred format. Any documents scanned as images must be converted to a
searchable text format using OCR (Optical Character Recognition) and reduced in
size prior to submission.
1.11.4 Product Data: Submit four (4) copies of the manufacturer's technical product data
for each control device, panel, and accessory furnished, indicating dimensions,
capacities, performance and electrical characteristics, and material finishes. Also
include installation and start-up instructions.
1.11.5 Shop Drawings: Submit four (4) copies of the shop drawings for each control
system, including a complete drawing for each air handling unit, system, pump,
device, etc. with all point descriptors, addresses and point names indicated. Each
shop drawing shall contain the following information:
1.11.5.4 Indicate network number, device ID, address, device instance, MAC address,
drawing reference number, and controller type for each control unit. Indicate
media, protocol, baud rate, and type of each network. All optical isolators,
repeaters, end-of-line resistors, junctions, ground locations etc. shall be
located on the floor plans.
1.11.5.5 Schematic flow diagram of each air and water system showing fans, coils,
dampers, valves, pumps, heat exchange equipment and control devices.
Include verbal description of sequence of operation.
1.11.5.6 Sequence of Operation: Provide description of operation for interlocks that
directly connect to the Work. Indicate references to the system flow diagram
by control device designation or point object name.
1.11.5.7 All physical points on the schematic flow diagram shall be indicated with
names, descriptors, and point addresses identified as listed in the point
summary table.
1.11.5.8 With each schematic, provide a point summary table listing building number
and abbreviation, system type, equipment type, full point name, point
description, Ethernet backbone network number, network number, device ID,
object ID (object type, instance number).
1.11.5.9 Submitted drawings to include labels for each control device with setting and
adjustable range of control and units.
1.11.5.10 Submitted drawings to include labels for each input and output with the
appropriate range and units.
1.11.5.11 The BAS vendor shall be instructed within the Design Specification to
include any relevant information from the others that the BAS system will be
integrated directly to EMRS.
1.11.6 Provide a Bill of Materials with each schematic. Indicate device identification to
match schematic and actual field labeling, quantity, actual product ordering number,
manufacturer, description, size, voltage range, pressure range, temperature range,
etc. as applicable.
1.11.7 Provide a Control Valve Schedule listing valve and actuator information including:
size, Cv, design flow, design pressure drop, manufacturer, model number, close off
rating, control signal, etc. Indicate normal positions of spring return valves.
1.11.8 Provide a Control Damper Schedule listing damper and actuator information
including: size, material, blade arrangement, manufacturer, model number, control
signal, etc. Indicate normal positions of spring return dampers.
1.11.9 Indicate all required electrical wiring. Electrical wiring diagrams shall include both
ladder logic type diagram for motor starter, control, and safety circuits and detailed
digital interface panel point termination diagrams with all wire numbers and
terminal block numbers identified, connections between control devices, controllers
and equipment; connections to sources of power and grounds; control device
designations, control device terminal designations, control device location;
equipment terminal designations; cabinet terminal strip designations; wire
designations. Provide panel termination drawings on separate drawings. Ladder
diagrams shall appear on system schematic. Clearly differentiate between portions
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 34 of 153
1.11.10 Provide details of control panels, including controls, instruments, and labeling
shown in plan or elevation indicating the installed locations. Provide panel layout
drawing including power supply, control unit(s) and wiring terminals.
1.11.10.1 Sheets shall be consecutively numbered.
1.11.10.2 Each sheet shall have a title indicating the type of information included and
the HVAC+L system controlled.
1.11.10.3 Table of Contents listing sheet titles and sheet numbers.
1.11.10.4 Provide a symbol legend and list of abbreviations.
1.11.10.5 All field labeling of devices must match the device identifications listed in
the Control schematic. Submit a sample of labeling to be used.
It is the responsibility of the Project Consultant to ensure that the project design
specifications include the requirements below:
1.11.13.1 PURPOSE
Purpose of this standard is to convey minimum University of Toronto,
Facilities and Services expectations in terms of the context and format of the
Sequence of Operation for Building Automation System (BAS) for the
Project Consultantconsultant to include in the Design Specification It is the
responsibility of the Project Consultant to ensure that the project design
specifications include the following requirements:
1.11.13.2 INTENT
Clear, detailed control sequence of operation is necessary to provide proper
operation of the building. It shall sufficiently describe in simple and
understandable language how the control system and associated building
systems and equipment shall operate. Energy consumption, savings and
demand as well as system performance troubleshooting are also part of the
building operation and BAS.
The sequence of operation shall provide a story of the design intent for the
building operation with set values to what the building shall be operated to
(set points). It shall clearly state what parameters shall be adjusted /
determined during initial start-up, balancing, commissioning and what are
user adjustable. It shall provide information on safety features (hardwired /
soft points), integration with life safety systems (fire alarm, smoke exhaust,
stair pressurization, and similar). It shall describe system operation during
power failure, scheduled start / stop and integration with any other building
systems / equipment.
BAS vendor is a controls integrator so the BAS shop drawings and sequence
of operation have to have all required details to allow the UofT Facilities and
Services to operate and maintain the buildings, which means that all relevant
info associated with packaged units and lab controls has to be included in
and/or clearly referenced & affixed as appendices with this document. These
mandatory requirements are applicable to all the projects listed in the section
1.2 of this document.
1.11.13.3 APPLICATION
This Standard is applicable for BAS controls and any other control systems
that may be provided by the separate control vendors / equipment packages
for integration with / through BAS system. Examples are Lab control, Fume
Hood control, VRF systems, packaged AHUs, chillers, boilers, VRF systems,
etc.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 37 of 153
Description of the how each component on the system will operate, including
start-up and shutdown; enable/disabled.
Sequence of events in case the equipment fails to start and/or in emergency
situation.
1.11.13.4.4 System Start/Stop
Description of the how each component on the system will operate, including
start-up and shutdown; enable/disabled.
Sequence of events in case the equipment fails to start and/or in emergency
situation.
1.11.13.4.5 Safeties
List of failure modes and safety devices or subsystems, safety hardwires / soft
points and interconnection with fire / life safety system.
The setpoints shall be defined with the ranges that can be adjusted but will
not adversely affect the system operation. The setpoints tolerances shall also
be included.
If the values are to be adjusted by operator through the EMRS (BAS)
interface, it shall state “operator adjustable”.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 39 of 153
Provide calculations that shall be used by the BAS controls vendors for the
output values such as:
Flow
Consumption
Supply and Return Temperature
Differential, Supply and Return Pressure
Energy Flow Calculation
1.11.13.4.9 Alarms
List all the mandatory process values that shall be included in the DDC
Alarm Notifications with the clear identification of the low and high alarm
limits.
Provide the list of all the necessary documents (ex. : floor plans, zoning
diagrams, etc.) to create the graphical interface with the visual indication of
the alarm state for each process value.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 40 of 153
Included in the
Consultant BAS Local controls with
List of Packaged units / control systems that are to be Specification (YES / display provided
integrated via BAS with EMRS (Consultants to populate) NO / N/A) (YES/NO/N/A)
1
2
3
4
5
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 42 of 153
The project consultant confirming that all the requirements in the Section 1.11 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 6
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 43 of 153
1.12.2 Record copies of product data and control shop drawings updated to reflect the final
installed condition. Submit four (4) copies.
1.12.3 Record copies of approved control logic programming and database on CD/DVD or
USB key.
1.12.4 Accurately record actual setpoints and settings of controls, final sequence of
operation, including changes to programs made after submission and approval of
shop drawings and including changes to programs made during specified testing.
1.12.5 “As-built” record drawings that represent the final system architecture, configuration
input/output points and device locations in the AutoCAD Editable format.
1.12.6 I/O points list shall include the name/description, display units, alarm
limit(s)/definitions and BACNET object description, including Object ID and Device
ID, for each I/O point.
1.12.7 Record copies of approved project specific graphic software on CD/DVD or USB
key.
1.12.8 Record copies shall include individual floor plans with controller locations with all
interconnecting wiring routing including space sensors, LAN wiring, power wiring,
low voltage power wiring.
1.12.11 Provide record riser diagram showing the location of all controllers, connection to F
& S switches, routers, wireless and repeaters.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 45 of 153
The project consultant confirming that all the requirements in the Section 1.12 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 7
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 46 of 153
1.13.2 Work shall have a single warranty date, even if U of T Project Team receives
beneficial use due to early system start-up. If specified work is split into multiple
contracts or a multi-phase contract, each contract or phase shall have a separate
warranty start date and period.
1.13.3 The University of Toronto reserves the right to make changes to the BAS during the
warranty period. Such changes do not constitute a waiver of warranty. The Project
Consultant shall warrant parts and installation work regardless of any such changes
made by the UofT, unless the Project Consultant provides clear and convincing
evidence that a specific problem is the result of such changes to the BAS. Any
disagreement between the University and the Project Consultant on such matters
shall be subject to resolution through the contract ‘Disputes’ clause.
1.13.4 At no cost to the UofT, during the warranty period, the Contractor shall provide
maintenance services for software and hardware components as specified below:
1.13.4.1 Maintenance Services: Shall be provided for all devices and hardware
specified for the project. Service all equipment per the manufacturer’s
recommendations. All devices shall be calibrated within the last month of the
warranty period.
1.13.4.2 Emergency Service: Any malfunction, failure, or defect in any hardware
component or failure of any control programming that would result in
property damage or loss of comfort control shall be corrected and repaired
following notification by the University to the Contractor.
1.13.4.2.1 Response by telephone to any request for service shall be provided
within one (1) hour of the University's initial telephone request for
service.
1.13.4.2.2 In the event that the malfunction, failure, or defect is not corrected
through the telephonic communication, at least one (1) hardware and
software technician, trained in the system to be serviced, shall be
dispatched to the University's site within two (2) hours of the
University's initial telephone request for such services, as specified.
1.13.4.3 Normal Service: Any malfunction, failure, or defect in any hardware
component or failure of any control programming that would not result in
property damage or loss of comfort control shall be corrected and repaired
following telephonic notification by the University to the Contractor.
1.13.4.3.1 Response by telephone to any request for service shall be provided
within two (2) working hours (contractor specified 40 hr. per week
normal working period) of the University's initial telephone request
for service.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 48 of 153
1.13.4.3.2 In the event that the malfunction, failure, or defect is not corrected
through the telephonic communication, at least one (1) hardware and
software technician, trained in the system to be serviced, shall be
dispatched to the University's site within three (3) working days of
the University's initial telephone request for such services, as
specified.
1.13.4.4 Request for Service: BAS Contractor shall specify a maximum of three (3)
telephone numbers for UofT Project Team to call in the event of a need for
service. At least one of the lines shall be attended at any given time at all
times. Once contacted a technician shall respond to every call within 15
minutes.
1.13.4.5 Technical Support: Contractor shall provide technical support to UofT
Project Team throughout the warranty period.
1.13.4.6 Preventive Maintenance: Shall be provided throughout the warranty period
in accordance with the hardware component manufacturer's requirements.
1.13.4.7 All warranty work to be performed by original manufacturer trained staff.
1.13.4.8 Provide updates to controller firmware that resolve Contractor identified
deficiencies at no charge during warranty period.
1.13.4.9 Contractor shall not be required to warrant reused devices except those that
have been rebuilt or repaired. Installation labor and materials shall be
warranted. Demonstrate operable condition of reused devices at time of
Project Team’s acceptance.
1.13.4.10 Factory mounted controllers shall be warranted by the manufacturer, not the
controls supplier.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 49 of 153
The project consultant confirming that all the requirements in the Section 1.13 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 8
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 50 of 153
PART 2 – PRODUCTS
2.2 UNIFORMITY
2.2.1 All equipment of the same type serving the same function shall be identical and from
the same manufacturer.
2.2.2 All naming conventions and graphics shall be consistent for all projects according to
these Standards.
2.2.3 UofT Project Team will review and confirm the systems, nomenclature and graphics
as uniform before accepting the final design. See Section 3.17 Fig. 1 - 5 for example
graphic and Fig 7 for sample point naming.
where:
xxx – building number
yy – controller index
z – Notification Class index
2.3.2.24 Every Analog Input and Analog Output point must have the Bacnet Change
of Value Increment (COV) parameters configured as per the table below:
Pressure
INW 0.01 0.1 0.1
PSI 0.5 0.5
Humidity 2 2 2 5 2
Volumetric 5% of 2% of 2% of 2% of 2% of 2% of
Flow setpoint setpoint setpoint setpoint setpoint setpoint
All types
Outputs 5% of range
2.3.2.26 BC Failure:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 58 of 153
2.3.3.1 Where these devices are included with HVAC+L equipment such as boilers,
chillers, variable speed drives, lighting, pump sets, air handling units, etc.,
they shall meet these Standards. In particular they shall be able to be
connected to the EMRS using BACNET communication and interoperability
protocols with complete accessibility to objects/points in the controller.
2.3.3.2 AACs and ASCs shall provide intelligent, standalone control of HVAC+L
equipment. Each unit shall have its own internal RAM, non-volatile memory
and will continue to operate all local control functions in the event of a loss of
communications on the ASC sub-network. It shall be able to share
information with every other BC and AAC /ASC on the entire network.
2.3.3.3 Each AAC and ASC shall include self-test diagnostics that allow the AAC
/ASC to automatically relay to the related BC, any malfunctions or abnormal
conditions within the AAC /ASC or alarm conditions of inputs that exceed
desired parameters as determined by programming input.
2.3.3.4 AACs and ASCs shall include sufficient memory to perform the specific
control functions required for its application and to communicate with other
devices.
2.3.3.5 Each AAC and ASC must be capable of stand-alone direct digital operation
utilizing its own processor, non-volatile memory, input/output, minimum 8
bit A to D conversion, voltage transient and lightning protection devices. All
volatile memory shall have a battery backup of at least fifty (50) hrs with a
minimum battery life of five (5) years.
2.3.3.6 All point data, algorithms and application software within an AAC /ASC
shall be modifiable from the Service Tool.
2.3.3.7 The following is the list of the mandatory Bacnet Interoperability Building
Blocks (BIBBs) for the B-AAC and B-ASC:
2.3.3.7.1 Alarm and Event Services:
2.3.3.7.1.1 Alarm and Event Notification – Acknowledgement: AE-
ACK-A; AE-ACK-B
2.3.3.7.1.2 Alarm and Event – Alarm Summary: AE-ASUM-A; AE-
ASUM-B
2.3.3.7.1.3 Alarm and Event Notification: AE-N-A
2.3.3.7.2 Data Sharing:
2.3.3.7.2.1 Read Property: DS-RP-A; DS-RP-B
2.3.3.7.2.2 Read Property Multiple: DS-RPM-A; DS-RPM-B
2.3.3.7.2.3 Write Property: DS-WP-A; DS-WP-B
2.3.3.7.2.4 Write Property Multiple: DS-WPM-A; DS-WPM-B
2.3.3.7.3 Device and Network Management:
2.3.3.7.3.1 Dynamic Device Binding: DM-DDB-A; DM-DDB-B
2.3.3.7.3.2 Dynamic Object Binding: DM-DOB-A; DM-DOB-B
2.3.3.7.3.3 Time Synchronization: DM-TS-A; DM-TS-B
2.3.3.7.3.4 UTC Time Synchronization: DM-UTC-A; DM-UTC-B
2.3.3.8 The following is the list of the mandatory Bacnet Object Types for the B-
AAC and B-ASC:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 60 of 153
where:
xxx – building number
yy – controller index
z – Notification Class index
2.3.3.10 B-ASC and B-AAC functionality and compliance with BIBB and Object
Types shall be presented to the U of T Project Team before shop drawing
submission. Functionality must be approved by the U of T Project Team.
2.3.3.11 All AACs and ASCs shall be BTL listed.
2.3.3.12 AAC(s) and ASC(s) shall communicate to the BACNET Building
Controller (B-BC) on the RS485 MSTP field bus.
The project consultant confirming that all the requirements in the Section 2.3 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 9
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 64 of 153
2.4 INSTRUMENTATION
2.4.1 General Notes
2.4.1.1 It is the responsibility of the Project Consultant to ensure that the project
design specifications include all requirements below.
2.4.1.2 All remote access instrumentation is to be compatible with the BAS and
EMRS for data access, control and monitoring. Systems with BACNET
protocol compatibility shall be the basis for all BAS instrumentation where
applicable.
2.4.1.3 All sensor, devices and instrumentation locations shall be shown on the
mechanical drawings and approved by the UofT Project Team.
2.4.1.4 BAS Contractor shall provide and install all instrumentation required to
satisfy the Sequences of Operation.
2.4.1.5 The following list of Instrumentation describes minimum specifications. The
Contractor is encouraged to suggest alternates that are more current in design
for review and approvals by the U of T Project Team.
2.4.1.6 The U of T Project Team is permitted to alter these specifications on a project
by project basis if required.
2.4.1.7 BAS Project Consultant is required to coordinate with the Mechanical and
Electrical contractors for supply of BAS components that may over-lap such
as metering, valves, line voltage devices. When in doubt, BAS Project
Consultant shall contact the U of T Project Team for clarity.
2.4.12 Thermowells
2.4.12.1 Stainless steel (316 SST ¾ inch) probe. Probe length shall be at minimum
30% of the pipe width.
2.4.12.2 Moisture/waterproof housing with conduit fitting.
2.4.12.3 Provide complete with drilled Stainless Steel thermowells.
2.4.12.4 Provide complete with thermal transfer compound inside thermal well.
2.4.21.2 Provide complete isolation between the control circuit and the BAS digital
output.
2.4.21.3 Located in the BC, ASC, AAC or other local enclosures.
2.4.21.4 10 amp contact rating.
2.4.21.5 LED status indication
2.4.30 Differential Pressure Switch - Water Service (not used in flow metering)
2.4.30.1 UL, CSA listed and approved.
2.4.30.2 SPDT or two SPST switches rated for 10 amps minimum at 120 Vac.
2.4.30.3 Adjustable set-point with a setpoint range to suit the application.
2.4.30.4 1/4 inch compression fittings suitable for copper sensing tubing.
2.4.30.5 Operating temperature and pressure range to suit application.
2.4.30.6 Durable NEMA-4 rated enclosure.
2.4.30.7 Provide sensing inputs complete with signal dampening facilities to
prevent nuisance tripping where required.
2.4.30.8 Suitable for continuous contact with the sensed fluid and rated for
operating temperature.
2.4.30.9 Repeatability of +/- 1 % of span.
2.4.30.10 Over pressure input protection to a minimum of five (5) times rated input.
2.4.30.11 Basis of design, Dwyer or Penn.
2.4.31 Water Pressure Sensor
2.4.31.1 Input range of 0 to 200 psi or as per UofT Project Team.
2.4.31.2 Complete with transducer with 4-20 mA output signal proportional to
water pressure.
2.4.31.3 0.5% accuracy over entire sensing range.
2.4.31.4 Temperature range of 0 ⁰C to 38 ⁰C.
2.4.31.5 Transducer with easily accessible, integral non-interacting zero and span
adjustment.
2.4.31.6 Over pressure input protection of two times rated input.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 73 of 153
2.4.43.3 The RTD is 100 ohm Platinum Class A (100 ohm +/- 0.06 ohm @ 0⁰C.)
stainless steel sheathed element.
2.4.43.4 Four-wire RTD's compensate for resistance resulting from length.
2.4.43.5 The sensors must be a matched pair.
2.4.43.6 Provide thermowells for temperature sensors in compliance with the
following requirements:
a) Stainless steel probe length shall be at minimum 30% of the pipe
width.
b) Moisture/waterproof housing with conduit fitting.
c) Provide complete with thermal transfer compound inside thermal
well.
2.4.45.3 Shall have Density Compensation via Pressure and /or Temperature.
2.4.45.4 High Precision Temperature Sensors as specified in Section 2.4.13.
2.4.45.5 Must have Local digital display or external Flow Computer Unit.
2.4.45.6 The Local display or Flow Computer unit shall be programmable for
various flow meter types including linear, square root, multi-point
linearization or BTU data interpretation.
2.4.45.7 4-20ma flow input from Flow/Pressure transmitters.
2.4.45.8 This Display or Flow computer unit shall operate in an environment of
0⁰C to 50⁰C shall include a keypad for data input and retrieval, and an
LCD display.
2.4.45.9 Shall include an EEPROM/nonvolatile RAM.
2.4.45.10 Power supply shall be 24VDC or 24VAC.
2.4.45.11 The flow and BTU data accumulated shall be stored in a battery backed
data logger in continuous and periodic modes. Unit shall have a real time
clock and shall date stamp logged data. Unit shall have an RS-232 port
and shall be capable of setup from the keypad or laptop computer.
2.4.45.12 Provide all configuration software and licenses and all required interface
cables by the UofT Project Team.
2.4.45.13 The BTU Display/Flow computer supplier shall set up, commission and
verify BTU measurement and shall train UofT Project Team in all aspects
of BTU computer setup and operation.
2.4.45.14 BTU meter installation shall be complete including sensor wiring, power
wiring, coordination of flow meter installation in a pipeline, setup for
operation, labeling, commissioning with commissioning reports.
2.4.53.3 Valves supplied for steam service over 35 psig shall be provided with
stainless steel plugs and Teflon packing.
2.4.53.4 For steam capacities with modulating steam valves greater than 2000
lbs/hr, two valves shall be supplied and sequenced, one sized for 2/3 and
the other for 1/3 capacity.
The project consultant confirming that all the requirements in the Section 2.4 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 10
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 86 of 153
PART 3 - EXECUTION
3.1 INSPECTION
3.1.1 Examine areas and conditions under which control systems are to be installed. Do
not proceed with work until unsatisfactory conditions have been corrected in
manner acceptable to BAS Project Consultant.
3.1.2 It is the responsibility of the BAS Project Consultant to ensure the site and system
design criteria can be met and to bring to the attention of UofT Project Team any
conflicts or discrepancies before proceeding.
3.1.3 It is the responsibility of the BAS Project Consultant to inspect the project
documents and ensure all BAS equipment required to bring about the full intent of
these Standards is included in their design. This includes all cabling, connections to
the UofT LAN, LAN interface devices, network cabling between UofT LAN,
switches and all BAS devices as required. The BAS Project Consultant shall
coordinate with the UofT Project Team to ensure the design meets these Standards.
3.1.4 Arrange for Electrical Authority inspection of all electrical work. Arrange for a
separate inspection of any field assembled electrical panels or systems that have
not been preapproved by CSA/ULC. Submit the Certificate of Inspection and
Product Approval Certificate with the as-built documentation.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 88 of 153
3.3.2 BAS Contractor shall extend power to the control panel from an acceptable power
panel. If the control contractor wishes to further distribute panels to other locations,
control contractor is responsible for extending power to that location by providing
the required circuit breaker. Furthermore, the Project Consultant is responsible for
ensuring adequate locations for the panels that do not interfere with other
requirements of the project and maintain adequate clearance for maintenance
access.
as close to the room space sensor as possible. Coordinate with UofT Project Team
to clarify acceptable mounting locations.
3.4.2 For equipment located above the drop ceiling, controllers shall be unit mounted.
(Notify UofT Project Team if 1 m clearance in front of control panel has not
or cannot be provided.) Provide adhesive backed ceiling labels, affixed to ceiling
grid below all ceiling concealed controllers, affix to ceiling panel access door for
solid ceilings.
3.6.3 Project Consultant is responsible for the supply and installation of all devices,
software, communication devices, power supplies to bring metered data to the
EMRS.
3.6.4 Project Consultant shall verify the communication of all metered data from the
field level meter point to the EMRS is consistent, reliable and matches actual field
measured data.
3.6.5 Mount sensors securely. Mountings shall be suitable for the environment within
which the sensor operates.
3.6.6 Install sensors to properly sense the controlled medium.
3.6.7 Sensor locations shall be such that the instruments can be accessed for service and
removal.
3.6.8 Sensors mounted on water lines shall have isolation valves that shall enable the
sensor to be easily removed without the need to drain any lines or portions of lines.
3.6.9 Flow meters shall have 30 pipe diameters of straight pipe length upstream and 5
pipe diameters downstream of the flow sensing device or as per Manufacturers
OEM instruction or as accepted and approved by UofT Project Team
3.6.10 A flow straighter shall be installed where sufficient upstream pipe length is not
available.
3.6.11 When installed on Steam service the DP transmitter must be installed below the
flow sensing device.
3.6.12 The DP transmitter must be equipped with a five-way manifold.
3.6.13 Where supplied, meter local display to be installed at a height that allows it to be
read while standing on floor.
3.6.14 The display must have back light display capabilities.
3.6.15 On steam flow measurement a remote display may be permitted with approvals by
U of T Project Team.
3.6.16 Project Consultant to verify that the remote output reading matches the local
display.
3.6.17 Differential pressure transmitter lead sensing lines shall be ½ inch OD x 0.035 316
Stainless steel and Swagelok fittings. The lead sensing lines must be sloped
downward toward the transmitter at a minimum slope of 1 inch per foot. Minimize
the length of the lead sensing lines. The lead sensing lines must have isolation
valves at the flow sensing device.
3.6.18 The Lead sensing lines must have filling Tee’s installed at the isolation valves.
These Tee’s should be installed in a Bull-nose fashion.
3.6.19 When installed on Steam service a blow-down must be added to the Lead sensing
lines.
3.6.20 Display or Flow computer units shall operate in an environment of 0 ⁰C to 50 ⁰C
3.6.21 The meter must be installed in a clean pipeline, free from any foreign materials.
3.6.22 Condensate flow meters must have 10 pipe diameters upstream of the unit and 5
downstream to ensure proper flow through the meter. (Installation details to be
shown in approved Mechanical Drawings.
3.6.23 A condensate flow meter shall be installed on the line leaving the Condensate tank
returning back to the Central Steam Plant.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 91 of 153
It is the responsibility of the Project Consultant to ensure that the project design specifications
include the requirements below.
3.7.1 Project Consultant shall assume that existing equipment that specifically is
indicated to be reused is in good condition and is operable. Coordinate with UofT
Project Team for clarification of reusable equipment. Project Consultant, during
the course of work, shall inspect these devices and determine if any devices are in
need of replacement or repair. Project Consultant shall prepare an itemized list of
suggested repairs/replacement. This repair/replacement will be at the discretion of
the UofT.
3.7.2 Existing wire, conduit, and control panel cabinets may be reused at the UofT
Project Team discretion, but only if such materials or equipment comply with the
applicable specification for new materials and equipment. Such materials shall not
be reused if visibly damaged or otherwise unsuitable for the intended service.
3.7.3 Where such materials are reused, the contractor’s shop drawings shall reflect the
existing wiring designation. If existing labeling is illegible or otherwise does not
comply with the applicable specification for labeling, wiring runs shall be relabeled
in accordance with the requirements specified elsewhere.
3.7.4 Existing pneumatic tubing and tubing conduit located between the existing BAS
panels and the pneumatic operators may be reused as long as such materials
comply with the applicable specification for new materials. Materials shall not be
reused if visibly damaged or otherwise unsuitable for the intended service.
3.7.5 All pneumatic tubing to be reused shall be pressure tested and all leaks shall be
repaired. All reused pneumatic tubing shall be purged with dry air or nitrogen.
3.7.6 The existing pneumatic main air supply system shall be modified as required and
reused to serve existing pneumatic controls that are to remain, and shall be
extended as necessary to serve new pneumatic controls. Where existing pneumatic
controls are removed, main air piping shall be removed back to the point of
connection to the main air supply which remains in use, and shall be capped or
plugged.
3.7.7 Existing valves and dampers and their operators may be reused only when
preapproved by UofT Project Team. Contractor shall lubricate all damper linkages
of dampers being controlled under this project.
3.7.8 Other materials and equipment not specifically mentioned herein may be reused
only if specifically allowed by indications on the drawings and approved by UofT
Project Team.
3.7.9 For HVAC systems which are indicated to receive a new BAS, all existing
materials and equipment associated with the existing pneumatic controls and BAS
shall be removed unless otherwise specified or indicated to remain, or unless
reused in accordance with the above requirements, except for the following:
3.7.9.1 Conduit and electrical boxes (but not wiring within conduit) may remain in
place if not reused (leave a pull line);
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 92 of 153
3.7.9.2 Inaccessible pneumatic tubing may remain in place if not reused. Tubing
must be sealed and permanently labeled as “Abandoned in Place”.
3.7.9.3 Existing materials and equipment to be removed shall be removed subject to
the requirements in paragraph “Sequence of Work”. For HVAC systems,
which are not to receive a new DDC BAS, the existing pneumatic control
system shall remain fully functional.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 93 of 153
3.8.6 Perform all field testing and calibration that does not require connection of
permanent pneumatic outputs.
3.8.7 Remove remaining existing pneumatic and digital control system materials and
equipment (except materials to be reused in accordance with provisions specified
elsewhere). All existing digital controls equipment for those subsystems that have
not yet been converted shall remain intact, on-line, and fully functional.
3.8.8 Schedule work in University occupied spaces 10 working days in advance with the
University’s representative. Scheduling shall not be required for work in
equipment rooms, electrical closets, and similar service areas.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 94 of 153
3.10 COORDINATION
It is the responsibility of the Project Consultant to ensure that the project design specifications
include the requirements below.
3.10.1 Integrate and coordinate work under this section to controls and control devices
provided or installed by others.
3.10.2 Coordinate access to and integration of the BAS onto the EMRS with UofT Project
Team. Access to the F&S LAN is strictly controlled by UofT - IT. UofT - IT
requires a minimum of three (3) days’ notice for any LAN IP addresses or access.
Note: No contractor switches or LAN extenders will be permitted without express
and written approval by UofT - IT.
3.10.3 Each supplier of control product to configure, program, start-up and commission
that product to satisfy requirements of Sequence of Operation regardless of where
within contract documents product is described or specified.
3.10.4 Resolve compatibility issues between control product provided under this section
and those provided under other sections or divisions of this specification.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 95 of 153
3.17.1 When EMRS Integration and Commissioning Process has been completed
satisfactorily, the UofT Project Team will give approval for commencement of the
Acceptance Test.
3.17.2 Notify UofT Project Team in writing 2 weeks prior to the testing date.
3.17.3 Furnish a new operator’s log book to building operators.
3.17.4 The Acceptance Test period shall be 21 days. Visit the site each morning, Monday
to Friday, to review the BAS operation and the building operators log book which
contains records of all problems experienced by the building operators, the point
object name and value and time and date of failure, and time of return to service.
During the first 14 days of the acceptance test, any operational failures due to
malfunction of wiring, controllers or Operator Interfaces, shall designate a restart
to testing for 21 days. Any failure of control devices shall be corrected and the
acceptance test shall continue from the date the failure has been corrected. During
the last 7 days of testing, no failures of any kind will be accepted, or the last 7 days
shall be repeated.
3.17.5 The BAS shall not be accepted or handed over until the Acceptance Test is
successfully completed.
3.17.6 Verify the overall networked system performs as specified.
3.17.7 Commissioning is to be in coordination with U of T Project Team Commissioning
Standards.
3.17.8 Carry out end-to-end checks for all control points, verifying their proper operation.
End-to-end checks are defined as VISUAL confirmation that an input or output
signal from the DDC system results in correct operation of physical system
components, not assumed operation as implied by output status indicated on
system interface screens or graphics. Produce documentation indicating the date
and results of all end-to-end checks, including calibration factors entered.
3.17.9 Subsystems not controlled electronically shall also be tested and commissioned.
3.17.10 At the successful completion of the Acceptance Test, provide a certificate of
completion.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 100 of 153
3.19.2 IMPLEMENTATION
3.19.2.1 Direct integration between EMRS and embedded non-compliant BACNET
controls components is not allowed.
3.19.2.2 It is full responsibility of the BAS vendor to identify the compliance level
of the embedded non-compliant BACNET controls components.
3.19.2.3 The compliance level must be approved by the UofT BAS Project Team
3.19.2.4 The non-compliant BACNET controls component that is serving a critical
mechanical system(s) must have implemented the fully functional and
alarmed Device Status heartbeat and watchdog algorithm. This will allow
to monitor that status of the non-compliant BACNET controls component.
This must be implemented for the critical BAS applications like chillers,
fume hoods, labs identified in written by UofT Project Team.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 102 of 153
The project consultant confirming that all the requirements in the Section 3.19 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 11
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 104 of 153
3.20.2 DEFINITIONS
Term Definition
BAS Building Automation System
BACnet The BACnet Instance number is a unique number associated with each BACnet object
Instance
Numbers
BACnet The precise definition of the constructs and rules needed for creating BACnet objects.
Metamodel
Definitions
Building The entire Distributed Digital control system as applied to a specific project or building, each
Automation BAS is integrated into the EMRS.
System (BAS)
Basis of Design Documentation of the primary thought processes and assumptions behind design decisions that
(BOD) were made to meet the owner's project requirements (OPR). The basis of design describes the
systems, components, and methods chosen to meet the OPR.
BAS Controller A fully programmable device capable of carrying out a number of tasks including controlling and
monitoring via direct digital control (DOC) of specific systems, acting as a communications router
between the F&S LAN and serial fields busses, and data storage for trend information, time
schedules, and alarm data.
Calibration The acceptable variation in instrument indication for a given input, for which no adjustment is
Tolerance required. The CTL is derived from the Instrument Manufacturers Limits. The CTL is within the
(CTL) Process Calibration Tolerance Limit of an instrument.
Change Any addition to, deletion from, or modification to an aspect material, facility, utility, equipment,
logic or practice within the scope of the Building Automation System (BAS). This differs from a
deviation due to unplanned events requiring temporary actions to be remediated to the initial
conditions prior to the unplanned event.
Commissioning An individual or company identified by an owner to lead the commissioning activity in the
Authority implementation of the Commissioning process.
(CxA)
End Device A device in the field that measures, monitors or controls connected to the BAS
Energy A Campus-wide administrative application level system provided by and maintained by F&S,
Management Each BAS is integrated to the EMRS.
and Reporting
System
(EMRS)
Functional A range of tests under actual load, conducted to verify the specific systems, subsystems,
Performance components and interfaces between the systems conform to given criteria.
Testing (FPT)
Human A device designed to enable humans to access the BAS and /or the EMRS by using a set of
Machine custom-built graphics.
Interface
(HMI)
Internet A numeric label assigned to each internet protocol capable device.
protocol (IP)
Address
Network A network device that connects devices together to a computer network
Switch
Operational Training of the individuals who use (owner), operate (facility personnel), or maintain (skilled
training trades, technicians, and engineers) using current versions of the commissioning documents
including operations and maintenance manuals. The training shall be designed specifically for
each group delivered both in the classroom and on-site.
Operation and A document that describes in lay terms, the operation of all systems and equipment in a facility.
Maintenance An operations manual details modes of operation with associated diagrams to illustrate the
Manual sequence of operation for each system and interaction between systems. The maintenance manual
describes maintenance requirements and sequences, with the required bill of material.
Owner's A document that provides the explanation of the ideas, concepts, and criteria that are considered
Project very important to the owner. The OPR cites specific measurable goals for the owner's objective.
Requirement
(OPR)
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 107 of 153
Patch Panel A device with a number of ports between field environments and network (EMRS) switches
Process The maximum allowable deviation of a quality subject to the measurement of the true value
Calibration before there is an impact on the control of the process.
Tolerance
Limits(PCTL)
Service Tool A device capable of connecting to, or accessing a BAS or EMRS for service, upgrade, monitoring
or repair of the BAS.
Static The verification and documentation that all system elements are in accordance with the design
Verification requirements, correctly installed, connected and labeled with consideration for accessibility.
Start-up The verification that documentation is complete, sensors are calibrated, control wiring integrity
Verification checked, correct response of all points in the system verified with the correct response from all
end devices.
System EMRS Built-in Graphic User Interface that provides the basic information on the BAS and/or
Graphic Screen EMRS related to any particular BAS data object for the commissioning task only
F&S Project F&S Project team, consists UOFT F&S Operations, UOFT F&S IT, UofT F&S Commissioning
team Coordinator
UOT Project University of Toronto Project Stakeholders, which includes members of the F&S Project Team.
Team
Cx Team The Cx Team will include the F&S project team along with the Cx Authority, Design Engineer,
Project Manager and related contractors carrying out Commissioning of the system
Automation The Group consists of the Control technicians and the BMS Technicians.
and Control
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 108 of 153
3.20.3 STANDARDS
3.20.3.1 The following standards shall be referenced in conjunction with this
document.
3.20.3.1.1 University of Toronto -Building Automation Design Standard:
http://www.fs.utoronto.ca/wp-content/uploads/standards/bas/UofT_FS_BAS_Standard.pdf
3.20.3.2 Comply with rules and regulations of codes and ordinances of local,
provincial, and federal authorities, such codes and ordinances, when more
restrictive, take precedence over the Contract Documents.
3.20.4 PROCEDURE
3.20.4.1 General
3.20.4.1.1 The process has been described in stages in which required
deliverables and responsibilities throughout the project
development and implementation are defined. To ensure a smooth
transition through the sequential stages through the project it is
necessary that each stage’s deliverables be submitted and
accepted prior to entering the next stage.
3.20.4.1.2 The Cx Authority will be responsible to coordinate with all
stakeholders to develop the Cx schedule that will incorporate
these milestones and establish timelines as agreed by all
stakeholders.
3.20.4.3.3.1 The CxA shall review the documents from the commission
ability standpoint. In their review, they should clearly state
that the shop drawings have all required information for
commissioning of the BAS system including testing all
sequences of operation.
3.20.4.3.3.2 The CxA shall submit their comments in editable document.
3.20.4.3.3.3 The Design Engineer shall provide responses to each of the
CxA comments in the editable document. This document
shall be provided to F&S Project team with reviewed shop
drawings for their record.
We are in the preparation phase for the EMRS Bacnet Compliance Testing.
Below is the list of project(s) and the most current submittal of the mandatory documentation.
List of project(s):
<insert UofT Project Identification> ex. P001-19-123 Main Building BAS Retrofit)
IMPORTANT NOTE:
The attached documents must be reviewed by BAS Controls Contractor team as the documents will
be used for the EMRS Bacnet Compliance Testing. Since all the information was shared, it is
expected that the accuracy of the documentation will match the current on site installation.
It is the responsibility of the BAS Controls Contractor to provide the proper information.
Any discrepancy between the documentation and the actual status during the compliance test will
be flagged as FAILED.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 112 of 153
ACTIONS REQUIRED:
1. BAS Controls Contractor to provide the as-built drawings or the final markup drawings that
reflects the completed state of the projects. The network architecture drawings is sufficient
to show the B-BC and AAC/ASC device count and the .
2. BAS Controls Contractor to provide the final confirmation that the projects are Network
Ready and EMRS Ready.
a. Network Ready – YES --- NO
i. IP device can be pinged from the properly labeled patch panel based on the
document: < Wiring Installation Qualification Document >
b. EMRS Ready – YES --- NO
i. B-BC and ASC/AAC are configured with the Bacnet Instance numbers and
Bacnet Object names based on the document: < EMRS Bacnet
Implementation Metafile >
ii. B-BC has properly defined Alarm Notification Classes based on the UofT
BAS Standard
iii. B-BC and ASC/AAC have properly configured Bacnet Change of Value
properties for all Analog Inputs and Analog Outputs
3. BAS Controls Contractor to provide specific report “EMRS Bacnet Compliance Test
Readiness Form.docx” based on the template listed in the UofT BAS Standard on Page 127,
Section 3.21.3 must be provided.
4. BAS Controls Contractor to provide specific report “Project Points List EMRS Submittal
Form.xlsx” based on the template listed in the UofT BAS Standard on Page 130, Section
3.21.4 must be provided.
5. UofT F&S IT : On site EMRS Compliance Testing (Total of # B-BC controller) – expected
completion: up to 5 business days following EMRS Ready report
6. UofT F&S IT : Final Report (pending on the test results) – expected completion: up to 5
business days following EMRS Ready report
7. UofT F&S IT : EMRS Integration (alarms, history trends) - expected completion: up to 5
business days following the Final Report
8. UofT F&S IT : EMRS Integration GUI (pending the final commissioning report) - expected
completion: up to 6 weeks following the EMRS Integration
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 113 of 153
3.20.5 TRAINING
3.20.5.1 General
3.20.5.1.1 This section describes the Structure of the training requirements
for the UofT Operations Staff. It consists of four modules that are
to be conducted at two stages of the EMRS Integration Process.
The CxA will develop a course outline along with the contractor
using the training plan structure described below and include
training dates in Cx Schedule.
3.20.5.1.2 Stage 1 which includes Modules A, B and C is a prerequisite for
occupancy and/or the mechanical building systems handover.
3.20.5.1.3 Stage 2 which include Modules D can be subsequent to the EMRS
GUI programming stage, described in section 3.20.4.5.
Completed
Not Done
Ongoing
Design/ Pre- Basis Of Design Design UOT Project
tender Engineer
Team
Estimates of EMRS F&S Project
Design
Execution Team Engineer ,
UOT Design
All Deliverables should be complete before commencing next stage of this process*
Construction Shop drawings Project Design
Stage Consultant Engineer,
CxA
Reviewed as Design F&S Project
Noted/Approved Shop Engineer Team
drawings with CxA
Comments
Cx Functional Performance CxA Cx Team
Test Plan
Field Cx Documentation CxA F&S Project
a. Completed FPT Sheets team
b. Issues Log
c. Shop drawing Variances
d. Network Fluke test
Report(Installation
Checklist)
e. GUI Screen used for Cx
f. Updated BACnet point
summary complete with
details
g. TEC Submittal Package
(refer to Section 3.23)
h. EMRS Bacnet
Compliance Test
Readiness Form (refer to
Section 3.20.4.3.6.1.8)
Verification Documentation F&S Project Cx Team
team
As Built Documentation BAS Cx Team
Contractor
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 119 of 153
The project consultant confirming that all the requirements in the Section 3.20 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 12
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 121 of 153
The following are the mandatory wiring requirements for the physical layer networking:
1. The CAT6 cable must be labeled on both ends with the following label syntax: TO [name of
the location].
2. The CAT6 cable must be terminated on both ends with the RJ45 Female Modular connector
as per the pictures below.
3. The RJ45 connector must be fully compliant with the patch panel and it is the installer’s
responsibility to use the RJ45 connector that properly fits the patch panel.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 124 of 153
Device Fluke Digital Picture(s) of the device with the Digital Picture(s) of the device cable label Digital Picture(s) of the patch panel Digital Picture(s) of the patch panel Date / Initials
Name Report wall module module cable label
Cable ID Label: Label: Label: Label:
Label: TO: Basement IT Room 44 Label: SIEMENS BAS Label: TO: Mech Rm20, Basement, HTG/CLG
111DDC02
The above document is attached in the UofT FS_BAS_Standard.pdf file as the PDF attachment
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 125 of 153
The LINKWARE Fluke Report must be provided as per the following template. Cable ID must
correspond with the Cable ID record from the Installation Checklist.
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 126 of 153
3.21.3 EMRS BACnet Compliance Test Readiness Form – Vendor Specific Template for B-BC controllers (ETHERNET Interface only)
IMPORTANT NOTE: The content of all the screenshots must be easily read. Failure to provide properly captured and easy to read screenshot will result in a delay of the approval process.
HONEYWELL (HBS)
Device Fluke Digital Picture(s) of the device TELNET session indicating Digital Picture(s) of the device TELNET session indicating Digital Picture(s) of the device TELNET session indicating Date / Initials
Name Report the current system time and TCP IP settings: the PORT CONFIGURATION INFORMATION the CONTROLLER DEVICE INFORMATION
Cable ID
EXAMPLE: 005_DDC01 01-MAR-
005_DDC01 2019, AB
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 127 of 153
SIEMENS (SBT)
Device Fluke Digital Picture(s) of the device TELNET session indicating the TCP IP settings: Date /
Name Report Initials
Cable ID
EXAMPLE: 08s 01-MAR-
080_DDC03 0_DDC03 2019, AB
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 128 of 153
The above document is attached in the UofT FS_BAS_Standard.pdf file as the PDF attachment
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 129 of 153
3.21.4 Project Points List EMRS Submittal Form – Specific Template for B-BC controllers (ETHERNET Interface only)
The above document is attached in the UofT FS_BAS_Standard.pdf file as the PDF attachment
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 130 of 153
VICTORIA UNIVERSITY
501 - Victoria College
502 - Emmanuel College
503 - Birge-Carnegie Library
504 - Burwash Hall
505 - Victoria Men's Resdence
506 - Annesley Hall
507 - Wymilwood
508 - Margaret Addison Hall
509 - Isabel Bader Theatre
513 - Stephenson House
514 - E.J. Pratt Library
515 - Northrop Frye Hall
518 - Rowell Jackman Hall
524 - 110 Charles St. West
528 - Lillian Massey
575 - Knox College
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 138 of 153
TRINITY COLLEGE
600 - Trinity College
601 - Chapel
602 - Gerald Larkin Building
603 - George Ignatieff Theatre
608 - St. Hilda's College
675 - Wycliffe College
970 - Clarke Institute
ABBREVIATION DESCRIPTION
AHU#; - AIR HANDLING UNIT
ALN#; - AUTOMATION LEVEL NETWORK
AMMICEPLT#; - AMMONIA ICE PLANT SYSTEM
ATS#; - AUTO TRANSFER SWITCH SYSTEM
BIOHLAB#; - BIOHAZARD LABS SYSTEM
BLR#; - BOILER SYSTEM
BLN#; - BUILDING LEVEL NETWORK
CTRAIR#; - CONTROL AIR SYSTEMS
CAV#; - CONTSTANT AIR VOLUME TERMINAL BOX CONTROL SYSTEMS
CHLR#; - CHILLER SYSTEM
CHLW#; - CHILLED WATER SYSTEM
CLDRM#; - COLD ROOM OR LAB COOLING SYSTEM
CLGPLT#; - COOLING PLANT SYSTEM
CLGTWR#; - COOLING TOWER SYSTEM
CGW#; - CAGE WASHING SYSTEMS
COMPARE - COMPRESSED AIR SYSTEM
CDNW#; - CONDENSER WATER SYSTEM
CNDP#; - CONDENSATE PUMP SYSTEMS
COR#; - CORRIDOR/HALLWAY CONTROL POINTS
DCW#; - DOMESTIC COLD WATER SYSTEM
DHW#; - DOMESTIC HOT WATER SYSTEM
DX#; - DIRECT EXPANSION SYSTEMS (The # is stage #)
EMGEN#; - EMERGENCY GENERATOR SYSTEM
FA#; - FIRE ALARM SYSTEM
FAN#; - MISCELLANEOUS & GENERAL PURPOSE FANS
FCU#; - FAN COIL UNITS
FREECLG#; - FREE COOLING SYSTEM
FLN#; - FLOOR LEVEL NETWORK
FUELOIL#; - FUEL OIL SYSTEM
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 139 of 153
ABBREVIATION DESCRIPTION
AFM#; - AIR FLOW METERING DEVICES
AFS#; - AIR FLOW SWITCH DEVICES
AIRCOMP#; - AIR COMPRESSOR
AIRX#; - AIR CHANGES
ALM#; - ALARM
AMP#; - AMPERAGE
ANALZ#; - ANALYSOR
AUTO#; - AUTOMATIC
AVG#; - AVERAGE
BAT#; - BATTERY
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 140 of 153
SS#; - START/STOP
START#; - START (COMMAND ONLY)
STOP#; - STOP (COMMAND ONLY)
STS#; - STATUS
STBY#; - STANDBY DEVICES
STM#; - STEAM DEVICES
STMFL#; - STEAM FLOW
STMGEN#; - CLEAN STEAM SYSTEMS
STMHX#; - STEAM HEAT EXCHANGER SYSTEM
SURGYVACS#; - SURGERY VACUUM AIR SYSTEM
SWIMPL#; - SWIMMIMING POOL
TEC#; - TERMINAL EQUIPMENT CONTROLLER
TIMEDLY#; - TIME DELAY
TEMP#; - TEMPERATURE
TIME#; - TIME CONTROL UNITS
TOT#; - TOTALIZED VALUE OR TOTAL
TT#; - TEMPERATURE TRANSMITTTER
ULTRSFLOM#; - ULTRA SONIC FLOW METER
UVLIT#; - ULTRAVIOLET LIGHT
VANDAMP - VANE DAMPER
VEN#; - VENTURI
VP#; - VELOCITY PRESSURE
VFD#; - VARIBLE FREQUENCY DRIVE OUTPUT SIGNAL
VTXFLOM#; - VORTEX FLOW METER
VLV#; - VALVE
WEST; - WEST
WD#; - WATER DETECTOR
#; - IDENTIFICATION NUMBERS
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 145 of 153
The project consultant confirming that all the requirements in the Section ‘PART 3 EXECUTION’
of this document have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 13
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 146 of 153
In order to complete the EMRS Bacnet Compliance Test, the BAS vendor shall submit the digital
version of the Bacnet Point Matrix for every Bacnet MSTP Terminal Equipment Controller (TEC)
that is connected and integrated to the EMRS Bacnet communication layer (IP, MSTP). TEC
includes any ASC or AAC controller used in the project.
Below is the screenshot of the digital file (Excel XLSX) that is expected to be submitted:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 148 of 153
In order to complete the EMRS Bacnet Compliance test, the BAS vendor shall submit the digital
version of the Bacnet Field Layer Network Schedule with the list of all the MSTP controllers and
their association with the routed networks and B-BC controllers.
Below is the screenshot of the digital file (Excel XLSX) that is expected to be submitted:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 150 of 153
The project consultant confirming that all the requirements in the Section 3.23 of this document
have been incorporated in the project’s Design Specification documentation.
☐ YES, all the requirements in this section have been incorporated in the Design Specification.
☐ NO, the requirements in this section haven’t been incorporated in the Design Specification.
☐ N/A, the requirements in this section are not applicable for the project the DS.
The project consultant to provide the cross-reference between the sections in the Building
Automation and Energy Systems Design Standard and the Project Design Specification:
Building Automation and Energy Systems Project Design Specification
Design Standard
Ex. 2.3 22.13
CHECKLIST 14
Date: Consulting Engineer: Signature:
University of Toronto Facilities and Services
Building Automation and Energy Systems Design Standard
Revision: 6 [May 2019] Page 152 of 153