Calculation Sheet
Calculation Sheet
0
Structural Design of Steel Truss Bridge
1.1 Basis
Basic design criteria have been prepared with a view to satisfy all the relevant technical requirements specified in the
contract.
The Bridge consists of 3 span seel truss bridge 72 m ,72m and 62 m c/c over RCC Pier with cantilever pier caps &
abutments.
1.3 Material :
a) Grades of concrete are as follows:
i) Foundation =M35
ii) Substructure =M35
iii) Superstructure Deck = M40
iv) Pedestal, crash barrier =M40
b) Grade of Reinforcement Fe 500
c) Grade of Structural Steel E410 BO
1.4 LOADS :
a) Unit Weight of Materials :
i) Unit weight of PSC super structure = 25 kN/m3
ii) Unit weight of RCC substructure & foundation = 25 kN/m3
iii) Unit weight of Structural steel = 78.5 kN/m3
iv) Unit weight of Wearing course = 22 kN/m3
v) Unit weight of Earth = 19 kN/m3
Self weight of Steel composite girder have been considered for design of superstructure. In addition of self weight of
superstructure, self weight of substructure & foundation have also been considered in design of substructure &
foundation respectively.
1 of 221
h) Seismic Load (EQ)
Earthquake Loads has been calculated as per IS:1893 and IRC: 6-2014. Project is located in earthquake
zone IV. Horizontal seismic forces has been computed as per clause no. 219.2 of IRC : 6-2014 for zone IV .
z = zone factor = For Zone III = 0.16 I = Importance factor = 1.20
R = Response Reduction factor = 2.50 Sa/g = = 2.50
q) Buoyancy (Gb)
Buoyancy is calculated as per clause no. 213 of IRC:6-2014 for water at HFL.
At HFL condition, earth pressure shall be reduced due to submerged unit wt of earth, dead load
of sub-structure & foundation.
2 of 221
3 (b) 1 1 1.1 or 0.9 1 0.6
4 (a) 1 1.2 1.1 or 0.9 0.75 1
4 (b) 1 1 1.1 or 0.9 0.75 1
5 (a) 1 1.2 1.1 or 0.9 1 0.6
5 (b) 1 1 1.1 or 0.9 1 0.6
6 (a) 1 1.2 1.1 or 0.9 0.75 1
6 (b) 1 1 1.1 or 0.9 0.75 1
1.5 Arrangement
The total length of Bridge is 206 m (2x72 m+1x62 m ) .Steel Truss over RCC piers/abutments and cantilever pier caps
on RCC pile foundation .For three lane bridge with footpath ,total width of carriageway is 13 m and total width of deck
slab is 16 m . POT-PTFE bearing and metalic guide bearing has been proposed to protect the superstructure from live
load breaking ,centrifugal force and seismic .
1.6 Analysis
All analysis and design has been carried out using MIDAS Civil software .
. SIDL, Live load have been done by MIDAS software Calculation of deflection has been done
by software . Forces & moment and design of abutment & its foundations have
been done by excel spreadsheet.
3 of 221
1.7 Construction Methodology
Foundation
For abutment and pier location ,Pile foundation shall be provided .
Substructure
RCC cast-in-situ pier and abutment shall be cast over pile cap .The pedestal and seismic restrainer shall be cast over
pier cap .Pot cun PTFE shall be placed over pedestal before erection of steel girder .
Superstructure
All steel truss memeber and besm shall be erected at bearing level by launcing nose a .
4 of 221
2.0 General Design Inputs
A Details of Span
Centre to centre distance of pier = 50.00 m
Distance between c/l of bearing end of girder = 0.50 m
Distance between c/l of bearing and c/l of expansion joint = 0.85 m
Effective Span of Girder = 48.30 m
5 of 221
Depth of web after curtailment of flange thickness = 2750.00 mm
Thickness of web after curtailment of flange thickness = 18.00 mm
Depth of web at support = 2762.00 mm
Thickness of web at support = 18.00 mm
Bottom Flange
Width of bottom flange at mid span = 850.00 mm
Thickness of bottom flange at mid span = 36.00 mm
Width of bottom flange at support = 850.00 mm
Thickness of bottom flange at support = 28.00 mm
F Details of End Cross Girder
Width of Top flange at span = 350.00 mm
Thickness of top flange at mid span = 18.00 m
Depth of web at mid span = 2525.00 mm
Thickness of web at mid span = 18.00 mm
Width of Bottom Flane at Mid span = 350.00 mm
Thickness of bottom flange at mid span = 18.00 mm
I Material Data
Grade of Steel conforming to IS :2062 = E410 BO 540
Grade of Concrete of Deck Slab = = M40
Grade of HYSD bar = =Fe 500
Creep factor for long term loading [ Cl.604.2.4 of IRC 222-2008] = = 0.50
Short term Elastic Modulus of concrete [ Cl 303.1 of IRC 21-2008] Ecs = 3.33E+04 N/mm2
Long term Elastic Modulus of concrete [ Ecl =0.5 Ecs] = 1.67E+04 N/mm2
Elastic Modulus of Steel Es [ Cl 502.2.2.1 of IRC 24-2010] = 2.00E+05 N/mm2
Short term modular ratio for transient loading ms= Max (Es/Ecs,7.5) = 7.5
Long term modular ratio for transient loading ml= Max (Es/Ecl,15) = 15
[Cl 604.2.4 of IRC 22-2008]
6 of 221
Shear stress in power driven field rivets 0.40 fy = 164 156 N/mm2
Bearing stress in power driven field rivets 0.90fy = 369 351 N/mm2
65 thk w/c
0.250
G1 G2 G3 G4
Center of Symmetry
0.000 0.000
0.85 48.30
50.00
0.500
Section Y-Y
7 of 221
X
1.5
Y Y
Longitudinal girder
12.000
3
3
Cross Girder
1.5
X
0.850 48.30
50.00
Plan
8 of 221
3.0 Sectional properties of Steel Girder and Composite Girder
Thickness of Web
When transverse stiffener are not required as per Cl .No. 509.6.11a of
IRC 24-2010 =
Thckness of web plate without any stiffener plates d/tw < 200 ԑw d= 2750 mm
ԑ = (250/fy)1/2 = 0.78
tw > 17.61 mm
Asp per Cl No.509.6.1.1 b (i) of IRC 24-2010 When 3d >c>d d/tw < 200 ԑw
Asp per Cl No.509.6.1.1 b (ii) of IRC 24-2010 When d >c>0.74d c/tw < 200 ԑw
Asp per Cl No.509.6.1.1 b (i) of IRC 24-2010 When c<0.74d d/tw < 270 ԑw
c= clear panel = = 1800 mm
tw = 11.526 mm
9 of 221
3.1 Sectional properties of Precast Longitudinal Girder : At Mid Span
3 m
0.75 m
0.25
0.1
0.032
0.55
1.3700
1.37
0.85
0.036
∑I0 +AY2-
Moment of Inertia IZ = ∑AY2 = 0.2352 m4
Torsional Constant Ix = ∑1/3*X*Y 3
= 1.08E-03 m4
10 of 221
∑I0 +AY2- 0.1213
Moment of Inertia IZ = ∑AY2 = m4
Torsional Constant Ix = ∑1/3*X*Y3 = 2.46E-05 m4
A. Section properties of Composite Section for short Term Modular Ratio (in equvalent of steel )
B Section properties of Composite Section for lONG Term Modular Ratio (in equvalent of steel )
Zpz = 0.188636 m3
Zpy = 0.01199 m3
11 of 221
4.0 Calculation of Load
A Dead Load During Construction
Dead Load will be carried by beam acting alone with no composite action
Steel Girder Alone
Unit weight of structural steel = 78.5 kN/m3
Cross sectional area of girder (Near Mid span) = 0.09752 m2
Considering 20% extra for stifener and splices = 9.186384 kN/m
Self weight of girder at Mid span
12 of 221
Outer girder G4 = 2.500 m = 3.575 kN/m 0.25 m
P = (P/-260 +4800/L)(16.5-W)/15
P/ = Live load in kg/cm2 as per sub clause 209.1 of IRC :6 = 500 kg/cm2
P = Live load in kg/cm2
L = Effective Span of main girder in m = 48.3 m
W = Width of footpath in m = 1.5 m
P = 339.379 kg/cm2
13 of 221
Hence pedestrian Live Load = 5.091 kN/m
CG form the extreme end for footpath side stringer = 0.15 m
Torsion Due to eccentricity = 0.764 kN/m/m
(For slab bridge, C D =1.1, For Single beam/Box girder, C D =1.5 for b/d<=2.0, C D =1.3 for b/d>=6.0 and inbetween interpolated C D to be considered)
G = Gust Factor (If Span<=150, G=2, Otherwise Wind tunnel testing required) = 2.0
CL = Lift coefficient = 0.75
14 of 221
4.3 Wind load on Unloaded structure
a) Wind load on Superstructure
Vb = design wind speed at any height = 55 m/s
Bridge situated in : = Plain Terrain
As per note no. 5 of cl no. 209 of IRC :6-2014, wind pressure shall be i 20 %
Wind Speed & design wind pressure for Basic wind speWind speed & design wind pr. for Basic wind speed of 55m/s
H Plain Terrain Terrain with Obstructions H Plain Terrain Terrain with Obstruct
(m) Vz (m/s) Pz (N/m ) 2
Vz (m/s) Pz (N/m ) 2
(m) Vz (m/s) Pz (N/m ) Vz (m/s) Pz (N/m2)
2
15 of 221
Vertical wind Force FV = 658.7 kN udl = 1.098 kN/m2
UDL on girder Outer udl = 3.29 kN/m
Inner udl = 3.29 kN/m
Outer udl = 3.29 kN/m
16 of 221
4.5
i) Single Lane 70-R Track Loading
0.84
2.06 2.9
0.84
0.914 0.914 0.914 0.914 0.914
4.57
3.656
12.00
0.50 9.00 0.50 1.500 0.5
2.9
1.2 0.84 0.84
13.4
18.80
17 of 221
12.00
0.50 9.00 0.50 1.500 0.5
0.4
1.8 1.7 1.8
4.6
1) Dead load +SIDL+Live load
2) Dead load +SIDL+ wind load (unloaded structure)
3) Dead load +SIDL+Live load(lead) + wind load (accompany) (loaded structure)
4) Dead load +SIDL+Live load(accompany) + wind load(lead) (loaded structure)
5) Dead load +SIDL+construction Live load(leading) + wind load(accompany)
Load Case DL SIDL Live load Wind load
1 1.35 1.75 1.5
2 (a) 1.35 1.75 1.5
2 (b) 1 1 1.5
3 (a) 1.35 1.75 1.5 0.9
3 (b) 1 1 1.5 0.9
4 (a) 1.35 1.75 1.15 1.5
4 (b) 1 1 1.15 1.5
5 (a) 1.35 1.75 1.35 0.9
5 (b) 1 1 1.35 0.9
1(a) 1 1.2
1(b) 1 1
2 (a) 1 1.2 1
2 (b) 1 1 1
3 (a) 1 1.2 1 0.6
3 (b) 1 1 1 0.6
4 (a) 1 1.2 0.75 1
4 (b) 1 1 0.75 1
5 (a) 1 1.2 1 0.6
5 (b) 1 1 1 0.6
6 (a) 1 1.2 0.75 1
6 (b) 1 1 0.75 1
18 of 221
5 Calculation of Load due to Shrinkage and Temperature Gradient
A Outer Girder
(i) Computation of Stresses due to differential shrinkage modified by creep
Diferential shrinkage occurs between the prefabricated steel girder and in-situ concrete deck slab and this results the
development of internal stresses
Force developed due to restaint of deck Fi = hi*bi*E*ɸ*ԑds
The efect of diferential shrinkage will be reduced by creep .Allowance is made for this in calculation by using a
rdction coefficient ,ɸ
At
At Mid
Splice
Span
point
Diferential shrinkage strain [Cl .220.3 of IRC :6-2006] ԑds = 0.0002 0.0002
The Creep modification factor [Cl.604.2.4 of IRC 22-1986] ɸ 0.5 0.5
Total height of the girder 3.17 3.17 m
Distance of long term N.A from top of deck 1.297 1.213 m
M.O.I of Section 0.2352 0.2105 m4
Area of the section 0.152 0.134 m2
Long term Elastic modulus of concrete ### 1.67E+07 kN/m2
Modulus of Elasticity of Steel ### 2.00E+08 kN/m2
Long term section modulus at the top of slab 0.1813 0.173486 m3
Long term section modulus at the top of girder 0.248273 0.243829 m3
Long term section modulus at the bottom girder 0.125757 0.107671 m3
-0.002
1 0.25 h1 = 0.25 m
h2 = 0.1 m
2 0.1
m m kN/m2 kN m m kNm
1 0.25 3 1.67E+07 -2499.78 0.125 1.172 -2930.93
2 0.1 0.75 1.67E+07 -249.98 0.3 0.997 -249.347
### -3180.3
Stress Final
Stress Final
Due to Equivale
Assumed End Due to Equivale
Release nt
Restrained Axial nt steel
of concret
Force Stress
Moment eStress
Section
19 of 221
At Splice Section
y from
h b E Force
top
e Moment
Segment
m m kN/m2 kN m m kNm
1 0.25 3 1.67E+07 -2499.78 0.125 1.088 -2720.27
2 0.1 0.75 1.67E+07 -249.98 0.3 0.913 -228.281
### -2948.5
Stress Final
Stress Final
Due to Equivale
Assumed End Due to Equivale
Release nt
Restrained Axial nt steel
of concret
Force Stress
Moment eStress
Section
B Inner Girder
(i) Computation of Stresses due to differential shrinkage modified by creep
Diferential shrinkage occurs between the prefabricated steel girder and in-situ concrete deck slab and this results the
development of internal stresses
Force developed due to restaint of deck Fi = hi*bi*E*ɸ*ԑds
The efect of diferential shrinkage will be reduced by creep .Allowance is made for this in calculation by using a
rdction coefficient ,ɸ
At
At Mid
Splice
Span
point
Diferential shrinkage strain [Cl .220.3 of IRC :6-2006] ԑds = 0.0002 0.0002
The Creep modification factor [Cl.604.2.4 of IRC 22-1986] ɸ 0.5 0.5
Total height of the girder 3.17 3.17 m
Distance of long term N.A from top of deck 1.660 1.580 m
M.O.I of Section 0.1037 0.0899 m4
Area of the section 0.122 0.108 m2
Long term Elastic modulus of concrete ### 1.67E+07 kN/m2
Modulus of Elasticity of Steel ### 2.00E+08 kN/m2
Long term section modulus at the top of slab 0.115024 0.109456 m3
Long term section modulus at the top of girder 0.187978 0.190701 m3
Long term section modulus at the bottom girder 0.068782 0.056609 m3
-0.002
1 0.25 h1 = 0.25 m
h2 = 0.1 m
2 0.1
20 of 221
At Mid Section
y from
h b E Force
top
e Moment
Segment
m m kN/m2 kN m m kNm
1 0.25 3 1.67E+07 -2499.78 0.125 1.535 -3836.77
2 0.1 0.75 1.67E+07 -249.98 0.3 1.360 -339.931
### -4176.7
Stress Final
Stress Final
Due to Equivale
Assumed End Due to Equivale
Release nt
Restrained Axial nt steel
of concret
Force Stress
Moment eStress
Section
At Splice Section
y from
h b E Force
top
e Moment
Segment
m m kN/m2 kN m m kNm
1 0.25 3 1.67E+07 -2499.78 0.125 1.455 -3636.01
2 0.1 0.75 1.67E+07 -249.98 0.3 1.280 -319.855
### -3955.9
Stress Final
Stress Final
Due to Equivale
Assumed End Due to Equivale
Release nt
Restrained Axial nt steel
of concret
Force Stress
Moment eStress
Section
21 of 221
(ii) Computation of Stresses due to Rise in Temperature
At
At Mid
Splice
Span
Point
Total Height of the girder h = 3.168 3.17
Distance of short term N.A from top of deck Yts = 1.423 1.35
M.O.I of the section I = 0.126 0.1072
Area of the Section A = 0.177 0.1631
Short term Elastic modulus of concrete Ecs = 3.33E+07 ###
Modulus of Elasticity of Steel Es = 2.00E+08 ###
Coefficient of Themal Expansion of Concrete α = 1.17E-05 1.17E-05
Short term section modulus at the top of slab Zts = 0.190 0.181183
Short term section modulus at the top of girder Ztg = 0.400 0.443387
Short term section modulus at the bottom of girder Zb = 0.072 0.058979
19.25
1 4 0.21 h1 = 0.21 m
h2 = 0.04 m
2 3.70 h3 = 0.10 m
0.04 h4 = 0.028 m
3 2.96 h5 = 0.372 m
0.10
4 2.76 T1 = 19.25 0
C
0.028 T2 = 4 0
C
T3 = 0 0
C
5
0.372
0.540
At Splice Point
Average Y form
h b E t Force e Moment
Segment Temp Top
m m kN/m 2 0
C 0
C kN m m kNm
1 0.21 3 3.33E+07 19.25 11.6 2856.012 0.08204 1.2678 3620.873
2 0.04 3 3.33E+07 4.00 3.9 180.251 0.22974 1.1201 201.900
3 0.10 0.75 3.33E+07 3.70 3.3 97.491 0.29815 1.0517 102.532
4 0.03 0.45 2.00E+08 2.96 2.9 84.302 0.36383 0.9860 83.124
5 0.37 0.016 2.00E+08 2.76 1.4 19.189 0.50200 0.8479 16.270
3237 4024.70
22 of 221
Fianl
Fianl
Stress Due to Stress Due to Equivale
Assuming End Equivale
Release of Axail Release of nt
Restrained nt Steel
Force Moment Concrete
Stress
Stress
Section
EαT -P/A -M/Z σ σ/m
-5.6
1 h1 = 0.21 m
0.21 h2 = 0.14 m
h3 = 0.028 m
0.14 h4 = 0.372 m
h5 = 2.386 m
h6 = 0.032 m
0.028
-0.6 T1 = -5.6 C
0
0.372 T2 = 8 C
0
-8
2.386
-8
0.032
-8
( As per Fig No 10(b) of IRC :6-2014
At Mid Span
Average Y form
h b E t Force e Moment
Segment Temp Top
m m kN/m 2 0
C 0
C kN m m kNm
1 0.21 3 3.33E+07 -5.60 -2.8 -687.900 0.07000 1.353 -930.9
2 0.028 0.45 2.00E+08 -0.56 -0.3 -8.256 0.369 1.055 -8.7
3 0.372 0.016 2.00E+08 -8.00 -4.3 -59.610 0.618 0.805 -48.0
4 2.386 0.016 2.00E+08 -8.00 -8.0 -714.655 1.943 -0.520 371.5
5 0.032 0.7 2.00E+08 -8.00 -8.0 -419.328 3.152 -1.729 725
-1890 108.83
At Splice Point
Average Y form
h b E t Force e Moment
Segment Temp Top
m m kN/m2 0
C 0
C kN m m kNm
1 0.210 3.0000 3.33E+07 -5.600 -2.8 -687.900 0.07000 1.2799 -880.409
2 0.028 0.4500 2.00E+08 -0.560 -0.3 -8.256 0.36867 0.9812 -8.100
3 0.372 0.0160 2.00E+08 -8.000 -4.3 -59.610 0.61789 0.7320 -43.633
4 2.386 0.0160 2.00E+08 -8.000 -8.0 -714.655 1.94300 -0.5931 423.897
5 0.032 0.7000 2.00E+08 -8.000 -8.0 -419.328 3.15200 -1.8021 755.692
-1890 247.45
23 of 221
Fianl
Fianl
Stress Due to Stress Due to Equivale
Assuming End Equivale
Release of Axail Release of nt
Restrained nt Steel
Force Moment Concrete
Stress
Stress
Section
EαT -P/A -M/Z σ σ/m
24 of 221
6.0 Calculation of Flexural Stress at Splice Point of Outer Girder (G1) = m
6.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
25 of 221
b/tf = 8.31 > 8.4ԑ = 6.73
> 9.4ԑ = 7.53
< 13.6ԑ = 10.9
Hence section is Semi Compact
d/tw = 156.55556 > 126ԑ = 98.4
Hence section is Selender
Hence a part of web section is efective for making the section is Semi-Compact .Efective Depth d= 1771 mm
This section is Semi-Compact
Hence ,the section is Semi -Compact for Shear and the section is Semi-compact for Bending
6.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.06
26 of 221
ϒm0 = 1.1
fbd = 355 N/mm 2
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
172 258
27 of 221
tw = Thickness of Web = 18 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = Av ꚍ v = 4152 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 4545664.332 N
Mtf = 22138838.49 N-mm 15733277
ɸ= 44.5349 Degree
28 of 221
MOI of the compressive flange aboyt Y axis at Max BM zone ,I 1 = 4.44E-04 m4
MOI of the both the flange aboyt Y axis at Max BM zone ,I 2= 2.29E-03 m4
Ratio of the compression flange to the sum of MOI of each flange = β = 0.194
Coefficient associated with β k2 = -0.62 [ Table G.7.of IRC 24-2010]
Effective Length of compression flange L = 4.63 m
MOI of minor axis Iy = 1.13E-03 m4
Cross sectional area of steel girder A = 0.0975 m2
Radius of Gyration of Minor Axis ry = 0.1075 m
Selenderness ratio λ = 43.05 <300
Overall Depth of Beam D = 2.818 m
Mean thickness of compression flange T = 0.032 m
Coefficient y = 26.5x105/λ2 = 1429.8 N/mm2
Coefficient x = y[1+1/20*(λT/D)2]^(1/2) = 1438.4 N/mm2
Lesser distance of extreme fibre from NA C1 = 1.225 m
Greater distance of extreme fibre from NA C2 = 1.593 m
Thickness of Web tw = 0.018 m
Thickness of compression flange to web ratio T/tw = 1.77777778
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 152.777778
Elastic critical stress fcb = 703 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 198.6 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy1/2d/t/4000{1+1/2(d/c)2}
if c>d
Hence permissible average shear stress in steel girder ꚍva = 121.9 N/mm2
OK
29 of 221
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 198.6
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Top of
Mid -1050 1899.000 370.19 -4.2 7.6 1.5 65.009 69.920 198.6
Girder
Span
Bottom of
8.35 -15.10 -2.94 -49.987 -59.682 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
30 of 221
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 7101.293 277.2 15.76 0.62 30.92 69.920 117.2 198.6
Girder
Span
Bottom of
-53.40 -2.08 -7.18 -59.682 -122.35 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 15.76 -13.35 30.92 69.92 103.25 < 198.6
Girder
Span
Bottom of
-53.40 24.41 -7.18 -59.68 -95.86 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 15.76 6.24 30.92 69.92 122.84 < 198.6
Girder
Span
Bottom of
-53.40 -3.923 -7.18 -59.68 -124.19 < -241.8
Girder
Hence ok
a) Load combination
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
31 of 221
Live load 1 1 0.75 0.75 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
Top of
52.7 13.8 -4.229 30.92 7.649 15.76 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -15.101 -53.40 -6.738 -3.4743 40.679 -6.54
Girder
Top of
0.684 1.1 0.954 4.06 3.918 3.33 3.191 4.2726 4.133
Slab
Top of
92.786 94.8 93.245 109.16 107.632 105.63 104.102 95.1952 93.665
Girder
Bottom
of -67.614 -74.4 -71.332 -123.10 -120.080 -111.14 -108.120 -96.6088 -93.589
Girder
32 of 221
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
3.7 3.549 3.69 3.551 2.72 2.579 4.2726 0.684 13.333 OK
Slab
Top of
82.4 80.825 114.79 113.259 115.01 113.481 115.0108 80.825 198.577 OK
Girder
Bottom
of -67.0 -63.967 -124.94 -121.919 -114.20 -111.183 -63.9667 -124.939 -241.800 OK
Girder
Thickness of Web tw = 18 mm
Comb 1 1 0.6
1
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
33 of 221
Total Deflection at service case = 82.71 mm > L/600 = 80.50
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
6. 6 Fatigue Check
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
=
A = 0.0015 m2
0.016*0.032+0.05*0.016
Y= 0.043 = 2.133 m
I= 0.011 = 0.0177899 m4
b = m
0.016
Fatigue strength is not required for f<27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
34 of 221
Total Number of Stress Cycle Nsc = 365NA = 3.65E+06 <5000000
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
35 of 221
6.0 Calculation of Flexural Stress at Splice Point of Outer Girder (G1) = m
6.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
36 of 221
Coefficient for Semi Compact = 126
6.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.05
37 of 221
XLT= 1.0 fy = 390
ϒm0 = 1.1
fbd = 355 N/mm 2
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
Type of Loading Description V Factor Vn
Erection Stage DL ,Con LL 1 1.35 1.35
Crash Barrier 7 1.35 9.45
Long Term Moment SIDL 3 1.75 5.25
Cons LL 0 1.35 0
Live LL+Snow
Short Term Load 158 1.5 237
Wind Load 0 0.9 0
Foot path LL 3 1.5 4.5
172 258
38 of 221
I) Resistance of Shear Buckling shall be verified as specified
d= Depth of effective Web = 1574 mm
tw = Thickness of Web = 16 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = Av ꚍv = 3280 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 2395911.047 N
Mtf = 36512718.23 N-mm 15733277
ɸ= 41.1721 Degree
39 of 221
C/s area of both flanges at the maximum BM zone A 1 = 0.0426 m2
C/s area of both flanges at the minimum BM zone A 2 = 0.027248 m2
Ratio of total area of both the flanges ,ψ = A 2/A1 = 0.64
Coefficient associated with ψ k1 = 0.98
[ Table G.6.of IRC 24-2010]
MOI of the compressive flange aboyt Y axis at Max BM zone ,I 1 = 3.88E-04 m4
MOI of the both the flange aboyt Y axis at Max BM zone ,I 2= 2.03E-03 m4
Ratio of the compression flange to the sum of MOI of each flange = β = 0.192
Coefficient associated with β k2 = -0.62 [ Table G.7.of IRC 24-2010]
Effective Length of compression flange L = 4.2 m
MOI of minor axis Iy = 1.13E-03 m4
Cross sectional area of steel girder A = 0.0975 m2
Radius of Gyration of Minor Axis ry = 0.1075 m
Selenderness ratio λ = 39.05 <300
Overall Depth of Beam D = 2.818 m
Mean thickness of compression flange T = 0.028 m
Coefficient y = 26.5x105/λ2 = 1737.6 N/mm2
Coefficient x = y[1+1/20*(λT/D)2]^(1/2) = 1744.1 N/mm2
Lesser distance of extreme fibre from NA C1 = 1.225 m
Greater distance of extreme fibre from NA C2 = 1.593 m
Thickness of Web tw = 0.016 m
Thickness of compression flange to web ratio T/tw = 1.75
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 171.875
Elastic critical stress fcb = 850 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 209.3 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy d/t/4000{1+1/2(d/c)2}
1/2
if c>d
Hence permissible average shear stress in steel girder ꚍva = 115.0 N/mm2
OK
40 of 221
Permissible Concrete Stress as per CL No.604.3.1 of IRC:22-2008 = 1/3*fck = 13.33 N/mm2
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 209.3
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Mid
Span
41 of 221
At
Top of
Mid -1050 988.003 370.19 -4.2 4.0 1.5 65.009 66.251 209.3
Girder
Span
Bottom of
8.35 -7.86 -2.94 -49.987 -52.438 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 4818.493 277.2 10.69 0.62 30.92 66.251 108.5 209.3
Girder
Span
Bottom of
-36.24 -2.08 -7.18 -52.438 -97.94 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 -13.35 30.92 66.25 94.51 < 209.3
Girder
Span
Bottom of
-36.24 24.41 -7.18 -52.44 -71.45 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 6.24 30.92 66.25 114.10 < 209.3
Girder
Span
Bottom of
-36.24 -3.923 -7.18 -52.44 -99.78 < -241.8
Girder
Hence ok
a) Load combination
42 of 221
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
Top of
52.7 13.8 -4.229 30.92 3.979 10.69 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -7.856 -36.24 -6.738 -3.4743 40.679 -6.54
Girder
43 of 221
Top of
0.282 0.7 0.619 2.61 2.539 2.15 2.073 2.8269 2.754
Slab
Top of
88.383 90.4 89.576 99.69 98.896 97.43 96.633 85.7258 84.930
Girder
Bottom
of -58.921 -65.7 -64.088 -97.24 -95.669 -89.57 -88.000 -70.7491 -69.178
Girder
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
2.5 2.431 2.24 2.172 1.53 1.461 2.8269 0.282 13.333 OK
Slab
Top of
74.2 73.356 105.32 104.524 106.81 106.012 106.8080 73.356 209.284 OK
Girder
Bottom
of -45.4 -43.847 -99.08 -97.508 -92.64 -91.064 -43.8475 -99.079 -241.800 OK
Girder
Thickness of Web tw = 16 mm
Comb 1 1 0.6
1
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
44 of 221
116 3.FOOTPATH LIVE 0 0.64 0 0.64 0 0
0
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
6. 6 Fatigue Check
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
=
A = 0.0013 m2
0.016*0.032+0.05*0.016
Y= 0.041 = 2.135 m
I= 0.011 = 0.0177899 m4
45 of 221
b = m
0.016
Fatigue strength is not required for f <27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
46 of 221
Grade of Concrete Deck Slab = = M40
Elastic modulus of Cocrete Ec = 3.33E+04
Elastic modulus of steel Es = 2.00E+05
Modular Ratio m = 7.5 Short Term
= 15 Long Term
0.25
0.1
0.032
0.55
1.1325
1.1325
0.85
0.036
47 of 221
Dist
anc
e of
CG
fro
m
Bott
om
Section properties of Composite Section for Long Term Modular Ratio
Fibr
Area
e ∑A = 0.1341 m2
(Y) ∑AY/∑A = 1.9548 m
∑I0 +AY2-
Moment of Inertia IZ
= ∑AY2 = 0.2105 m4
Torsional Constant Ix = ∑1/3*X*Y3 = 1.08E-03 m4
A. Section properties of Composite Section for short Term Modular Ratio (in equvalent of steel )
B Section properties of Composite Section for lONG Term Modular Ratio (in equvalent of steel )
Zpz = 0.1615058 m3
Zpy = 0.01199 m3
48 of 221
13 Design of Slpice Joint
A inner Girder
[ As per Clause 512.5.2 of IRC:24-
(i) Design of Slice Joint of Top Flange Plate
2010]
200 = 200 mm
50 of 221
Girder at Mid Span for STAAD Input ( Inner)
Efective flange width of longitudianl girder as per Cl No- 603.3 (b) of IRC L0 = 48.3 m
22-2008
bef = L0/4<B1+B2/2 where L0/4 < B and B =B1=B2
Efective width of compression flange of external girder = 3 m
Grade of Concrete Deck Slab = = M40
Elastic modulus of Cocrete Ec = 3.33E+04
Elastic modulus of steel Es = 2.00E+05
Modular Ratio m = 7.5 Short Term
= 15 Long Term
0.25
0.1
0.028
0.45
2 0.016
0.7
0.032
51 of 221
∑I0 +AY2-
Moment of Inertia IZ = ∑AY2 = 0.1037 m4
Torsional Constant Ix = ∑1/3*X*Y3 = 1.08E-03 m4
A. Section properties of Composite Section for short Term Modular Ratio (in equvalent of steel )
B Section properties of Composite Section for lONG Term Modular Ratio (in equvalent of steel )
Zpz = 0.1031727 m3
Zpy = 0.01199 m3
52 of 221
Girder at Splice STTAD INPUT (Inner Girde)
Grade of Concrete Deck Slab = = M40
Elastic modulus of Cocrete Ec = 3.33E+04
Elastic modulus of steel Es = 2.00E+05
Modular Ratio m = 7.5 Short Term
= 15 Long Term
0.25
0.1
0.028
0.45
2 0.016
1
0.7
0.032
53 of 221
Dist
anc
e of ∑I0 +AY2-
CG
Moment of Inertia IZ
= ∑AY2 = 0.1072 m4
fro
Torsional Constant
m
Ix = ∑1/3*X*Y3 = 2.14E-03 m4
Bott
om
Section properties of Composite Section for Long Term Modular Ratio
Fibr
Area
e ∑A = 0.1081 m2
(Y) ∑AY/∑A2 = 1.5885 m
∑I0 +AY -
Moment of Inertia IZ = ∑AY2 = 0.0899 m4
Torsional Constant Ix = ∑1/3*X*Y3 = 1.08E-03 m4
A. Section properties of Composite Section for short Term Modular Ratio (in equvalent of steel )
B Section properties of Composite Section for lONG Term Modular Ratio (in equvalent of steel )
54 of 221
3.5 Sectional properties of End Cross Girder
0.016
0.3
0.7870
0.787
0.3
0.016
Zpz = 0.0199 m3
Zpy = 0.0008288 m3
55 of 221
3.6 Sectional properties of End Cross Girder (STAAD)
0.016
0.3
1.7000 0.016
0.3
0.016
Zpz = 0.0198 m3
Zpy = 0.0008288 m3
56 of 221
3.6 Sectional properties of End Cross Girder (STAAD)
0.004
0.0082
0.125 2 Nos of ISMC 125
0.0053
1.775
0.065
Zpz = #DIV/0! m3
Zpy = 0 m3
57 of 221
7.0 Calculation of Flexural Stress at Support of Outer Girder (G1) = m
7.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
58 of 221
Hence section is Semi Compact
d/tw = 2000/16 = 125 > 126ԑ = 98.4
Hence section is Selender
Hence a part of web section is efective for making the section is Semi-Compact .Efective Depth d= 1574 mm
This section is Semi-Compact
Hence ,the section is Semi -Compact for Shear and the section is Semi-compact for Bending
7.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.05
59 of 221
Where βb = 1 for Plastic and Compact Sections
= Ze/Zp for Semi-Compact Section
Zpz = 166441399 mm3 Zpy = 21754509 mm3
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
Type of Loading Description V Factor Vn
Erection Stage DL ,Con LL 1 1.35 1.35
Crash Barrier 7 1.35 9.45
Long Term Moment SIDL 3 1.75 5.25
Cons LL 0 1.35 0
Live LL+Snow
Short Term Load 158 1.5 237
Wind Load 0 0.9 0
Foot path LL 3 1.5 4.5
172 258
tw = Thickness of Web = 16 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
60 of 221
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = A v ꚍv = 3280 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 2395911.047 N
Mtf = 36512718.23 N-mm 15733277
ɸ= 41.1721 Degree
61 of 221
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 171.875
Elastic critical stress fcb = 850 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 209.3 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy1/2d/t/4000{1+1/2(d/c)2}
if c>d
Hence permissible average shear stress in steel girder ꚍva = 115.0 N/mm2
OK
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
62 of 221
Yb = m 1.225 1.8705262 2.2
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 209.3
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Top of
Mid -1050 988.003 370.19 -4.2 4.0 1.5 65.009 66.251 209.3
Girder
Span
Bottom of
8.35 -7.86 -2.94 -49.987 -52.438 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 4818.493 277.2 10.69 0.62 30.92 66.251 108.5 209.3
Girder
Span
Bottom of
-36.24 -2.08 -7.18 -52.438 -97.94 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 -13.35 30.92 66.25 94.51 < 209.3
Girder
Span
Bottom of
-36.24 24.41 -7.18 -52.44 -71.45 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
63 of 221
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 6.24 30.92 66.25 114.10 < 209.3
Girder
Span
Bottom of
-36.24 -3.923 -7.18 -52.44 -99.78 < -241.8
Girder
Hence ok
a) Load combination
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
64 of 221
Temp (-ve) 0.6 0.6 1 1
Top of
52.7 13.8 -4.229 30.92 3.979 10.69 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -7.856 -36.24 -6.738 -3.4743 40.679 -6.54
Girder
Top of
0.282 0.7 0.619 2.61 2.539 2.15 2.073 2.8269 2.754
Slab
Top of
88.383 90.4 89.576 99.69 98.896 97.43 96.633 85.7258 84.930
Girder
Bottom
of -58.921 -65.7 -64.088 -97.24 -95.669 -89.57 -88.000 -70.7491 -69.178
Girder
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
2.5 2.431 2.24 2.172 1.53 1.461 2.8269 0.282 13.333 OK
Slab
Top of
74.2 73.356 105.32 104.524 106.81 106.012 106.8080 73.356 209.284 OK
Girder
Bottom
of -45.4 -43.847 -99.08 -97.508 -92.64 -91.064 -43.8475 -99.079 -241.800 OK
Girder
Thickness of Web tw = 16 mm
Comb 1 1 0.6
1
65 of 221
DISPACEMENT OBTAINED FROM STAAD MODEL
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
7. 6 Fatigue Check
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
66 of 221
Shear Force V = 158.151 kN
=
A = 0.0013 m2
0.016*0.032+0.05*0.016
Y= 0.041 = 2.135 m
I= 0.011 = 0.0177899 m4
b = m
0.016
Fatigue strength is not required for f<27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
67 of 221
8.0 Calculation of Flexural Stress at Mid Span of Outer Girder (G2) = m
8.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
68 of 221
Hence section is Semi Compact
d/tw = 2000/16 = 125 > 126ԑ = 98.4
Hence section is Selender
Hence a part of web section is efective for making the section is Semi-Compact .Efective Depth d= 1574 mm
This section is Semi-Compact
Hence ,the section is Semi -Compact for Shear and the section is Semi-compact for Bending
8.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.05
69 of 221
Where βb = 1 for Plastic and Compact Sections
= Ze/Zp for Semi-Compact Section
Zpz = 166441399 mm3 Zpy = 21754509 mm3
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
Type of Loading Description V Factor Vn
Erection Stage DL ,Con LL 1 1.35 1.35
Crash Barrier 7 1.35 9.45
Long Term Moment SIDL 3 1.75 5.25
Cons LL 0 1.35 0
Live LL+Snow
Short Term Load 158 1.5 237
Wind Load 0 0.9 0
Foot path LL 3 1.5 4.5
172 258
tw = Thickness of Web = 16 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
70 of 221
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = A v ꚍv = 3280 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 2395911.047 N
Mtf = 36512718.23 N-mm 15733277
ɸ= 41.1721 Degree
71 of 221
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 171.875
Elastic critical stress fcb = 850 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 209.3 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy1/2d/t/4000{1+1/2(d/c)2}
if c>d
Hence permissible average shear stress in steel girder ꚍva = 115.0 N/mm2
OK
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
72 of 221
Yb = m 1.225 1.8705262 2.2
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 209.3
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Top of
Mid -1050 988.003 370.19 -4.2 4.0 1.5 65.009 66.251 209.3
Girder
Span
Bottom of
8.35 -7.86 -2.94 -49.987 -52.438 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 4818.493 277.2 10.69 0.62 30.92 66.251 108.5 209.3
Girder
Span
Bottom of
-36.24 -2.08 -7.18 -52.438 -97.94 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 -13.35 30.92 66.25 94.51 < 209.3
Girder
Span
Bottom of
-36.24 24.41 -7.18 -52.44 -71.45 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
73 of 221
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 6.24 30.92 66.25 114.10 < 209.3
Girder
Span
Bottom of
-36.24 -3.923 -7.18 -52.44 -99.78 < -241.8
Girder
Hence ok
a) Load combination
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
74 of 221
Temp (-ve) 0.6 0.6 1 1
Top of
52.7 13.8 -4.229 30.92 3.979 10.69 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -7.856 -36.24 -6.738 -3.4743 40.679 -6.54
Girder
Top of
0.282 0.7 0.619 2.61 2.539 2.15 2.073 2.8269 2.754
Slab
Top of
88.383 90.4 89.576 99.69 98.896 97.43 96.633 85.7258 84.930
Girder
Bottom
of -58.921 -65.7 -64.088 -97.24 -95.669 -89.57 -88.000 -70.7491 -69.178
Girder
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
2.5 2.431 2.24 2.172 1.53 1.461 2.8269 0.282 13.333 OK
Slab
Top of
74.2 73.356 105.32 104.524 106.81 106.012 106.8080 73.356 209.284 OK
Girder
Bottom
of -45.4 -43.847 -99.08 -97.508 -92.64 -91.064 -43.8475 -99.079 -241.800 OK
Girder
Thickness of Web tw = 16 mm
Comb 1 1 0.6
1
75 of 221
DISPACEMENT OBTAINED FROM STAAD MODEL
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
8. 6 Fatigue Check
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
76 of 221
Shear Force V = 158.151 kN
=
A = 0.0013 m2
0.016*0.032+0.05*0.016
Y= 0.041 = 2.135 m
I= 0.011 = 0.0177899 m4
b = m
0.016
Fatigue strength is not required for f<27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
77 of 221
9.0 Calculation of Flexural Stress at Splice Point of Outer Girder (G2) = m
9.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
78 of 221
Coefficient for Semi Compact = 126
9.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.05
79 of 221
XLT= 1.0 fy = 390
ϒm0 = 1.1
fbd = 355 N/mm 2
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
Type of Loading Description V Factor Vn
Erection Stage DL ,Con LL 1 1.35 1.35
Crash Barrier 7 1.35 9.45
Long Term Moment SIDL 3 1.75 5.25
Cons LL 0 1.35 0
Live LL+Snow
Short Term Load 158 1.5 237
Wind Load 0 0.9 0
Foot path LL 3 1.5 4.5
172 258
80 of 221
I) Resistance of Shear Buckling shall be verified as specified
d= Depth of effective Web = 1574 mm
tw = Thickness of Web = 16 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = Av ꚍv = 3280 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 2395911.047 N
Mtf = 36512718.23 N-mm 15733277
ɸ= 41.1721 Degree
81 of 221
C/s area of both flanges at the maximum BM zone A 1 = 0.0426 m2
C/s area of both flanges at the minimum BM zone A 2 = 0.027248 m2
Ratio of total area of both the flanges ,ψ = A 2/A1 = 0.64
Coefficient associated with ψ k1 = 0.98
[ Table G.6.of IRC 24-2010]
MOI of the compressive flange aboyt Y axis at Max BM zone ,I 1 = 3.88E-04 m4
MOI of the both the flange aboyt Y axis at Max BM zone ,I 2= 2.03E-03 m4
Ratio of the compression flange to the sum of MOI of each flange = β = 0.192
Coefficient associated with β k2 = -0.62 [ Table G.7.of IRC 24-2010]
Effective Length of compression flange L = 4.2 m
MOI of minor axis Iy = 1.13E-03 m4
Cross sectional area of steel girder A = 0.0975 m2
Radius of Gyration of Minor Axis ry = 0.1075 m
Selenderness ratio λ = 39.05 <300
Overall Depth of Beam D = 2.818 m
Mean thickness of compression flange T = 0.028 m
Coefficient y = 26.5x105/λ2 = 1737.6 N/mm2
Coefficient x = y[1+1/20*(λT/D)2]^(1/2) = 1744.1 N/mm2
Lesser distance of extreme fibre from NA C1 = 1.225 m
Greater distance of extreme fibre from NA C2 = 1.593 m
Thickness of Web tw = 0.016 m
Thickness of compression flange to web ratio T/tw = 1.75
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 171.875
Elastic critical stress fcb = 850 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 209.3 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy d/t/4000{1+1/2(d/c)2}
1/2
if c>d
Hence permissible average shear stress in steel girder ꚍva = 115.0 N/mm2
OK
82 of 221
Permissible Concrete Stress as per CL No.604.3.1 of IRC:22-2008 = 1/3*fck = 13.33 N/mm2
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 209.3
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Mid
Span
83 of 221
At
Top of
Mid -1050 988.003 370.19 -4.2 4.0 1.5 65.009 66.251 209.3
Girder
Span
Bottom of
8.35 -7.86 -2.94 -49.987 -52.438 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 4818.493 277.2 10.69 0.62 30.92 66.251 108.5 209.3
Girder
Span
Bottom of
-36.24 -2.08 -7.18 -52.438 -97.94 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 -13.35 30.92 66.25 94.51 < 209.3
Girder
Span
Bottom of
-36.24 24.41 -7.18 -52.44 -71.45 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 6.24 30.92 66.25 114.10 < 209.3
Girder
Span
Bottom of
-36.24 -3.923 -7.18 -52.44 -99.78 < -241.8
Girder
Hence ok
a) Load combination
84 of 221
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
Top of
52.7 13.8 -4.229 30.92 3.979 10.69 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -7.856 -36.24 -6.738 -3.4743 40.679 -6.54
Girder
85 of 221
Top of
0.282 0.7 0.619 2.61 2.539 2.15 2.073 2.8269 2.754
Slab
Top of
88.383 90.4 89.576 99.69 98.896 97.43 96.633 85.7258 84.930
Girder
Bottom
of -58.921 -65.7 -64.088 -97.24 -95.669 -89.57 -88.000 -70.7491 -69.178
Girder
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
2.5 2.431 2.24 2.172 1.53 1.461 2.8269 0.282 13.333 OK
Slab
Top of
74.2 73.356 105.32 104.524 106.81 106.012 106.8080 73.356 209.284 OK
Girder
Bottom
of -45.4 -43.847 -99.08 -97.508 -92.64 -91.064 -43.8475 -99.079 -241.800 OK
Girder
Thickness of Web tw = 16 mm
Comb 1 1 0.6
1
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
86 of 221
116 3.FOOTPATH LIVE 0 0.64 0 0.64 0 0
0
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
9. 6 Fatigue Check
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
=
A = 0.0013 m2
0.016*0.032+0.05*0.016
Y= 0.041 = 2.135 m
I= 0.011 = 0.0177899 m4
87 of 221
b = m
0.016
Fatigue strength is not required for f <27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
88 of 221
10.0 Calculation of Flexural Stress at Support of Outer Girder (G2) = m
10.1 Moment and Shear From STAAD Output
Member Load Case Node No: FX (kN) Fy (kN) Fz (kN) MX (kNm) My (kNm) Mz (kNm)
248 1. DEAD LOAD 108 0 29.078 0 0 0.000 -960.1
116 0 -0.991 0 0 0.000 1024.56
2. SIDL 108 0 86.1 0 0 0.000 -2691.7
116 0 0 0 0 0.000 2872.48
3.CONSTRUCTION 108 0 31.5 0 0 0.000 -985.02
116 0 0 0 6.517 0.000 1051.17
459 1. DEAD LOAD 210 0 -7.089 0 6.755 0.000 -370.19
216 0 17.589 0 0.948 0.000 352.915
2. SIDL 210 0 10.707 0 0.977 0.000 -978.4
216 0 -3.007 0 0 0.000 988.003
3.CONSTRUCTION
210 0 -10.5
( Removal ) 0 0 0.000 1042.65
216 0 0 0 -0.004 0.000 -1050
459 4.FOOTPATH 210 0 -2.842 0 0.004 0.000 148.293
216 0 2.842 0 0 0.000 -152.27
5.WIND LOAD (UNLOAD) 210 0 -8.96 0 0 0.000 889.728
216 0 0 0 0 0.000 -896
6. WIND LOAD (LOADED) 210 0 4.62 0 0 0.000 -458.77
216 0 0 0 1.104 0.000 462
459 7. Live Load
MAX ( +VE) 0 185.567 0 0 0.000 -4670.2
0 0
MAX ( -VE) 0 -158.151 0 -0.226 0.000
89 of 221
Coefficient for Semi Compact = 126
10.3.3 Check for resistance of the section against material due to the Bending :(Clause -509 of IRC :24-2010)
λLT =
λz = hf = 2784 m
= 0.05
90 of 221
XLT= 1.0 fy = 390
ϒm0 = 1.1
fbd = 355 N/mm 2
XLT= = fy = 390
Erection
DL +Cons LL 0 1.35
Stage
Moment
SIDL 0 1.75
CONS LL 0 1.35
Long Term
Moment
Shear capacity shall be calculated as per shear buckling method as specified in 509.4.2.2(a) of IRC 24-2010
Vn =Vcr =Avꚍv Fyw = 410 N/mm2
Where Vn = Applied Shear Force
Type of Loading Description V Factor Vn
Erection Stage DL ,Con LL 1 1.35 1.35
Crash Barrier 7 1.35 9.45
Long Term Moment SIDL 3 1.75 5.25
Cons LL 0 1.35 0
Live LL+Snow
Short Term Load 158 1.5 237
Wind Load 0 0.9 0
Foot path LL 3 1.5 4.5
172 258
91 of 221
I) Resistance of Shear Buckling shall be verified as specified
d= Depth of effective Web = 1574 mm
tw = Thickness of Web = 16 mm
d/tw = 98.4 > 67ԑ = 53.64 For web without Stiffeners
> 67ԑw*SQRT(Kv/5.35)
Vcr = Shear Force correspond to web buckling
Av = Area of Web
λw = Non dimensional selenderness ratio of shear buckling stress
SQRT(FYW/SQRT(3) ꚍcr
ꚍcr = Elastic critical Shear stress of the web
Kv*pi^2*E/(12*(1-ɥ^2)*(d/tw)^2)
ɥ = Poision Ratio 0.3
E = Young's Modulus = 200000 Mpa
Kv = 5.35 for unstiffened Web
= 4+5.35/(c/d)^2 for c/d<1
5.35+4/(c/d)^2 for c/d>1
c= = 1800 mm c/d = 1.57
Kv = = 6.98
ꚍcr = 130
λw = = 1.35 > 0.8 and 1.2
ꚍv = Shear stress corresponding to web buckling
λw <0.8 ꚍv = fyw/sqrt(3) = 236.714 Mpa
0.8< λw <1.2 ꚍv =(1-0.8*(λw -0.8))*fyw/sqrt(3) 132.911 Mpa
λw >1.2 =fyw/sqrt(3)/λw ^2 = 130.242 Mpa
Vcr = Av ꚍv = 3280 kN
II) Tension Field Method As per Clause 8.4.2.2b of IRC 24-2010 Vn =Vtf
Vtf = [ Avtv+0.9wttwfysinɸ]<Vnp
ꚍv = 130.242 Mpa
Mtf = 0.25bftf2fyf[1-{Nf/bftffyf/ϒm0}^2]
bf = 550.000 mm tf = 28 mm fyf = 390.000 Mpa
Nf = Mu /d 2395911.047 N
Mtf = 36512718.23 N-mm 15733277
ɸ= 41.1721 Degree
92 of 221
C/s area of both flanges at the maximum BM zone A 1 = 0.0426 m2
C/s area of both flanges at the minimum BM zone A 2 = 0.027248 m2
Ratio of total area of both the flanges ,ψ = A 2/A1 = 0.64
Coefficient associated with ψ k1 = 0.98
[ Table G.6.of IRC 24-2010]
MOI of the compressive flange aboyt Y axis at Max BM zone ,I 1 = 3.88E-04 m4
MOI of the both the flange aboyt Y axis at Max BM zone ,I 2= 2.03E-03 m4
Ratio of the compression flange to the sum of MOI of each flange = β = 0.192
Coefficient associated with β k2 = -0.62 [ Table G.7.of IRC 24-2010]
Effective Length of compression flange L = 4.2 m
MOI of minor axis Iy = 1.13E-03 m4
Cross sectional area of steel girder A = 0.0975 m2
Radius of Gyration of Minor Axis ry = 0.1075 m
Selenderness ratio λ = 39.05 <300
Overall Depth of Beam D = 2.818 m
Mean thickness of compression flange T = 0.028 m
Coefficient y = 26.5x105/λ2 = 1737.6 N/mm2
Coefficient x = y[1+1/20*(λT/D)2]^(1/2) = 1744.1 N/mm2
Lesser distance of extreme fibre from NA C1 = 1.225 m
Greater distance of extreme fibre from NA C2 = 1.593 m
Thickness of Web tw = 0.016 m
Thickness of compression flange to web ratio T/tw = 1.75
Clear Depth of web d3 = 2.75 m
Clear depth of web to thickness ratio d3/tw = 171.875
Elastic critical stress fcb = 850 N/mm2
fcb = 1.2xk1[X+K2Y][C2/C1] If T/tw <2 and d3/tw <85
fcb=k1[X+K2Y][C2/C1]
Yeild stress of steel fy = 390 N/mm2
Permissible bending compressive stress
σbc =0.66xfcbxfy/[(fcb)1.4+(fy)1.4]^(1/1.4) σbc = 209.3 N/mm2
Maximum bending stress σb = 0.62fy = 241.8 N/mm2
During service condition compression flange is fully restrained with deck slab by shear connector
Permissible average shear stress in un stiffend steel girder =0.35fy 136.5 N/mm2
=0.35fy[1.3- fy d/t/4000{1+1/2(d/c)2}
1/2
if c>d
Hence permissible average shear stress in steel girder ꚍva = 115.0 N/mm2
OK
93 of 221
Permissible Concrete Stress as per CL No.604.3.1 of IRC:22-2008 = 1/3*fck = 13.33 N/mm2
Permissible steel bending stress at service stage (all sections) 241.8 N/mm2
=
Max Elastic Steel Stress at service condition as per Cl N0.604.3.1 of IRC
22-2008 =0.87fy 339.3 N/mm2
=
Mid Span
Top of Slab
At
Top of
Mid 1024.56 1051.17 2872.48 13.46 13.81 37.74 65.009 < 209.3
Girder
Span
Bottom of
-10.35 -10.62 -29.02 -49.987 < -241.8
Girder
At
Mid
Span
94 of 221
At
Top of
Mid -1050 988.003 370.19 -4.2 4.0 1.5 65.009 66.251 209.3
Girder
Span
Bottom of
8.35 -7.86 -2.94 -49.987 -52.438 -241.8
Girder
(iii) Calculation of stress at different section at Service condition with wind load -short term Hence ok
Stress for
Moment Due to Live Load Moment Due to Wind Load x Stress for Stress for Differential Stress Total Permissible
Section
+Snow Load ( kNm) 0.6 (kNm) Live Load Wind Load Shrinkage After SIDL Stress Stress
(Mpa) (Mpa) (Mpa) (Mpa) (Mpa) (Mpa)
At
Top of
Mid 4818.493 277.2 10.69 0.62 30.92 66.251 108.5 209.3
Girder
Span
Bottom of
-36.24 -2.08 -7.18 -52.438 -97.94 -241.8
Girder
Hence ok
Stress for
Stress 0.6 x Temerature
Section Stress Live Load (Mpa) Differential Total Stress (Mpa) Check Permissible
(Mpa)
Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 -13.35 30.92 66.25 94.51 < 209.3
Girder
Span
Bottom of
-36.24 24.41 -7.18 -52.44 -71.45 < -241.8
Girder
(iv) Calculation of stress at different section at Service condition with (-) Temperature Hence ok
Stress for
Stress 0.6 x Temerature Differential Permissible
Section Stress Live Load (Mpa) Total Stress (Mpa) Check
(Mpa) Shrinkage Stress After Stress
(Mpa) SIDL (Mpa) (Mpa)
At
Top of
Mid 10.69 6.24 30.92 66.25 114.10 < 209.3
Girder
Span
Bottom of
-36.24 -3.923 -7.18 -52.44 -99.78 < -241.8
Girder
Hence ok
a) Load combination
95 of 221
Load Case 1 (a) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1 1
Wind load-
Unloaded
1 1
Wind load-
Loaded
0.6 0.6 1 1
Temp (-ve)
DL 1 1 1 1 1 1 1
Shrinkage 1 1 1 1 1 1 1
Wind load-
Unloaded
Wind load-
Loaded
Top of
52.7 13.8 -4.229 30.92 3.979 10.69 1.988 1.0253 -22.252 10.40
Girder
Bottom
of -42.3 -10.6 8.349 -7.18 -7.856 -36.24 -6.738 -3.4743 40.679 -6.54
Girder
96 of 221
Top of
0.282 0.7 0.619 2.61 2.539 2.15 2.073 2.8269 2.754
Slab
Top of
88.383 90.4 89.576 99.69 98.896 97.43 96.633 85.7258 84.930
Girder
Bottom
of -58.921 -65.7 -64.088 -97.24 -95.669 -89.57 -88.000 -70.7491 -69.178
Girder
Permissibl
Max Stress Min Stress
Section 5(c) 5(d) 6(a) 6(b) 6(c) 6(d) e Stress Check
(Mpa) (Mpa)
(Mpa)
Top of
2.5 2.431 2.24 2.172 1.53 1.461 2.8269 0.282 13.333 OK
Slab
Top of
74.2 73.356 105.32 104.524 106.81 106.012 106.8080 73.356 209.284 OK
Girder
Bottom
of -45.4 -43.847 -99.08 -97.508 -92.64 -91.064 -43.8475 -99.079 -241.800 OK
Girder
Thickness of Web tw = 16 mm
Comb 1 1 0.6
1
Absolute
Absolute Absolute Absolute
Node No : Load Case x y z Displaceme
rotation x rotation y rotation Z
nt
97 of 221
116 3.FOOTPATH LIVE 0 0.64 0 0.64 0 0
0
CAMBER REQUIRED
Deflection for Live Load Case Only = 19.252 mm < L/800 = 60.375
HENCE OK
The girder is built-up welded .as per Table 19(b) of IRC 24-2010 detail category = 80 Mpa
ϒmft = Partial safety factor for fatigue strength (Refer Table 18 of IRC :24-2010) =
1.15
Applying partial factor of safety ,allowable stress variation (f/(ϒfft*ϒmft)) = 69.6 Mpa
=
A = 0.0013 m2
0.016*0.032+0.05*0.016
Y= 0.041 = 2.135 m
I= 0.011 = 0.0177899 m4
98 of 221
b = m
0.016
Fatigue strength is not required for f <27/ϒmft or Nsc <5x10^6X(27/ϒmft/ϒfftxf)^3 = 23.48 Mpa
=5x10^6x(27/ϒmft /ϒfft
> f <27/ϒmft 23.48 Mpa Nsc <
xf)
Hence OK
99 of 221
5.0 Calculation of Stresses for Girder LG2 = 1.100 m
5.1. Load calculation
5.1.1 Dead Load Moment & Shear for Precast girder only
Unit weight of concrete #REF! kN/m3
Cross-sectional area at span = 0.873 m2
Cross-sectional area at support = 1.806 m2
Unit Weight at span #REF! kN/m
Unit Weight at support #REF! kN/m
Thickness of intermediate Cross Girder = 0.30 m
Thickness of end Cross Girder = 0.60 m
1.250 1.750 1.250
0.475 0
0.1 0.063
0
0
0.175 0.175
0.65 2.350 0.65
Part of intermediate cross girder #REF! #REF! kN
Part of End cross girder #REF! #REF! kN
#REF! kN
#REF! kN
#REF! #REF!
#REF!
0.500 0.00 0.00 0.10 0.00 0.00 0.500
5.1.3 Dead Load Moment & Shear for Deck slab & X-girder
Unit weight of concrete #REF! kN/m3
Thickness of deck slab = 0.250 m2
Thickness of deck slab at expansion joint = 0.400 m
Width of deck slab at support = 3.000 m
Width of deck slab at midspan = 3.000 m
Average width of deck slab = 3.000 m
Wt. of End X-girder #REF! #REF! kN
Wt of Inner X-girder #REF! #REF! kN
#REF! #REF! #REF!
0.55
#REF! #REF! kN/m
100 of 221
0.850 0.10 0.850
Support Reaction = #REF! kN
101 of 221
Table : Maximum BM & SF at critical sections
Section At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.038 0.050
Bending Moment (kNm) #REF! #REF! #REF! #REF! #REF!
Shear Force (kN) #REF! #REF! #REF! #REF! #REF!
5.1.4 Summary of Bending Moment & Shear Force for inner girder
a) Bending Moment (kNm)
Description At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.038 0.050
Precast girder only #REF! #REF! #REF! #REF! #REF!
Construction load -0.8 -0.8 -0.8 -0.8 -0.8
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total wt of deck slab = #REF! #REF! #REF! #REF! #REF!
SIDL from staad output -16.8 354.8 626.2 841.2 1033.9
Removal of shutter 3.3 -246.4 -424.6 -531.6 -585.8
Footpath live load -4.2 22.7 40.6 58.65 76.69
Live load incl. snow load -230.4 1642.6 2605.6 2903.4 2856.1
Total Live Load incl.snow load -234.6 1665.3 2646.2 2962.1 2932.8
Wind load (unloaded structure) 3.2 -240.7 -414.8 -519.35 -572.24
Wind load (loaded structure) -1.6 124.7 214.9 269.1 296.5
Construction load (1.5kN/m2) -0.2 -0.2 -0.2 -0.2 -0.2
Total Live Load -234.6 1665.3 2646.2 2962.1 2932.8
b) Shear force (kN) For SIDL & Live load - Refer STAAD Output
Desription At support Near L/8 Near L/4 Near 3L/8 At L/2
Precast girder only #REF! #REF! #REF! #REF! #REF!
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total DL #REF! #REF! #REF! #REF! #REF!
SIDL from staad output 112.3 91.5 74.4 57.8 37.5
Footpath live load 0.2 5.3 5.3 5.4 5.4
Live load incl. snow load 618.7 506.4 358.2 209.0 329.9
Total Live Load incl.snow load 618.8 511.7 363.5 214.4 335.3
Wind load (unloaded structure) -84.1 -63.1 -42.1 -21.0 0.0
Wind load (loaded structure) 43.6 32.7 21.8 10.9 0.0
Construction load 0.1 0.1 0.0 0.0 0.0
Total #REF! #REF! #REF! #REF! #REF!
102 of 221
4 (b) #REF! #REF! #REF! #REF! #REF!
5 (a) #REF! #REF! #REF! #REF! #REF!
5 (b) #REF! #REF! #REF! #REF! #REF!
Maximum #REF! #REF! #REF! #REF! #REF!
103 of 221
5.2 Cable Details
Maximum midspan Moment for outer girder =
Precast Girder Only = #REF! kN-m
Deck Slab & Cross Girder = #REF! kN-m
SIDL = 1033.87 kN-m
Wind load = 296.48 kN-m
Live Load = 2932.76 kN-m
Total Moment = #REF! kN-m
Sectional Properties Inner Composite Girder at Midspan :-
Area - A = 1.100 m2
Moment of Inertia - I = 0.969 m4
CG from bottom = 1.743 m
Z Bottom = 0.556 m3
Assume Nos. of Cable = N
Ultimate Force of each 19T13 strands P = #REF! kN
Applied Force = #REF! kN
CG From bottom = 0.237 m
"e" from CG of Girder = 1.506 m
Assum overall Loss = 30 %
Stress at bottom of Girder = NP/A+NP*e/ZBottom-M/Zbottom = 0
N = (M/ZBottom)/(P/A+P*e/ZBottom) = #REF!
Say, No of Cables Provided = 3.63
1.275
4
0.375
X X X 3
2.75 0.375
2
4 0.180 0.375
1 3 2 0.180 1 0.350
0.125
0.17 0.310 0.17
0.65 0.65
Section at Midspan Section at Support
0.50 0.050
Y
4.50
1 2 X 0.155
0.155
0.15 0.550
0.15
1.28 4
0.375
3
0.375 Z
2
0.375 0.180
1 0.180
0.125
0.35 0.50 4.500 4.50 1.80 -10.750
.
Cable profile in Elevation
104 of 221
Vertical bending of Cable 1 =Tan-1{(0.35-0.125)/(0.5+4.5-0.15)} = 2.656 o
Radius for 1 to 3 = 20 m
Horizontal bending of Cable 1 2.536 o
Position of Cable
Cable Anchorage Location of vertical Bending
No. X Y Z X Y Z
1 0.000 0.000 0.350 4.850 0.000 0.125
2 0.000 0.000 0.725 9.350 -0.155 0.125
3 0.000 0.000 1.10 11.150 0.000 0.305
3 0.000 0.000 1.48 11.150 0.000 0.485
Cable 1 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link
meter Degree Radian e (mf+kl) friction loss slip loss
(kN) (kN)
1 #REF! #REF!
1-2 4.855 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.503 3.672 0.064 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
4 #REF! 2585.89
105 of 221
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = 36.616 m
Extension of cable at each side = #REF! mm
106 of 221
Cable 2 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 4.860 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.512 4.462 0.078 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
4 #REF! 2594.76
4.860 4.512 8.950
#REF! #REF!
1 2 #REF! #REF!
= 3
= 2594.76 4
#REF! #REF!
#REF! #REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2594.76 kN
Point of Zero Slip from node 3 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = 36.644 m
Extension of cable = #REF! mm
Cable 3 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.178 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 4.078 0.071 #REF!
3 #REF! 2597.84
11.178 -10.750
#REF! #REF!
1 2 #REF!
= 3
= 2597.84
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2597.84 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.178+-10.75)x2 = 0.857 m
Extension of cable at each side = #REF! mm
Cable 4 12 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.194 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 5.074 0.089 #REF!
3 #REF! 1644.87
11.194 -10.750
#REF! #REF!
1 2 #REF!
107 of 221
= 3
= 1644.87
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 1644.8733 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.194+-10.75)x2 = 0.888 m
Extension of cable at each side = #REF! mm
4.2.2 Summary of Cable Forces after Friction & Slip at different Points
Position Support L/8 L/4 3L/8 L/2
Cable No 0.350 0.363 0.375 0.388 0.400
Cable 1 #REF! #REF! #REF! #REF! 2585.89
Vert. angle 2.656 2.656 2.656 0.000 0.000
Hor. angle 0.000 0.000 2.536 0.000 0.000
C.G. 0.334 0.125 0.125 0.125 0.125
Cable 2 #REF! #REF! #REF! #REF! 2594.76
Vert. angle 3.672 3.672 3.672 0.000 0.000
Hor. angle 0.000 0.000 2.536 2.536 0.000
C. G. 0.703 0.702 0.701 0.125 0.125
Cable 4 #REF! #REF! #REF! #REF! 1644.87
Vert. angle 5.074 5.074 5.074 5.074 0.000
Hor. angle 0.000 0.000 0.155 0.155 0.000
C.Total
G. cable 1.444 1.443 1.442 1.441 0.485
forces Normal
at first stage #REF! #REF! #REF! #REF! 6825.53
CG of Cable #REF! #REF! #REF! #REF! 0.212
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Cable 3 #REF! #REF! #REF! #REF! 2597.84
Vert. angle 4.078 4.078 4.078 4.078 0.000
Hor. angle 0.000 0.000 0.000 0.000 0.000
C. G. 1.075 1.074 1.073 1.072 0.305
Total cable
forces Normal #REF! #REF! #REF! #REF! 2597.84
CG of Cable 1.075 1.074 1.073 1.072 0.305
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Overall CG
of Cable #REF! #REF! #REF! #REF! 0.237
% loss #REF! #REF! #REF! #REF! #REF!
108 of 221
5.3 Stress Calculation of girder
After 5 days casting of Precast Girder, first stage Cables shall be stressed as per given force & elongation.
Second stage Cables shall be stressed after 28 days of casting of precast girder. After that all Precast Girders
shall be erected at bearing locations and Deck slab & X-Girder shall be cast erecting necessary shuttering from
precast girder at 60 days. After 30 days casting of Deck Slab i.e. after 90 days casting of Precast Girder,
all shuttering material shall be removed and SIDL shall be laid. In such case Precast Longitudinal Girder shall be
checked for DL of Precast Girder, wt of Deck slab, wt of X-girder at 60 days. But composite girder
(precast girder+RCC deck) shall be checked for SIDL & Live load cases.
5.3.1 Loss calculation
5.3.1.1 Loss due to Elastic Shortening
Refer clause no.6.4.2.2, Annexure A-2 of IRC 112-2011 Average loss in Cable Stress = 1/2 m fc
fcm (t) = bcc(t)fcm bcc(t) = exp{S[1-(28/(t/t1)0^0.5]}
fck = Grade of concrete = #REF!
fcm (t) = mean concrete compressive strength at age 't' days
fcm = mean concrete compressive strength at age '28' days = #REF! Mpa
t = Age of concrete in days = 5 days
t1 = 1 day S = 0.25
bcc(t) = 0.71 fcm (t) = #REF! Mpa
fck (t) = #REF! Mpa
corresponding Ecm = 22x(fcm/12.5)^0.3 = #REF! Gpa
Ep = #REF! Gpa m =Modular Ratio = Ec/E = #REF!
To calculate average stress fc at CG of Cables due to Prestress and
Depth of Girder = 2.750 m Assume, Elastic Shortening = 69.33 kN/Cable
26.35 %
Area of each Cable = #REF! mm2 Number of cables (cable 1 to 3) = 2.63 Nos
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m2 Area = 1.806 m2
I= 0.601 m4 I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Sustained Stress of precast girder only at 5 days :-
Cable Force (kN) Cable CG Dead Load Dead Load Total Stress at
Section After fr. & After fr., slip from soffit Stress Moment Stress Stress cable CG
slip loss & ES loss (m) (Mpa) (kN-m) (kN/m2) (Mpa) (Mpa)
T #REF! #REF! #REF!
End #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T -10.18 #REF! #REF!
L/2 6825.53 6643.07 0.212 #REF! #REF!
B 27.41 #REF! #REF!
Average stress fc = #REF! = #REF! Mpa
Average Loss of cable stress = 1/2 m fc = #REF! Mpa
Loss of each cable due to Elastic shortening = 1/2 m fc As = #REF! kN
-10.18 Mpa #REF! Mpa #REF! Mpa
#REF! #REF!
Mpa
X X
+ = #REF! #REF!
Mpa
#REF!
109 of 221
Permissible Compressive stress 0.48xfcm(t) #REF! MPa
Permissible tensile stress 0.7xftmj #REF! MPa
5.3.1.2 Loss due to Relaxation of Steel (clause no. 6.3.6 of IRC 112-2011)
Total Relaxation Loss at service condition = 3 x (1000 hr. value)
Initial force after Friction, slip & ES loss #REF! #REF! kN
Percentage of Initial force = #VALUE! UTS
Relaxation Loss at 1000hr. for low relaxation steel = #VALUE! % of initial force
Relaxation Loss at 1000hr. for low relaxation steel #REF! #VALUE! kN/Cable
Immediate Loss i.e 1 hr. of stressing as per Table 6.2 of IRC 112-2011, = 37 % of Total Loss
5 - 28 days Loss 23 days 552 = 42.00 % of Total Loss
28 - 60 days Loss 32 days 768 = 21.00 % of Total Loss
60 - 90 days Loss 30 days = 0.00 % of Total Loss
90 - a days Loss = 200.0 % of Total Loss
i.e. 3 x (1000 hr. value)
Immediate Loss i.e 1 hr. of stressing = #VALUE! kN/Cable
5 - 28 days Loss = #VALUE! kN/Cable
28 - 60 days Loss = #VALUE! kN/Cable
60 - 90 days Loss = #VALUE! kN/Cable
90-a days Loss = #VALUE! kN/Cable
Total = #VALUE! kN/Cable
#VALUE! #VALUE! %
110 of 221
The coefficient a 1 =(43.75/fcm)^0.7 #REF!
The coefficient a 2 =(43.75/fcm)^0.2 #REF!
The coefficient b(fcm) = 18.78/sqrt(fcm) #REF!
The coefficient b (t0) = 1/(0.1+to^0.2) = 0.68
Where, age of concrete at first loading t0 =5 day
bc(t,to) =[(t-to)/(bH +t-to)]^0.3
bH = = 1.5 x [1+(0.012RH)^18] x ho + 250 <= 1500 for fcm <= 35MPa
= 1.5 x [1+(0.012RH)^18] x ho + 250a3 <= 1500a3 for fcm <= 35MPa
The coefficient a 3 =(43.75/fcm)^0.5 #REF!
For temperature greater than 40oC theby 10% in absence of accurate data coefficient may be increased by 10%
in absence of accurate data. This is valid for concrete using normal cement.
Development of creep
Loss due to
Creep
Days h0 (mm) f RH fo bH b c(t,to) creep of
coeff. fo concrete
Section Stress at 5 loss bet. 5 Cable CG Stress due Cable CG Total Stress at
days - 28 days from soffit to loss After fr. & After fr., slip from soffit Stress Stress cable CG
(kN/m2) (Tons) (m) (Mpa) slip loss & ES loss (m) (Mpa) (Mpa) (Mpa)
T #REF! #REF! #VALUE! #REF!
End #REF! #REF! #REF! #VALUE! 1.075 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/8 #REF! #REF! #REF! #VALUE! 1.074 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/4 #REF! #REF! #REF! #VALUE! 1.073 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
3L/8 #REF! #REF! #REF! #VALUE! 1.072 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/2 #REF! 0.212 2597.84 #VALUE! 0.305 #REF!
B #REF! #REF! #VALUE! #REF!
Average stress s s at CG of cables for 28 days = #REF! #REF! Mpa
Loss of cable stress = m (fc-fc') #REF! Mpa
Loss of each cable due to Elastic shortening = m f c As #REF! kN
111 of 221
#REF! #REF!
Mpa
#REF! Mpa #REF! Mpa #VALUE! Mpa #REF! Mpa #REF!
Stress due to loss between 5 Stress due to stressing of Resultant Stress at 28
Resultant Stress at 5 days to28 days cables 3 days
Stress Diagram at Midspan of Precast Girder at 28 days of Casting of Girder
112 of 221
5.3.3. Sustained Stress of precast girder at 60 days after Casting of Deck with X-Girder
Losses for first 3 cables:- Losses for last 1 cable:-
Shrinkage = #REF! kN/Cable Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable Relaxation = #VALUE! kN/Cable
Creep = 38.44 kN/Cable Creep = 38.44 kN/Cable
Total = #REF! kN/Cable Total = #REF! kN/Cable
actual time dependent losses = #REF! kN/Cable actual time dependent losses = #REF! kN/Cable
Total Loss of 4 Cables = #REF! kN Actual Loss of third Cables = #REF! kN
Depth of Precast Girder = 2.750 m
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m2 Area = 1.806 m2
I= 0.601 m4
I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Stress at loss bet. 28 Cable CG Stress due Moment Stress Total Stress at
Section 28 days - 60 days from soffit to loss Total Stress due to slab due to Stress cable CG
(kN/m2) (kN) (m) (Mpa) (kN/m2) (kN-m) slab (Mpa) (Mpa) (Mpa)
Top of girder #REF! #REF! #REF! #REF! #REF!
End #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/2 #REF! 0.237 #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Average stress s s at CG of cables for 60 days = #REF! = #REF! Mpa
+ + =
#REF! #REF!
Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! Mpa #REF!
Resultant Stress at 28 Stress due to loss between Stress due to DL of Slab & Resultant Stress at 60
days 28 to 60 days wt of shuttering days
Stress Diagram at Midspan of Precast Girder at 60 days of Casting of Girder
Sectional Properties of Composite Girder at Midspan = Sectional Properties of Composite Girder at Support =
Area = 1.100 m2 Area = 2.034 m2
I= 0.969 m4 I= 1.608 m4
CG = 1.743 m CG = 1.555 m
Losses:- Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable
Creep = 18.18 kN/Cable
Total = #REF! kN/Cable
Total Loss = #REF! kN/Cable
actual time dependent losses = #REF! kN
113 of 221
Total Stress
Section Stress due Loss of CG of Cables Stress due Moment due due to Total Stress at
at 60 days Cables from soffit to loss to SIDL SIDL Stress cable CG
(Mpa) (kN) (m) (Mpa) (kN-m) (Mpa) (Mpa) (Mpa)
Top of slab 0.00 #REF! -0.01 #REF!
Top of girder #REF! #REF! -13.53 -0.01 #REF!
End #REF! #REF! #REF!
Bottom #REF! #REF! 0.01 #REF!
Top of slab 0.00 #REF! 0.15 #REF!
Top of girder #REF! #REF! 108.37 0.12 #REF!
L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -0.19 #REF!
Top of slab 0.00 #REF! 0.28 #REF!
Top of girder #REF! #REF! 201.55 0.23 #REF!
L/4 #REF! #REF! #REF!
Bottom #REF! #REF! -0.36 #REF!
Top of slab 0.00 #REF! 0.43 #REF!
Top of girder #REF! #REF! 309.62 0.35 #REF!
3L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -0.56 #REF!
Top of slab 0.00 #REF! 0.63 #REF!
Top of girder #REF! #REF! 448.11 0.51 #REF!
L/2 #REF! 0.237 #REF!
Bottom #REF! #REF! -0.81 #REF!
Average stress at 90 days = #REF! = #REF! Mpa
+ + =
114 of 221
#REF! Mpa #REF! #REF! Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! #REF! Mpa
Mpa #REF!
+ =
+ =
115 of 221
DL of girder+ deck slab Prestressing force & Loss SIDL
Section Prestress Loss of Stress
Moment Stress CG of cables Loss of pre. Moment Stress
comp. girder
(kN-m) (Mpa) (kN) (m) Girder (kN)
(kN) (Mpa) (kN-m) (Mpa)
Top of slab #REF! -0.02
Top of girder #REF! #REF! -0.01
End #REF! #REF! #REF! #REF! #REF! -16.78
Bottom #REF! #REF! 0.02
Top of slab #REF! 0.46
Top of girder #REF! #REF! 0.37
L/8 #REF! #REF! #REF! #REF! #REF! 354.76
Bottom #REF! #REF! -0.64
Top of slab #REF! 0.81
Top of girder #REF! #REF! 0.65
L/4 #REF! #REF! #REF! #REF! #REF! 626.20
Bottom #REF! #REF! -1.13
Top of slab #REF! 1.09
Top of girder #REF! #REF! 0.87
3L/8 #REF! #REF! #REF! #REF! #REF! 841.23
Bottom #REF! #REF! -1.51
Top of slab #REF! 1.34
Top of girder #REF! #REF! 1.07
L/2 #REF! #REF! #REF! #REF! #REF! 1033.87
Bottom #REF! #REF! -1.86
Section Live load Wind load - loaded structure Temp (+ve) Temp (-ve)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
116 of 221
Live load 1 1 1 0.75 0.75 0.75 0.75
Wind load
Temp (+ve) 0.6 1 1
Temp (-ve) 0.6 0.6 1 1
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
117 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.48 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = #REF! Mpa #REF! #REF! #REF!
Stress with/without Live load at top of deck slab near support section only exceeds the permissible tensile stress i.e. 2.29Mpa.
Necessary reinforcement shall be provided to resist the tensile stress of deck slab.
Maximum tensile force = #REF! kN Permissible working stress = 240.00 MPa
Area of reinforcement required = #REF! mm2 Ast provided= 1021.02 mm2
Hence Provide 10 T @ 140 c/c + 10 T @ 140 c/c at top
5.3.9 Load Combination for frequent Combination (SL2) - for prestressing member
1) Dead load +SIDL+Prestress
2) Dead load +SIDL+Prestress+ wind load(lead) (unloaded structure)
3) Dead load +SIDL+Prestress+Live load(lead)+wind load (accompany)
4) Dead load +SIDL+Prestress+Live load(accompany)+wind load (lead)
5) Dead load +SIDL+Prestress+Live load(lead)+Temperature(accompany)
6) Dead load +SIDL+Prestress+Live load(accompany)+Temperature(lead)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
118 of 221
Load Case 5 (b) 5 (c) 5 (d) 6 (a) 6 (b) 6 (c) 6 (d)
DL 1 1 1 1 1 1 1
SIDL 1 1.2 1 1.2 1 1.2 1
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.75 0.2 0.2 0.2 0.2
Wind load
Temp (+ve) 0.5 0.6 0.6
Temp (-ve) 0.5 0.5 0.6 0.6
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
119 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.36 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = 0.00 Mpa #REF! #REF! #REF!
120 of 221
5.4 Check for ultimate strength of girder in Flexure :-
Grade of concrete #REF! Modulus of elasticity of concrete E #REF! MPa
Design yield strength fpd #REF! MPa Modulus of elasticity of steel #REF! Gpa
910 0.00350 #REF!
250 #REF!
197.28
NA NA
3000 300
121 of 221
Vertical Component of Cable Force (kN)
Position Support L/8 L/4 3L/8 L/2
Cable No #REF! #REF! #REF! #REF! #REF!
Cable 1 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 2 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 3 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 4 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Total Ver.
Comp. of
cable1 to 4 #REF! #REF! #REF! #REF! #REF!
ii) Shear Capacity of Uncracked Section as per clause 10.3.2(2) of IRC 112-2010
The shear resistance of the beam section uncracked in flexure is given below:-
VRd,c = ( I * bwc )/ S x √ (fctd2 + k1 scp fctd)
Where, I = Moment of inertia bwc= Width of beam after deduction due to duct
S = First moment of area between cetroidal axis and extreme compression fibre about the centrodial axis.
fctd = design tensile strength of concrete = fctk/gm = #REF! Mpa
Description Support L/8 L/4 3L/8 L/2
Prestress Force after all losses (kN) #REF! #REF! #REF! #REF! #REF!
Effective width of the Web 650 300 300 300 300
Effective Depth of the Section (d) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Stress due to Prestress (scp) #REF! #REF! #REF! #REF! #REF!
Design tensile strength of the Concrete
#REF! #REF! #REF! #REF! #REF!
(fctd)
First moment of inertia about the CG (S) 3.11E+09 1.79E+09 1.79E+09 1.79E+09 1.79E+09
Transmission length factor, k1 1.00 1.00 1.00 1.00 1.00
Moment of Inertia (I) (mm4) 1.6E+12 9.7E+11 9.7E+11 9.7E+11 9.7E+11
Design Shear resistance ( VRd,c) (kN) #REF! #REF! #REF! #REF! #REF!
iii) Summary of the Shear resistance of the Beam when shear reinforcement isn't required :
The maximum shear capacity of the Beam as cl.10.3.2 (5) of IRC 112-2010
VEd ≤ 0.50 bw d n fcd where, n =0.60 [ 1 - fck/310]
122 of 221
Description Support L/8 L/4 3L/8 L/2
Distance from bearing in m 0.00 0.01 0.03 0.04 0.05
Distance modification factor b for Precast Beam 1.00 #VALUE! ### ### ###
Distance modification factor b for Composite### #VALUE! ### ### ###
Effective Shear for Precast Beam #REF! #REF! #REF! #REF! #REF!
Effective Shear for Composite Section (kN 0.0 0.0 0.0 0.0 0.0
Effective Shear due to prestressing force #REF! #REF! #REF! #REF! #REF!
Total Shear force for the Beam (kN) #REF! #REF! #REF! #REF! #REF!
Precast member Area (m2) 1.81 0.87 0.87 0.87 0.87
Zb (m3) 0.84 0.41 0.41 0.41 0.41
Composite member Area (m2) 2.03 1.10 1.10 1.10 1.10
Zb (m3) 1.03 0.56 0.56 0.56 0.56
Stress due to prestress at tensile fibre s bpt #REF! #REF! #REF! #REF! ###
Section at Maximum Bending Moment #REF! #REF! #REF! #REF! ###
Shear capacity of Beam Section (kN) #REF! #REF! #REF! #REF! ###
Maximum shear capacity of the Section ( ### #VALUE! ### ### ###
Whether shear reinforcement required or #REF! #REF! #REF! #REF! ###
123 of 221
Busting reinforcement in end block
2Yo = #REF! mm 2Ypo = #REF! mm
Ypo/Yo = #REF! As per Table 13.1 of IRC 112-2011 Fbst/Pk = 0.120
Fbst = #REF! #REF! kN
Area of Steel Required = Fbst/(0.87xfy) #REF! mm2
Hence Provide 12T- 4L -4Nos along Web and Normal to Web Ast = 1809.56 mm2
124 of 221
5.9 Calculation for Deflection of Longitudinal girders
(i) Precast Girder - Prestress of cables 1, 2, 3 + wt of precast Girder at 5 days
Young Modulus = #REF! kN/m2
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.038 0.050
CG of Precast girder from bottom , m 1.389 1.448 1.448 1.448 1.448
Moment of Inertia for Precast
1.161 0.601 0.601 0.601 0.601
girder only (I) m4
CG of cables 1 to 2 from bot.(m) #REF! #REF! #REF! #REF! #REF!
Moment due to stressing after
#REF! #REF! #REF! #REF! #REF!
Momentlosses
due to(kN-m)
Wt of Precast
#REF! #REF! #REF! #REF! #REF!
Total
Girder
moment
(kN-m)
due to
prestress+wt of precast Girder #REF! #REF! #REF! #REF! #REF!
(kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
(iii) Precast Girder - Prestress + wt of precast Girder +wt of deck slab at 60 days
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.038 0.050
CG of all cables from bot.(m) #REF! #REF! #REF! #REF! #REF!
Loss #REF! #REF! #REF! #REF! #REF!
Moment due to prestressing
#REF! #REF! #REF! #REF! #REF!
losses
Moment dueof to
cables
Wt of (kN-m)
Deck Slab
#REF! #REF! #REF! #REF! #REF!
(kN-m) due to
Total moment #REF! #REF! #REF! #REF! #REF!
prestress+DL (kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
0.0 0.013 0.013 0.013
A B C D E
125 of 221
#REF! #REF! #REF!
4 #REF! #REF!
3 1
2
M/EI Diagram for Ist Stage Prestress after losses at 60 days
126 of 221
At Midspan
Average Moment of M/EI about
Section Marked Distance CG from A M/EI Rotation
M/EI A
A #REF!
B 4 0.013 0.006 #REF! #REF! #REF! #REF!
C 3 0.013 0.019 #REF! #REF! #REF!
D 2 0.013 0.031 #REF! #REF! #REF!
E 1 0.013 0.044 #REF! #REF! #REF!
Total #REF!
So, Midspan deflection due to Prestress losses + DL = = #REF! mm
Total Deflection at 60 days #REF! = #REF! mm
127 of 221
6.0 Calculation of Stresses for Girder LG2 = 1.100 m
6.1. Load calculation
6.1.1 Dead Load Moment & Shear for Precast girder only
Unit weight of concrete #REF! kN/m3
Cross-sectional area at span = 0.873 m2
Cross-sectional area at support = 1.806 m2
Unit Weight at span #REF! kN/m
Unit Weight at support #REF! kN/m
Thickness of intermediate Cross Girder = 0.30 m
Thickness of end Cross Girder = 0.60 m
1.250 1.750 1.250
0.475 0
0.1 0.063
0
0
0.175 0.175
0.65 2.350 0.65
Part of intermediate cross girder #REF! #REF! kN
Part of End cross girder #REF! #REF! kN
#REF! kN
#REF! kN
#REF! #REF!
#REF!
0.500 0.00 0.00 0.10 0.00 0.00 0.500
128 of 221
Table : Maximum BM & SF at critical sections
129 of 221
Section At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.038 0.050
Bending Moment (kNm) #REF! #REF! #REF! #REF! #REF!
Shear Force (kN) #REF! #REF! #REF! #REF! #REF!
6.1.4 Summary of Bending Moment & Shear Force for inner girder
a) Bending Moment (kNm)
Description At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.038 0.050
Precast girder only #REF! #REF! #REF! #REF! #REF!
Construction load -0.8 -0.8 -0.8 -0.8 -0.8
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total wt of deck slab = #REF! #REF! #REF! #REF! #REF!
SIDL from staad output -13.7 398.8 705.0 932.9 1085.0
Removal of shutter 3.3 -246.4 -424.6 -531.6 -567.2
Footpath live load -6.4 64.8 120.9 175.77 230.46
Live load incl. snow load -216.0 1585.6 2519.6 2818.0 2743.6
Total Live Load incl.snow load -222.4 1650.4 2640.4 2993.8 2974.0
Wind load (unloaded structure) 3.2 -240.7 -414.8 -519.35 -554.15
Wind load (loaded structure) -1.6 124.7 214.9 269.1 287.1
Construction load (1.5kN/m2) -0.2 -0.2 -0.2 -0.2 -0.2
Total Live Load -222.4 1650.4 2640.4 2993.8 2974.0
b) Shear force (kN) For SIDL & Live load - Refer STAAD Output
Desription At support Near L/8 Near L/4 Near 3L/8 At L/2
Precast girder only #REF! #REF! #REF! #REF! #REF!
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total DL #REF! #REF! #REF! #REF! #REF!
SIDL from staad output 127.0 104.4 80.8 57.5 34.9
Footpath live load 0.5 17.0 16.6 16.5 16.5
Live load incl. snow load 594.5 486.1 343.8 201.6 307.8
Total Live Load incl.snow load 595.0 503.1 360.4 218.1 324.4
Wind load (unloaded structure) -84.1 -63.1 -42.1 -21.0 0.0
Wind load (loaded structure) 43.6 32.7 21.8 10.9 0.0
Construction load 0.1 0.1 0.0 0.0 0.0
Total #REF! #REF! #REF! #REF! #REF!
130 of 221
5 (b) #REF! #REF! #REF! #REF! #REF!
Maximum #REF! #REF! #REF! #REF! #REF!
131 of 221
6.2 Cable Details
Maximum midspan Moment for outer girder =
Precast Girder Only = #REF! kN-m
Deck Slab & Cross Girder = #REF! kN-m
SIDL = 1085.03 kN-m
Wind load = 287.11 kN-m
Live Load = 2974.02 kN-m
Total Moment = #REF! kN-m
Sectional Properties Inner Composite Girder at Midspan :-
Area - A = 1.100 m2
Moment of Inertia - I = 0.969 m4
CG from bottom = 1.743 m
Z Bottom = 0.556 m3
Assume Nos. of Cable = N
Ultimate Force of each 19T13 strands P = #REF! kN
Applied Force = #REF! kN
CG From bottom = 0.237 m
"e" from CG of Girder = 1.506 m
Assum overall Loss = 30 %
Stress at bottom of Girder = NP/A+NP*e/ZBottom-M/Zbottom = 0
N = (M/ZBottom)/(P/A+P*e/ZBottom) = #REF!
Say, No of Cables Provided = 3.63
4.2.1 Calculation of Friction & Slip loss
1.275
4
0.375
X X X 3
2.75 0.375
2
4 0.180 0.375
1 3 2 0.180 1 0.350
0.125
0.17 0.310 0.17
0.65 0.65
Section at Midspan Section at Support
0.50 0.050
Y
4.50
1 2 X 0.155
0.155
0.15 0.550
Radius for 1 to 3 = 20 m
132 of 221
Horizontal bending of Cable 1 2.536 o
133 of 221
Position of Cable
Cable Anchorage Location of vertical Bending
No. X Y Z X Y Z
1 0.000 0.000 0.350 4.850 0.000 0.125
2 0.000 0.000 0.725 9.350 -0.155 0.125
3 0.000 0.000 1.10 11.150 0.000 0.305
3 0.000 0.000 1.48 11.150 0.000 0.485
Cable 1 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link
meter Degree Radian e (mf+kl) friction loss slip loss
(kN) (kN)
1 #REF! #REF!
1-2 4.855 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.503 3.672 0.064 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
4 #REF! 2585.89
Cable 2 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 4.860 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.512 4.462 0.078 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
134 of 221
4 #REF! 2594.76
135 of 221
4.860 4.512 8.950
#REF! #REF!
1 2 #REF! #REF!
= 3
= 2594.76 4
#REF! #REF!
#REF! #REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2594.76 kN
Point of Zero Slip from node 3 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = 36.644 m
Extension of cable = #REF! mm
Cable 3 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.178 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 4.078 0.071 #REF!
3 #REF! 2597.84
11.178 -10.750
#REF! #REF!
1 2 #REF!
= 3
= 2597.84
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2597.835 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.178+-10.75)x2 = 0.857 m
Extension of cable at each side = #REF! mm
Cable 4 12 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.194 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 5.074 0.089 #REF!
3 #REF! 1644.87
11.194 -10.750
#REF! #REF!
1 2 #REF!
= 3
= 1644.87
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 1644.8733 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.194+-10.75)x2 = 0.888 m
Extension of cable at each side = #REF! mm
136 of 221
4.2.2 Summary of Cable Forces after Friction & Slip at different Points
Position Support L/8 L/4 3L/8 L/2
Cable No 0.350 0.363 0.375 0.388 0.400
Cable 1 #REF! #REF! #REF! #REF! 2585.89
Vert. angle 2.656 2.656 2.656 0.000 0.000
Hor. angle 0.000 0.000 2.536 0.000 0.000
C.G. 0.334 0.125 0.125 0.125 0.125
Cable 2 #REF! #REF! #REF! #REF! 2594.76
Vert. angle 3.672 3.672 3.672 0.000 0.000
Hor. angle 0.000 0.000 2.536 2.536 0.000
C. G. 0.703 0.702 0.701 0.125 0.125
Cable 4 #REF! #REF! #REF! #REF! 1644.87
Vert. angle 5.074 5.074 5.074 5.074 0.000
Hor. angle 0.000 0.000 0.155 0.155 0.000
C. G. 1.444 1.443 1.442 1.441 0.485
Total cable
forces Normal #REF! #REF! #REF! #REF! 6825.53
at first stage
CG of Cable #REF! #REF! #REF! #REF! 0.212
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Cable 3 #REF! #REF! #REF! #REF! 2597.84
Vert. angle 4.078 4.078 4.078 4.078 0.000
Hor. angle 0.000 0.000 0.000 0.000 0.000
C. G. 1.075 1.074 1.073 1.072 0.305
Total cable
forces Normal #REF! #REF! #REF! #REF! 2597.84
CG of Cable 1.075 1.074 1.073 1.072 0.305
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Overall CG
of Cable
#REF! #REF! #REF! #REF! 0.237
% loss #REF! #REF! #REF! #REF! #REF!
137 of 221
6.3 Stress Calculation of girder
After 5 days casting of Precast Girder, first stage Cables shall be stressed as per given force & elongation.
Second stage Cables shall be stressed after 28 days of casting of precast girder. After that all Precast Girders
shall be erected at bearing locations and Deck slab & X-Girder shall be cast erecting necessary shuttering from
precast girder at 60 days. After 30 days casting of Deck Slab i.e. after 90 days casting of Precast Girder,
all shuttering material shall be removed and SIDL shall be laid. In such case Precast Longitudinal Girder shall be
checked for DL of Precast Girder, wt of Deck slab, wt of X-girder at 60 days. But composite girder
(precast girder+RCC deck) shall be checked for SIDL & Live load cases.
6.3.1 Loss calculation
6.3.1.1 Loss due to Elastic Shortening
Refer clause no.6.4.2.2, Annexure A-2 of IRC 112-2011 Average loss in Cable Stress = 1/2 m fc
fcm (t) = bcc(t)fcm bcc(t) = exp{S[1-(28/(t/t1)0^0.5]}
fck = Grade of concrete = #REF!
fcm (t) = mean concrete compressive strength at age 't' days
fcm = mean concrete compressive strength at age '28' days = #REF! Mpa
t = Age of concrete in days = 5 days
t1 = 1 day S = 0.25
bcc(t) = 0.71 fcm (t) = #REF! Mpa
fck (t) = #REF! Mpa
corresponding Ecm = 22x(fcm/12.5)^0.3 = #REF! Gpa
Ep = #REF! Gpa m =Modular Ratio = Ec/E = #REF!
To calculate average stress fc at CG of Cables due to Prestress and
Depth of Girder = 2.750 m Assume, Elastic Shortening = 69.33 kN/Cable
26.35 %
Area of each Cable = #REF! mm2 Number of cables (cable 1 to 3) = 2.63 Nos
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m2 Area = 1.806 m2
I= 0.601 m4 I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Sustained Stress of precast girder only at 5 days :-
Cable Force (kN) Cable CG Dead Load Dead Load Total Stress at
Section After fr. & After fr., slip from soffit Stress Moment Stress Stress cable CG
slip loss & ES loss (m) (Mpa) (kN-m) (kN/m2) (Mpa) (Mpa)
T #REF! #REF! #REF!
End #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T -10.18 #REF! #REF!
L/2 6825.53 6643.07 0.212 #REF! #REF!
B 27.41 #REF! #REF!
Average stress fc = #REF! = #REF! Mpa
Average Loss of cable stress = 1/2 m fc = #REF! Mpa
Loss of each cable due to Elastic shortening = 1/2 m fc As = #REF! kN
-10.18 Mpa #REF! Mpa #REF! Mpa
#REF! #REF!
Mpa
X X
+ = #REF! #REF!
Mpa
#REF!
138 of 221
6.3.1.2 Loss due to Relaxation of Steel (clause no. 6.3.6 of IRC 112-2011)
Total Relaxation Loss at service condition = 3 x (1000 hr. value)
Initial force after Friction, slip & ES loss #REF! #REF! kN
Percentage of Initial force = #VALUE! UTS
Relaxation Loss at 1000hr. for low relaxation steel = #VALUE! % of initial force
Relaxation Loss at 1000hr. for low relaxation steel #REF! #VALUE! kN/Cable
Immediate Loss i.e 1 hr. of stressing as per Table 6.2 of IRC 112-2011, = 37 % of Total Loss
5 - 28 days Loss 23 days 552 = 42.00 % of Total Loss
28 - 60 days Loss 32 days 768 = 21.00 % of Total Loss
60 - 90 days Loss 30 days = 0.00 % of Total Loss
90 - a days Loss = 200.0 % of Total Loss
i.e. 3 x (1000 hr. value)
Immediate Loss i.e 1 hr. of stressing = #VALUE! kN/Cable
5 - 28 days Loss = #VALUE! kN/Cable
28 - 60 days Loss = #VALUE! kN/Cable
60 - 90 days Loss = #VALUE! kN/Cable
90-a days Loss = #VALUE! kN/Cable
Total = #VALUE! kN/Cable
#VALUE! #VALUE! %
139 of 221
The coefficient b (t0) = 1/(0.1+to^0.2) = 0.68
Where, age of concrete at first loading t0 =5 day
bc(t,to) =[(t-to)/(bH +t-to)]^0.3
bH = = 1.5 x [1+(0.012RH)^18] x ho + 250 <= 1500 for fcm <= 35MPa
= 1.5 x [1+(0.012RH)^18] x ho + 250a3 <= 1500a3 for fcm <= 35MPa
The coefficient a 3 =(43.75/fcm)^0.5 #REF!
For temperature greater than 40 oC theby 10% in absence of accurate data coefficient may be increased by 10%
in absence of accurate data. This is valid for concrete using normal cement.
Development of creep
Loss due to
Creep
Days h0 (mm) f RH fo bH b c(t,to) creep of
coeff. fo concrete
Section Stress at 5 loss bet. 5 Cable CG Stress due Cable CG Total Stress at
days - 28 days from soffit to loss After fr. & After fr., slip from soffit Stress Stress cable CG
(kN/m2) (Tons) (m) (Mpa) slip loss & ES loss (m) (Mpa) (Mpa) (Mpa)
T #REF! #REF! #VALUE! #REF!
End #REF! #REF! #REF! #VALUE! 1.075 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/8 #REF! #REF! #REF! #VALUE! 1.074 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/4 #REF! #REF! #REF! #VALUE! 1.073 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
3L/8 #REF! #REF! #REF! #VALUE! 1.072 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/2 #REF! 0.212 2597.84 #VALUE! 0.305 #REF!
B #REF! #REF! #VALUE! #REF!
Average stress s s at CG of cables for 28 days = #REF! #REF! Mpa
Loss of cable stress = m (fc-fc') #REF! Mpa
Loss of each cable due to Elastic shortening = m fc As #REF! kN
140 of 221
Permissible Compressive stress 0.5xfcm #REF! MPa
Permissible tensile stress 0.7xftmj #REF! MPa
6.3.3. Sustained Stress of precast girder at 60 days after Casting of Deck with X-Girder
Losses for first 3 cables:- Losses for last 1 cable:-
Shrinkage = #REF! kN/Cable Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable Relaxation = #VALUE! kN/Cable
Creep = 38.44 kN/Cable Creep = 38.44 kN/Cable
Total = #REF! kN/Cable Total = #REF! kN/Cable
actual time dependent losses = #REF! kN/Cable actual time dependent losses = #REF! kN/Cable
Total Loss of 4 Cables = #REF! kN Actual Loss of third Cables = #REF! kN
Depth of Precast Girder = 2.750 m
141 of 221
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m 2
Area = 1.806 m2
I= 0.601 m 4
I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Stress at loss bet. 28 Cable CG Stress due Moment Stress Total Stress at
Section 28 days - 60 days from soffit to loss Total Stress due to slab due to Stress cable CG
(kN/m2) (kN) (m) (Mpa) (kN/m2) (kN-m) slab (Mpa) (Mpa) (Mpa)
Top of girder #REF! #REF! #REF! #REF! #REF!
End #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/2 #REF! 0.237 #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Average stress s s at CG of cables for 60 days = #REF! = #REF! Mpa
+ + =
#REF! #REF!
Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! Mpa #REF!
Resultant Stress at 28 Stress due to loss between Stress due to DL of Slab & Resultant Stress at 60
days 28 to 60 days wt of shuttering days
Stress Diagram at Midspan of Precast Girder at 60 days of Casting of Girder
Sectional Properties of Composite Girder at Midspan = Sectional Properties of Composite Girder at Support =
Area = 1.100 m 2
Area = 2.034 m2
I= 0.969 m 4
I= 1.608 m4
CG = 1.743 m CG = 1.555 m
Losses:- Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable
Creep = 18.18 kN/Cable
Total = #REF! kN/Cable
Total Loss = #REF! kN/Cable
actual time dependent losses = #REF! kN
Total Stress
Section Stress due Loss of CG of Cables Stress due Moment due due to Total Stress at
at 60 days Cables from soffit to loss to SIDL SIDL Stress cable CG
(Mpa) (kN) (m) (Mpa) (kN-m) (Mpa) (Mpa) (Mpa)
Top of slab 0.00 #REF! -0.01 #REF!
Top of girder #REF! #REF! -10.42 -0.01 #REF!
End #REF! #REF! #REF!
Bottom #REF! #REF! 0.01 #REF!
Top of slab 0.00 #REF! 0.21 #REF!
Top of girder #REF! #REF! 152.44 0.17 #REF!
L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -0.27 #REF!
Top of slab 0.00 #REF! 0.39 #REF!
Top of girder #REF! #REF! 280.34 0.32 #REF!
142 of 221
L/4 #REF! #REF! #REF!
Bottom #REF! #REF! -0.50 #REF!
Top of slab 0.00 #REF! 0.56 #REF!
Top of girder #REF! #REF! 401.28 0.46 #REF!
3L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -0.72 #REF!
Top of slab 0.00 #REF! 0.72 #REF!
Top of girder #REF! #REF! 517.79 0.59 #REF!
L/2 #REF! 0.237 #REF!
Bottom #REF! #REF! -0.93 #REF!
Average stress at 90 days = #REF! = #REF! Mpa
+ + =
143 of 221
#REF! Mpa #REF! #REF! Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! #REF! Mpa
Mpa #REF!
+ =
+ =
144 of 221
DL of girder+ deck slab Prestressing force & Loss SIDL
Section Loss of
Moment Stress Prestress CG of cables Loss of pre.
comp. girder
Stress Moment Stress
(kN-m) (Mpa) (kN) (m) Girder (kN) (Mpa) (kN-m) (Mpa)
(kN)
Top of slab #REF! -0.01
Top of girder #REF! #REF! -0.01
End #REF! #REF! #REF! #REF! #REF! -13.67
Bottom #REF! #REF! 0.01
Top of slab #REF! 0.52
Top of girder #REF! #REF! 0.41
L/8 #REF! #REF! #REF! #REF! #REF! 398.83
Bottom #REF! #REF! -0.72
Top of slab #REF! 0.91
Top of girder #REF! #REF! 0.73
L/4 #REF! #REF! #REF! #REF! #REF! 704.98
Bottom #REF! #REF! -1.27
Top of slab #REF! 1.21
Top of girder #REF! #REF! 0.97
3L/8 #REF! #REF! #REF! #REF! #REF! 932.90
Bottom #REF! #REF! -1.68
Top of slab #REF! 1.41
Top of girder #REF! #REF! 1.13
L/2 #REF! #REF! #REF! #REF! #REF! 1085.03
Bottom #REF! #REF! -1.95
Section Live load Wind load - loaded structure Temp (+ve) Temp (-ve)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
145 of 221
Wind load
Temp (+ve) 0.6 1 1
Temp (-ve) 0.6 0.6 1 1
146 of 221
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
147 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.48 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = #REF! Mpa #REF! #REF! #REF!
Stress with/without Live load at top of deck slab near support section only exceeds the permissible tensile stress i.e. 2.29Mpa.
Necessary reinforcement shall be provided to resist the tensile stress of deck slab.
Maximum tensile force = #REF! kN Permissible working stress = 240.00 MPa
Area of reinforcement required = #REF! mm2 Ast provided= 1021.02 mm2
Hence Provide 10 T @ 140 c/c + 10 T @ 140 c/c at top
6.3.9 Load Combination for frequent Combination (SL2) - for prestressing member
1) Dead load +SIDL+Prestress
2) Dead load +SIDL+Prestress+ wind load(lead) (unloaded structure)
3) Dead load +SIDL+Prestress+Live load(lead)+wind load (accompany)
4) Dead load +SIDL+Prestress+Live load(accompany)+wind load (lead)
5) Dead load +SIDL+Prestress+Live load(lead)+Temperature(accompany)
6) Dead load +SIDL+Prestress+Live load(accompany)+Temperature(lead)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
148 of 221
Load Case 5 (b) 5 (c) 5 (d) 6 (a) 6 (b) 6 (c) 6 (d)
DL 1 1 1 1 1 1 1
SIDL 1 1.2 1 1.2 1 1.2 1
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.75 0.2 0.2 0.2 0.2
Wind load
Temp (+ve) 0.5 0.6 0.6
Temp (-ve) 0.5 0.5 0.6 0.6
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
149 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.36 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = 0.00 Mpa #REF! #REF! #REF!
150 of 221
6.4 Check for ultimate strength of girder in Flexure :-
Grade of concrete #REF! Modulus of elasticity of concrete E #REF! MPa
Design yield strength fpd #REF! MPa Modulus of elasticity of steel #REF! Gpa
910 0.00350 #REF!
250 #REF!
197.28
NA NA
3000 300
151 of 221
Vertical Component of Cable Force (kN)
Position Support L/8 L/4 3L/8 L/2
Cable No #REF! #REF! #REF! #REF! #REF!
Cable 1 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 2 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 3 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 4 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Total Ver.
Comp. of
cable1 to 4 #REF! #REF! #REF! #REF! #REF!
ii) Shear Capacity of Uncracked Section as per clause 10.3.2(2) of IRC 112-2010
The shear resistance of the beam section uncracked in flexure is given below:-
VRd,c = ( I * bwc )/ S x √ (fctd2 + k1 scp fctd)
Where, I = Moment of inertia bwc= Width of beam after deduction due to duct
S = First moment of area between cetroidal axis and extreme compression fibre about the centrodial axis.
fctd = design tensile strength of concrete = f ctk/gm = #REF! Mpa
Description Support L/8 L/4 3L/8 L/2
Prestress Force after all losses (kN) #REF! #REF! #REF! #REF! #REF!
Effective width of the Web 650 300 300 300 300
Effective Depth of the Section (d) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Stress due to Prestress (scp) #REF! #REF! #REF! #REF! #REF!
Design tensile strength of the Concrete
#REF! #REF! #REF! #REF! #REF!
(fctd)
First moment of inertia about the CG (S) 3.11E+09 1.79E+09 1.79E+09 1.79E+09 1.79E+09
Transmission length factor, k1 1.00 1.00 1.00 1.00 1.00
Moment of Inertia (I) (mm4) 1.6E+12 9.7E+11 9.7E+11 9.7E+11 9.7E+11
Design Shear resistance ( VRd,c) (kN) #REF! #REF! #REF! #REF! #REF!
iii) Summary of the Shear resistance of the Beam when shear reinforcement isn't required :
The maximum shear capacity of the Beam as cl.10.3.2 (5) of IRC 112-2010
VEd ≤ 0.50 bw d n fcd where, n =0.60 [ 1 - fck/310]
152 of 221
Description Support L/8 L/4 3L/8 L/2
Distance from bearing in m 0.00 0.01 0.02 0.04 0.05
Distance modification factor b for Precast Beam 1.00 #VALUE! ### ### ###
Distance modification factor b for Composite### #VALUE! ### ### ###
Effective Shear for Precast Beam #REF! #REF! #REF! #REF! #REF!
Effective Shear for Composite Section (kN 0.0 0.0 0.0 0.0 0.0
Effective Shear due to prestressing force #REF! #REF! #REF! #REF! #REF!
Total Shear force for the Beam (kN) #REF! #REF! #REF! #REF! #REF!
Precast member Area (m2) 1.81 0.87 0.87 0.87 0.87
Zb (m3) 0.84 0.41 0.41 0.41 0.41
Composite member Area (m2) 2.03 1.10 1.10 1.10 1.10
Zb (m3) 1.03 0.56 0.56 0.56 0.56
Stress due to prestress at tensile fibre s bpt #REF! #REF! #REF! #REF! ###
Section at Maximum Bending Moment #REF! #REF! #REF! #REF! ###
Shear capacity of Beam Section (kN) #REF! #REF! #REF! #REF! ###
Maximum shear capacity of the Section ( ### #VALUE! ### ### ###
Whether shear reinforcement required or #REF! #REF! #REF! #REF! ###
153 of 221
Ypo/Yo = #REF! As per Table 13.1 of IRC 112-2011 Fbst/Pk = 0.120
Fbst = #REF! #REF! kN
Area of Steel Required = Fbst/(0.87xfy) #REF! mm2
Hence Provide 12T- 4L -4Nos along Web and Normal to Web Ast = 1809.56 mm2
154 of 221
6.9 Calculation for Deflection of Longitudinal girders
(i) Precast Girder - Prestress of cables 1, 2, 3 + wt of precast Girder at 5 days
Young Modulus = #REF! kN/m2
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.038 0.050
CG of Precast girder from bottom , m 1.389 1.448 1.448 1.448 1.448
Moment of Inertia for Precast
1.161 0.601 0.601 0.601 0.601
girder only (I) m4
CG of cables 1 to 2 from bot.(m) #REF! #REF! #REF! #REF! #REF!
Moment due to stressing after
#REF! #REF! #REF! #REF! #REF!
Momentlosses
due to(kN-m)
Wt of Precast
#REF! #REF! #REF! #REF! #REF!
Girder (kN-m)
Total moment due to
prestress+wt of precast Girder #REF! #REF! #REF! #REF! #REF!
(kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
(iii) Precast Girder - Prestress + wt of precast Girder +wt of deck slab at 60 days
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.038 0.050
CG of all cables from bot.(m) #REF! #REF! #REF! #REF! #REF!
Loss #REF! #REF! #REF! #REF! #REF!
Moment due to prestressing
#REF! #REF! #REF! #REF! #REF!
Moment due to Wt of (kN-m)
losses of cables Deck Slab
#REF! #REF! #REF! #REF! #REF!
(kN-m) due to
Total moment #REF! #REF! #REF! #REF! #REF!
prestress+DL (kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
0.0 0.013 0.013 0.013
A B C D E
#REF! #REF! #REF!
4 #REF! #REF!
3 1
2
155 of 221
4
3 1
2
M/EI Diagram for Ist Stage Prestress after losses at 60 days
156 of 221
At Midspan
Average Moment of M/EI about
Section Marked Distance CG from A M/EI Rotation
M/EI A
A #REF!
B 4 0.013 0.006 #REF! #REF! #REF! #REF!
C 3 0.013 0.019 #REF! #REF! #REF!
D 2 0.013 0.031 #REF! #REF! #REF!
E 1 0.013 0.044 #REF! #REF! #REF!
Total #REF!
So, Midspan deflection due to Prestress losses + DL = = #REF! mm
Total Deflection at 60 days #REF! = #REF! mm
157 of 221
7.0 Calculation of Stresses for Girder LG2 = 1.100 m
7.1. Load calculation
7.1.1 Dead Load Moment & Shear for Precast girder only
Unit weight of concrete #REF! kN/m3
Cross-sectional area at span = 0.873 m2
Cross-sectional area at support = 1.806 m2
Unit Weight at span #REF! kN/m
Unit Weight at support #REF! kN/m
Thickness of intermediate Cross Girder = 0.30 m
Thickness of end Cross Girder = 0.60 m
1.250 1.750 1.250
0.475 0
0.1 0.063
0
0
0.175 0.175
0.65 2.350 0.65
Part of intermediate cross girder #REF! #REF! kN
Part of End cross girder #REF! #REF! kN
#REF! kN
#REF! kN
#REF! #REF!
#REF!
0.500 0.00 0.00 0.10 0.00 0.00 0.500
158 of 221
Table : Maximum BM & SF at critical sections
159 of 221
Section At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.037 0.050
Bending Moment (kNm) #REF! #REF! #REF! #REF! #REF!
Shear Force (kN) #REF! #REF! #REF! #REF! #REF!
7.1.4 Summary of Bending Moment & Shear Force for inner girder
a) Bending Moment (kNm)
Description At support Near L/8 Near L/4 Near 3L/8 At L/2
Distance (m) 0.000 0.013 0.025 0.037 0.050
Precast girder only #REF! #REF! #REF! #REF! #REF!
Construction load -0.8 -0.8 -0.8 -0.8 -0.8
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total wt of deck slab = #REF! #REF! #REF! #REF! #REF!
SIDL from staad output -43.7 534.5 913.5 1092.1 1067.7
Removal of shutter -3.3 -246.4 -424.6 -531.6 -567.3
Footpath live load 30.8 147.9 264.2 318.05 307.05
Live load incl. snow load -50.4 968.2 1746.5 2355.2 2786.9
Total Live Load incl.snow load -19.6 1116.1 2010.7 2673.2 3093.9
Wind load (unloaded structure) 3.2 -240.7 -414.8 -519.33 -554.17
Wind load (loaded structure) -1.6 124.7 214.9 269.1 287.1
Construction load (1.5kN/m2) -0.2 -0.2 -0.2 -0.2 -0.2
Total Live Load -19.6 1116.1 2010.7 2673.2 3093.9
b) Shear force (kN) For SIDL & Live load - Refer STAAD Output
Desription At support Near L/8 Near L/4 Near 3L/8 At L/2
Precast girder only #REF! #REF! #REF! #REF! #REF!
Deck slab & X-girder #REF! #REF! #REF! #REF! #REF!
Total DL #REF! #REF! #REF! #REF! #REF!
SIDL from staad output 205.7 145.6 85.1 23.8 38.3
Footpath live load 64.1 44.4 25.8 6.4 13.4
Live load incl. snow load 314.7 264.5 212.9 172.3 152.9
Total Live Load incl.snow load 378.9 308.9 238.7 178.7 166.3
Wind load (unloaded structure) -84.1 -63.1 -42.1 -21.0 0.0
Wind load (loaded structure) 43.6 32.7 21.8 10.9 0.0
Construction load 0.1 0.1 0.0 0.0 0.0
Total #REF! #REF! #REF! #REF! #REF!
160 of 221
5 (a) #REF! #REF! #REF! #REF! #REF!
5 (b) #REF! #REF! #REF! #REF! #REF!
Maximum #REF! #REF! #REF! #REF! #REF!
161 of 221
7.2 Cable Details
Maximum midspan Moment for outer girder =
Precast Girder Only = #REF! kN-m
Deck Slab & Cross Girder = #REF! kN-m
SIDL = 1067.69 kN-m
Wind load = 287.12 kN-m
Live Load = 3093.91 kN-m
Total Moment = #REF! kN-m
Sectional Properties Inner Composite Girder at Midspan :-
Area - A = 1.100 m2
Moment of Inertia - I = 0.969 m4
CG from bottom = 1.743 m
Z Bottom = 0.556 m3
Assume Nos. of Cable = N
Ultimate Force of each 19T13 strands P = #REF! kN
Applied Force = #REF! kN
CG From bottom = 0.237 m
"e" from CG of Girder = 1.506 m
Assum overall Loss = 30 %
Stress at bottom of Girder = NP/A+NP*e/ZBottom-M/Zbottom = 0
N = (M/ZBottom)/(P/A+P*e/ZBottom) = #REF!
Say, No of Cables Provided = 3.63
4.2.1 Calculation of Friction & Slip loss
1.275
4
0.375
X X X 3
2.75 0.375
2
4 0.180 0.375
1 3 2 0.180 1 0.350
0.125
0.17 0.310 0.17
0.65 0.65
Section at Midspan Section at Support
0.50 0.050
Y
4.50
1 2 X 0.155
0.155
0.15 0.550
Radius for 1 to 3 = 20 m
162 of 221
Horizontal bending of Cable 1 2.536 o
163 of 221
Position of Cable
Cable Anchorage Location of vertical Bending
No. X Y Z X Y Z
1 0.000 0.000 0.350 4.850 0.000 0.125
2 0.000 0.000 0.725 9.350 -0.155 0.125
3 0.000 0.000 1.10 11.150 0.000 0.305
3 0.000 0.000 1.48 11.150 0.000 0.485
Cable 1 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link
meter Degree Radian e (mf+kl) friction loss slip loss
(kN) (kN)
1 #REF! #REF!
1-2 4.855 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.503 3.672 0.064 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
4 #REF! 2585.89
Cable 2 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian
(kN) (kN)
1 #REF! #REF!
1-2 4.860 0.00 0.000 #REF!
2 #REF! #REF!
2-3 4.512 4.462 0.078 #REF!
3 #REF! #REF!
3-4 8.950 2.536 0.044 #REF!
4 #REF! 2594.76
164 of 221
4.860 4.512 8.950
#REF! #REF!
1 2 #REF! #REF!
= 3
= 2594.76 4
#REF! #REF!
#REF! #REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2594.76 kN
Point of Zero Slip from node 3 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = 36.644 m
Extension of cable = #REF! mm
Cable 3 19 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.178 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 4.078 0.071 #REF!
3 #REF! 2597.84
11.178 -10.750
#REF! #REF!
1 2 #REF!
= 3
= 2597.84
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 2597.835 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.178+-10.75)x2 = 0.857 m
Extension of cable at each side = #REF! mm
Cable 4 12 T13
Force after Force after
Length (l) in Deflection Angle (f)
Node Link e (mf+kl) friction loss slip loss
meter Degree Radian (kN) (kN)
1 #REF! #REF!
1-2 11.194 0.00 0.000 #REF!
2 #REF! #REF!
2-3 -10.750 5.074 0.089 #REF!
3 #REF! 1644.87
11.194 -10.750
#REF! #REF!
1 2 #REF!
= 3
= 1644.87
#REF! #REF!
#REF!
Force Diagram before & after Slip Loss
Assume Force of zero slip = 1644.8733 kN
Point of Zero Slip from node 1 = #REF! m
Area of Shaded Portion = ExAxDL = #REF! kN-m
Area of Shaded Portion = #REF! kN-m
Diferance of these two forces #REF! = #REF! kN-m #REF!
Length of Cable = (11.194+-10.75)x2 = 0.888 m
Extension of cable at each side = #REF! mm
165 of 221
4.2.2 Summary of Cable Forces after Friction & Slip at different Points
Position Support L/8 L/4 3L/8 L/2
Cable No 0.350 0.363 0.375 0.388 0.400
Cable 1 #REF! #REF! #REF! #REF! 2585.89
Vert. angle 2.656 2.656 2.656 0.000 0.000
Hor. angle 0.000 0.000 2.536 0.000 0.000
C.G. 0.334 0.125 0.125 0.125 0.125
Cable 2 #REF! #REF! #REF! #REF! 2594.76
Vert. angle 3.672 3.672 3.672 0.000 0.000
Hor. angle 0.000 0.000 2.536 2.536 0.000
C. G. 0.703 0.702 0.701 0.125 0.125
Cable 4 #REF! #REF! #REF! #REF! 1644.87
Vert. angle 5.074 5.074 5.074 5.074 0.000
Hor. angle 0.000 0.000 0.155 0.155 0.000
C. G. 1.444 1.443 1.442 1.441 0.485
Total cable
forces Normal #REF! #REF! #REF! #REF! 6825.53
at first stage
CG of Cable #REF! #REF! #REF! #REF! 0.212
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Cable 3 #REF! #REF! #REF! #REF! 2597.84
Vert. angle 4.078 4.078 4.078 4.078 0.000
Hor. angle 0.000 0.000 0.000 0.000 0.000
C. G. 1.075 1.074 1.073 1.072 0.305
Total cable
forces Normal #REF! #REF! #REF! #REF! 2597.84
CG of Cable 1.075 1.074 1.073 1.072 0.305
Total cable
forces Per. #REF! #REF! #REF! #REF! 0.00
Overall CG
of Cable
#REF! #REF! #REF! #REF! 0.237
% loss #REF! #REF! #REF! #REF! #REF!
166 of 221
7.3 Stress Calculation of girder
After 5 days casting of Precast Girder, first stage Cables shall be stressed as per given force & elongation.
Second stage Cables shall be stressed after 28 days of casting of precast girder. After that all Precast Girders
shall be erected at bearing locations and Deck slab & X-Girder shall be cast erecting necessary shuttering from
precast girder at 60 days. After 30 days casting of Deck Slab i.e. after 90 days casting of Precast Girder,
all shuttering material shall be removed and SIDL shall be laid. In such case Precast Longitudinal Girder shall be
checked for DL of Precast Girder, wt of Deck slab, wt of X-girder at 60 days. But composite girder
(precast girder+RCC deck) shall be checked for SIDL & Live load cases.
7.3.1 Loss calculation
7.3.1.1 Loss due to Elastic Shortening
Refer clause no.6.4.2.2, Annexure A-2 of IRC 112-2011 Average loss in Cable Stress = 1/2 m fc
fcm (t) = bcc(t)fcm bcc(t) = exp{S[1-(28/(t/t1)0^0.5]}
fck = Grade of concrete = #REF!
fcm (t) = mean concrete compressive strength at age 't' days
fcm = mean concrete compressive strength at age '28' days = #REF! Mpa
t = Age of concrete in days = 5 days
t1 = 1 day S = 0.25
bcc(t) = 0.71 fcm (t) = #REF! Mpa
fck (t) = #REF! Mpa
corresponding Ecm = 22x(fcm/12.5)^0.3 = #REF! Gpa
Ep = #REF! Gpa m =Modular Ratio = Ec/E = #REF!
To calculate average stress fc at CG of Cables due to Prestress and
Depth of Girder = 2.750 m Assume, Elastic Shortening = 69.33 kN/Cable
26.35 %
Area of each Cable = #REF! mm2 Number of cables (cable 1 to 3) = 2.63 Nos
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m2 Area = 1.806 m2
I= 0.601 m4 I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Sustained Stress of precast girder only at 5 days :-
Cable Force (kN) Cable CG Dead Load Dead Load Total Stress at
Section After fr. & After fr., slip from soffit Stress Moment Stress Stress cable CG
slip loss & ES loss (m) (Mpa) (kN-m) (kN/m2) (Mpa) (Mpa)
T #REF! #REF! #REF!
End #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF! #REF!
B #REF! #REF! #REF!
T -10.18 #REF! #REF!
L/2 6825.53 6643.07 0.212 #REF! #REF!
B 27.41 #REF! #REF!
Average stress fc = #REF! = #REF! Mpa
Average Loss of cable stress = 1/2 m fc = #REF! Mpa
Loss of each cable due to Elastic shortening = 1/2 m fc As = #REF! kN
-10.18 Mpa #REF! Mpa #REF! Mpa
#REF! #REF!
Mpa
X X
+ = #REF! #REF!
Mpa
#REF!
167 of 221
7.3.1.2 Loss due to Relaxation of Steel (clause no. 6.3.6 of IRC 112-2011)
Total Relaxation Loss at service condition = 3 x (1000 hr. value)
Initial force after Friction, slip & ES loss #REF! #REF! kN
Percentage of Initial force = #VALUE! UTS
Relaxation Loss at 1000hr. for low relaxation steel = #VALUE! % of initial force
Relaxation Loss at 1000hr. for low relaxation steel #REF! #VALUE! kN/Cable
Immediate Loss i.e 1 hr. of stressing as per Table 6.2 of IRC 112-2011, = 37 % of Total Loss
5 - 28 days Loss 23 days 552 = 42.00 % of Total Loss
28 - 60 days Loss 32 days 768 = 21.00 % of Total Loss
60 - 90 days Loss 30 days = 0.00 % of Total Loss
90 - a days Loss = 200.0 % of Total Loss
i.e. 3 x (1000 hr. value)
Immediate Loss i.e 1 hr. of stressing = #VALUE! kN/Cable
5 - 28 days Loss = #VALUE! kN/Cable
28 - 60 days Loss = #VALUE! kN/Cable
60 - 90 days Loss = #VALUE! kN/Cable
90-a days Loss = #VALUE! kN/Cable
Total = #VALUE! kN/Cable
#VALUE! #VALUE! %
168 of 221
The coefficient b (t0) = 1/(0.1+to^0.2) = 0.68
Where, age of concrete at first loading t0 =5 day
bc(t,to) =[(t-to)/(bH +t-to)]^0.3
bH = = 1.5 x [1+(0.012RH)^18] x ho + 250 <= 1500 for fcm <= 35MPa
= 1.5 x [1+(0.012RH)^18] x ho + 250a3 <= 1500a3 for fcm <= 35MPa
The coefficient a 3 =(43.75/fcm)^0.5 #REF!
For temperature greater than 40 oC theby 10% in absence of accurate data coefficient may be increased by 10%
in absence of accurate data. This is valid for concrete using normal cement.
Development of creep
Loss due to
Creep
Days h0 (mm) f RH fo bH b c(t,to) creep of
coeff. fo concrete
Section Stress at 5 loss bet. 5 Cable CG Stress due Cable CG Total Stress at
days - 28 days from soffit to loss After fr. & After fr., slip from soffit Stress Stress cable CG
(kN/m2) (Tons) (m) (Mpa) slip loss & ES loss (m) (Mpa) (Mpa) (Mpa)
T #REF! #REF! #VALUE! #REF!
End #REF! #REF! #REF! #VALUE! 1.075 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/8 #REF! #REF! #REF! #VALUE! 1.074 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/4 #REF! #REF! #REF! #VALUE! 1.073 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
3L/8 #REF! #REF! #REF! #VALUE! 1.072 #REF!
B #REF! #REF! #VALUE! #REF!
T #REF! #REF! #VALUE! #REF!
L/2 #REF! 0.212 2597.84 #VALUE! 0.305 #REF!
B #REF! #REF! #VALUE! #REF!
Average stress s s at CG of cables for 28 days = #REF! #REF! Mpa
Loss of cable stress = m (fc-fc') #REF! Mpa
Loss of each cable due to Elastic shortening = m fc As #REF! kN
169 of 221
Permissible Compressive stress 0.5xfcm #REF! MPa
Permissible tensile stress 0.7xftmj #REF! MPa
7.3.3. Sustained Stress of precast girder at 60 days after Casting of Deck with X-Girder
Losses for first 3 cables:- Losses for last 1 cable:-
Shrinkage = #REF! kN/Cable Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable Relaxation = #VALUE! kN/Cable
Creep = 38.44 kN/Cable Creep = 38.44 kN/Cable
Total = #REF! kN/Cable Total = #REF! kN/Cable
actual time dependent losses = #REF! kN/Cable actual time dependent losses = #REF! kN/Cable
Total Loss of 4 Cables = #REF! kN Actual Loss of third Cables = #REF! kN
Depth of Precast Girder = 2.750 m
Sectional Properties of Precast Girder at Midspan = Sectional Properties of Precast Girder at Support =
Area = 0.873 m2 Area = 1.806 m2
I= 0.601 m4
I= 1.161 m4
CG = 1.448 m CG = 1.389 m
Stress at loss bet. 28 Cable CG Stress due Moment Stress Total Stress at
Section 28 days - 60 days from soffit to loss Total Stress due to slab due to Stress cable CG
(kN/m2) (kN) (m) (Mpa) (kN/m2) (kN-m) slab (Mpa) (Mpa) (Mpa)
Top of girder #REF! #REF! #REF! #REF! #REF!
End #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/4 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
3L/8 #REF! #REF! #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF!
L/2 #REF! 0.237 #REF! #REF!
Bottom #REF! #REF! #REF! #REF! #REF!
Average stress s s at CG of cables for 60 days = #REF! = #REF! Mpa
+ + =
#REF! #REF!
Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! Mpa #REF!
Resultant Stress at 28 Stress due to loss between Stress due to DL of Slab & Resultant Stress at 60
days 28 to 60 days wt of shuttering days
Stress Diagram at Midspan of Precast Girder at 60 days of Casting of Girder
Sectional Properties of Composite Girder at Midspan = Sectional Properties of Composite Girder at Support =
Area = 1.100 m2 Area = 2.034 m2
I= 0.969 m 4
I= 1.608 m4
CG = 1.743 m CG = 1.555 m
Losses:- Shrinkage = #REF! kN/Cable
Relaxation = #VALUE! kN/Cable
Creep = 18.29 kN/Cable
Total = #REF! kN/Cable
Total Loss = #REF! kN/Cable
actual time dependent losses = #REF! kN
170 of 221
Total Stress
Section Stress due Loss of CG of Cables Stress due Moment due due to Total Stress at
at 60 days Cables from soffit to loss to SIDL SIDL Stress cable CG
(Mpa) (kN) (m) (Mpa) (kN-m) (Mpa) (Mpa) (Mpa)
Top of slab 0.00 #REF! -0.05 #REF!
Top of girder #REF! #REF! -47.00 -0.04 #REF!
End #REF! #REF! #REF!
Bottom #REF! #REF! 0.05 #REF!
Top of slab 0.00 #REF! 0.40 #REF!
Top of girder #REF! #REF! 288.10 0.33 #REF!
L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -0.52 #REF!
Top of slab 0.00 #REF! 0.68 #REF!
Top of girder #REF! #REF! 488.85 0.56 #REF!
L/4 #REF! #REF! #REF!
Bottom #REF! #REF! -0.88 #REF!
Top of slab 0.00 #REF! 0.78 #REF!
Top of girder #REF! #REF! 560.51 0.64 #REF!
3L/8 #REF! #REF! #REF!
Bottom #REF! #REF! -1.01 #REF!
Top of slab 0.00 #REF! 0.70 #REF!
Top of girder #REF! #REF! 500.42 0.57 #REF!
L/2 #REF! 0.237 #REF!
Bottom #REF! #REF! -0.90 #REF!
Average stress at 90 days = #REF! = #REF! Mpa
+ + =
171 of 221
#REF! Mpa #REF! #REF! Mpa
#REF! Mpa #REF! Mpa #REF! Mpa #REF! #REF! Mpa
Mpa #REF!
+ =
+ =
172 of 221
DL of girder+ deck slab Prestressing force & Loss SIDL
Section Loss of
Moment Stress Prestress CG of cables Loss of pre.
comp. girder
Stress Moment Stress
(kN-m) (Mpa) (kN) (m) Girder (kN) (Mpa) (kN-m) (Mpa)
(kN)
Top of slab #REF! -0.04
Top of girder #REF! #REF! -0.03
End #REF! #REF! #REF! #REF! #REF! -43.74
Bottom #REF! #REF! 0.04
Top of slab #REF! 0.69
Top of girder #REF! #REF! 0.56
L/8 #REF! #REF! #REF! #REF! #REF! 534.47
Bottom #REF! #REF! -0.96
Top of slab #REF! 1.18
Top of girder #REF! #REF! 0.95
L/4 #REF! #REF! #REF! #REF! #REF! 913.46
Bottom #REF! #REF! -1.64
Top of slab #REF! 1.42
Top of girder #REF! #REF! 1.13
3L/8 #REF! #REF! #REF! #REF! #REF! 1092.11
Bottom #REF! #REF! -1.96
Top of slab #REF! 1.38
Top of girder #REF! #REF! 1.11
L/2 #REF! #REF! #REF! #REF! #REF! 1067.69
Bottom #REF! #REF! -1.92
Section Live load Wind load - loaded structure Temp (+ve) Temp (-ve)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
173 of 221
Wind load
Temp (+ve) 0.6 1 1
Temp (-ve) 0.6 0.6 1 1
174 of 221
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 1 1 0.75 0.75 1
Wind load 0.6 0.6 0.6 0.6 1 1
Temp (+ve) 0.6
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
175 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.48 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = #REF! Mpa #REF! #REF! #REF!
Stress with/without Live load at top of deck slab near support section only exceeds the permissible tensile stress i.e. 2.29Mpa.
Necessary reinforcement shall be provided to resist the tensile stress of deck slab.
Maximum tensile force = #REF! kN Permissible working stress = 240.00 MPa
Area of reinforcement required = #REF! mm2 Ast provided= 1021.02 mm2
Hence Provide 10 T @ 140 c/c + 10 T @ 140 c/c at top
7.3.9 Load Combination for frequent Combination (SL2) - for prestressing member
1) Dead load +SIDL+Prestress
2) Dead load +SIDL+Prestress+ wind load(lead) (unloaded structure)
3) Dead load +SIDL+Prestress+Live load(lead)+wind load (accompany)
4) Dead load +SIDL+Prestress+Live load(accompany)+wind load (lead)
5) Dead load +SIDL+Prestress+Live load(lead)+Temperature(accompany)
6) Dead load +SIDL+Prestress+Live load(accompany)+Temperature(lead)
a) Load combination
Load Case 1 (a) 1 (b) 2 (a) 2 (b) 3 (a) 3 (b) 4 (a) 4 (b) 5 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
176 of 221
Load Case 5 (b) 5 (c) 5 (d) 6 (a) 6 (b) 6 (c) 6 (d)
DL 1 1 1 1 1 1 1
SIDL 1 1.2 1 1.2 1 1.2 1
Prestress 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Live load 0.75 0.75 0.75 0.2 0.2 0.2 0.2
Wind load
Temp (+ve) 0.5 0.6 0.6
Temp (-ve) 0.5 0.5 0.6 0.6
Load Case 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
DL 1 1 1 1 1 1 1 1 1
SIDL 1.2 1 1.2 1 1.2 1 1.2 1 1.2
Prestress 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Live load 0.75 0.75 0.2 0.2 0.75
Wind load 0.6 0.6 0.5 0.5 0.6 0.6
Temp (+ve) 0.5
Temp (-ve)
Section 5 (b) 5 (c ) 5 (d) 6 (a) 6 (b) 6 (c) 6 (c) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
177 of 221
Section 7 (a) 7 (b) 8 (a) 8 (b) 9 (a) 9 (b) 10 (a) 10 (b) 11 (a)
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Section 11 (b) 11 (c) 11 (d) 12 (a) 12 (b) 12 (c) 12 (d) Max comp.Max Tension
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
End
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/4
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3L/8
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of slab #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Top of girder #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
L/2
Bottom #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Permissible compressive stress in concrete at service = 0.36 x fck #REF! Mpa #REF! #REF!
Permissible Tensile stress in concrete at service = 0.00 Mpa #REF! #REF! #REF!
178 of 221
7.4 Check for ultimate strength of girder in Flexure :-
Grade of concrete #REF! Modulus of elasticity of concrete E #REF! MPa
Design yield strength fpd #REF! MPa Modulus of elasticity of steel #REF! Gpa
910 0.00350 #REF!
250 #REF!
197.28
NA NA
3000 300
179 of 221
Vertical Component of Cable Force (kN)
Position Support L/8 L/4 3L/8 L/2
Cable No #REF! #REF! #REF! #REF! #REF!
Cable 1 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 2 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 3 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Cable 4 #REF! #REF! #REF! #REF! #REF!
Vert. angle #REF! #REF! #REF! #REF! #REF!
Total Ver.
Comp. of
cable1 to 4 #REF! #REF! #REF! #REF! #REF!
ii) Shear Capacity of Uncracked Section as per clause 10.3.2(2) of IRC 112-2010
The shear resistance of the beam section uncracked in flexure is given below:-
VRd,c = ( I * bwc )/ S x √ (fctd2 + k1 scp fctd)
Where, I = Moment of inertia bwc= Width of beam after deduction due to duct
S = First moment of area between cetroidal axis and extreme compression fibre about the centrodial axis.
fctd = design tensile strength of concrete = f ctk/gm = #REF! Mpa
Description Support L/8 L/4 3L/8 L/2
Prestress Force after all losses (kN) #REF! #REF! #REF! #REF! #REF!
Effective width of the Web 650 300 300 300 300
Effective Depth of the Section (d) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Stress due to Prestress (scp) #REF! #REF! #REF! #REF! #REF!
Design tensile strength of the Concrete
#REF! #REF! #REF! #REF! #REF!
(fctd)
First moment of inertia about the CG (S) 3.11E+09 1.79E+09 1.79E+09 1.79E+09 1.79E+09
Transmission length factor, k1 1.00 1.00 1.00 1.00 1.00
Moment of Inertia (I) (mm4) 1.6E+12 9.7E+11 9.7E+11 9.7E+11 9.7E+11
Design Shear resistance ( VRd,c) (kN) #REF! #REF! #REF! #REF! #REF!
iii) Summary of the Shear resistance of the Beam when shear reinforcement isn't required :
The maximum shear capacity of the Beam as cl.10.3.2 (5) of IRC 112-2010
VEd ≤ 0.50 bw d n fcd where, n =0.60 [ 1 - fck/310]
180 of 221
Description Support L/8 L/4 3L/8 L/2
Distance from bearing in m 0.00 0.01 0.02 0.04 0.05
Distance modification factor b for Precast Beam 1.00 #VALUE! ### ### ###
Distance modification factor b for Composite### #VALUE! ### ### ###
Effective Shear for Precast Beam #REF! #REF! #REF! #REF! #REF!
Effective Shear for Composite Section (kN 0.0 0.0 0.0 0.0 0.0
Effective Shear due to prestressing force #REF! #REF! #REF! #REF! #REF!
Total Shear force for the Beam (kN) #REF! #REF! #REF! #REF! #REF!
Precast member Area (m2) 1.81 0.87 0.87 0.87 0.87
Zb (m3) 0.84 0.41 0.41 0.41 0.41
Composite member Area (m2) 2.03 1.10 1.10 1.10 1.10
Zb (m3) 1.03 0.56 0.56 0.56 0.56
Stress due to prestress at tensile fibre s bpt #REF! #REF! #REF! #REF! ###
Section at Maximum Bending Moment #REF! #REF! #REF! #REF! ###
Shear capacity of Beam Section (kN) #REF! #REF! #REF! #REF! ###
Maximum shear capacity of the Section ( ### #VALUE! ### ### ###
Whether shear reinforcement required or #REF! #REF! #REF! #REF! ###
181 of 221
Ypo/Yo = #REF! As per Table 13.1 of IRC 112-2011 Fbst/Pk = 0.120
Fbst = #REF! #REF! kN
Area of Steel Required = Fbst/(0.87xfy) #REF! mm2
Hence Provide 12T- 4L -4Nos along Web and Normal to Web Ast = 1809.56 mm2
182 of 221
7.9 Calculation for Deflection of Longitudinal girders
(i) Precast Girder - Prestress of cables 1, 2, 3 + wt of precast Girder at 5 days
Young Modulus = #REF! kN/m2
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.037 0.050
CG of Precast girder from bottom , m 1.389 1.448 1.448 1.448 1.448
Moment of Inertia for Precast
1.161 0.601 0.601 0.601 0.601
girder only (I) m4
CG of cables 1 to 2 from bot.(m) #REF! #REF! #REF! #REF! #REF!
Moment due to stressing after
#REF! #REF! #REF! #REF! #REF!
Momentlosses
due to(kN-m)
Wt of Precast
#REF! #REF! #REF! #REF! #REF!
Girder (kN-m)
Total moment due to
prestress+wt of precast Girder
#REF! #REF! #REF! #REF! #REF!
(kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
(iii) Precast Girder - Prestress + wt of precast Girder +wt of deck slab at 60 days
Section At support Near L/8 At L/4 At 3L/8 At L/2
Distance 0.000 0.013 0.025 0.037 0.050
CG of all cables from bot.(m) #REF! #REF! #REF! #REF! #REF!
Loss #REF! #REF! #REF! #REF! #REF!
Moment due to prestressing
#REF! #REF! #REF! #REF! #REF!
losses
Moment of to
due cables
Wt of (kN-m)
Deck Slab
#REF! #REF! #REF! #REF! #REF!
(kN-m) due to
Total moment #REF! #REF! #REF! #REF! #REF!
prestress+DL (kN-m)
M/EI (1/m) #REF! #REF! #REF! #REF! #REF!
0.0 0.013 0.013 0.013
A B C D E
#REF! #REF! #REF!
4 #REF! #REF!
3 1
2
183 of 221
4
3 1
2
M/EI Diagram for Ist Stage Prestress after losses at 60 days
At Midspan
Average Moment of M/EI about
Section Marked Distance CG from A M/EI Rotation
M/EI A
A #REF!
B 4 0.013 0.006 #REF! #REF! #REF! #REF!
C 3 0.013 0.019 #REF! #REF! #REF!
D 2 0.013 0.031 #REF! #REF! #REF!
E 1 0.013 0.044 #REF! #REF! #REF!
Total #REF!
So, Midspan deflection due to Prestress losses + DL = = #REF! mm
Total Deflection at 60 days #REF! = #REF! mm
184 of 221
11.0 Design of Stiffener
11.1 Outer Girder
(i) Design of Intermediate stiffeners [ As per Clause 509.7 of IRC:24-2010]
When transverse stifener are not required as per CL No .509.6.11a of IRC :24 -2010
Thickness of web plate without stifener plates d/tw <200ԑw d = 2000 mm
Where ԑw =(250/fy)^(1/2) = 0.78 tw > 12.81 mm
As per Clause No: 509.7 of IRC 24 -2010 Shear buckling resistance Shall be checked
If C/d >SQRT(2) Is > 0.75dtw3 If C/d <SQRT(2) Is > 1.5d3tw3/c2
Depth of Stifener = dt = 2 m
Total Shear Force = Vsf = 610 kN
No of Weld Surface Available = = 2 Nos
Minimum Weld Size required as per [ IS :9595-1980] = 4 mm
Weld Size Provided = 8 mm
Efective Length of Weld = 4 m
Permissible Shear Cpacity of Fiilet Weld in Shop = 236.7 N/mm2
Shear Capacity of continuous weld = 1339.0 kN/m
> 304.75 kN/m
Hence OK
185 of 221
(iii) Design of Bearing Stiffener [ As per Cl NO: 508.11.1 of IRC:24-2010]
As per Clause No: 507.12 Pd =Ae fcd ϒmo = 1.1 fcd = Design Compressive Stress
A = 16060 mm2
Ixx = 4E+08
r = 149.33 mm
Ix = 0.34αs D3 Tef
αs = 0.006 for L/ry < 50
= 0.006 for 50 <L/ry < 100
= 30/(L/ry)^2 for L/ry >101
Here αs = 0.006
D = 2060 mm
Tef = 28 mm
Ix = 5E+08 mm4
Ixx = 3.6E+08 mm4
Hence OK
186 of 221
11.2 Inner Girder
(i) Design of Intermediate stiffeners [ As per Clause 509.7 of IRC:24-2010]
When transverse stifener are not required as per CL No .509.6.11a of IRC :24 -2010
Thickness of web plate without stifener plates d/tw <200ԑw d = 2000 mm
Where ԑw =(250/fy)^(1/2) = 0.78 tw > 12.81 mm
As per Clause No: 509.7 of IRC 24 -2010 Shear buckling resistance Shall be checked
If C/d >SQRT(2) Is > 0.75dtw3 If C/d <SQRT(2) Is > 1.5d3tw3/c2
Depth of Stifener = dt = 2 m
Total Shear Force = Vsf = 610 kN
No of Weld Surface Available = = 2 Nos
Minimum Weld Size required as per [ IS :9595-1980] = 4 mm
Weld Size Provided = 8 mm
Efective Length of Weld = 4 m
Permissible Shear Cpacity of Fiilet Weld in Shop = 236.7 N/mm2
Shear Capacity of continuous weld = 1339.0 kN/m
> 304.75 kN/m
Hence OK
187 of 221
(iii) Design of Bearing Stiffener [ As per Cl NO: 508.11.1 of IRC:24-2010]
As per Clause No: 507.12 Pd =Ae fcd ϒmo = 1.1 fcd = Design Compressive Stress
A = 16060 mm2
Ixx = 4E+08
r = 149.33 mm
Ix = 0.34αs D3 Tef
αs = 0.006 for L/ry < 50
= 0.006 for 50 <L/ry < 100
= 30/(L/ry)^2 for L/ry >101
Here αs = 0.006
D = 2060 mm
Tef = 28 mm
Ix = 5E+08 mm4
Ixx = 3.6E+08 mm4
Hence OK
188 of 221
12 Design of Connection at Support
A Outer Girder
[ As per Clause 512.4 of IRC:24-
(i) Design of welds between web and top flange
2010]
Horizontal shear force at the junction of web and top flange has been given by
H1 = V x Af x Y
I
Load acting on Steel Section Only
Shear Force in Steel Section Due to DL V1 = 791.3 kN
Cross Sectional Area of Top Flange Af = 0.0126 m2
Moment of Inertia of top flangeabout major axis I1 = 0.0450 m4
Distance of CG of flange plate from top of girder Y= 0.01400 m
Distance Between CG of Top Fibre to CG of Girde Y1 = 1.5751 m
Horizontal Shear Force H1 = 349.0 kN/m
877.3 kN/m
P/fa x Izz
lw = P/fa ∑t = xq /VAfYf
= 8.190 m
fa = 0.3588 N/mm2
189 of 221
Horizontal shear force at the junction of web and top flange has been given by
H1 = V x Ab x Y
I
Load acting on Steel Section Only
Shear Force in Steel Section Due to DL V1 = 791.3 kN
Cross Sectional Area of Bottom Ab1
Flange
= 0.0306 m2
486.3 kN/m
P/fa x Izz
lw = P/fa ∑t = xq /VAfYf
= 11.574 m
fa = 0.4513 N/mm2
190 of 221
14 Design of Connection Between Deck Slab and Inner Girder
[ As per Clause No. 606 of IRC :22-2008]
Calculation of Longitudinal shear at junction of deck slab and girder
shear connector has been designed from the consideration of fatigue strength of
connector and ultimate flexural strength of the composite section.Stud type shear
connector is used here
The maximum longitudinal force due to bending is to be calculated over the shear span from from
zero moment to maximum moment section and is given by smaller of Aslfy10-3/ϒm and H2 =
0.36fckAec10-3kN
192 of 221
9.0 Design of Deck Slab
Assume Width of Slab = 1.000 m
Maximum cantilever span of deck slab = 1.500 m
9.1 Design of Cantilever Slab beyond outer longitudinal girder
500 mm
Wearing course.
65
250 250 mm
300 1350 mm
1500 mm
193 of 221
9.2 Deck slab between girders
9.2.1 Dead Load +SIDL
Dead load #REF! = #REF! kN/m
SIDL for crash barrier = 7.5 kN/m
Wearing course 0.065*22 = 1.43 kN/m
7.5 7.5 7
1.43 kN/m
1.500 3 3 3 1.500
4.57
0.84 0.840
2.9
2.06
2.06
1.5
1.50 3 3 3 1.50
70R- Track Loading position over Deck for maximum moment
Centre to centre distance between X-gider b = 0.010 m
Span L = 3 m
Total Load = 700 kN
Impact Factor = 25 %
Dispersion of load along direction of movement
As per Annexure B-3 of IRC 112:2011 bef = a a(1-a/L)+b1
b/L = 0.00 a = 2.6
a1 = 1.5 m
Thickness of W/C = 65 mm Thick. of Deck slab = 250 mm
b1 =4.57+0.065x2 = 4.70 m
bef 1 = 6.650 m
=10/((0.86-0.05)x5.273x10) 1.22
0.234
0.86 0.86
2.79
1.93
Position of 70R Wheel bogie load
1.93
194 of 221
1.5
1.50 3 3 3 1.50
70R- Track Loading position over Deck for maximum moment
Total Load = 400 kN
Impact Factor = 25 %
Dispersion of load along direction of movement
As per Annexure B-3 of IRC 112:2011 bef = a a(1-a/L)+b1
a = 2.6 a = 1.5 m
Thickness of W/C = 65 mm Thick. of Deck slab = 250 mm
b1 =0.234+0.065x2 = 0.364 m
bef = 2.314 m
> 1.220 m Overlaps.
Modified bef =2.314+1.22 = 3.534 m
1.2
0.250
0.5 0.50
2.3
1.8
Position of Class-A loading
1.50 3 3 3 1.50
70R- Track Loading position over Deck for maximum moment
Each Axle load = 114 kN
Impact Factor = 50 %
Dispersion of load along direction of movement
As per Annexure B-3 of IRC 112:2011 bef = a a(1-a/L)+b1
a = 2.6 For Ist Wheel a = 1.500 m
Thickness of W/C = 65 mm Thick. of Deck slab = 250 mm
b1 =0.250+0.065x2 = 0.380 m bef = 2.030 m
> 1.200 m Overlaps.
Modified bef1 = 3.230 m
195 of 221
Modified bef3 = 3.313 m
600 700 mm
End cross Girder 1000 mm
Wearing course.
Cross Section Showing Cantilever slab
i) Dead load +SIDL Wt (kN) D (m) M (kN-m)
Slab Uniform 0.4x0.7x25 7.00 0.350 2.450
Varying (0.4-0.4)x0.7/2x25 0.00 0.233 0.000
Wearing course 0.065x0.7x22 1.00 0.350 0.350
Total 8.00 2.80
65
400
196 of 221
400
L= 700 mm
Wearing course.
Cross Section Showing placing of 70R-Tracked Loading
Total load per track = 350 kN
Length of Track = 4.57 m
Impact Factor = 25 %
Total weight on Cantilever slab 350x0.7x(1+25/100)/4.57 = 67.0 kN
Overall width of track = 0.84 m
As per Annexure B-3 of IRC 112:2011
bef = 1.2a+b1
a = The distance of the C.G. of loading from support = 0.350 m
b1= The breadth of con.area of the wheel over slab = 0.970 m
bef = = 1.390 m
< 2.060 m
does not overlap
Shear = 67.0/1.39 48.21 kN/m width
Moment = 67.0x0.35/1.39 16.87 kN-m/m width
iii) 70R-Wheeled Loading- 20t axle load 250.00 kN
65
400
400
L= 700 mm
65
400
400
L= 700 mm
197 of 221
bef = 1.2a+b1
a = The distance of the C.G. of loading from support = 0.575 m
b1= The breadth of con.area of the wheel over slab = 0.630 m
bef = 1.320 m
< 1.800 m
does not overlap
Modified bef 1.32 = 1.320 m
Shear = 171.0/2/1.32 64.77 kN/m width
Moment = 171.0/2x0.57/1.32 37.24 kN-m/m width
v) Summary of loading
DL SIDL 70R- Trac 70R- Wheel Class A
Shear 7.00 1.00 48.21 73.99 64.77
Moment 2.45 0.35 16.87 43.13 37.24
198 of 221
9.4 Summary of Bending Moment of slab
Tranverse section of slab Cantilever
Location End Inner slab at exp.
Span Joint
support support
DL 5.70 1.264 3.801 2.45
Service SIDL 8.88 -2.947 -1.09 0.35
condition Live
Load
16.23 25.391 35.506 43.13
Cant. slab at
Tranverse section of slab exp. Joint
Inner
End support Moment (kN-
Load Case (kN-m)
Span (kN-m) support
m)
(kN-m)
Service
condition
1 16.35 -2.27 2.49 2.87
48 0.0162 #REF!
1000 Strain Diagram Stress Diagram
199 of 221
Grade Concrete = #REF! Grade of steel = #REF!
Width of the section = 1000 mm Depth of the section = 250 mm
Clear Cover = 40 mm Main dia of bar used = 16 mm
Dia of shear reinf. = 0 mm Effective depth, d = 202 mm
R = Mu/bd2 = 1.166 MPa Design Moment = 47.58 kN-m
Mu,Lim/bd2
= 0.133xfc = #REF! MPa Ast = #REF! mm2
Lower fractile tensile fctm #REF! MPa Where, pt = fck/(2*fy)*(1-sqrt(1-(4.598*R/fck))*100
Min. reinforcement 0.26xfctm/fykxbtxd but not less than 0.0013btd = #REF! mm2
Hence provide 12 dia @ 170 c/c Ast = 1330.6 mm2
12 dia @ 170 c/c #REF! #REF! mm2 #REF!
200 of 221
#REF! 8.75
197.71
45.21
NA NA
#REF!
#REF!
Strain Diagram Stress Diagram
#REF! =
Total compressive for = 197.71 kN Total tensile force = #REF! kN
Compressive force C = 15.07 mm Moment of resistance = #REF! kNm
Rare Combination (SL1) Quasi-permanent Combination (SL2)
Tranverse section of slab Cant. slab Tranverse section of slab Cant. slab
Description Inner Inner
End support Span Support End support Span Support
support support
h or D 250 250 250 400 250 250 250 400
b 1000 1000 1000 1000 1000 1000 1000 1000
d 202 202 202 352 202 202 202 352
Moment 32.59 23.71 38.22 46.00 16.35 -2.27 2.49 2.87
Reinf provided 12 dia 12 dia 12 dia 10 dia 12 dia 12 dia 12 dia 10 dia
@ 170 c/c @ 170 c/c @ 170 c/c @ 140 c/c @ 170 c/c @ 170 c/c @ 170 c/c @ 140 c/c
12 dia 12 dia 12 dia 10 dia 12 dia 12 dia 12 dia 10 dia
@ 170 c/c @ 170 c/c @ 170 c/c @ 140 c/c @ 170 c/c @ 170 c/c @ 170 c/c @ 140 c/c
Ast provided 1330.6 1330.6 1330.6 1122.0 1330.6 1330.6 1330.6 1122.0
Stress in concrete 8.7 6.5 10.4 4.5 4.3 -0.6 0.7 0.3
Actual NA 45.21 45.21 45.21 61.63 45.21 45.21 45.21 61.63
Stress in steel #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Total ultimate tensile #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Total ultimate compre 198 146 236 139 97 -14 15 9
Diference of force #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Compressive force C 15.1 15.1 15.1 20.5 15.1 15.1 15.1 20.5
Moment of resistance #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Dif. of moment #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
9.6.2. Check for crack width Check crack width As per IRC : 112-2011
Crack width, Wk = Sr,max * (esm-ecm)
Where, esm-ecm = (ssc-kt*fct,eff/rp,eff*(1+ae*rp,eff))/Es >= 0.6ssc/Es
ssc = #REF! Mpa ae =Es/Ecm = #REF!
kt = 0.5 hc,eff=min of [2.5(h-d),(h-x/3),h/2]= 120.0 mm
Ac,eff =b*hc,eff rp,eff = As/Ac,eff = 0.011
fct,eff = #REF! Mpa esm-ecm = #REF!
>= 0.6ssc/Es= #REF!
Sr,max =3.4c+0.425*k1*k2*f/rp,eff Where, c = 40 mm
k1 = 0.8
feq=(n1*f1^2+n2*f2^2)/((n1*f1+n2*f2) = 12.0 mm k2 = 0.5
Sr,max = 320.0 mm Crack width, Wk = = #REF! mm
< 0.3 mm #REF!
Tranverse section of slab Cant. slab
Description End Inner
Span Support
support support
Stress in steel, ss #REF! #REF! #REF! #REF!
As 1330.6 1330.6 1330.6 1122.0
Actual NA 45 45 45 62
hc,ef 120.0 120.0 120.0 120.0
rp,eff 0.011 0.011 0.011 0.009
esm-ecm #REF! #REF! #REF! #REF!
feq 12.0 12.0 12.0 10.0
Crack spacing Sr,max 320.0 320.0 320.0 317.8
Crack width, Wk #REF! #REF! #REF! #REF!
Check #REF! #REF! #REF! #REF!
201 of 221
9.6.3. Tranverse reinforcement
Minimum main reinf. 0.26xfctm/fykxbtxd but not less than 0.0013btd = #REF! mm2
Main reinf. provided = 1330.6 mm2
As per clause 16.6.1.1 (3) of IRC-112:2011, minimum tranverse reinforcement is 20% of main reinforcement.
Minimum tranverse reinforcement = 266.1 mm2
As per clause 16.5.4 (4) of IRC-112:2011,the area of surface reinforcement is 0.01 A ct ext.
Where Act ext is the area of cover = 400.0 mm2
Stress at top of deck slab near support section exceeds the permissible tensile stress i.e. 1.53Mpa.
Necessary reinforcement shall be provided to resist the tensile stress of deck slab.
Maximum tensile stress = #REF! MPa Maximum tensile force = #VALUE! kN/m width
Permissible working stress = 240.00 MPa Area of reinforcement required = #VALUE! mm2
Hence Provide 10 dia 140 c/c at top & bottom Ast provided = 1122.00 mm2
10 dia 140 c/c at top of supports #VALUE!
202 of 221
10.0 Load data for POT-PTFE Bearing
TYPE 2 TYPE 3
GIRDER 3
TYPE 1 TYPE 1
GIRDER 4
TYPE 1 TYPE 1
203 of 221
1000 kN 170kN load.
B A
1.000 0.10 1.000
204 of 221
left free- right fixed 70R Wheel
RA (fixed bearing)= (0.1 - (5.124 - 1))/0.1 * 1000 = -40240.0
RB (free bearing)= = 41240.0
Transverse eccentricity 12/2-0.5-1.2-2.79/2 = 2.905
Horizontal Force, Fh =1000*0.2 = 200
Velocity, V = 60
Radius, R = 1E+15
Braking & centrifugal force act at 1.2m above deck level
Height of structure above bearing = 4.37
Centrifugal Force = WV /127R
2 = 0.0000 W
Total Tranverse Force Centrifugal Force = 0.00
Dead load+SIDL reaction(Rg) at RA or RB = = 4192.68
Value of " m " = = 0.05 0.03
Horizontal force at free bearing of longer span (RB) =mxRB = -1802.37
Horizontal force at fixed bearing of longer span (RA) =Fh-mxRB = 2002.37
Horizontal force at fixed bearing of longer span (RA) =Fh/2+mxRB = -1702.37
Total Longitudinal horizontal force = 2002.37
Sum(r^2) in Tranverse direction = 90.00
Number of PSC longitudinal girder = 4 Nos. Spacing of longitudinal girder = 3.00 m
205 of 221
Vertical load Horizontal force Rotation
Max Min Long. Trans. DL+SIDL Live load
DL 0.00 0.00 550
SIDL 0.00 0.00 0.000345
Wind load 0.00 0.00 111.45 222.90 0.000024
Footpath LL 0.00011
Pin bearing Live load 0.00 0.00 0.00101
Braking 0.00 0.00 2002.37
Centrifugal
force 0.00 0.00 0.00
Total 0.00 0.00 2113.82 222.90 550.00037 0.00112
206 of 221
Horizontal coefficient -Longitudinal = #REF! = #REF!
Vertical coefficient for tranverse seismic = #REF!
Horizontal coefficient -Transverse = #REF! = #REF!
207 of 221
10.2 Longitudinal Seismic case
MAXIMUM Longitudinal moment case or Maximum Reaction
(a)1-lane Class 70R wheeled Loading
200 kN
0.50 9 0.50 1.5 0.50
1.2 2.79
0.86
12.00
Section showing location of 70R wheeled loading
208 of 221
Load on each bearing
Vertical load Horizontal force Rotation
Max Min Long. Trans. DL+SIDL Live load
DL 550.00 550.00 550
SIDL 92.88 92.88 0.000345
Footpath LL 9.38 0.00002
Live load 160.31 0.00 0.00020
Girder2 Braking 436.50 -436.50 -48.19
Centrifugal
force 0.00 0.00
long
seismic #REF! #REF!
Total #REF! #REF! -48.19 0.00 550.00035 0.00022
209 of 221
10.3 Tranverse Seismic case
Horizontal force in each bearing Longitudinal force = 232.77 kN
Tranverse force = 0.00 kN
Reaction due to horizontal load Longitudinal force = 436.50 kN
Tranverse force = 0.00 kN
= 0.00 kN
Vertical coefficient = #REF!
Horizontal coefficient -Longitudinal = #REF!
Horizontal seismic force for fixed bearings #REF! + #REF! = #REF! KN
Verical seismic force for all bearing #REF! + #REF! = #REF! KN
C,G. of superstructure = 1.100 m
C,G. of live load = 4.365 m
Horizontal seismic force for each bearings = #REF! KN
Reaction due to Vertical load = #REF! KN
Vertical load due to horizontal load = #REF! KN
= #REF! KN
Load Combination As per Clause 706 of IRC:78-2014
1) Dead load +SIDL+Live load incl. braking & centrifugal force
2) Dead load +SIDL+Wind load - unloaded strructure
3) Dead load +SIDL+Live load incl. braking & centrifugal force + wind load - loaded structure
4) Dead load +SIDL+ Live load incl. braking & centrifugal force + Longitudinal seismic
5) Dead load +SIDL+Live load incl. braking & centrifugal force + Tranverse seismic
Load on each bearing
Vertical load Horizontal force Rotation
Max Min Long. Trans. DL+SIDL Live load
DL 550.00 550.00 550
SIDL 92.88 92.88 0.000345
Footpath LL 9.38 0.00 0.00002
Live load 160.31 0.00 0.00020
Girder2 Braking 436.50 -436.50 -48.19
Centrifugal
force 0.00 0.00
210 of 221
Pin bearing
Centrifugal
force 0.00 0.00 0.00
Tranverse
seismic 0.00 0.00 #REF!
Total 0.00 0.00 232.77 #REF! ### 0.00021
Load data of POT-PTF/Pin /metalic guide bearing for Long seismic case
Vertical load Horizontal force Rotation
Max Min Long. Trans. SIDL Live load
Free bearing #REF! #REF! -51 -51 1302.5570 0.0002
Pin bearing 0 0 244 #REF! 1302.5570 0.0002
Metalic Guide bearing 0 0 0 #REF! 1302.5570 0.0002
211 of 221
11.0 Staad Analysis
1.500 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1
3.000 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 3
3.000 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 5
3.000 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 7
1.500
77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 9
Y X
Z Load 1
212 of 221
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
109114 119 124 129 134 139 144 149 154 159 164 169 174 179 184 189 1941
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
110115 120 125 130 135 140 145 150 155 160 165 170 175 180 185 190 1952
37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
111116 121 126 131 136 141 146 151 156 161 166 171 176 181 186 191 1962
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
112117 122 127 132 137 142 147 152 157 162 167 172 177 182 187 192 1972
73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
113118 123 128 133 138 143 148 153 158 163 168 173 178 183 188 193 1982
91 92 Member No 95
93 94 96 97 98 99 100 101 102 103 104 105 106 107 108
Y X
Z Load 1
213 of 221
11.1 Analysis of Girder
STAAD SPACE
START JOB INFORMATION
ENGINEER DATE 28-jan-09
END JOB INFORMATION
INPUT WIDTH 79
UNIT METER KN
JOINT COORDINATES
1 0 0 0; 2 1 0 0; 3 2.656 0 0; 4 4.313 0 0; 5 5.969 0 0; 6 7.625 0 0;
7 9.281 0 0; 8 10.938 0 0; 9 12.594 0 0; 10 14.25 0 0; 11 15.906 0 0;
12 17.563 0 0; 13 19.219 0 0; 14 20.875 0 0; 15 22.531 0 0; 16 24.188 0 0;
17 25.844 0 0; 18 27.5 0 0; 19 28.5 0 0; 20 0 0 1.5; 21 1 0 1.5;
22 2.656 0 1.5; 23 4.313 0 1.5; 24 5.969 0 1.5; 25 7.625 0 1.5; 26 9.281 0 1.5;
27 10.938 0 1.5; 28 12.594 0 1.5; 29 14.25 0 1.5; 30 15.906 0 1.5;
31 17.563 0 1.5; 32 19.219 0 1.5; 33 20.875 0 1.5; 34 22.531 0 1.5;
35 24.188 0 1.5; 36 25.844 0 1.5; 37 27.5 0 1.5; 38 28.5 0 1.5; 39 0 0 4.5;
40 1 0 4.5; 41 2.656 0 4.5; 42 4.313 0 4.5; 43 5.969 0 4.5; 44 7.625 0 4.5;
45 9.281 0 4.5; 46 10.938 0 4.5; 47 12.594 0 4.5; 48 14.25 0 4.5;
49 15.906 0 4.5; 50 17.563 0 4.5; 51 19.219 0 4.5; 52 20.875 0 4.5;
53 22.531 0 4.5; 54 24.188 0 4.5; 55 25.844 0 4.5; 56 27.5 0 4.5;
57 28.5 0 4.5; 58 0 0 7.5; 59 1 0 7.5; 60 2.656 0 7.5; 61 4.313 0 7.5;
62 5.969 0 7.5; 63 7.625 0 7.5; 64 9.281 0 7.5; 65 10.938 0 7.5;
66 12.594 0 7.5; 67 14.25 0 7.5; 68 15.906 0 7.5; 69 17.563 0 7.5;
70 19.219 0 7.5; 71 20.875 0 7.5; 72 22.531 0 7.5; 73 24.188 0 7.5;
74 25.844 0 7.5; 75 27.5 0 7.5; 76 28.5 0 7.5; 77 0 0 10.5; 78 1 0 10.5;
79 2.656 0 10.5; 80 4.313 0 10.5; 81 5.969 0 10.5; 82 7.625 0 10.5;
83 9.281 0 10.5; 84 10.938 0 10.5; 85 12.594 0 10.5; 86 14.25 0 10.5;
87 15.906 0 10.5; 88 17.563 0 10.5; 89 19.219 0 10.5; 90 20.875 0 10.5;
91 22.531 0 10.5; 92 24.188 0 10.5; 93 25.844 0 10.5; 94 27.5 0 10.5;
95 28.5 0 10.5; 96 0 0 12; 97 1 0 12; 98 2.656 0 12; 99 4.313 0 12;
100 5.969 0 12; 101 7.625 0 12; 102 9.281 0 12; 103 10.938 0 12;
104 12.594 0 12; 105 14.25 0 12; 106 15.906 0 12; 107 17.563 0 12;
108 19.219 0 12; 109 20.875 0 12; 110 22.531 0 12; 111 24.188 0 12;
112 25.844 0 12; 113 27.5 0 12; 114 28.5 0 12;
MEMBER INCIDENCES
1 1 2; 2 2 3; 3 3 4; 4 4 5; 5 5 6; 6 6 7; 7 7 8; 8 8 9; 9 9 10; 10 10 11;
11 11 12; 12 12 13; 13 13 14; 14 14 15; 15 15 16; 16 16 17; 17 17 18; 18 18 19;
19 20 21; 20 21 22; 21 22 23; 22 23 24; 23 24 25; 24 25 26; 25 26 27; 26 27 28;
27 28 29; 28 29 30; 29 30 31; 30 31 32; 31 32 33; 32 33 34; 33 34 35; 34 35 36;
35 36 37; 36 37 38; 37 39 40; 38 40 41; 39 41 42; 40 42 43; 41 43 44; 42 44 45;
43 45 46; 44 46 47; 45 47 48; 46 48 49; 47 49 50; 48 50 51; 49 51 52; 50 52 53;
51 53 54; 52 54 55; 53 55 56; 54 56 57; 55 58 59; 56 59 60; 57 60 61; 58 61 62;
59 62 63; 60 63 64; 61 64 65; 62 65 66; 63 66 67; 64 67 68; 65 68 69; 66 69 70;
67 70 71; 68 71 72; 69 72 73; 70 73 74; 71 74 75; 72 75 76; 73 77 78; 74 78 79;
75 79 80; 76 80 81; 77 81 82; 78 82 83; 79 83 84; 80 84 85; 81 85 86; 82 86 87;
83 87 88; 84 88 89; 85 89 90; 86 90 91; 87 91 92; 88 92 93; 89 93 94; 90 94 95;
91 96 97; 92 97 98; 93 98 99; 94 99 100; 95 100 101; 96 101 102; 97 102 103;
98 103 104; 99 104 105; 100 105 106; 101 106 107; 102 107 108; 103 108 109;
104 109 110; 105 110 111; 106 111 112; 107 112 113; 108 113 114; 109 1 20;
110 20 39; 111 39 58; 112 58 77; 113 77 96; 114 2 21; 115 21 40; 116 40 59;
117 59 78; 118 78 97; 119 3 22; 120 22 41; 121 41 60; 122 60 79; 123 79 98;
124 4 23; 125 23 42; 126 42 61; 127 61 80; 128 80 99; 129 5 24; 130 24 43;
131 43 62; 132 62 81; 133 81 100; 134 6 25; 135 25 44; 136 44 63; 137 63 82;
138 82 101; 139 7 26; 140 26 45; 141 45 64; 142 64 83; 143 83 102; 144 8 27;
145 27 46; 146 46 65; 147 65 84; 148 84 103; 149 9 28; 150 28 47; 151 47 66;
152 66 85; 153 85 104; 154 10 29; 155 29 48; 156 48 67; 157 67 86; 158 86 105;
159 11 30; 160 30 49; 161 49 68; 162 68 87; 163 87 106; 164 12 31; 165 31 50;
166 50 69; 167 69 88; 168 88 107; 169 13 32; 170 32 51; 171 51 70; 172 70 89;
173 89 108; 174 14 33; 175 33 52; 176 52 71; 177 71 90; 178 90 109; 179 15 34;
180 34 53; 181 53 72; 182 72 91; 183 91 110; 184 16 35; 185 35 54; 186 54 73;
187 73 92; 188 92 111; 189 17 36; 190 36 55; 191 55 74; 192 74 93; 193 93 112;
194 18 37; 195 37 56; 196 56 75; 197 75 94; 198 94 113; 199 19 38; 200 38 57;
201 57 76; 202 76 95; 203 95 114;
214 of 221
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 3.4313e+007
POISSON 0.17
DENSITY 25
ALPHA 5.5e-006
DAMP 0.05
END DEFINE MATERIAL
MEMBER PROPERTY INDIAN
19 20 35 TO 38 53 TO 56 71 TO 74 89 90 PRIS AX 2 IX 0.123 IY 0.587 IZ 0.808
21 34 39 52 57 70 75 88 PRIS AX 1.781 IX 0.056 IY 0.562 IZ 0.742
22 TO 33 40 TO 51 58 TO 69 76 TO 87 PRIS AX 1.583 IX 0.036 IY 0.554 IZ 0.686
1 TO 18 91 TO 108 PRIS YD 0.225 ZD 0.2
109 TO 113 199 TO 203 PRIS YD 0.4 ZD 0.4
114 118 194 198 PRIS YD 0.225 ZD 1.241
119 TO 154 158 TO 193 PRIS YD 0.225 ZD 1.681
115 TO 117 195 TO 197 PRIS AX 1.224 IX 0.09 IY 0.075 IZ 0.371
155 TO 157 PRIS AX 0.851 IX 0.018 IY 0.093 IZ 0.269
CONSTANTS
MATERIAL CONCRETE ALL
SUPPORTS
21 37 40 56 59 75 78 94 FIXED BUT MX MY MZ
DEFINE MOVING LOAD
TYPE 1 LOAD 77 77 77 77 77
DIST 0.914 0.914 0.914 0.914 WID 2.06
*70R Wheeled LOADING
TYPE 2 LOAD 45.47 68.21 68.21 96.63 96.63 96.63 96.63
DIST 3.96 1.52 2.13 1.37 3.05 1.37 WID 1.93
*CLASS-A LOADING
TYPE 3 LOAD 15.35 15.35 64.8 64.8 38.65 38.65 38.65 38.65
DIST 1.1 3.2 1.2 4.3 3 3 3 WID 1.8
LOAD 1 REMOVAL OF SHUTERING
MEMBER LOAD
19 TO 36 73 TO 90 UNI GY 6.5
37 TO 72 UNI GY 6.5
***************************
LOAD 2 SIDL
MEMBER LOAD
19 TO 36 UNI GY -7.5 0 0 -1.265
19 TO 36 UNI GY -5.5 0 0 0.25
37 TO 72 UNI GY -6.6
73 TO 90 UNI GY -7.5 0 0 -0.735
73 TO 90 UNI GY -1.1 0 0 -1.25
73 TO 90 UNI GY -3.3 0 0 0.25
73 TO 90 UNI GY -7 0 0 1.25
*******************************
LOAD 3 FOOTPATH LL
MEMBER LOAD
73 TO 90 UNI GY -6.21 0 0 0.25
***************************************
LOAD 4 WIND LOAD
MEMBER LOAD
19 TO 36 73 TO 90 UNI GY 6.35
37 TO 72 UNI GY 6.35
***********************************
LOAD 5 WIND LOAD
MEMBER LOAD
19 TO 36 73 TO 90 UNI GY -3.29
37 TO 72 UNI GY -3.29
************************************
LOAD 6 SNOW LOAD
MEMBER LOAD
19 TO 90 UNI GY -7.5
215 of 221
*********************************
LOAD 7 SNOW LOAD
MEMBER LOAD
19 TO 90 UNI GY -15
*********************************
*ONE LANE 70R TRACKED + SNOW LOAD
LOAD GENERATION 70 ADD LOAD 7
TYPE 1 -1.828 0 4.18 XINC 0.5
LOAD GENERATION 70 ADD LOAD 7
TYPE 1 -1.828 0 5.53 XINC 0.5
LOAD GENERATION 70 ADD LOAD 7
TYPE 1 -1.828 0 7.88 XINC 0.5
**********************************
*ONE LANE 70R WHEELED + SNOW LOAD
LOAD GENERATION 90 ADD LOAD 6
TYPE 2 -7.61 0 4.06 XINC 0.5
LOAD GENERATION 90 ADD LOAD 6
TYPE 2 -7.61 0 5.465 XINC 0.5
LOAD GENERATION 90 ADD LOAD 6
TYPE 2 -7.61 0 7.87 XINC 0.5
********************************
*TWO LANE CLASS-A + SNOW LOAD
LOAD GENERATION 130 ADD LOAD 6
TYPE 3 -18.8 0 2.7 XINC 0.5
TYPE 3 -18.8 0 6.2 XINC 0.5
LOAD GENERATION 130 ADD LOAD 6
TYPE 3 -18.8 0 5.6 XINC 0.5
TYPE 3 -18.8 0 9.1 XINC 0.5
*ONE LANE CLASS-A + SNOW LOAD
LOAD GENERATION 130 ADD LOAD 6
TYPE 3 -18.8 0 2.7 XINC 0.5
LOAD GENERATION 130 ADD LOAD 6
TYPE 3 -18.8 0 9.1 XINC 0.5
PERFORM ANALYSIS
FINISH
216 of 221
11.1.3 Support Reaction for Wind load of Unloaded structure
Horizontal Vertical Horizontal Moment
Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm
21 4 WIND L 0 -90.5 0 0 0 0
37 4 WIND L 0 -90.5 0 0 0 0
40 4 WIND L 0 -90.475 0 0 0 0
56 4 WIND L 0 -90.475 0 0 0 0
59 4 WIND L 0 -90.475 0 0 0 0
75 4 WIND L 0 -90.475 0 0 0 0
78 4 WIND L 0 -90.5 0 0 0 0
94 4 WIND L 0 -90.5 0 0 0 0
217 of 221
94 +ve 0 328.728 0 0 0 0
- 177 LOAD - - - -
94 -ve 0 0 0 0 0 0
- - - - - -
11.2 Analysis of End Cross Girder
STAAD PLANE
START JOB INFORMATION
ENGINEER DATE 11-Sep-08
END JOB INFORMATION
INPUT WIDTH 79
UNIT METER KN
JOINT COORDINATES
1 0 0 0; 2 0.75 0 0; 3 3 0 0; 4 3.75 0 0; 5 5.25 0 0; 6 6 0 0; 7 8.25 0 0;
8 9 0 0;
MEMBER INCIDENCES
1 1 2; 2 2 3; 3 3 4; 4 4 5; 5 5 6; 6 6 7; 7 7 8;
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 3.43e+007
POISSON 0.17
DENSITY 25
ALPHA 1.17e-005
DAMP 0.05
END DEFINE MATERIAL
CONSTANTS
MATERIAL CONCRETE ALL
MEMBER PROPERTY AMERICAN
1 TO 7 PRIS YD 1.8 ZD 0.6
SUPPORTS
2 4 5 7 FIXED BUT MX MY MZ
LOAD 1 DL
JOINT LOAD
1 8 FY -632.85
3 6 FY -658.59
LOAD 2 SIDL
JOINT LOAD
1 FY -184.32
3 FY -92.88
6 FY -124.94
8 FY -240.53
PERFORM ANALYSIS
PRINT MAXFORCE ENVELOPE LIST 1 TO 7
FINISH
11.3 Analysis of Deck slab
STAAD PLANE
START JOB INFORMATION
ENGINEER DATE 28-jan-09
END JOB INFORMATION
INPUT WIDTH 79
UNIT METER KN
JOINT COORDINATES
1 0 0 0; 2 1.5 0 0; 3 4.5 0 0; 4 7.5 0 0; 5 10.5 0 0; 6 12 0 0;
MEMBER INCIDENCES
1 1 2; 2 2 3; 3 3 4; 4 4 5; 5 5 6;
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 3.4e+007
POISSON 0.17
DENSITY 25
ALPHA 1e-005
DAMP 0.05
218 of 221
END DEFINE MATERIAL
CONSTANTS
MATERIAL CONCRETE ALL
MEMBER PROPERTY AMERICAN
1 TO 5 PRIS YD 0.225 ZD 1
SUPPORTS
2 TO 5 FIXED BUT MX MY MZ
LOAD 1 SELFWEIGHT
SELFWEIGHT Y -1
LOAD 2 SIDL
MEMBER LOAD
1 CON GY -7.5 0.235
1 UNI GY -1.43 0.5 1.5
2 3 UNI GY -1.43
4 UNI GY -1.43 0 2
4 UNI GY -1.43 2.5 3
4 CON GY -7.5 2.265
5 UNI GY -1.43 0 1
5 CON GY -7 1.25
LOAD 3 70R TRACKED LIVE LOAD
MEMBER LOAD
2 UNI GY -46.3 0.79 2.21
2 UNI GY -52.4 2.85 3
3 UNI GY -52.4 0 1.27
1 TO 5 UNI GY -5
LOAD 4 70R WHEELED LIVE LOAD
MEMBER LOAD
2 UNI GY -49.1 0.78 2.22
2 UNI GY -68.3 2.71 3.0
3 UNI GY -68.3 0 1.15
1 TO 5 UNI GY -2.5
LOAD 5 CLASS A LIVE LOAD
MEMBER LOAD
2 UNI GY -49.0 0.96 2.04
2 UNI GY -69.4 2.76 3.0
3 UNI GY -69.4 0 0.84
3 UNI GY -47.8 1.46 2.54
4 UNI GY -51.0 0.26 1.34
1 TO 5 UNI GY -2.5
PERFORM ANALYSIS
LOAD LIST ALL
PRINT MEMBER FORCES LIST 1 TO 5
FINISH
219 of 221
53 22.656 0 4.5; 54 24.338 0 4.5; 55 26.019 0 4.5; 56 27.7 0 4.5;
57 28.5 0 4.5; 58 0 0 7.5; 59 0.8 0 7.5; 60 2.481 0 7.5; 61 4.163 0 7.5;
62 5.844 0 7.5; 63 7.525 0 7.5; 64 9.206 0 7.5; 65 10.888 0 7.5;
66 12.569 0 7.5; 67 14.25 0 7.5; 68 15.931 0 7.5; 69 17.613 0 7.5;
70 19.294 0 7.5; 71 20.975 0 7.5; 72 22.656 0 7.5; 73 24.338 0 7.5;
74 26.019 0 7.5; 75 27.7 0 7.5; 76 28.5 0 7.5; 77 0 0 10.5; 78 0.8 0 10.5;
79 2.481 0 10.5; 80 4.163 0 10.5; 81 5.844 0 10.5; 82 7.525 0 10.5;
83 9.206 0 10.5; 84 10.888 0 10.5; 85 12.569 0 10.5; 86 14.25 0 10.5;
87 15.931 0 10.5; 88 17.613 0 10.5; 89 19.294 0 10.5; 90 20.975 0 10.5;
91 22.656 0 10.5; 92 24.338 0 10.5; 93 26.019 0 10.5; 94 27.7 0 10.5;
95 28.5 0 10.5; 96 0 0 12; 97 0.8 0 12; 98 2.481 0 12; 99 4.163 0 12;
100 5.844 0 12; 101 7.525 0 12; 102 9.206 0 12; 103 10.888 0 12;
104 12.569 0 12; 105 14.25 0 12; 106 15.931 0 12; 107 17.613 0 12;
108 19.294 0 12; 109 20.975 0 12; 110 22.656 0 12; 111 24.338 0 12;
112 26.019 0 12; 113 27.7 0 12; 114 28.5 0 12; 115 0.8 0 6; 116 27.7 0 6;
MEMBER INCIDENCES
1 1 2; 2 2 3; 3 3 4; 4 4 5; 5 5 6; 6 6 7; 7 7 8; 8 8 9; 9 9 10; 10 10 11;
11 11 12; 12 12 13; 13 13 14; 14 14 15; 15 15 16; 16 16 17; 17 17 18; 18 18 19;
19 20 21; 20 21 22; 21 22 23; 22 23 24; 23 24 25; 24 25 26; 25 26 27; 26 27 28;
27 28 29; 28 29 30; 29 30 31; 30 31 32; 31 32 33; 32 33 34; 33 34 35; 34 35 36;
35 36 37; 36 37 38; 37 39 40; 38 40 41; 39 41 42; 40 42 43; 41 43 44; 42 44 45;
43 45 46; 44 46 47; 45 47 48; 46 48 49; 47 49 50; 48 50 51; 49 51 52; 50 52 53;
51 53 54; 52 54 55; 53 55 56; 54 56 57; 55 58 59; 56 59 60; 57 60 61; 58 61 62;
59 62 63; 60 63 64; 61 64 65; 62 65 66; 63 66 67; 64 67 68; 65 68 69; 66 69 70;
67 70 71; 68 71 72; 69 72 73; 70 73 74; 71 74 75; 72 75 76; 73 77 78; 74 78 79;
75 79 80; 76 80 81; 77 81 82; 78 82 83; 79 83 84; 80 84 85; 81 85 86; 82 86 87;
83 87 88; 84 88 89; 85 89 90; 86 90 91; 87 91 92; 88 92 93; 89 93 94; 90 94 95;
91 96 97; 92 97 98; 93 98 99; 94 99 100; 95 100 101; 96 101 102; 97 102 103;
98 103 104; 99 104 105; 100 105 106; 101 106 107; 102 107 108; 103 108 109;
104 109 110; 105 110 111; 106 111 112; 107 112 113; 108 113 114; 109 1 20;
110 20 39; 111 39 58; 112 58 77; 113 77 96; 114 2 21; 115 21 40; 116 40 115;
117 59 78; 118 78 97; 119 3 22; 120 22 41; 121 41 60; 122 60 79; 123 79 98;
124 4 23; 125 23 42; 126 42 61; 127 61 80; 128 80 99; 129 5 24; 130 24 43;
131 43 62; 132 62 81; 133 81 100; 134 6 25; 135 25 44; 136 44 63; 137 63 82;
138 82 101; 139 7 26; 140 26 45; 141 45 64; 142 64 83; 143 83 102; 144 8 27;
145 27 46; 146 46 65; 147 65 84; 148 84 103; 149 9 28; 150 28 47; 151 47 66;
152 66 85; 153 85 104; 154 10 29; 155 29 48; 156 48 67; 157 67 86; 158 86 105;
159 11 30; 160 30 49; 161 49 68; 162 68 87; 163 87 106; 164 12 31; 165 31 50;
166 50 69; 167 69 88; 168 88 107; 169 13 32; 170 32 51; 171 51 70; 172 70 89;
173 89 108; 174 14 33; 175 33 52; 176 52 71; 177 71 90; 178 90 109; 179 15 34;
180 34 53; 181 53 72; 182 72 91; 183 91 110; 184 16 35; 185 35 54; 186 54 73;
187 73 92; 188 92 111; 189 17 36; 190 36 55; 191 55 74; 192 74 93; 193 93 112;
194 18 37; 195 37 56; 196 56 116; 197 75 94; 198 94 113; 199 19 38; 200 38 57;
201 57 76; 202 76 95; 203 95 114; 204 115 59; 205 116 75;
DEFINE MATERIAL START
ISOTROPIC CONCRETE
E 3.4313e+007
POISSON 0.17
DENSITY 25
ALPHA 5.5e-006
DAMP 0.05
END DEFINE MATERIAL
MEMBER PROPERTY INDIAN
19 20 35 TO 38 53 TO 56 71 TO 74 89 90 PRIS AX 2 IX 0.123 IY 0.587 IZ 0.808
21 34 39 52 57 70 75 88 PRIS AX 1.781 IX 0.056 IY 0.562 IZ 0.742
22 TO 33 40 TO 51 58 TO 69 76 TO 87 PRIS AX 1.583 IX 0.036 IY 0.554 IZ 0.686
1 TO 18 91 TO 108 PRIS YD 0.225 ZD 0.2
109 TO 113 199 TO 203 PRIS YD 0.4 ZD 0.4
114 118 194 198 PRIS YD 0.225 ZD 1.241
119 TO 154 158 TO 193 PRIS YD 0.225 ZD 1.681
115 TO 117 195 TO 197 204 205 PRIS AX 1.224 IX 0.09 IY 0.075 IZ 0.371
155 TO 157 PRIS AX 0.851 IX 0.018 IY 0.093 IZ 0.269
CONSTANTS
220 of 221
MATERIAL CONCRETE ALL
SUPPORTS
21 37 40 56 59 75 78 94 FIXED BUT FX FZ MX MY MZ
116 FIXED BUT FY MX MY MZ
115 FIXED BUT FX FY MX MY MZ
LOAD 1 LATERAL FORCE NORMAL CASE
JOINT LOAD
37 56 75 94 FX -86.70
LOAD 2 LATERAL FORCE SEISMIC CASE
JOINT LOAD
37 56 75 94 FX -241.52
PERFORM ANALYSIS
FINISH
221 of 221