Detail of Measurement Name of Work:-Construction of Proposed Commercial Building of Smt. Rajni Rawat D/O Shri Shyam Singh Rawat
Detail of Measurement Name of Work:-Construction of Proposed Commercial Building of Smt. Rajni Rawat D/O Shri Shyam Singh Rawat
Name of Work:- Construction of Proposed commercial Building of Smt. Rajni Rawat D/O Shri Shyam Singh Rawat
situated at Village Islampur Deepa on Meerut Pauri road NH-119 in Km.79.492-79.500,Bijnor.
S.NO. PARTICULARS OF ITEM NO. L in Ft. B in Ft. H/D in Ft. QTY. UNIT
( A ) SUB-GROUND FLOOR
…2…
S.NO. PARTICULARS OF ITEM NO. L in Ft. B in Ft. H/D in Ft. QTY. UNIT
…3…
S.NO. PARTICULARS OF ITEM NO. L in Ft. B in Ft. H/D in Ft. QTY. UNIT
18 Apply primming coat on wood work. Qty.Same as in item No 16 Above i.e. 4.46 Sqm
( B ) GROUND FLOOR
11 Approximate cost of Iron fittings. Qty Same as in item No 10 Above 18.76 Sqm
12 Approximate cost of oxidized iron fittings. Qty Same as in item No 10 Above 18.76 Sqm
…6…
S.NO. PARTICULARS OF ITEM NO. L in Ft. B in Ft. H/D in Ft. QTY. UNIT
18 Apply primming coat on wood work. 1.5 X Qty Same as in item No 10 Above
i.e. 1.50 x 18.76 = 28.14 Sqm
19 Painting two coats with ready mixed
superior quality paint. Qty same as in item no.17+18 above i.e. 43.19 Sqm
…7…
S.NO. PARTICULARS OF ITEM NO. L in Ft. B in Ft. H/D in Ft. QTY. UNIT
( C ) FIRST FLOOR
10 Approximate cost of Iron fittings. Qty Same as in item No 9 Above 25.24 Sqm
11 Approximate cost of oxidized iron fittings. Qty Same as in item No 9 Above 25.24 Sqm
17 Apply primming coat on wood work. 1.5 X Qty Same as in item No 9 Above
i.e. 1.50 x 25.24 = 37.86 Sqm
18 Painting two coats with ready mixed
superior quality paint. Qty same as in item no.16+17 above i.e. 65.47 Sqm
Name of Work:- Construction of Proposed commercial Building of Smt. Rajni Rawat D/O Shri Shyam Singh Rawat
situated at Village Islampur Deepa on Meerut Pauri road NH-119 in Km.79.492-79.500,Bijnor.
…2…
S.NO. ITEM OF WORK Qty Unit Rate Per
Total
…3…
S.NO. ITEM OF WORK Qty Unit Rate Per
( B ) GROUND FLOOR
8 Mild steel work in fabrication of hold fasts. 0.44 Qtl 6050.00 Qtl
Total
…5…
S.NO. ITEM OF WORK Qty Unit Rate Per
( C ) FIRST FLOOR
8 Mild steel work in fabrication of hold fasts. 0.55 Qtl 6050.00 Qtl
Total
Total
Say Rs
Amount
16734.90
10964.80
77520.00
154440.00
89712.00
27959.00
45216.00
100130.00
225044.00
525886.00
12434.40
113214.51
6500.00
726.00
5120.00
Amount
2118.50
200.80
98.12
609.00
5802.72
600.00
11336.50
1432367.25
Amount
30733.00
45216.00
20250.00
67308.00
2989.00
112585.50
219936.00
2662.00
22673.00
34706.00
1407.00
2063.60
7680.00
30955.20
4503.00
109469.19
301.00
619.08
1813.98
14445.76
Amount
525.00
732841.31
Amount
23068.00
23184.00
25750.00
47123.50
2989.00
83375.50
151090.00
3327.50
46694.00
1893.00
2776.40
14144.00
23592.00
6270.00
101082.93
552.20
832.92
2749.74
11009.60
300.00
Amount
1129.14
2195.55
21955.50
40000.00
637084.48
2802293.04
280229.30
3082522.34
30,83,000/-
and Only)
SUMMARY OF PROJECT
Name of Project :- Construction of Proposed Building of " CITY HOSPITAL " for " Rahat Foundation Society "
situated at Mohallah-Mirdgan,Bijnor.
( Rs. Two Crore Eighty Lac & Fifty Five Thousand Only )