Maintenance Guide
Maintenance Guide
Maintenance Guide
June 30, 1998
New Information
Maintenance Guide
ABB Power T&D Company Inc. continually strives to NO WARRANTIES, EXPRESSED, OR IMPLIED, IN-
make its instruction literature current, accurate, and CLUDING WARRANTIES OF FITNESS FOR A
easy to understand. Suggestions to improve this PARTICULAR PURPOSE OR MERCHANTABILITY,
document may be sent to: Literature Coordinator fax OR WARRANTIES ARISING FROM COURSE OF
(901) 696-5269 or use the above mailing address. For DEALING OR USAGE OF TRADE, ARE MADE RE-
a reply, please include name, company, phone num- GARDING THE INFORMATION,
ber, and/or fax number. RECOMMENDATIONS, DESCRIPTIONS AND
SAFETY NOTATIONS CONTAINED HEREIN. In no
event will ABB Power T&D Company Inc. be
responsible to the user in contract, in tort (including
negligence), strict liability or otherwise for any special,
indirect, incidental or consequential damage or loss
whatsoever including but not limited to damage to or
loss or use of equipment, plant or power system, cost
of capital, loss of profits or revenues, cost of replace-
ment power, additional expenses in the use of existing
power facilities, or claims against the user by its
customers resulting from the use of the information,
recommendations, description, and safety notations
contained herein.
This document must not be copied without our written permission, and the contents thereof
must not be imparted to a third party nor be used for any unauthorized purpose.
Contravention will be prosecuted.
Recommended Practices
ABB Power T&D Company recommends careful consideration of the following factors
for
maintenance work on load tap changers.
Before you start any work, make sure that the personnel doing the job have read and
fully understood the Maintenance documents provided with the unit.
To avoid damaging the unit, never exceed the operating limits stated in delivery
documents and on rating plates.
Do not alter or modify a unit without first consulting ABB.
Follow local and international wiring regulations at all times.
Use only factory authorized replacement parts and procedures.
CAUTION
A CAUTION provides information which, if disregarded, could cause damage to the
equipment.
NOTE: A NOTE provides additional information to assist in carrying out the work
described.
Safety Precautions
WARNING
The Maintenance Guide should be read and understood before any work is started,
and the procedures in this document should be followed at all times.
WARNING
Before any work is carried out on the load tap changer:
Make sure that the transformer is disconnected and the earthing is properly done.
Obtain a signed certificate from the engineer in charge.
WARNING
Before starting any work in the load tap changer the protective motor switch and
the LOCAL/REMOTE switch shall be set at “0”.
iii
WARNING
Before starting any work inside the motor-drive mechanism the auxiliary power
must be switched off.
N.B. The motor, contactors and heating element may be energized from separate
sources.
CAUTION
Approval should be given for inspection as well as for operating the load
tap changer.
CAUTION
ABB recommends that only maintenance engineers educated by
ABB carry out contact replacement.
During Service
WARNING
Small amounts of explosive gases will always come out from the breathing devices
(dehydrating breather or one-way breather). Make sure that no open fire, hot
surfaces or sparks occurs in the immediate surroundings of the breathing devices.
WARNING
If a power failure occurs during operation, the operation will be completed when
the power returns.
WARNING
The hand crank must not be inserted during electrical operation.
WARNING
The motor drive can move suddenly when power is restored after a power failure.
CAUTION
After a pressure relay trip, follow the instructions under chapter ”Pressure Relay” in
the Repair Guide.
iv
During Oil Handling
WARNING
Unused transformer oil is slightly harmful. Fumes from unused warm oil may
irritate the respiratory organs and the eyes. After long and repeated contact with
transformer oil the skin becomes very dry.
Used load tap changer oil from diverter switch housings and selector switch
housings contains harmful substances. Fumes are irritating to the respiratory
organs and the eyes and are very easily set on fire. Used transformer oil may wel
be carcinogenic.
Avoid contact with the oil as much as possible and use oil tight protective gloves
when handling the oil.
First aid:
Skin contact: Wash the hands. Use skin cream to counteract the
drying.
In the eyes: Rinse the eyes in clean water.
Swallowing: Drink water or milk. Avoid vomiting. Call a doctor.
Collect used oil in oil drums.
Waste and cleaning up: Should be absorbed by an absorber. Treat it as
hazardous to the environment.
Upon fire: The fire is extinguished by using powder, foam or carbon acid.
WARNING
When oil that has been used in a selector switch compartment is pumped out,
conducting tubes and hoses that are earthed should be used to avoid the risk for
explosion due to the gases produced by the arcs during service.
WARNING
The oil in the selector switch compartment may be hot. Be cautious!
WARNING
There is always a cushion of explosive gases in the top of the diverter switch
housing. No open fire, hot surfaces or sparks may be present during opening of the
housing or draining from the valve. After the cover is removed let the gas vent
away approximately 15 min before any work is started.
CAUTION
Take care to avoid ingestion of moist air when oil is drained. If the ambient air is
moist, let incoming air pass through a dehydrating breather with slow air flow to
obtain proper dehydration.
v
CAUTION
Do not fill oil into the load tap changer if the transformer tank is under vacuum and the load
tap changer is not.
CAUTION
Do not fill oil into the transformer tank if the load tap changer is under vacuum and the
transformer tank is not.
vi
Contents
1 Introduction ___________________________________________ 9
1.1 General _______________________________________________ 9
1.2 Maintenance Schedule ___________________________________ 11
1.2.1 Inspection _____________________________________________ 11
1.2.2 Overhaul______________________________________________ 12
1.2.3 Contact Replacement ____________________________________ 12
1.3 Tightening Torque ______________________________________ 12
2 Inspection _____________________________________________ 13
2.1 Required Tools _________________________________________ 13
2.2 Procedure _____________________________________________ 13
3 Overhaul______________________________________________ 15
3.1 Required Tools and Materials _____________________________ 15
3.2 Procedure _____________________________________________ 16
3.3 Preparations ___________________________________________ 16
3.3.1 Load Tap Changer Position _______________________________ 16
3.3.2 Disconnection and Earthing of the Transformer _______________ 17
3.3.3 Oil Volumes ___________________________________________ 17
3.3.4 Recommended Set of Spare Parts __________________________ 18
3.4 Oil Testing and Oil Draining ______________________________ 18
3.5 Cleaning ______________________________________________ 19
3.5.1 Cleaning the load tap changer _____________________________ 19
3.5.2 Cleaning the Oil Filter (if any) _____________________________ 19
3.5.3 Oil Filtration __________________________________________ 20
3.6 Checking of Breather ____________________________________ 20
3.6.1 Drying of Silica Gel _____________________________________ 20
3.7 Checking Contacts ______________________________________ 21
3.7.1 Contact Alignment ______________________________________ 21
3.7.2 Moving Contact ________________________________________ 21
3.7.3 Fixed Contact with Tips of Copper-Tungsten _________________ 22
3.7.4 Fixed Contact made of Copper ____________________________ 23
3.8 Checking the Transition Resistors __________________________ 24
3.9 Checking the Pressure Relay ______________________________ 25
3.9.1 Functional Check of the Pressure Relay _____________________ 25
3.9.2 Replacing the Pressure Relay ______________________________ 26
3.10 Checking of Motor-Drive Mechanism, BUF3 _________________ 26
3.10.1 Motor Protection, BUF3 _________________________________ 26
3.10.2 Ground Fault Protection (Option) __________________________ 27
3.10.3 Counter, BUF3 _________________________________________ 27
3.10.4 Heater, BUF3 __________________________________________ 27
3.10.5 V-belt, BUF3 __________________________________________ 27
3.10.6 Cable Connections, BUF3 ________________________________ 27
3.10.7 Gland for the Main Shaft, BUF3 ___________________________ 27
3.10.8 Disc Brake, BUF3 ______________________________________ 28
3.10.9 Starting Contact, BUF3 __________________________________ 28
3.10.10 Position Transmitter and other Position Switches, BUF3 ________ 29
3.10.11 Lubrication, BUF3 ______________________________________ 30
vii
3.11 Operation Test, BUF3 ____________________________________ 31
3.12 Checking of Motor-Drive Mechanism Type BUL _______________ 32
3.12.1 Motor Protection, BUL ___________________________________ 34
3.12.2 Ground Fault Protector (Option), BUL _______________________ 34
3.12.3 Counter, BUL __________________________________________ 34
3.12.4 Heater, BUL ____________________________________________ 34
3.12.5 Toothed Belt, BUL _______________________________________ 34
3.12.6 Cable Connections, BUL __________________________________ 35
3.12.7 Disc Brake, BUL ________________________________________ 35
3.12.8 Position Transmitter and other Position Switches, BUL __________ 35
3.12.9 Lubrication, BUL ________________________________________ 36
3.13 Operation Test, BUL _____________________________________ 36
3.14 Closing ________________________________________________ 36
3.15 Checking of Disc Brake in Gear Box and Drive System for UZG ___ 37
3.15.1 Disc Brake (Gear Box), UZG ______________________________ 37
3.15.2 Lubrication of the Drive Shaft System, UZG __________________ 38
3.16 Oil Filling ______________________________________________ 38
3.16.1 Filling Methods and Restrictions ____________________________ 38
3.16.2 Filling at Atmospheric Pressure _____________________________ 38
3.16.3 Correct Oil Level ________________________________________ 39
3.17 Waiting Period __________________________________________ 40
3.18 Putting into Operation ____________________________________ 40
4 Contact Replacement _____________________________________ 40
4.1 Moving Contacts ________________________________________ 41
4.2 Fixed Contacts __________________________________________ 42
5 Specification of Materials _________________________________ 43
5.1 General ________________________________________________ 43
5.2 Load Tap Changer Tank __________________________________ 43
5.3 Active Part _____________________________________________ 43
5.4 Motor-Drive Mechanism, BUF3 ____________________________ 44
5.5 Motor-Drive Mechanism, BUL _____________________________ 45
viii
1 Introduction
1 Introduction
1.1 General
The UZ range of Load Tap Changers manufactured by ABB Components Sweden has
been developed over many years to provide maximum of reliability. The simple and
rugged design gives a service life equal to the service life of the transformer. Minimum
maintenance is required for trouble-free operation. The only parts requiring
maintenance are contacts that might need replacement during the service life, the
insulating oil and the motor-drive mechanism.
The design allows excellent access to all parts, making inspection and maintenance
quick and simple.
The load tap changer type UZE/UZF/UZG is placed in a tank separated from the
transformer tank, see fig. 1. The motor-drive mechanism is attached to the side of the
load tap changer tank for UZE/UZF. It is separate for UZG.
Oil Val;ve
Oil valve
Oil valve
A. UZE B. UZF C. UZG
9
1 Introduction
Fig. 2 shows the general arrangement of a UZ-type load tap changer. The main
component is the selector-switch (combined tap selector and diverter switch). For
maintenance the oil is drained and the front cover is opened. The contacts are then
immediately visible and can be inspected for wear.
Attachment flange to
transformer tank Front cover
Terminals for
conductors
Moulding
Change-over
selector
Fixed contact
Pressure relay
Moving contact
system
Transition
Load tap changer tank resistor
fm_00069
Oil valve
10
1 Introduction
The separate load tap changer tank keeps the oil of the load tap changer separated from
the oil in the transformer. This is required since the oil of the load tap changer
deteriorates as a result of the operation of the selector-switch. The oil needs to be
checked and filtered at regular intervals to maintain adequate dielectric strength as well
as to prevent mechanical wear.
The load tap changer generally comprises three phases. Main components for each
phase are:
nMoulding
nSelector-switch (with replaceable fixed and moving contacts)
nTransition resistors
nChange-over selector for plus/minus or coarse/fine switching.
It is necessary to inspect and clean the load tap changer inside at regular intervals.
Besides the maintenance of the load tap changer and cleaning of the oil, the motor-drive
mechanism should be checked and lubricated.
The pressure relay should also be checked.
1.2.1 Inspection
On the rating plate, ”inspection once a year” is recommended. This primarily
concerns the motor-drive mechanism and refers to a visual inspection inside the motor
cabinet to check that nothing is loose, and the heater is functioning.
In the motor-drive mechanism a counter registers every tap-changer operation. During
inspection the counter is read. If possible, motor and counter are tested by operating
one step and then back.
If the load tap changer has its own oil conservator, the breather and the oil level
indicator on the oil conservator are checked.
The inspection is carried out while the transformer is in service.
WARNING
This work must be carried out from ground level since the transformer is
energized.
11
1 Introduction
1.2.2 Overhaul
The contact life and the frequency of operations determine the time interval between
overhauls.
The number of operations run by the load tap changer is recorded by a counter, housed
in the motor-drive mechanism. The registered number of operations should be noted at
every overhaul.
The load tap changer should normally be overhauled regularly at intervals of 1/5 of the
estimated contact life. The relevant information is stated on the rating plate. Hereby, the
contact wear can be followed and necessary preparations can be made for replacing the
contacts.
If the tap-change operations occur infrequently and a very long time elapses until the
number of operations amounts to 1/5 of the estimated contact life, the interval between
overhauls should be limited to the time stated on the rating plate (normally 7 years).
CAUTION
The number of operations must in no case exceed 500 000, due to weakening spring
tension of the contacts.
12
2 Inspection
2 lnspection
The inspection consists of a visual check of the motor-drive mechanism, the load tap
changer tank, and the conservator once a year while the transformer is in service.
WARNING
This work must be carried out from ground level since the transformer is
energized.
2.2 Procedure
CAUTION
Approval should be given for inspection as well as for operating the load tap changer.
WARNING
This work must be carried out from ground level since the transformer is
energized.
13
2 Inspection
5. Turn the control switch to the LOWER (Raise) position. Check that the motor also
works properly in that direction, the position indicator decreases one step and the
counter advances one step more.
6. Check the emergency stop. (BUL) See figure 3.
Give a RAISE or LOWER impulse and after about one second press the
emergency stop. The operation should be interrupted. Reset the emergency stop
by turning the knob clockwise and by switching on the protective motor switch.
The started operation should now be completed. Operate back to service position.
7. Check the ground fault protector (option BUL). See figure 3.
If the motor-drive mechanism is equipped with an outlet, the ground fault protector
should be tested by pressing the test knob on the separate earth fault protector on
BUL.
8. Disconnect the incoming auxiliary power.
WARNING
Before starting any work inside the motor-drive mechanism the auxiliary power
must be switched off.
N. B. The motor, contactors and heating element may be energized from separate
sources.
9. Check by feeling with a finger on the protection plate that the heater has been
functioning.
10.Reconnect the incoming auxiliary power.
11.Complete the inspection by turning the switch to the REMOTE position and
closing the cabinet door.
1 2 3 4 5 6
17 18 19 20 21 22 23 24
Fig. 3. Motor-drive mechanism, type BUL
14
3 Overhaul
3 Overhaul
WARNING
The transformer must be disconnected and effectively earthed.
15
3 Overhaul
3.2 Procedure
The overhaul procedure includes the following points:
nOil testing and oil draining
nCleaning the load tap changer
nOil filtration
nChecking contacts
nChecking the transition resistors
nChecking the pressure relay
nChecking the motor-drive mechanism
nOperation test
nChecking gear box and shafts (UZG)
nChecking before closing
nOil filling
nPutting into operation.
3.3 Preparations
NOTE: If the load tap changer is oil filled under atmospheric pressure, a waiting
period of three to five hours is needed before energizing. To save out of service time of
the transformer, carry out all work on the load tap changer and do the oil filling
before the maintenance of the motor-drive mechanism is started.
16
3 Overhaul
WARNING
Before starting any work in the load tap changer the protective motor switch and
the LOCAL/REMOTE switch shall be set at ”0”.
Oil conservator for UZF made by ABB, oil volumes at 20 oC (68 oF)
Alternatively, the oil may be replaced by new oil and the used oil filtered at some later
date. A certain quantity of new oil, say 30 gallons (about 100 litres), should be kept
ready to replace waste oil.
CAUTION
Do not energize the transformer until oil has been filled as per section 3.16.
17
3 Overhaul
Main contact
Switching
contact
Fixed contact
(single)
contact unit
WARNING
When oil that has been used in a selector switch compartment is pumped out,
conducting tubes and hoses that are earthed should be used to avoid the risk of
explosion due to the gases produced by the arcs during service.
18
3 Overhaul
Take an oil-sample from the oil valve and carry out the dielectric strength test accor-
ding to IEC 156 (between spherical calottes, distance 2.5 mm).
The dielectric strength of the oil should not be allowed to be less than 120 kV/cm for a
load tap changer in service.
NOTE: When taking the oil-sample, first drain some oil into a bucket to clean the
valve.
Use the filtering equipment or the pump to drain oil from the load tap changer into a
carefully cleaned oil drum. Connect the pump to the oil valve and drain the oil from the
load tap changer tank and the conservator. Draining will be more efficient if the
filtering equipment is used since all the oil will be filtered, at once.
If the oil conservator of the load tap changer is common with the oil conservator of the
transformer tank, close the valve in the pipe connection to the oil conservator and open
the oil valve. After a while, open the air release vent.
3.5 Cleaning
3.5.1 Cleaning the load tap changer
WARNING
There is always a cushion of explosive gases over the oil surface. This is sucked
into the load tap changer tank during draining of the oil. No open fire, hot surfaces
or sparks may be present when the front cover is opened.
After draining, open the front cover of the tank of the load tap changer and wash it
clean with oil by using a filter press hose or pump.
WARNING
The hands or tools must be kept away from the contacts when making a manual or
electrical operation. The contact arm is operated by a spring battery and can cause
severe damage.
After washing, wipe the inside of the load tap changer clean with rags (not cotton
waste). Carefully wipe off carbon residues from the epoxy mouldings.
19
3 Overhaul
WARNING
The breathers and the tube from the conservator contains explosive gases. No open
fire, hot surfaces or sparks may be present when loosening the breather.
If the load tap changer is equipped with an air relief valve, (one-way breather) check it
by applying air pressure to the outlet of the valve. No air leakage is allowed through the
valve. If leaky, replace the valve.
20
3 Overhaul
Compare the measurement of the most worn roller with the diameters given in table 1.
21
3 Overhaul
In each phase, dismantle the fixed contact closest to the door and operate the load tap
changer to this position. Now all the rollers can be measured.
When the measurement is done, operate the load tap changer to another position and
remount all the fixed contacts, see section 4.2.
Table 1. Contact minimum dimensions
Maintenance Measure a (mm)
Interval1)
1 < 18.5
2 < 18
3 < 17.5
4 < 17
5 < 17
CAUTION
If the load tap changer has exceeded 500 000 operations, the contacts must be
replaced, due to weakening spring tension of the contacts.
a
8 mm
A A
b
View A – A
Figure 6.
22
3 Overhaul
The values within brackets apply to situations of equal wear of the contact’s upper and
lower surfaces (within ± 0.5 mm).
As applicable, reinstall the old contacts or install new ones, according to instructions in
section 4.2 Fixed Contacts.
A A
~ 20
a fm_00023
b=32
Figure 7.
23
3 Overhaul
Table 3.
The values within brackets apply to situations of equal wear of the contact’s upper and
lower surfaces (within ± 0.5 mm).
As applicable, reinstall the old contacts or install new ones, according to instructions in
section 4.2 Fixed Contacts.
Least worn surface
A A
~ 20
b=26
Figure 8.
24
3 Overhaul
Measure the
resistance here
and measure
resistance here
Figure 9
Valve handle
(in service
position)
Quick
coupling
,,
1.Set the valve handle to the test position as shown on the information plate.
2.Connect the air pump and the pressure gauge to the test tap on the pressure relay.
(Thread R 1/8”).
3.Raise the pressure until the pressure relay trips the circuit breakers of the
transformer.
4.Read the pressure on the manometer and check against the pressure stated on the
information plate. Max. permitted deviation is ±10 %. If the deviation is greater,
the pressure relay should be replaced.
5.Check that the signal disappears when the pressure is released.
6.After finishing the check, turn back the valve handle to service position.
25
3 Overhaul
nHeater function
nV-belt tightness
nMotor contactors connections
nTightness of the gland for the main shaft
nDisc brake function
nStarting contact movement
nPosition transmitter and other position switches
nLubrication
Reconnect the power supply and make operation tests according to section 3.11.
Protective motor switches for DC motors or single-phase AC motors are not necessary
to test.
26
3 Overhaul
N.B. The motor, contactors and heating element may be energized from seperate
sources.
~ 5 mm
10 N
Figure 11.
27
3 Overhaul
Starting contact
Screws
Brake rod Dismantle when
removing the
Springs brake Starting contact
fm_00098
Figure 12. Starting contact
28
3 Overhaul
Contact arm
0.8 + 0.4mm
Geneva wheel
Contact plate
Fixed contact
A A A–A
fm_00096
29
3 Overhaul
30
3 Overhaul
WARNING
The hands or tools must be kept away from the contacts when making a manual or
electrical operation. The contact arm is operated by a spring battery and can cause
severe damages.
31
3 Overhaul
32
3 Overhaul
Operation counter
Roller
(Grease)
Notch
Cam disc
(Grease)
Brake arm
Geneva
wheel Adjusting
screw
Maintaining
contact
Bracket
Brake disc
Limit switch
Toothed belt
Multi-position switches
(Grease)
33
3 Overhaul
WARNING
The motor power voltage is dangerous.
If the protective motor switch does not trip within 60 seconds, switch off the power and
adjust the current setting. Repeat the test when the motor is cold.
Protective motor switches for DC motors and for single-phase AC motors are not
tested.
Check by feeling with a finger that the heating element has been functioning.
34
3 Overhaul
Cam disc
Lock nut
Adjusting screw
Brake disc
Min 15
CAUTION
If the motor-drive still does not stop when the brake is adjusted to min. 15 mm
according to Fig. 16 please contact ABB for advisory.
35
3 Overhaul
If needed, the bevel gears for the hand crank, the geneva wheels, and the bevel gears for
the position indicator might be sparingly lubricated with the same grease as the shaft
system. (GULF-718EP Synthetic Grease, Mobilgrease 28, Shell-Aero Shell Grease 22
or similar). See figure 15.
3.14 Closing
Before closing the front cover of the load tap changer, make sure that no foreign objects,
tools, wires, rags etc. are left in the tank.
Close the front cover. Tightening torque for the dome nuts should be approximately
42 Nm.
36
3 Overhaul
Figure 17
Check that the flywheel is free from grease. The flywheel shall stop in its middle
position with a tolerance of ± 30 degrees.
The middle position of the flywheel is marked with two conical holes and the tolerances
of ± 30 degrees are marked with single holes. The middle position of the brake is the
centres of the roller shafts.
The braking force can be adjusted by tightening the springs in the brake until the
required tolerance is achieved. If adjustment is not sufficient and the driving roller runs
too far and is on its way into the grooves of the flywheel, oil or grease has probably
entered into the brake linings and these must therefore be cleaned.
The cleaning should be done as follows:
Dismantle the springs on the brake. Dismantle the two pins and two bolts holding the
brake and remove the brake carefully together with the two brake blocks (fig. 17). The
linings of the two brake blocks should be carefully cleaned by using toluol spirit or any
degreasing agent.
When reassembling the brake, check that the flywheel is completely free from grease.
Adjust the brake until the flywheel stops in its right position, as described above.
Check and lubricate the gears with grease if necessary. Use the same grease as for the
drive shaft system.
Lubricate the bearing for the spring battery with oil. Use oil for plain ball and roller
bearings.
Replace the cover of the gearbox
37
3 Overhaul
Check and lubricate with grease if necessary. Reccommended types of grease are
GULF-718 EP Synthetic Grease, Mobilgrease 28, Shell-Aero Shell Grease 22, or
similar.
Remount covers (make sure the gaskets are properly in place).
38
3 Overhaul
39
4 Contact Replacement
Make sure that no tools or foreign objects are left in the motor-drive cabinet. Close the
door. Sign the maintenance protocol and give it to the engineer in charge and inform
him that the load tap changer is ready for energizing.
4 Contact Replacement
CAUTION
ABB Components recommends that only maintenance engineers trained by ABB
Components carry out contact replacement.
fm_00094
40
4 Contact Replacement
NOTE: If the moving contacts are replaced, also replace any fixed contacts that are
considerably worn, in order to minimize the wear of the new moving contacts.
Transition resistor
B (10 Nm)
B
C (25 Nm)
D (10 Nm)
Figure 19. Transition resistor and contacts
Thereafter mount the new main contact unit and transition contact unit. Mount the main
contact by tightening the two screws (D). The transition contact unit will be correctly
positioned by the guiding of the roll pins and fixed by tightening the two bolts (C).
Assemble the transition resistors by first tightening the four screws (B) and then the two
screws (A). All bolts should be tightened according to fig. 19. It is not necessary to use
a torque wrench. The stated torques (in brackets) are guide values only.
41
4 Contact Replacement
fm_00101
After replacing the contacts, operate the load tap changer by normal spring operation.
Check that the moving main contact goes up on the flat part of the fixed contact. The
centre of the main contact tip must be at least 1 mm in on the flat part after finished
operation. This inspection should be made in all positions on all three phases and
operation in both directions. If the 1 mm is not achieved, the contact blade might be
loosened and turned within the clearance of the holes.
WARNING
The hands or tools must be kept away from the contacts when making a manual or
electrical operation. The contact arm is operated by a spring battery and can cause
severe damages.
42
5 Specification of Materials
5 Specification of Materials
5.1 General
This chapter specifies the materials used in the load tap changer.
Steel 400–600 kg
Steel 10–75 kg
Aluminium 5 kg
Silver 25–50 g
Tungsten 0–1.5 kg
Polyester resin 2 kg
43
5 Specification of Materials
Steel 100 kg
Silver 10 g
Plastics:
chlorsulphonded polyethylene
polyamide
phenol resin laminate
polyester
PVC
carbonate plastic
Rubbers:
nitrile rubber
fluorine rubber
CAUTION
Materials listed in the table above without any specification of amount are included
because they may cause pollution problems during de-commissioning, even in the
small quantities used.
44
5 Specification of Materials
Steel 55 kg
Silver 10 g
Plastics:
chlorsulphonated polyethylene x
polyamide with MoS2 x
phenol resin laminate
polyester x
PVC x
carbonate plastic x
Rubbers:
nitrile rubber x
fluorine rubber x
CAUTION
Materials listed in the table above without any specification of amount are included
because they may cause pollution problems during de-commissioning, even in the
small quantities used.
45