Flowchart 9 - Construction Process
Flowchart 9 - Construction Process
Construction Phase
Video 9.9
2 to 4 weeks
Notification The Region oversees the LPA and If project is on a CDOT Region and During the course of construction, the
Consultant Staff in accordance facility, Region and specialty unit Region performs random project
CDOT
with Form 1243, Local Agency specialty unit staff staff review reviews to ensure that the project is
Contract Administration review Work Zone shop drawings being administered in accordance with
9.2 Checklist, of the IGA. Traffic Control (MHTs) (if on a CDOT the terms of the IGA, contract and the
facility). Construction Manual.
9.3 9.20 9.21 9.22
START END
Oversee all aspects of construction, provides project inspection/quality assurance,
LPA (employee in responsible and resolves design/construction problems/discrepancies, including: 9.4
charge) appoints a qualified
Local Public Agency/Consultant
Video 9.1 Video 9.2 Video 9.3 Video 9.4 Video 9.6
Review and approve shop Ongoing oversight of DBE Perform traffic control Resolve contractor claims
drawings participation inspections and disputes
Video 9.7 Video 9.8 9.9 9.10 9.15 9.16
the pre-construction completion, certified test reports, and Buy America(n) documents), shop drawings, monthly schedule updates, Region Materials Staff,
meeting, Contractor MHTs, certified payrolls and certifications, and Form 205 (Sublet Permit Application) as applicable. The perform Project Acceptance
completes mobilization contractor signs Form 262/263 (Weekly Time Count Report) or equivalent. These documents pass to the LPA Sampling / Testing
and commences and to CDOT for review as appropriate. The contractor also helps identify the need for change orders. (See (Form 250) and if the
construction. Flowchart 9.2 Change Order Approval Process and Flowchart 9.1 Reimbursement Process.) project is located on the
9.23 9.24 NHS, IAT (Form 379).