Problem10 18 and 10 20
Problem10 18 and 10 20
Price Variance, Quantity Variance,
$2,000 F $600 U*
*Given.
**500 kits × 3.8 yards per kit = 1,900 yards
Rate Variance, Efficiency Variance,
$450 U $1,000 U
*Given.
Problem 10-18 (continued)
6. Actual Hours of Actual Hours of Standard Hours
Input, at the Input, at the Allowed for Output,
Actual Rate Standard Rate at the Standard Rate
(AH × AR) (AH × SR) (SH × SR)
$1,620* 900 hours* × $1,600*
$2 per hour*
= $1,800
Spending Variance, Efficiency Variance,
$180 F $200 U
*Given.
7. Standard Standard
Quantity or Standard Price Cost per
Hours per Kit or Rate Kit
Direct materials 3.8 yards 1
$ 6 per yard $22.80
Direct labor 1.6 hours 2
$10 per hour 3
16.00
Variable manufacturing
overhead 1.6 hours $ 2 per hour 3.20
Total standard cost per kit $42.00
1
From part 2.
2
800 hours (from part 4) ÷ 500 kits = 1.6 hours per kit.
3
From part 4.
Problem 10-20 (75 minutes)
1. Actual Quantity of Actual Quantity of Standard Quantity
Inputs, at Inputs, at Allowed for Output,
Actual Price Standard Price at Standard Price
(AQ × AP) (AQ × SP) (SQ × SP)
290,000 feet × 290,000 feet × 300,000 feet* ×
$2.10 per foot $2.00 per foot $2.00 per foot
= $609,000 = $580,000 = $600,000
Price Variance, Quantity Variance,
$29,000 U $20,000 F
Alternative Solution:
Materials Price Variance = AQ (AP – SP)
290,000 feet ($2.10 per foot – $2.00 per foot) = $29,000 U
Materials Quantity Variance = SP (AQ – SQ)
$2 per foot (290,000 feet – 300,000 feet) = $20,000 F
Yes, the decrease in waste is apparent because of the $20,000
favorable quantity variance.
If the company wants to continue to compute the material price
variance, then the standard price per board foot should be
changed to reflect current JIT purchase costs. The old standard
price of $2 per board foot is no longer relevant.
Problem 10-20 (continued)
2. Actual Hours of Actual Hours of Standard Hours
Input, at the Input, at the Allowed for Output,
Actual Rate Standard Rate at the Standard Rate
(AH × AR) (AH × SR) (SH × SR)
35,000 hours × 35,000 hours × 30,000 hours* ×
$9.80 per hour $10.00 per hour $10.00 per hour
= $343,000 = $350,000 = $300,000
Rate Variance, Efficiency Variance,
$7,000 F $50,000 U
Alternative Solution:
Labor Rate Variance = AH (AR – SR)
35,000 hours ($9.80 per hour – $10.00 per hour) = $7,000 F
Labor Efficiency Variance = SR (AH – SH)
$10 per hour (35,000 hours – 30,000 hours) = $50,000 U
Problem 10-20 (continued)
No, the labor efficiency variance is not appropriate as a measure
of performance in this situation. The reasons are:
• Labor is largely a fixed cost rather than a variable cost since the
company maintains a stable work force to operate its flow line.
Thus, the variance is not a valid measure of efficiency.
• In a JIT environment the goal is not to have high efficiency in
the use of labor if such efficiency results in the production of
unneeded goods. The goal is to produce only as needed to
meet demand. Tom Hanson is tied to the past in that he is
focusing solely on the utilization of labor time and is overlooking
the impact of unneeded goods on the organization.
Unfortunately, the situation posed in the problem is a common
one as companies switch from a traditional system to JIT, and
sometimes JIT doesn’t work because of misplaced emphasis on
efficiency variances. In a JIT setting, it is an interesting paradox
that one of the “costs” of greater efficiency on the production
line is greater “inefficiency” on the part of labor as it is
occasionally idle or as it spends time at various tasks other than
producing goods.
Problem 10-20 (continued)
3. Actual Hours of Actual Hours of Standard Hours
Input, at the Input, at the Allowed for Output,
Actual Rate Standard Rate at the Standard Rate
(AH × AR) (AH × SR) (SH × SR)
$118,000 35,000 hours × 30,000 hours* ×
$4.00 per hour $4.00 per hour
= $140,000 = $120,000
Spending Variance, Efficiency Variance,
$22,000 F $20,000 U