Saudi Aramco Typical Inspection Plan

This document outlines the inspection plan for reconditioning and replacing sections of existing pipelines in Saudi Aramco. It details the inspection responsibilities and quality procedures for various project phases including: 1. Document review and material receiving 2. Reconditioning of pipelines through repair sleeve installation, welding, coating and testing 3. Replacement of pipeline sections through cutting, welding, coating, pressure testing and reinstatement 4. Acceptance inspections and mechanical completion paperwork. The plan assigns inspection responsibilities to Saudi Aramco and contractor personnel and references relevant Saudi Aramco technical inspection procedures.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
740 views3 pages

Saudi Aramco Typical Inspection Plan

This document outlines the inspection plan for reconditioning and replacing sections of existing pipelines in Saudi Aramco. It details the inspection responsibilities and quality procedures for various project phases including: 1. Document review and material receiving 2. Reconditioning of pipelines through repair sleeve installation, welding, coating and testing 3. Replacement of pipeline sections through cutting, welding, coating, pressure testing and reinstatement 4. Acceptance inspections and mechanical completion paperwork. The plan assigns inspection responsibilities to Saudi Aramco and contractor personnel and references relevant Saudi Aramco technical inspection procedures.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Pipeline Rehabilitation - Reconditioning and Replacement of Sections of
SATIP-L-450-06 25-May-05 MECHANICAL
Existing Pipelines (Mainline)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD CNTRCTR
SAUDI
ARAMCO

1.0 DOCUMENT REVIEW


Welding Procedure Specification
1.1
(WPS & PQR) Refer to SATIP-W-012-01

1.2 Welder Qualification/Certification


Refer to SATIP-W-012-01
Refer to the respective SATIP for NDE. (SATIP-
1.3 Nondestructive Testing Procedures
NDE-UT-01, LPT-01 MPT-01, RT-01)

1.4 Control of Welding Consumables SAIC-W-2009 RH1 R1

2.0 MATERIAL RECEIVING

S.Aramco to be notified for the arrival of the first


Visual inspection & Material verification
2.1 SAIC-L-2142 SAIC-L-2143 W1 W2/R2 batch of delivered materials, then random inspection
Repair Sleeves
thereafter.
Receiving Inspection of Pipe, Fittings & Pre-
2.1 SAIC-L-2112 SAIC-L-2112
formed Bends

3.0 RECONDITIONING

Exploration (excavation, preliminary


3.1 cleaning) AND assessment of Pipe SAIC-L-2143 SAIC-L-2143
External Surface.

3.2 Repair sleeve fit-up inspection SAIC-L-2144 SAIC-L-2144

3.3 Welding Refer to SATIP-W-012-01

In-Process Welding Inspection


3.4 SAIC-W-2031 SAIC-W-2031
of Repair Sleeves

3.5 Verification of NDE Application Refer to the SATIP for the applicable NDE Method

External Coating of Field Welds and


3.6 Refer to SATIP-H-002-03 OR SATIP-H-002-04/05
Reinforcing Sleeves

Page 1 of 3
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Pipeline Rehabilitation - Reconditioning and Replacement of Sections of
SATIP-L-450-06 25-May-05 MECHANICAL
Existing Pipelines (Mainline)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD CNTRCTR
SAUDI
ARAMCO

SECTION
4.0
REPLACEMENT
Preparatory Requirements prior to Pipeline
4.1 SAIC-L-2107 SAIC-L-2107
cutting
Post-Cut and Pre-Welding Inspection,
4.2 SAIC-L-2108 SAIC-L-2108
Including Tie-In Temperature

4.3 Welding Inspection See Remarks Refer to SATIP-W-012-01

4.4 Verification of NDE Application Refer to the SATIP for the applicable NDE Method

External Coating of Field Welds and


4.5 Refer to SATIP-H-002-03 OR SATIP-H-002-04/05
Reinforcing Sleeves

4.6 Hydrostatic Pressure Testing See Remarks Refer to SATIP-A-004-02

PIPELINE
4.0
RE-INSTATEMENT

3.7 Road Crossing Refer to SATIP-Q-006-02

3.8 Backfilling, Berming & Stabilization Refer to SATIP-L-450-02

3.9 Cathodic Protection Refer to SATIP-X-400-01 or SATIP-X-400-02

4.0 ACCEPTANCE

SAIC-L-2133
4.1 Pipeline Re-instatement/Final Inspection SAIC-L-2133 H1 S
SATR-A-2011
Final Inspection for Mech. Completion
4.2 SA Form-6133 H1
(MCC)

Page 2 of 3
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Pipeline Rehabilitation - Reconditioning and Replacement of Sections of
SATIP-L-450-06 25-May-05 MECHANICAL
Existing Pipelines (Mainline)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD CNTRCTR
SAUDI
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH2 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH1 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance

Page 3 of 3