Design and Safety Requirements For Liquefied Petroleum Gas Mounded Storage Facility
Design and Safety Requirements For Liquefied Petroleum Gas Mounded Storage Facility
For restricted
Circulation only
Prepared by
FUNCTIONAL COMMITTEE
0
NOTE
OISD publications are prepared for use in the oil and gas industry
under the Ministry of Petroleum and Natural Gas. These are the
property of Ministry of Petroleum and Natural Gas and shall not be
reproduced or copied and loaned or exhibited to others without
written consent from OISD.
Though every effort has been made to assure the accuracy and
reliability of data contained in these documents, OISD hereby
expressly disclaims any liability or responsibility for loss or damage
resulting from their use.
1
FOREWORD
With this in view, the Ministry of Petroleum and Natural Gas in 1986
constituted a Safety Council assisted by the Oil Industry Safety
Directorate (OISD) staffed from within the industry in formulating and
implementing a series of self regulatory measures aimed at
removing obsolescence, standardising and upgrading the existing
standards to ensure safe operations. Accordingly, OISD constituted
a number of functional committees of experts nominated from the
industry to draw up standards and guidelines on various subjects.
The Coordinator,
FUNCTIONAL COMMITTEE
ON “Design and Safety Requirements For
Liquefied Petroleum Gas Mounded Storage Facility”
2
FUNCTIONAL COMMITTEE
on
“Design and Safety Requirements
For
Liquefied Petroleum Gas
Mounded Storage Facility”
NAME ORGANISATION
LEADER
MEMBERS
SPECIAL INVITEE
Dr M.B.Mishra PDIL
MEMBER COORDINATOR
(In addition to the above, several other experts from the industry contributed in the preparation,
review and finalisation of this document.)
3
Design and Safety Requirements
For
Liquefied Petroleum Gas
Mounded Storage Facility
CONTENTS
1.0 INTRODUCTION
2.0 SCOPE
3.0 DEFNITIONS
12.0 REFRENCES
4
1.0 INTRODUCTION
Bullet
Liquefied Petroleum Gas (LPG) handling
has many challenges due to its inherent A horizontal pressure vessel used for
dangerous properties. Some of the major storage or transportation by rail/ road.
fires/explosions have underlined the need
for total in depth review of design, Compressed Gas
procedures maintenance fire fighting and
safety aspects in LPG handling. The Any permanent gas, liquefiable gas or gas
conventional method of storage of LPG in dissolved in liquid under pressure or gas
India is in a pressurised vessel installed mixture which in a closed container
aboveground. exercises a pressure either exceeding two
atmosphere (gauge) at the maximum
The mounded storage of LPG has proved to working temperature, which for vessels
be safer compared to above ground storage without insulation or refrigeration shall
vessels since it provides intrinsically passive be considered as 55°C".
and safe environment and eliminates the .
possibility of Boiling Liquid Expanding Explosive mixture
Vapour Explosion (BLEVE). The cover of the
mound protects the vessel from fire It is a mixture of combustion agent (oxidising
engulfment, radiation from a fire in close substance-gaseous,, liquid or solid) and a
proximity and acts of sabotage or vandalism. fuel (oxidisable substance- gaseous, liquid
The area of land required to locate a or solid) in such proportions that it could give
mounded system is minimal compared to rise to a very rapid and voilent oxidation
conventional storage. reaction liberating more energy than is
dissipated through conduction and
convection causing practical effect of
2.0 SCOPE explosion.
A storage vessel(s) sited above ground and The volume of water in liters that the
completely covered by a mound of earth or container can hold at 15 Deg. C.
similar inert material except for nozzles,
manhole covers, inspection covers fitted on Earthing & Bonding
vessel(s).
5
Earthing is the provision of a safe path of
electrical current to ground, in order to
protect structures, plant and equipment from
the effects of stray electrical current, and Kerb Wall
electrostatic discharge.
A wall of appropriate height and size
Bonding is the provision of connecting constructed of suitable material and
different parts of an equipment or system by designed to contain the LPG spillage and to
way of bond wire/strip so as to maintain direct it to a safe location around the storage
electrical continuity among all parts of the vessel.
system
Liquefied Petroleum Gas (LPG)
Fire safe
LPG is a mixture of commercial butane and
As applied to valves, it is a provision of dual commercial propane having both saturated
seating to control leakage to acceptable and unsaturated hydrocarbons. LPG
level even after damage due to fire. marketed in India shall be governed by
Indian Standard Code IS-4576 (Refer Table
Fire proof/proofing 1.0) and the test methods by IS-1448.
Sources of Ignition.
Shall.
Competent Person
7
4.0 LOCATION AND SEPARATION
DISTANCES:
4.2 SEPARATION DISTANCES:
4.1 LOCATION:
Separation distances are intended to
The location of mounded storage to be minimise both the potentials for small leak
decided after careful consideration of all ignition and exposure risk presented to
influencing factors, including the following adjacent vessels, equipment or installations
aspects: in case ignition occurs. Separation distances
are not intended to provide protection from a
a) The area to be covered by mound and major incident. Risk analysis and dispersion
the area within the separation distances, modeling are recommended tools to limit the
as given in clause 4.2, shall be clear of exposure risk to adjacent facilities.
any trees, stumps, roots bushes,
combustible material and other 4.2.1
objectionable matter.
The separation distances for mounded
b) Space requirement for, movement of storage shall be as follows:
construction/fabrication equipment and
materials, onsite fabrication and a) Minimum separation distance
maintenance for each mounded vessel. between mounded LPG storage and
Boundary, property line ,group of
c) A detailed soil testing shall be carried buildings not associated with LPG
out, further analysed to ascertain the plant shall be 15 meters.
suitability of the location and as a
support document for selection and b) Minimum separation distance between
design of the foundation. mounded LPG storage vessel and
LPG pump house/compressor house
d) The manhole and pressure relief valves shall be kept based on operational
of mounded vessels are in a well- needs. In case of the liquid outlet from
ventilated position and conforms to the top of the mounded vessel,
separation distances given in submersible pump may be installed
Clause 4.2.1. from the top of the vessel.
e) Fire hydrant/monitors will be Minimum separation distance between
positioned at a safe distance as given in mounded LPG storage and any other
clause 9.3 (other than LPG pump/compressor
house) facility associated with LPG
f) Each mound shall have plant (e.g. decantation shed) shall be
accessibility to Fire Tender from at least 15 meters.
two sides.
c) Minimum separation distance between
g) Vessel(s) shall be located such that they mounded LPG storage vessel and
do not affect or are affected by other firewater pump house and / or
underground structures, e.g., Firewater tank shall be 30 meters
foundations, pipelines, sewers, electrical
cables are themselves not subjected to All the above distances to be measured
loads from vehicular traffic or affected by from the edge of the mound at finished
other hazards like power cables, ground level and also from the first valve
cathodically protected pipelines etc. on the vessel i.e. ROV.
8
b) Since H2S presence cannot be
4.2.2 completely ruled out in the Refinery LPG
storage, high stress material shall not be
The minimum inter-distance between the used for vessels as it is prone to
edge of the vessel(s) in a mound shall be Hydrogen induced stress corrosion
determined by the site conditions and the cracking.
need for safe installation, testing,
maintenance and removal of vessels. c) Recommended maximum tensile
However in any case this distance shall not stress shall be below 80,000 PSI.
be less than 1.5meters between the vessels
having diameter of 2meter and 2meters for d) Material of construction shall
all other cases.(Refer attached Drawing-2) conform to design code. However, for
any reasons, these codes differ (i.e.
4.2.3 Design code and selection of material
code), the selected material should
The minimum inter-distance between the confirm to equivalence of design code.
edge of the mounds on finished ground level
shall be determined by the site conditions, e) FOR REFINERY SERVICE:
the need for safe installation, testing,
maintenance and removal of vessels and ASTM A516 Gr. 60 ,impact tested
the requirement for the passage for (The material specified in BS-5500
emergency equipment e.g. Fire Tender, shall not be used for the above).
hydrant system. In any case this distance
shall not be less than 3.5 meters. f) FOR MARKETING INSTALLATION:
10
i) Overall settlement Reference may be made to attached
ii) Differential settlement which Drawing-4
causes bending of the vessel
iii) Differential settlement which 5.2.7
causes sloping of vessel
The earth cover shall be protected against
5.2.4 erosion by rain or wind by providing a suitable
protective cover such as covering with
a) The sand bed beneath the vessel should prefabricated stone elements, open concrete
be of adequate elevation not less than tiles.
0.76 meter to facilitate drainage from
liquid outlet pipe by gravity. In this case, 5.2.8
bottom connection shall be permitted on
mounded vessel(s) with an access to Moisture ingress into the mound shall be
connections by providing an opening or minimised by a suitable method to check
tunnel with 1.2-meter minimum diameter the corrosion by providing impervious layer
and a 0.9-meter minimum clear area. with a suitable material. Proper drainage
Bottom connections shall be considered and slope on top of the mound shall also be
as part of the vessel where they extend provided to achieve this objective. However
beyond the mound and shall be a continuous impermeable cover shall not
designed for the forces that can act on be installed, to prevent the possibility of gas
the connection. accumulation inside the mound.
12
6.5
- an audiovisual alarm at the local/
Each storage vessel shall have minimum main control panel and fire water
two different types of level indicators and station, indicating the fire.
one independent high level switch. High
level alarms shall be set at not more than - the Remote Operated Valve (ROV)
85% level of the volumetric capacity of the on liquid inlet/ outlet line to the
vessel. affected vessel will close.
Audiovisual indication shall be at local panel - the ROVs on vapor balance line and
& control room. liquid return line of the affected
vessel will close.
6.6
- LPG pumps and compressors in LPG
All these instruments and fittings on the storage area will trip.
vessel shall be isolated with two valves of
suitable type wherever required. Additionally push buttons for initiating all the
above actions shall be provided on remote
6.7 AREAS OF HEAVY SNOWFALL. operating panel and also in field at safe
location for enabling manual actuation of a
In areas where heavy snowfall can be trip by operator. Arrangement to routinely
expected, piping, regulators, meters, and test the security system shall also be
other equipment installed in the piping provided.
system shall be protected from the forces
anticipated as a result of accumulated snow. 7.2 GAS DETECTION SYSTEM
7.1 Auto Fire Detection /Protection Audio- visual alarms showing the location of
System: gas leakage shall be provided on the control
panel in the control room. First level alarm
Automatic fire detection and /or protection can be set at 20% LEL and second level
(Fixed) system based on heat detection alarm at 60 % LEL.
through thermal fuses/ quartz bulbs/ EP
detectors shall be employed. Sensors shall 8.0 HAZARDOUS AREA
be installed at all critical places described CLASSIFICATION
below:
The hazardous area shall be classified as
a) Minimum 1 detector shall be provided per IS- 5571, IS-5572 (Part I), and OISD
on each exposed portion of the vessel. standard No.113.The electrical
However if the nozzles are covered in fittings/equipment in the respective classified
a dome, each group shall have 2 Nos. area/zone shall be of a type suitable for the
of detectors particular area/zone as per classification".
b) At-least one near the each liquid line
ROV to take care of failure of flanges. 9.0 FIRE PROTECTION
The actuation of pressure switch on any one The cover provided for mounded storage
of above said detector on or around the will afford protection against direct flame
mound shall initiate the following: impingement and will minimise heat
13
absorption from nearby fires. For 9.2
mounded storage portion, the following
clauses of OISD STD –144 namely clause Hydrant and monitor coverage shall also be
10.3 iii) and 10.4.2 (a), shall not be provided on all four sides of the mound for
applicable adequate coverage of unprotected portions
exposed to thermal radiation including for
Quote: top of the mound and for product pipelines,
in the immediate vicinity of the mound. In
10.3 iii) view of accessibility of unprotected portions
of the vessels, for effectiveness, installation
All LPG storage Vessels, Cylinder of remote operated monitors at appropriate
Storage/ Filling/ Repair Sheds, LPG height shall be considered.
Pump Houses, Bulk Lorry and Tank
Wagon Gantries shall be fully 9.3
covered by medium velocity water
spray system. Hydrant /monitors should be located at a
safe place around the mound .In any case
10.4.2 a) Storage Vessels Fire hydrant and /or monitors shall not be
installed within 15 meters from the
In case of Bulk Storage of LPG, facilities/equipment to be protected
automatic detection of heat for
automatic actuation of medium 9.4
velocity (MV) sprinkler system
having remote/ local operated Measures to prevent the freezing of cooling
deluge valve with spray density of water supplies and frost damage to supply
10 LPM/Sq.M. of surface area shall lines, etc. shall be provided in the areas
be provided. For water flow where heavy snowfall can be expected.
calculations adjoining vessels within
distance of R+30 Mts. (Where R is
the Radius of the LPG vessel and 10.0 MAINTENANCE AND
30 Mts. shall be measured from the INSPECTION
periphery of the LPG vessel), water
density for cooling shall be
considered at the rate of 10 The following provisions specific to
LPM/Sq.M. surface area. mounded storage facility shall be followed
and respective records to be maintained:
Unquote
10.1.1
9.1
The Pressure Relief valves shall be tested
The fire proofing (02 Hours rating) of all and calibrated every year by a competent
exposed portion of the vessel shall be done person and records maintained.
including piping upto the first ROV,
provisions for appurtenances etc. 10.1.2
Alternatively, auto actuated fixed water spray
system shall be Provided and this system Cathodic protection system, shall be
should be actuated through heat detection maintained, tested and records maintained
device installed as per above clause 7.1. as follows
14
ii) The PSP reading at the test lead whichever is earlier, by a competent person
points for entire vessel shall be and records maintained.
taken once in a quarter. The PSP
survey results shall be plotted 10.1.5
graphically to identify and locate
cathodic holidays. The minimum Mounded vessel shall be tested once in
pipe to soil potential shall be more every 5 years internally using visual and
negative than - 0.85 volts with other techniques for the following:
respect to copper/copper sulphate
half-cell. In areas where anaerobic a) All the weld joints of the vessel shall
bacteria are active minimum PSP be examined through Non-
shall be more negative than - 0.95 Destructive Testing (NDT)
volts instead of - 0.85 volts. Over techniques e.g., radiography, Wet
protection of coated vessel shall Magnetic Particle method (WPT),
be avoided by ensuring that Dye Penetration Test (DPT),
polarisation potential is below - hardness, ultrasonic flaw detection
1.2 volts with respect to to ensure the integrity of the joints.
copper/copper sulphate half cells. b) The wall thickness of the vessel
Polarisation potential can be shall be measured ultrasonically.
measured at a given location on a
coated vessel by measuring pipe For (a) and (b) above other established NDT
to earth potential immediately techniques may be used for example
(within the first second or two) acoustic emission testing.
after simultaneously interrupting
the current output from all Note: - In case of any indication of defect or
cathodic protection sources doubts about any defect , the mound
affecting that portion of the vessel. cover of the vessel shall be removed to
expose the outer surface for necessary
iii) The PSP readings shall also be examination from outside.
recorded on weekly basis with
respect to permanent Zinc
reference cell. 10.1.6
iv) The polarisation cell shall be If internal access to mounded vessel is not
checked for replenishing the liquid possible, the external surface of the vessel
levels(KOH) will need to be exposed to enable
examination to take place as given in
v) The protective current shall be above clause no.10.1.5.
monitored every quarter
10.1.7
b) Insulating Joint/Coupling Inspection
Any repairs or modifications undertaken
Insulating joints and couplings shall be should be after statutory approval from
inspected once in a year. applicable authority.
16
17
18
19
20
21
22